December 16, 2024 |
2024 |
|
SR2024-02-008195 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide –Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (LT) – K0935 + 125 – K0935 + 250
Physical Target: Allocation:
CW1- Construction of Road Slope Protection P 71.816265 M
Structure: 1,200.00 Square meters
EAO P 2.604735 M
Total P 74.421 M
AS MODIFIED:
Daang Maharlika (LT) – K0935 + (-122.80) – K0935 + (-039), K0935 + 125 – K0935 + 250
Physical Target: Allocation:
CW1- Construction of Road Slope Protection P 71.816265 M
Structure: 1,257.6 Square meter
EAO P 2.604735 M
Total P 74.421 M
|
December 12, 2024 |
FY 2024 |
P00832860MN |
SR2024-01-000869 |
January 29, 2024 |
Region XII |
Regional Office XII |
Contract ID: 24M00030
Project Name: Tuka-Bai Saripinang Road in Bagumbayan SK in support of Agri-based Industries: Pineapple, Coffee, Rubber, Corn and Muscovado Processing Plant, Bagumbayan, Sultan Kudarat
Amount: P65M
Physical Target (From):
CW1: 3.92 Lane Km
CW2: 40.01 Square meters
Physical Target (To):
CW1: 1.216 Lane Km
CW2: 190.80 Square meters
CW3: 820 Lineal meters |
December 11, 2024 |
CY 2024 |
P00837492LZ |
SR2024-11-020397 |
November 6, 2024 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 30021400913000
Project ID.: P00837492LZ
Convergence and Special Support Program
Special Road Fund – Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation/Application of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Zebra Pedestrian Crossing along Epifanio Delos Santos Ave., (EDSA) – K0016+679 – K0017+525, Quezon City
Physical Target: CW1 = CW1 – Road Safety: Road Signs = 50 No. of Signs
Unit Cost (P’000) = P 29.998/ No. of Signs
Allocation = P 1,499,400.00
EAO = P 30,600.00
Total = P 1,530,000,00
As Modified
UACS No. 30021400913000
Project ID.: P00837492LZ
Convergence and Special Support Program
Special Road Fund – Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation/Application of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Zebra Pedestrian Crossing along Epifanio Delos Santos Ave., (EDSA) – (S05142LZ) K0018+383 – K0017+475, Quezon City
Physical Target: CW1 = CW1 – Road Safety: Road Signs = 50 No. of Signs
Unit Cost (P’000) = P 29.529/ No. of Signs
Allocation = P 1,476,450.00
EAO = P 53,550.00
Total = P 1,530,000,00
|
November 28, 2024 |
2024 |
WIN4XY00450 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00820500LZ
UACS : 32010111112000
FROM :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Road Dike, Budiao, Daraga, Albay (Package 2)
Physical Target :
Construction of Flood Mitigation Structure - 573.86 Lineal meters
TO :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Road Dike, Budiao, Daraga, Albay (Package 2)
Physical Target :
Construction of Flood Mitigation Structure - 458.7 Lineal meters |
November 22, 2024 |
2024 |
WIN4XY00389 |
FY 2024 GAA |
November 20, 2024 |
Region III |
Bataan 2nd District Engineering Office |
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and / or Bridges from the National Road/s leading to Major / Strategic Public Buildings / Facilities
Construction of Bridge at Barangay Wawa, Pilar, Bataan
|
November 20, 2024 |
FY 2024 |
WIN4XW00170 |
310205101245000 |
September 30, 2024 |
Region IX |
Regional Office IX |
UACS No. 310205101245000
Project ID: P00800268MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Package 1, Zamboanga del Norte
CW1- Construction of Concrete Bridge: 294.786 sq.m.
Unit Cost: ₱ 230,354.80/sq.m. CW2- Construction of Concrete Bridge: 1,156.248 sq.m.
Unit Cost: ₱ 88,268.38/ sq.m. CW3- Construction of Concrete Road: 1.049 Lane-km
Unit Cost: ₱ 37,164,927.68/ Lane-km ROW Acquisition: 25,410.00 sq.m. Unit Cost: ₱ 118.06/ sq.m.
EAO: ₱ 7,700,000.00 Excess: ₱ 348,478.86
Allocation: ₱ 220,000,000.00 |
November 20, 2024 |
FY 2024 |
|
310108101770000 |
July 2, 2024 |
Region IX |
Regional Office IX |
UACS No. 310108101770000
Project ID: P00800546MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Slope Protection along Seit-Tayungan-Camp Andres Road Section
CW1- Construction of Road Slope Protection Structure/ 5,196.74 sq. m.
Unit Cost: ₱ 13,369.92 sq. m.
EAO: ₱ 2,520,000.00
Allocation: ₱ 72,000,000.00 |
November 20, 2024 |
FY 2024 |
WIN4B01223 |
310105101057000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 310105101057000
Project ID: P00802721MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Jolo Port-Bud Daho-Romandier Road K4+340-K5+404, Patikul, Sulu
CW1- Rehabilitation of Paved Road: 2.128 Lane-km
Unit Cost: ₱ 18,139,097.74/ Lane-km
EAO: ₱ 1,400,000.00
Allocation: ₱ 40,000,000.00 |
November 20, 2024 |
FY 2024 |
WIN4XW00157 |
300214100809000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300214100809000 Project ID: P00833090MN Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Lanao-Pagadian-Zamboanga City Rd - K1766+114.22 - K1767+000, K1785+000 - K1786+320, K1789+000 - K1789+237, K1809+500 - K1810+000, K1812+332 - K1812+458, K1812+458 - K1813+000, K1845+000 - K1846+820
CW1 - Rehabilitation of Paved Road: 10.6 Lane-km
Unit Cost: ₱ 9,832,229.56/ Lane-km CW1 - Road Widening: 5.1 Lane-km
Unit Cost: ₱ 18,300,753.89/ Lane-km
EAO: ₱ 7,352,800.00 EXCESS: ₱ 5,171,721.77
Allocation: ₱ 210,080,000.00 |
November 20, 2024 |
FY 2024 |
|
300225102216000 |
June 26, 2024 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 300225102216000
Project ID: P00836172MN
Convergence and Special Support Program (CSSP)– Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Flood Control Structure, Poblacion, Polanco, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure : 68.00 Linear Meters
Unit Cost: ₱ 446,635.59/ Linear Meter
EAO: ₱ 306,780.00 EXCESS: ₱ 322,000.00
Allocation: ₱ 31,000,000.00 |
November 20, 2024 |
FY 2024 |
|
300219102955000 |
June 7, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300219102955000
Project ID: P00835858MN
Convergence and Special Support Program Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
Construction of Flood Mitigation Structure along Tumaga River (Sta. Maria Section), Barangay Santa Maria, Zamboanga City
CW1- Construction of Flood Mitigation Structure: 45.95 Lineal meters
Unit Cost: ₱ 383,895.539/ Lineal meters
EAO: ₱ 360,000.00
Allocation: ₱ 18,000,000.00 |
November 19, 2024 |
2024 |
300219102254000 |
FY 2024 GAA |
January 3, 2024 |
Region II |
Isabela 3rd District Engineering Office |
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
FROM:
Rehabilitation of Minanga Flood Control Project, Sta. 0+000 - Sta. 0+330, Naguillian, Isabela
TO:
Rehabilitation of Minanga Flood Control Project, Sta. 0+000 - Sta. 0+270.20, Naguillian, Isabela |
November 18, 2024 |
2024 |
WIN4F08284 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00821397LZ
UACS : 320102106464000
FROM :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Flood Mitigation Structure, Bato River, Sipi Section, Bato, Catanduanes
Physical Target :
CW1 - Construction of Flood Mitigation Structure - 198 Lineal meters
TO :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Flood Mitigation Structure, Bato River, Sipi Section, Bato, Catanduanes
Physical Target :
CW1 - Construction of Flood Mitigation Structure - 165.7 Lineal meters |
November 14, 2024 |
2024 |
WIN4XY00448 |
SR2024-04-014740 |
April 12, 2024 |
Region VIII |
Regional Office VIII |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
AS PER GAA/ORIGINAL:
Construction of flood Control structure along Suhi River ( downstream ) phase 2-A, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation Structure: P 144.750 M
1,068.952 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
AS MODIFIED:
Construction of Flood Control Structure along Suhi River (downstream) Phase 2-A, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation Structure: P 139.750M
430.50 Lineal Meters
ROW- ROW Acquisition: P 5.00 M
4,305 Square Meters
EAO P 5.250 M
Total P 150.00 M
|
November 14, 2024 |
2024 |
WIN4XY00449 |
SR2024-10-019907 |
October 24, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0884 + 000 - K0885 + 000, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Road Safety: Pavement P 7.704760 M
Markings: 1,007 Lineal Meters
EAO P .157240 M
Total P 7.862 M
AS MODIFIED:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0884 + 000 - K0885 + 500, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Off-Carriageway Improvement: Paving: P 7.51209840 M
of Shoulders: 2,340 Square Meters
CW2- Road Safety: Pavement P .7473160 M
Markings: 42 Lineal Meters
EAO P .275170 M
Total P 7.862 M
|
November 14, 2024 |
2024 |
WIN4XY00446 |
SR2024-10-019904 |
October 9, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0829 + 200 - K0830 + 200, Paranas, Samar
Physical Target: Allocation:
CW1- Road Safety: Pavement P 5.266520 M
Markings: 1,014 Lineal Meters
EAO P .107480 M
Total P 5.374 M
AS MODIFIED:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0829 + 200 - K0830 + 200, Paranas, Samar
Physical Target: Allocation:
CW1- Off-Carriageway Improvement: Paving: P 3.12278551 M
of Shoulders: 819 Square Meters
CW2- Road Safety: Guardrails P 1.3178302 M
: 366 Lineal Meters
CW2- Road Safety: Road P .74529429 M
Signs: 53 Number of Signs
EAO P .188090 M
Total P 5.374 M
|
November 14, 2024 |
2024 |
WIN4XY00447 |
SR2024-10-019908 |
October 9, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0885 + 500 - K0886 + 500, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Road Safety: Pavement P 7.029540 M
Markings: 1,006 Lineal Meters
EAO P .143460 M
Total P 7.173 M
AS MODIFIED:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0885 + 500 - K0886 + 500, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Off-Carriageway Improvement: Paving: P 6.144217 M
of Shoulders: 1,872 Square Meters
CW2- Road Safety: Guardrails P .7777271 M
: 219 Lineal Meters
EAO P .251055 M
Total P 7.173 M
|
November 12, 2024 |
2024 |
WIN4XW00148 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300215104142000
Project ID: P00834950MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Costruction of Dike in Barangay Cabangahan, Cantillan, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 520.905 Lineal meters
Allocation:
TOTAL: P 75,000,000
CW1: P 72,375,000
EAO: P 2,625,000
Unit Cost:
CW1: P 138,940.88/Lineal meters
TO:
Construction of Dike in Barangay Cabangahan, Cantilan, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 195.20 Lineal meters
Allocation:
TOTAL: P 75,000,000
CW1: P 72,375,000
EAO: P 2,625,000
Unit Cost:
CW1: P 370,773.57/Lineal meters
|
November 12, 2024 |
2024 |
WIN4E03652 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300219102710000
Project ID: P00835811MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Flood Control Structure Phase I of Barangay Bonglud, Tandag City, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 694.54 Lineal meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 138,940.88/Lineal meters
TO:
Construction of Flood Control Structure Phase I of Barangay Bonglud, Tandag City, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 140 Lineal meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 689,285.71/Lineal meters
|
November 12, 2024 |
2024 |
WIN4E03644 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300219102712000
Project ID: P00835813MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Flood Control Structure of Pagbahanan River Dike at Barangay Magobawok, Bayabas, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 347.270 Lineal meters
Allocation:
TOTAL: P 50,000,000
CW1: P 48,250,000
EAO: P 1,750,000
Unit Cost:
CW1: P 138,940.88/Lineal meters
TO:
Construction of Flood Control Structure of Pagbahanan River Dike at Barangay Magobawok, Bayabas, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 229.200 Lineal meters
Allocation:
TOTAL: P 50,000,000
CW1: P 48,250,000
EAO: P 1,750,000
Unit Cost:
CW1: P 210,514.83/Lineal meters
|
November 12, 2024 |
2024 |
WIN4XW00160 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300219102711000
Project ID: P00835812MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Flood Control Structure at Barangay Bangsud, Tago, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 486.178 Lineal meters
Allocation:
TOTAL: P 70,000,000
CW1: P 67,550,000
EAO: P 2,450,000
Unit Cost:
CW1: P 138,940.88/Lineal meters
TO:
Construction of Flood Control Structure at Barangay Bangsud, Tago, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 177.200 Lineal meters
Allocation:
TOTAL: P 70,000,000
CW1: P 67,550,000
EAO: P 2,450,000
Unit Cost:
CW1: P 381,207.67/Lineal meters
|
November 11, 2024 |
2024 |
WIN4XY00434 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00801630LZ
UACS : 310206100088000
FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Construction of Flyovers/ Interchanges/ Underpasses/ Long Span Bridges - Daraga Albay Diversion Road (Tabon-tabon Flyover), Albay
Physical Target :
CW1 - Construction of Flyover - 5724 Square meters
TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Construction of Flyovers/ Interchanges/ Underpasses/ Long Span Bridges - Daraga Albay Diversion Road (Tabon-tabon Flyover), Albay
Physical Target :
CW1 - Construction of Flyover - 3417.35 Square meters
ROW - ROW Acquisition - 13669.4 Square meters |
November 11, 2024 |
2024 |
WIN4XW00145 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310204102780000
Project ID: P00800840MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Lianga Coastal Bypass Road (SDCR Alternate Route), Surigao del Sur
Type of Work:
CW1: Construction of Concrete Road
Physical Target:
CW1- 5.328 Lane Km
Allocation:
TOTAL: P 53,280,000
CW1: P 51,415,200
EAO: P 1,864,800
Unit Cost:
CW1: P 5.328/Lane Km
TO:
Lianga Coastal Bypass Road (SDCR Alternate Route), Surigao del Sur
Type of Work:
CW1: Construction of Concrete Bridge
CW2- Construction of Road Slope Protection Structure
CW3- Construction of Drainage Structure along Road
Physical Target:
CW1- 1391.688 Square meters
CW2- 681.3 Square meters
CW3- 54 Lineal meters
Allocation:
TOTAL: P 53,280,000
CW1: P 25,090,000
CW2; P 17,110,415
CW3- P 9,214,785
EAO: P 1,864,800
Unit Cost:
CW1: P 18,028.47/Square meters
CW2: P 25,114.36/Square meters
CW3- P 170,644.17/Lineal meters
|
November 11, 2024 |
2024 |
WIN4XW00143 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 300215104136000
Project ID: P00834944MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of NRJ Tagbalili-Dumaganas Road Phase 2, Esperanza, Agusan del Sur
Type of Work:
CW1: Construction of Concrete Road
Physical Target:
CW1- 17.604 Lane Km
Allocation:
TOTAL: P 200,000,000
CW1: P 193,000,000
EAO: P 7,000,000
Unit Cost:
CW1: P 10,963,417.41/Lane Km
TO:
Construction of NRJ Tagbalili-Dumaganas Road Phase 2, Esperanza, Agusan del Sur
Type of Work:
CW1: Construction of Concrete Road
Physical Target:
CW1- 4.96 Lane Km
CW2- 1177.463 Square meters
Allocation:
TOTAL: P 200,000,000
CW1: P 128,912,420
CW2: P 64,087,580
EAO: P 7,000,000
Unit Cost:
CW1: P 25,990,407.26/Lane Km
CW2: P 54,428.53/Square meters
|
November 11, 2024 |
2024 |
WIN4XW00149 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310101101420000
Project ID: P00801131MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Daang Maharlika (Agusan-Davao Sect) - K1339 + 490 - K1339 + 904, K1340 + 228 - K1340 + 804, K1341 + 027 - K1341 + 230, K1341 + 536 - K1341 + 742, K1341 + 858 - K1341 + 964, K1342 + 713 - K1342 + 727, K1343 + 559 - K1343 + 832, K1344 + 405 - K1345 + 985
Type of Work:
CW1: Preventive Maintenance of Road: Concrete Reblocking
Physical Target:
CW1- 10.092 Lane Km
Allocation:
TOTAL: P 55,677,000
CW1: P 53,728,305
EAO: P 1,948,695
Unit Cost:
CW1: P 5,323,851.07/Lane Km
TO:
Daang Maharlika (Agusan-Davao Sect) - K1339 + 000 - K1340 + 000, K1340 + 228 - K1341 + 536, K1341 + 858 - K1342 + 000, K1344 + 365 - K1346 + 000
Type of Work:
CW1: Preventive Maintenance of Road: Concrete Reblocking
Physical Target:
CW1- 3.789 Lane Km
Allocation:
TOTAL: P 55,677,000
CW1: P 53,728,305
EAO: P 1,948,695
Unit Cost:
CW1: P 14,180,075.22/Lane Km
|
November 11, 2024 |
2024 |
WIN4XW00146 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 300214101341000
Project ID: P00833161MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
FROM:
Installation/Application/Construction of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Median Island along Daang Maharlika (Agusan-Davao Sect) (S00439MN) - K1310 + 100 - K1311 + 100, Barangay San Isidro, San Francisco, Agusan del Sur
Type of Work:
CW1: Road Safety: Pavement Markings
Physical Target:
CW1- 1000 Lineal meters
Allocation:
TOTAL: P 3,880,000
CW1: P 3,802,400
EAO: P 77,600
Unit Cost:
CW1: P 3,802.4/Lineal meters
TO:
Installation/Application/Construction of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Median Island along Daang Maharlika (Agusan-Davao Sect) (S00439MN) - K1310 + 100 - K1311 + 100, Barangay San Isidro, San Francisco, Agusan del Sur
Type of Work:
CW1: Road Safety: Road Signs
CW2: Off-Carriageway Improvement: Construction of Median/Center Island
Physical Target:
CW1- 24 Number of Signs
CW2- 494.27 Square meters
Allocation:
TOTAL: P 3,880,000
CW1: P 848,235
CW2: P 2,895,965
EAO: P 135,800
Unit Cost:
CW1: P 35,343.13/ Number of Signs
CW2: P 5,859.075/Square meters
|
November 11, 2024 |
2024 |
WIN4XW00141 |
FY 2024 GAA, R.A 11975 |
December 23, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101369000
Project ID: P00800162MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1198 + 000 - K1199 + 000, K1201 + 025 - K1202 + 814, K1202 + 915.50 - K1203 + 577
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 6.915 Lane Km
Allocation:
TOTAL: P 210,000,000
CW1: P 202,650,000
EAO: P 7,350,000
Unit Cost:
CW1: P 29,305,856.83/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1198 + 000 - K1199 + 000, K1201 + 025 - K1202 +480, K1203 + 260 - K1204 + 148
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 6.686 Lane Km
CW2- 24,153.50 Square meters
Allocation:
TOTAL: P 210,000,000
CW1: P 183,350,000
CW2: P 19,300,000
EAO: P 7,350,000
Unit Cost:
CW1: P 27,422,973.38/Lane Km
CW2: P 799.06/Square meters
|
November 11, 2024 |
2024 |
WIN4XW00134 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101370000
Project ID: P00800154MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1224 + 779 - K1224 + 920, K1224 + 986 - K1225 + 010, K1225 + 148 - K1225 + 824, K1225 + 923 - K1226 + 000, K1235 + 515 - K1238 + 135, K1240 + 694 - K1240 + 863
Type of Work:
CW1: Road Widening
CW2- ROW Acquisition
Physical Target:
CW1- 6.794 Lane Km
CW2- 2.072 Lane Km
Allocation:
TOTAL: P 156,870,000
CW1: P 146,554,550
CW2; P 4,825,000
EAO: P 5,490,450
Unit Cost:
CW1: P 21,571,173.09/Lane Km
CW2: P 2,328,667.95/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1225 + 923 - K1226 + 000, K1235 + 515 - K1238 + 135
Type of Work:
CW1: Road Widening
CW2- ROW Acquisition
Physical Target:
CW1- 5.182 Lane Km
CW2- 45,000,000 Square meters
Allocation:
TOTAL: P 156,870,000
CW1: P 146,554,550
CW2; P 4,825,000
EAO: P 5,490,450
Unit Cost:
CW1: P 28,281,464.68/Lane km
CW2: P 107.22/Square meters
|
November 11, 2024 |
2024 |
WIN4XW00158 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310204102792000
Project ID: P00803872MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Construction of San Francisco, Agusan del Sur to Lianga, Surigao del Sur Bypass Road, Package 1
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 30 Lane Km
Allocation:
TOTAL: P 300,000,000
CW1: P 289,500,000
EAO: P 10,500,000
Unit Cost:
CW1: P 9,650,000/Lane Km
TO:
Construction of San Francisco, Agusan del Sur to Lianga, Surigao del Sur Bypass Road, Package 1
Type of Work:
CW1- Construction of Gravel Road
Physical Target:
CW1- 11.600 Lane Km
Allocation:
TOTAL: P 300,000,000
CW1: P 289,500,000
EAO: P 10,500,000
Unit Cost:
CW1: P 24,956,896.55/Lane Km
|
November 11, 2024 |
2024 |
|
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 300214101342000
Project ID: P00833160MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
FROM:
Installation/Application/Construction of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Median Island along Daang Maharlika (Agusan-Davao Sect), (S00439MN) - K1307 + 160 - K1308 + 160, Barangay Hubang and Barangay 3 (Poblacion), San Francisco, Agusan del Sur
Type of Work:
CW1- Road Safety: Pavement Markings
Physical Target:
CW1- 1001 Lineal meters
Allocation:
TOTAL: P 2,450,000
CW1: P 2,401,000
EAO: P 49,000
Unit Cost:
CW1: P 2,398.6/Lineal meters
TO:
Installation/Application/Construction of Signage-Warning, Advisory and Regulatory Signs, Pavement Markings, and Median Island along Daang Maharlika (Agusan-Davao Sect), (S00439MN) - K1307 + 160 - K1308 + 160, Barangay Hubang and Barangay 3 (Poblacion), San Francisco, Agusan del Sur
Type of Work:
CW1- Road Safety: Pavement Markings
CW2- Road Safety: Road Signs
CW3- Off-Carriageway Improvement: Construction of Median/Center Island
Physical Target:
CW1- 1001 Lineal meters
CW2- 20 Number of Signs
CW3- 255.230 Square meters
Allocation:
TOTAL: P 2,450,000
CW1: P 495,817
CW2: P 362,526.38
CW3: P 1,505,906.62
EAO: P 85,750
Unit Cost:
CW1: P 495.322/Lineal meters
CW2: P 18,126.319/Number of Signs
CW3: P 5,900.19/Square meters
|
November 11, 2024 |
2024 |
WIN4E03672 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 300221104921000
Project ID: P00835944MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Bunawan - Veruela - Santa Josefa Road, Agusan del Sur (Phase 10)
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 26.406 Lane Km
Allocation:
TOTAL: P 300,000,000
CW1: P 297,000,000
EAO: P 3,000,000
Unit Cost:
CW1: P 11,247,443.76/Lane Km
TO:
Construction of Bunawan - Veruela - Santa Josefa Road, Agusan del Sur (Phase 10)
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4.992 Lane Km
CW2- 5158.10 Square meters
Allocation:
TOTAL: P 300,000,000
CW1: P 187,993,170
CW2: P 109,906,830
EAO: P 3,000,000
Unit Cost:
CW1: P 37,478,599.76/Lane Km
CW2: P 21,307.62/Square meters
|
November 11, 2024 |
2024 |
WIN4XW00155 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101367000
Project ID: P00800163MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1153 + 200 - K1153 + 595, K1153 + 609.48 - K1155 + 782, K1155 + 807.70 - K1157 + 163, K1157 + 179.49 - K1157 + 767, K1157 + 793 - K1158 + 222, K1158 + 229 - K1158 + 543, K1158 + 583.02 - K1160 + 500
Type of Work:
CW1- Road Widening
CW2- ROW Acquisition
Physical Target:
CW1- 14.369 Lane Km
CW2- 55530.031 Square meters
Allocation:
TOTAL: P 200,000,000
CW1: P 183,350,000
CW2: P 9,650,000
EAO: P 7,000,000
Unit Cost:
CW1: P 12,760,108.57/Lane Km
CW2: P 173.779842/Square meters
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1153 + 200 - K1153 + 595, K1153 + 609.48 - K1155 + 782, K1155 + 807.70 - K1157 + 163, K1157 + 179.49 - K1157 + 767, K1157 + 793 - K1158 + 222, K1158 + 229 - K1158 + 543, K1158 + 583.02 - K1160 + 500
Type of Work:
CW1- Road Widening
CW2- ROW Acquisition
Physical Target:
CW1- 6.760 Lane Km
CW2- 55530.031 Square meters
Allocation:
TOTAL: P 200,000,000
CW1: P 183,350,000
CW2: P 9,650,000
EAO: P 7,000,000
Unit Cost:
CW1: P 27,122,781.07/Lane Km
CW2: P 173.779842/Square meters
|
November 8, 2024 |
FY 2024 |
P00803786MN |
SR2024-03-013774 |
March 20, 2024 |
Region XII |
Regional Office XII |
Asphalt Overlay |
November 8, 2024 |
FY 2024 |
P00803787MN |
SR2024-03-013770 |
March 20, 2024 |
Region XII |
Regional Office XII |
Aphalt Overlay |
November 8, 2024 |
FY 2024 |
P00800770MN |
SR2024-01-000600 |
January 26, 2024 |
Region XII |
Regional Office XII |
Panatan Bridge |
November 7, 2024 |
2024 |
WIN4E03673 |
SR2024-01-004597 |
January 29, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Balbalan-Pinukpuk Rd - K0516 + 200 - K0518 + 939, K0519 + 053 - K0522 + 1128;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
13.666 Lane Km;
Allocation:
Php 80,139,000"
"To:
Balbalan-Pinukpuk Rd - K0516 + 200 - K0518 + 939, K0519 + 053 - K0520 + 263.065;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
7.92213 Lane Km;
Allocation:
Php 80,139,000"
|
November 7, 2024 |
2024 |
WIN4XW00166 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Drainage Canal along Mt. Province Bdry. - Calanan - Pinukpuk - Abbut Road, Calanan-Pinukpuk Junction Section, K0496+(-150) - K0496+250, Calanan, Tabuk City, Kalinga;
Type of Work:
Construction of Drainage Structure;
Physical Target:
2596.85 Lineal meters;
Allocation:
Php 27,998,000"
"To:
Construction of Drainage Canal along Mt. Province Bdry. - Calanan - Pinukpuk - Abbut Road, Calanan-Pinukpuk Junction Section, K0496+(-150) - K0497+346, Calanan, Tabuk City, Kalinga;
Type of Work:
Construction of Drainage Structure;
Physical Target:
1573 Lineal meters;
Allocation:
Php 27,998,000"
|
November 7, 2024 |
2024 |
WIN4XW00165 |
SR2024-01-004814 |
January 30, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Ngipen Bridge, Bantay Flood Control along Chico River, Bantay Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
492.298 Lineal meter;
Allocation:
Php 60,000,000"
"To:
Construction of Ngipen Bridge, Bantay Flood Control along Chico River, Bantay Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
150 Lineal meters;
Allocation:
Php 60,000,000"
|
November 7, 2024 |
2024 |
WIN4XW00167 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Drainage Canal along Mt. Province Bdry. - Calanan - Pinukpuk - Abbut Road, Calanan-Pinukpuk Junction Section, K0508+447 - K0508+647 (B/S), Tannong, Tabuk City, Kalinga;
Type of Work:
Construction of Drainage Structure;
Physical Target:
3246.289 Lineal Meters;
Allocation:
Php 35,000,000"
"To:
Construction of Drainage Canal along Mt. Province Bdry. - Calanan - Pinukpuk - Abbut Road, Calanan-Pinukpuk Junction Section, K0508+414 - K0508+856, Tabuk City, Kalinga;
Type of Work:
Construction of Drainage Structure;
Physical Target:
442 Lineal Meters;
Allocation:
Php 35,000,000"
|
November 6, 2024 |
2024 |
WIN4F08272 |
SR2024-02-008216 |
February 24, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0680 + (-169) - K0680 + 088
Physical Target: Allocation:
CW1- Construction of Road Slope Protection: P 96.5 M
Structure : 10,000 Square Meters
EAO P 3.5 M
Total P 100.00 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0680 + (-106) - K0680 + 088, K0688 + 410 - K0688+570
Physical Target: Allocation:
CW1- Construction of Road Slope Protection: P 96.5 M
Structure : 3,729.367 Square Meters
EAO P 3.5 M
Total P 100.00 M
|
November 6, 2024 |
2024 |
WIN4F08277 |
SR2024-02-008191 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
AS PER GAA/ORIGINAL:
Tigbao - Sta. Fe - San Miguel Road - K0907 + 745 - K0907 + 775, K0907 + 940 - K0908 + 012, K0908 + 340 - K0908 + 410, K0908 + 413 - K0908 + 418, K0908 + 555 - K0908 + 567
Physical Target: Allocation:
CW1- Reconstruction to Concrete Pavement: P 96.5 M
4.60 Lane Km
EAO P 3.5 M
Total P 100.00 M
AS MODIFIED:
Tigbao - Sta. Fe - San Miguel Road – K0904+093 - K0905+000, K0907 + 250 - K0907 + 268, K0907 + 745 - K0907 + 775, K0907 + 940 - K0908 + 000
Physical Target: Allocation:
CW1- Rehabilitation of Paved Road: P 48.30270519 M
2.39 Lane Km
CW2- Construction of Road Slope Protection: P 48.19729481 M
Structure : 1,969.7 Square Meters
EAO P 3.5 M
Total P 100.00 M
|
November 6, 2024 |
2024 |
WIN4F08276 |
SR2024-01-007894 |
January 31, 2024 |
Region VIII |
Regional Office VIII |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure along Diit River, Phase 2, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 96.5 M
Structure: 712.635 Lineal Meters
EAO P 3.5 M
Total P 100.00 M
AS MODIFIED:
Construction of Flood Control Structure along Diit River, Phase 2, Tacloban City
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 91.44483455 M
Structure: 305 Lineal Meters
ROW- ROW Acquisition P 5.00 M
: 3,050 Square Meters
EAO P 3.5 M
EXC P.5516545 M
Total P 100.00 M
|
November 6, 2024 |
2024 |
WIN4F08274 |
SR2024-04-014783 |
April 15, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure, barangay Benuwangan, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 1,068.952 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
AS MODIFIED:
Construction of Flood Control Structure, Barangay Benuwangan, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 422 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
|
November 6, 2024 |
2024 |
WIN4F08271 |
GAA FY 2024 |
January 1, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development – Road Widening – Tertiary Roads
AS PER GAA/ORIGINAL:
Tanauan-Dagami Rd - K0928 + 802 - K0929 + 012
Physical Target: Allocation:
CW1- Road Widening: P 6.1642 M
0.360 Lane Km
CW2- Construction of Road Slope Protection: P .6958 M
Structure : 1,104.33 Square Meters
EAO P .140 M
Total P 7.00 M
AS MODIFIED:
Tanauan-Dagami Rd - K0928 + 802 - K0928 + 930
Physical Target: Allocation:
CW1- Road Widening: P 3.64877667 M
0.256 Lane Km
CW2- Construction of Road Slope Protection: P 3.21122333 M
Structure : 491.498 Square Meters
EAO P .140 M
Total P 7.00 M
|
November 5, 2024 |
2024 |
WIN4F08273 |
SR2024-02-008140 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0680 + 155 - K0680 + 572, K0680 + 596 - K0680 + 879, K0680 + 909 - K0680 + 914, K0682 + 960 - K0683 + 000
Physical Target: Allocation:
CW1- Preventive Maintenance of Road: P 55.235635 M
Asphalt Overlay : 3.367 Lane Km
EAO P 2.003365 M
Total P 57.239 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0680 + 155 - K0680 + 572, K0680 + 596 - K0680 + 879, K0680 + 909 - K0680 + 914, K0682 + 960 - K0683 + 000
Physical Target: Allocation:
CW1- Preventive Maintenance of Road: P 55.235635 M
Asphalt Overlay : 2.14 Lane Km
EAO P 2.003365 M
Total P 57.239 M
|
November 5, 2024 |
2024 |
WIN4F08275 |
SR2024-02-008271 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure, barangay Calingatngan, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Flood Mitigation: P 144.750 M
Structure : 1,000 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
AS MODIFIED:
Construction of Flood Control Structure, barangay Calingatngan, Borongan City, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Flood Mitigation: P 144.750 M
Structure : 478 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
|
November 4, 2024 |
2024 |
WIN4XY00442 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Regional Office III |
Network Development Program - Construction of By-Pass and Diversion Roads
Lubao-Floridablanca Bypass Road |
November 4, 2024 |
2024 |
WIN4XW00164 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Apayao 1st District Engineering Office |
"From:
Construction (Completion) of Multi-Purpose Building Conner Central National High School,
Barangay Ripang, Luna, Apayao;
Type of Work:
Construction of
Multi Purpose
Building;
Physical Target:
1 Number of Building;
Allocation:
Php 3,500,000"
"To:
Construction (Completion) of Multi-Purpose Building Conner Central National High School,
Barangay Ripang, Conner, Apayao;
Type of Work:
Construction of
Multi Purpose
Building;
Physical Target:
1 Number of Building;
Allocation:
Php 3,500,000"
|
October 30, 2024 |
2024 |
P00803858MN |
P00803858MN |
January 29, 2024 |
Region X |
Regional Office X |
P00803858MN
310204102716000
OO1: Network Development Program - Construction of By-Pass and Diversion Roads
FROM:
Construction of Jct. Sayre Highway Daling - Kisolon Bypass Road, Bukidnon, Package 11
Type of Work:
CW1- Construction of Concrete Bridge
CW2- Construction of Concrete Road
ROW- ROW Acquisition
Physical Target:
CW1-572.40 Square meters
CW2-1.75 Lane Km
ROW-5,000.00 Square meters
Allocation:
Total: Php 200,000,000.00
CW1: Php 115,800,000.00
CW2: Php 67,550,000.00
ROW: Php 9,650,000.00
EAO: Php 7,000,000.00
TO:
Construction of Jct. Sayre Highway Dalirig - Kisolon Bypass Road, Bukidnon, Package 11
Type of Work:
CW1- Construction of Concrete Bridge
CW2- Construction of Gravel Road
ROW- ROW Acquisition
Physical Target:
CW1-572.40 Square meters
CW2-2.769 Lane Km
ROW-5,000.00 Square meters
Allocation:
Total: Php 200,000,000.00
CW1: Php 115,800,000.00
CW2: Php 67,550,000.00
ROW: Php 9,650,000.00
EAO: Php 7,000,000.00 |
October 30, 2024 |
2024 |
P00801101MN |
SR2024-10-019986 |
October 11, 2024 |
Region X |
Regional Office X |
P00801101MN
310101101565000
OO1: Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Sayre Highway - K1431 + 900 - K1432 + 575
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 4.088 Lane Km
Allocation:
Total: Php 44,232,000.00
CW1: Php 43,347,360.00
EAO: Php 884,640.00
TO:
Sayre Highway - K1431 + 900 - K1432 + 575
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 3.824 Lane Km
Allocation:
Total: Php 44,232,000.00
CW1: Php 42,683,880.00
EAO: Php 1,548,120.00 |
October 30, 2024 |
2024 |
P00834989MN |
SR2024-10-019968 |
October 11, 2024 |
Region X |
Regional Office X |
P00834989MN
300215105020000
CSSP: Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Jct. Sayre Highway (Jct. Bukidnon-Davao City Rd.- Cotabato Bdry) to Purok 2, Poblacion to Purok 1 Poblacion, Brgy. Sagbayan Road, Dangcagan, Bukidnon
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 2.74 Lane Km
Allocation:
Total: Php 41,000,000.00
CW1: Php 40,180,000.00
EAO: Php 820,000.00
TO:
Construction of Jct. Sayre Highway (Jct. Bukidnon-Davao City Rd.- Cotabato Bdry) to Purok 2, Poblacion to Purok 1 Poblacion, Brgy. Sagbayan Road, Dangcagan, Bukidnon
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 2.00 Lane Km
Allocation:
Total: Php 41,000,000.00
CW1: Php 39,565,000.00
EAO: Php 1,435,000.00
|
October 30, 2024 |
2024 |
P00830264MN |
SR2024-10-019960 |
October 11, 2024 |
Region X |
Regional Office X |
P00830264MN
300203102801000
CSSP: Construction/ Improvement of Access Roads leading to Declared Tourism Destinations (Tourism Road Infrastructure Program - TRIP)
FROM:
Access Road leading to Kipilas Falls with Bridge, Kitaotao, Bukidnon (Package 2)
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Concrete Bridge
Physical Target:
CW1- 2.50 Lane Km
CW2- 238.50 Square meters
Allocation:
Total: Php 100,000,000.00
CW1: Php 68,600,000.00
CW2: Php 29,400,000.00
EAO: Php 2,000,000.00
TO:
Access Road leading to Kipilas Falls with Bridge, Kitaotao, Bukidnon (Package 2)
Type of Work:
CW1- Construction of Gravel Road
CW2- Construction of Concrete Bridge
Physical Target:
CW1- 5.287 Lane Km
CW2- 1,049.40 Square meters
Allocation:
Total: Php 100,000,000.00
CW1: Php 67,550,000.00
CW2: Php 28,950,000.00
EAO: Php 3,500,000.00 |
October 28, 2024 |
2024 |
|
SR2024-10-019906 |
October 9, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0876 + 000 - K0877 + 000, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Road Safety: Pavement P 6.1544 M
Markings: 1,008 Lineal Meters
EAO P .1256 M
Total P 6.280 M
AS MODIFIED:
Installation/Application/Construction of Signage, Pavement Markings, and Paved Shoulders along Daang Maharlika (SM) (Sn Isidro- Sn Juanico Section) - K0876 + 000 - K0877 + 000, Sta. Rita, Samar
Physical Target: Allocation:
CW1- Off-Carriageway Improvement: P 6.0602 M
Paving of Shoulders: 1,734 Square Meters
EAO P .2198 M
Total P 6.280 M
|
October 28, 2024 |
2024 |
WIN4XY00347 |
SR2024-10-020171 |
October 17, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Road and Bridge connecting Sulat Poblacion to National Highway, Sulat, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Concrete Bridge P 39.200 M
: 225 Square Meters
EAO P .800 M
Total P 40.00 M
AS MODIFIED:
Construction of Road and Bridge connecting Sulat Poblacion to National Highway, Sulat, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Concrete Bridge P 33.966670 M
: 295.74 Square Meters
CW2- Construction of Concrete Road: P 4.633330 M
:0.374 Lane Km
EAO P 1.4 M
Total P 40.00 M
|
October 24, 2024 |
2024 |
|
SR2024-02-008263 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Bridge - Widening of Permanent Bridges
AS PER GAA/ORIGINAL:
Mawo Parallel Br. (B00599SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br)
Physical Target: Allocation:
CW1-Widening of Bridge: 387.130 Square meters P 39.159700 M
EAO P 1.420300 M
Total P 40.580 M
AS MODIFIED:
Mawo Parallel Br. (B00599SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br)
Physical Target: Allocation:
CW1-Widening of Bridge:2,030.112 Square meters P 39.159700 M
EAO P 1.420300 M
Total P 40.580 M
|
October 24, 2024 |
2024 |
|
SR2024-09-019072 |
September 18, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Improvement of Intersection - Daang Maharlika (LT) (S00022LT) - K0909 + (-172) and Tigbao-Sta. Fe-San Miguel Road (S00033LT)
Physical Target: Allocation:
CW1-Road Safety: Traffic Signals P 9.800 M
: 1.00 Number of Traffic Signals
EAO P 0.200 M
Total P 10.00 M
AS MODIFIED:
Improvement of Intersection - Daang Maharlika (LT) (S00002LT) - K0902 + 135 and Tigbao-Sta. Fe-San Miguel Road (S00033LT)
Physical Target: Allocation:
CW1-Road Safety: Traffic Signals P 9.650 M
: 1.00 Number of Traffic Signals
EAO P 0.350 M
Total P 10.00 M
|
October 22, 2024 |
2024 |
WIN4F08246 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00837762LZ
UACS : 300214101149000
From :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Improvement of Intersection - Daang Maharlika Rd (LZ) - (S03617LZ) - K0494 + 660 and Oas - Poblacion Rd (S03726LZ)
Physical Target :
CW1 - Off-Carriageway Improvement - Paving of Shoulders - 1 Number of Intersection
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Improvement of Intersection - Daang Maharlika Rd (LZ) - (S03617LZ) - K0496 + 693 and Oas - Poblacion Rd (S03726LZ)
TO :
CW1 - Off-Carriageway Improvement - Paving of Shoulders - 1 Number of Intersection
CW2 - Construction of Drainage Structure along Road - 196.48 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 224.92 Square meters |
October 22, 2024 |
2024 |
WIN4F08248 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00842606LZ
UACS : 30021510383600
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Matara to Moroponros Road, Barangay Matara Package 1, Libong and Barangay Moroponros, Oas, Albay
Physical Target :
CW1 - Construction of Concrete Road - 4.396 Lane Km
CW2 - Construction of Drainage Structure along Road - 2845 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 24888.63 Square meters
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Matara to Moroponros Road, Barangay Matara Package 1, Libong and Barangay Moroponros, Oas, Albay
Physical Target :
CW1 - Construction of Concrete Road - 2.732 Lane Km
CW2 - Construction of Gravel Road - 2.800 Lane Km
CW3 - Construction of Road Slope Protection Structure - 12,310.59 Square meters |
October 22, 2024 |
2024 |
WIN4F08245 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00842607LZ
UACS : 300215103837000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities Construction of Matara to Moroponros Road, Barangay Matara Package 2, Libon and Barangay Moroponros, Oas, Albay
Physical Target :
CW1 - Construction of Concrete Road - 4.5 Lane Km
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - SIPAG - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities Construction of Matara to Moroponros Road, Barangay Matara Package 2, Libon and Barangay Moroponros, Oas, Albay
Physical Target :
CW1 - Construction of Concrete Road - 2.8 Lane Km
CW2 - Construction of Gravel Road - 3.8 Lane Km
CW3 - Construction of Road Slope Protection Structure - 2,570.8 Square meters |
October 22, 2024 |
2024 |
WIN4F08244 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00844921LZ
UACS : 300221104748000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Magallang - Moroponros, Libon/ Oas, Albay (Phase 2)
Physical Target :
CW1 - Construction of Concrete Road - 5.878 Lane Km
CW2 - Construction of Drainage Structure along Road - 3,045 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 24,896.06 Square meters
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/ or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road, Magallang - Moroponros, Libon/ Oas, Albay (Phase 2)
Physical Target :
CW1 - Construction of Concrete Road - 3.32 Lane Km
CW2 - Construction of Drainage Structure along Road - 3.94 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 16701.72 Square meters |
October 19, 2024 |
2024 |
|
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00837429LZ
UACS : 300214100754000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0416 + 113 - K0416 + 378, K0420 + 500 - K0420 + 843, K0428 + 625 - K0429 +183
Physical Target :
CW1 - Rehabilitation to Concrete Pavement - 2.602 Lane Km
CW2 - Road Widening - 0.898 Lane Km
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0404 + 000 - K0405 + 876, K0406 + 147.15 - K0406 + 912, K0409 + 000 - K0409 + 815
Physical Target :
CW1 - Rehabilitation to Concrete Pavement - 2.8397 Lane Km
|
October 18, 2024 |
2024 |
|
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00837420LZ
UACS : 300214100756000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0456 + 000 - K0457 + 000, K0458 + 150 - K0458 + 284, K0479 + 700 - K0479 + 840
Physical Target :
CW1 - Reconstruction to Concrete Pavement - 4.944 Lane Km
CW2 - Road Widening - 0.14 Lane Km
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0458 + 000 - K0458 + 314, K0464 + 023 - K0465 + 085.30, K0469 + 000 - K069 + 172, K0474 + 830 - K0475 + 108, K0477 + 097 - K0477 + 840, K0478 + 861 - K0480 + 146
Physical Target :
CW1 - Reconstruction to Concrete Pavement - 8.8165 Lane Km |
October 17, 2024 |
2024 |
WIN4XY00415 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00801612LZ
UACS : 310204102835000
FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Camarines Sur Expressway Package 20, Camarines Sur
Physical Target :
CW1 - Construction of Concrete Road - 3.72 Lane Km
TO :
ORGANIZATIONAL OUTCOME 1- Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads - Camarines Sur Expressway Package 20, Camarines Sur
Physical Target :
CW1 - Construction of Concrete Bridge - 630.15 Square meters
CW2 - Construction of Road Slope Protection Structure - 1491.57 Square meters |
October 17, 2024 |
2024 |
WIN4F08251 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00805234LZ
UACS : 310201101398000
FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0611 + 595 - K0612 + 261, K0615 + 500 - K0615 + 699, K0618 + 000 - K0618 + 325
Physical Target :
CW1 - Road Widening - 2.378 Lane Km
CW2 - Construction of Drainage Structure along Road - 1189 Lineal meters
CW3 - Construction of Road Slope Protection Structure
ROW - ROW Acquisition - 23780 Square meters
TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0611 + 595 - K0612 + 261, K0615 + 500 - K0615 + 699, K0618 + 000 - K0618 + 325
Physical Target :
CW1 - Road Widening - 2.38 Lane Km
CW2 - Construction of Drainage Structure along Road - 666 Lineal meters
ROW - ROW Acquisition - 1189 Square meters |
October 17, 2024 |
2024 |
|
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00832312LZ
UACS : 300207101062000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Various Infrastructures in Support of National Security (Tatag ng Imprastraktura para sa Kapayaan at Seguridad Program - TIKAS) - Construction of Barracks and Other Military Camps Facilities at Sitio Barayong, Purok 1, Talahib, Daraga, Albay
Physical Target :
CW1 - Construction of Other Facilities - 1 Number of Facilities
CW2 - Construction of Other Facilities - 1 Number of Facilities
CW3 - Construction of Other Facilities - 1 Number of Facilities
CW4 - Construction of Other Facilities - 1 Number of Facilities
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Various Infrastructures in Support of National Security (Tatag ng Imprastraktura para sa Kapayaan at Seguridad Program - TIKAS) - Construction of Barracks and Other Military Camps Facilities at Sitio Barayong, Purok 1, Talahib, Daraga, Albay
Physical Target :
CW1 - Construction of Other Facilities - 9 Number of Facilities |
October 16, 2024 |
FY 2024 |
WIN4B01231 |
300215104014000 |
June 11, 2024 |
Region IX |
Regional Office IX |
UACS No. 300215104014000
Project ID: P00834848MN
Convergence and Special Support Program Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Brgy. Buansa to Laum Saing Road Km 0+000-Km 0+320 Brgy, Kagay, Indanan
CW1- Rehabilitation of Paved Road: 0.64 Lane-km
Unit Cost: ₱ 15,078,125.00/ Lane-km
EAO: ₱ 350,000.00
Allocation: ₱ 10,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300219102635000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300219102635000
Project ID: P00835749MN
Convergence and Special Support Program Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
Construction of Seawall along Bongao-Pahut-Sanga-Sanga Road Package 1, Tawi-Tawi
CW1- Construction of Flood Mitigation Structure: 600.00 Lineal meters
Unit Cost: ₱ 273,416.67/ Lineal meters
EAO: ₱ 5,950,000.00
Allocation: ₱ 170,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300219102636000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300219102636000
Project ID: P00835750MN
Convergence and Special Support Program Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
Construction of Seawall along Bongao-Pahut-Sanga-Sanga Road Package 2, Tawi-Tawi
CW1- Construction of Flood Mitigation Structure: 607.00 Lineal meters
Unit Cost: ₱ 270,263.59/ Lineal meters
EAO: ₱ 5,950,000.00
Allocation: ₱ 170,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300219102637000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300219102637000
Project ID: P00835751MN
Convergence and Special Support Program Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
Construction of Shore Protection along Tapian-Ballak, Tawi-Tawi
CW1- Construction of Flood Mitigation Structure: 572.00 Lineal meters
Unit Cost: ₱ 269,930.07/ Lineal meters
EAO: ₱ 5,600,000.00
Allocation: ₱ 160,000,000.00 |
October 16, 2024 |
FY 2024 |
WIN4B01221 |
300221104836000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104836000
Project ID: P00835908MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Dahiram Sali Road, Languyan, Tawi-Tawi
CW1- Construction of Concrete Road: 0.684 Lane-km
Unit Cost: ₱ 26,017,135.30/ Lane-km CW2- Construction of Road Slope Protection Structure: 507.00 sq.m.
Unit Cost: ₱ 3,953.21/ sq.m.
EAO: ₱ 200,000.00
Allocation: ₱ 20,000,000.00 |
October 16, 2024 |
FY 2024 |
WIN4B01218 |
300221104847000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104847000
Project ID: P00835910MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Jolo-Kasanyangan Road Sta. 0+000.00 - Sta. 0+117.82, Sta. 0+640 - Sta. 2+120
CW1- Rehabilitation of Paved Road: 3.196 Lane-km
Unit Cost: ₱ 15,488,110.14/ Lane-km
EAO: ₱ 500,000.00
Allocation: ₱ 50,000,000.00 |
October 16, 2024 |
FY 2024 |
WIN4E03568 |
300221104859000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104859000
Project ID: P00835913MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Indanan-Lapa Road, Sta. 18+900 - Sta. 20+170, Maimbung, Sulu
CW1- Rehabilitation of Paved Road: 2.54 Lane-km
Unit Cost: ₱ 19,488,188.97/ Lane-km
EAO: ₱ 500,000.00
Allocation: ₱ 50,000,000.00 |
October 16, 2024 |
FY 2024 |
WIN4B01225 |
300221104861000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104861000
Project ID: P00835915MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Indanan-Lapa Road, Sta. 16+400 - Sta. 17+410, Maimbung, Sulu
CW1- Rehabilitation of Paved Road: 2.020 Lane-km
Unit Cost: ₱ 19,603,960.40/ Lane-km
EAO: ₱ 400,000.00
Allocation: ₱ 40,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300221104862000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104862000
Project ID: P00835916MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Parang-Maimbung Road Sta. 20+386.25 - Sta. 21+182.75, Sta. 21+009.00 - Sta. 21+189, Sta. 21+398.50 - Sta. 21+520, Sta. 21+653 - Sta. 22+071.50, Sta. 28+028.10 - Sta. 29+001.07, Maimbung, Sulu
CW1- Rehabilitation of Paved Road:3.460 Lane-km
Unit Cost: ₱ 11,445,086.71/ Lane-km
EAO: ₱ 400,000.00
Allocation: ₱ 40,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300221104862000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104862000
Project ID: P00835916MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of Parang-Maimbung Road Sta. 20+386.25 - Sta. 21+182.75, Sta. 21+009.00 - Sta. 21+189, Sta. 21+398.50 - Sta. 21+520, Sta. 21+653 - Sta. 22+071.50, Sta. 28+028.10 - Sta. 29+001.07, Maimbung, Sulu
CW1- Rehabilitation of Paved Road:3.460 Lane-km
Unit Cost: ₱ 11,445,086.71/ Lane-km
EAO: ₱ 400,000.00
Allocation: ₱ 40,000,000.00 |
October 16, 2024 |
FY 2024 |
WIN4E03609 |
310203100879000 |
June 27, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310203100879000
Project ID: P00800014MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Old Rd (Ayala-Talisayan) - K1957+260 - K1958+006
CW1- Road Widening: 1.466 Lane-km
Unit Cost: ₱ 16,544,419.34/ Lane-km CW2- Construction of Drainage Structure along Road: 1,466.00 sq.m.
Unit Cost: ₱ 14,558.21/ sq.m. ROW Acquisition: 6,816.90 sq.m. Unit Cost: ₱ 4,459.16/ sq.m.
EAO: ₱ 1,550,900.00
Allocation: ₱ 77,545,000.00 |
October 16, 2024 |
FY 2024 |
WIN4E03583 |
310212100266000 |
April 11, 2024 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310212100266000
Project ID: P00800210MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads
Olutanga Circumferential Rd - (S01223MN) Chainage 4503 - Chainage 4961, Chainage 5341 - Chainage 5821, Chainage 7372 - Chainage 7798
CW1- Paving of Unpaved Roads: 2.278 Lane-km
Unit Cost: ₱ 20,901,376.47/ Lane-km
EAO: ₱ 2,068,045.00
Allocation: ₱ 59,087,000.00 |
October 16, 2024 |
FY 2024 |
|
310102101622000 |
June 11, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310102101622000
Project ID: P00801116MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Zamboanga City-Labuan-Limpapa Rd - K1941+631 - K1944+620
CW1- Preventive Maintenance of Road/Asphalt Overlay: 11.912 Lane-km
Unit Cost: ₱ 7,720,324.04/ Lane-km
EAO: ₱ 3,335,500.00
Allocation: ₱ 95,300,000.00 |
October 16, 2024 |
FY 2024 |
WIN4XW00128 |
310102101626000 |
June 27, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310102101626000
Project ID: P00802641MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Patalon Br. along Zamboanga City Labuan-Limpapa Road
CW1- Preventive Maintenance of Road/Asphalt Overlay: 1.78 Lane-km
Unit Cost: ₱ 9,144,409.63/ Lane-km CW2- Construction of Drainage Structure along Road: 88.55 Ln.m.
Unit Cost: ₱ 124,132.36/ Ln.m.
EAO: ₱ 989,030.00
Allocation: ₱ 28,258,000.00 |
October 16, 2024 |
FY 2024 |
|
300204101062000 |
June 18, 2024 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 300204101062000
Project ID: P00832825MN
Convergence and Special Support Program (CSSP) - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
Road in Brgy. Silal, Payao, connecting Barangay Silal and Provincial Road and National Highway Road in Support to Rubber and Coal Industries, Zamboanga Sibugay
CW1- Construction of Concret Road: 2.220 Lane-km
Unit Cost: ₱ 19,066,950.45/ Lane-km CW2- Road Safety/ Roadway Lighting: 44 number of units
Unit Cost: ₱ 151,622.05/ number of units
EAO: ₱ 1,000,000.00
Allocation: ₱ 50,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300203102689000 |
June 13, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300203102689000
Project ID: P00832874MN
Convergence and Special Support Program (CSSP) - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations - (Tourism Road Infrastructure Program - TRIP)
Construction of Access Road leading to Nancy Falls, La Paz, Zamboanga City CW1- Construction of Concret Road: 0.494 Lane-km
Unit Cost: ₱ 20,318,750.59/ Lane-km CW2- Construction of Road Slope Protection Structure: 1,473.00 sq.m.
Unit Cost: ₱ 6,288.21/ sq.m.
EAO: ₱ 700,000.00
Allocation: ₱ 20,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300215104992000 |
June 27, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300215104992000
Project ID: P00834963MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Concrete Road at Camp Abendan PRO9, Barangay Mercedes, Zamboanga City
CW1 - Construction of Concrete Road: 0.89 Lane Km
Unit Cost: ₱ 11,663,368.60/ Lane Km CW2- Construction of Drainage Structure along Road: 746.00 Ln.m.
Unit Cost: ₱ 7,104.02/ Ln.m.
EAO: ₱ 320,000.00
Allocation: ₱ 16,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300215104999000 |
June 11, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300215104999000
Project ID: P00834970MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Rehabilitation/ Reconstruction of Road at Zone 3B, Brgy. Lumbangan, Zamboanga City
CW1 - Reconstruction to Concrete Pavement: 1.04 Lane Km
Unit Cost: ₱ 9,423,076.92/ Lane Km
EAO: ₱ 200,000.00
Allocation: ₱ 10,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300215105000000 |
June 27, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300215105000000
Project ID: P00834971MN
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Concrete Road at Barangay Manicahan, Zamboanga City
CW1 - Construction of Concrete Road: 0.72 Lane Km
Unit Cost: ₱ 8,877,007.44/ Lane Km CW2- Construction of Slope Protection Structure: 478.88 sq.m.
Unit Cost: ₱ 7,117.79/ sq.m.
EAO: ₱ 200,000.00
Allocation: ₱ 10,000,000.00 |
October 16, 2024 |
FY 2024 |
|
300221106669000 |
June 27, 2024 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 300221106669000 Project ID: P00837085MN Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Concrete Road at Sitio Camp Pilar, Barangay Curuan, Zamboanga City
CW1 - Construction of Concrete Road: 1.85 Lane-km
Unit Cost: ₱ 8,027,027.027/ Lane-km
EAO: ₱ 150,000.00
Allocation: ₱ 15,000,000.00 |
October 15, 2024 |
FY 2024 |
|
310106101060000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 310106101060000
Project ID: P00801258MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
Bato-Bato-Tarawakan Rd - Chainage 0000 - Chainage 3780, Chainage 805.68 - Chainage 1680
CW1- Rehabilitation of Paved Road: 7.56 Lane-km
Unit Cost: ₱ 13,366,153.68/ Lane-km CW2- Road Widening: 1.75 Lane-km Unit Cost: ₱ 23,800,716.11/ Lane-km
EAO: ₱ 5,175,625.00
Allocation: ₱ 147,875,000.00 |
October 15, 2024 |
FY 2024 |
|
310105101053000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 310105101053000
Project ID: P00801261MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Jolo-Taglibi-Tiptipon Rd - Chainage 7000 - Chainage 7610
CW1- Rehabilitation of Paved Road: 1.220 Lane-km
Unit Cost: ₱ 19,774,590.16/ Lane-km
EAO: ₱ 875,000.00
Allocation: ₱ 25,000,000.00 |
October 15, 2024 |
FY 2024 |
|
310105101051000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 310105101051000
Project ID: P00801262MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Jolo-Indanan-Parang-Silangkan Rd - Chainage 11660 - Chainage 12740
CW1- Rehabilitation of Paved Road: 2.160 Lane-km
Unit Cost: ₱ 22,337,962.96/ Lane-km
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
October 15, 2024 |
FY 2024 |
|
310105101047000 |
April 4, 2024 |
Region IX |
Regional Office IX |
UACS No. 310105101047000
Project ID: P00801264MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Jolo Port-Bud Daho-Romadier Rd - Chainage 10450 - Chainage 12450
CW1- Rehabilitation of Paved Road: 4.00 Lane-km
Unit Cost: ₱ 15,269,787.21/ Lane-km CW2- Road Widening: 3.27 Lane-km Unit Cost: ₱ 16,734,205.24
EAO: ₱ 4,200,000.00
Allocation: ₱ 120,000,000.00 |
October 15, 2024 |
FY 2024 |
|
300221104832000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104832000
Project ID: P00833304MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities Construction of Road, Barangay Ipil, Maimbung, Sulu
CW1- Construction of Concrete Road: 1.460 Lane-km
Unit Cost: ₱ 23,732,876.71/ Lane-km
EAO: ₱ 350,000.00
Allocation: ₱ 35,000,000.00 |
October 15, 2024 |
FY 2024 |
|
300221104849000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104849000
Project ID: P00833317MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Road, Siratang-Subah Mamah, Languyan, Tawi-Tawi
CW1- Construction of Concrete Road: 1.20 Lane-km
Unit Cost: ₱ 28,875,000.00/ Lane-km
EAO: ₱ 350,000.00
Allocation: ₱ 35,000,000.00 |
October 15, 2024 |
FY 2024 |
|
300221104850000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300221104850000
Project ID: P00833318MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Road, Subah Mamah, Lower Siluan Section, Languyan, Tawi-Tawi
CW1- Construction of Concrete Road: 1.525 Lane-km
Unit Cost: ₱ 23,948,431.38/ Lane-km
EAO: ₱ 500,000.00 Excess: ₱ 1,250,000.00
Allocation: ₱ 50,000,000.00 |
October 15, 2024 |
FY 2024 |
|
300215103997000 |
April 17, 2024 |
Region IX |
Regional Office IX |
UACS No. 300215103997000
Project ID: P00834831MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Old Luna Logging Road (Phase 1), Barangay Marang-Marang, Languyan, Tawi-Tawi
CW1- Construction of Concrete Road: 1.720 Lane-km
Unit Cost: ₱ 28,052,325.58/ Lane-km
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
October 15, 2024 |
FY 2024 |
|
300215104003000 |
June 11, 2024 |
Region IX |
Regional Office IX |
UACS No. 300215104003000
Project ID: P00834837MN
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities
Rehabilitation of Sitio Mumang to Sitio Igangan Road Km. 0+000-km. 0+362 Brgy. Tanduh Bagua, Patikul
CW1- Rehabilitation of Paved Road: 0.724 Lane-km
Unit Cost: ₱ 13,328,729.28/ Lane-km
EAO: ₱ 350,000.00
Allocation: ₱ 10,000,000.00 |
October 15, 2024 |
FY 2024 |
WIN4E03554 |
310201101308000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 310201101308000
Project ID: P00800039MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Primary Roads
Pagadian City-Zamboanga City Rd - K1700 + 291.66 - K1702 + 950.59, K1717 + 917.74 - K1718 + 160.00
CW1- Road Widening: 5.802 Lane-km
Unit Cost: ₱ 29,037,226.75/ Lane-km CW2- ROW Acquisition: 500.00 sq.m. Unit Cost: ₱ 500.00/ sq.m.
EAO: ₱ 6,475,000.00 Excess: ₱ 51,010.37
Allocation: ₱ 185,000,000.00 |
October 15, 2024 |
FY 2024 |
WIN4E03545 |
310201101312000 |
June 18, 2024 |
Region IX |
Regional Office IX |
UACS No. 310201101312000
Project ID: P00800041MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1802+127 - K1803+000, K1813+847.37 - K1815+140
CW1- Road Widening: 4.33 Lane-km
Unit Cost: ₱ 23,064,982.68/ Lane-km CW2- ROW Acquisition: 449.00 sq.m. Unit Cost: ₱ 11,135.86/ sq.m.
EAO: ₱ 3,803,625.00 Excess: ₱ 84,603.24
Allocation: ₱ 108,675,000.00 |
October 15, 2024 |
FY 2024 |
WIN4E036000 |
310204101586000 |
June 28, 2024 |
Region IX |
Regional Office IX |
UACS No. 310204101586000
Project ID: P00800805MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of By-Pass and Diversion Roads
NRJ Biasong - Minaog Bypass Road, Zamboanga del Norte
CW1- Construction of Concrete Bridge: 1,445.31 sq.m.
Unit Cost: ₱ 26,464.91/ sq.m. ROW Acquisition: 819.00 sq.m. Unit Cost: ₱ 12,210.01/ sq.m.
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
October 15, 2024 |
FY 2024 |
WIN4XW00129 |
310204102632000 |
June 25, 2024 |
Region IX |
Regional Office IX |
UACS No. 310204102632000
Project ID: P00800807MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of By-Pass and Diversion Roads
Labangan-Pagadian City-Dumalinao By-Pass Road, Package 1, Zamboanga del Sur
CW1- Construction of Concrete Road: 2.00 Lane-Km
Unit Cost: ₱ 19,718,331.75/ Lane-Km CW2- Construction of Concrete Bridge: 294.786 sq.m.
Unit Cost: ₱ 160,419.10/ sq.m. CW3- Construction of Concrete Bridge: 294.786 sq.m.
Unit Cost: ₱ 195,647.11/ sq.m. ROW Acquisition: 665.60 sq.m. Unit Cost: ₱ 15,024.04/ sq.m.
EAO: ₱ 5,600,000.00
Allocation: ₱ 160,000,000.00 |
October 15, 2024 |
FY 2024 |
WIN4E03553 |
310201101315000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 310201101315000
Project ID: P00802654MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Primary Roads
Pagadian City-Zamboanga City Rd - K1900+640 - K1901+460, K1902+269.99 - K1902+314.98, K1902+346.09 - K1902+422.66
CW1- Road Widening: 1.883 Lane-km
Unit Cost: ₱ 26,576,352.81/ Lane-km ROW Acquisition: 10,528.00 sq.m. Unit Cost: ₱ 284.95/ sq.m.
EAO: ₱ 1,925,000.00 Excess: ₱ 31,727.64
Allocation: ₱ 55,000,000.00 |
October 15, 2024 |
FY 2024 |
WIN4E03567 |
320101111307000 |
May 23, 2024 |
Region IX |
Regional Office IX |
UACS No. 320101111307000
Project ID: P00820888MN
OO2: Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems | Construction of Flood Control Structure along Puliran River, Puliran Br. Section Package 1, Sibuco, Zamboanga del Norte CW1- Construction of Flood Mitigation Structure: 520.00 Ln.m.
Unit Cost: ₱ 315,114.65/ Ln.m.
EAO:₱ 5,950,000.00 Excess: ₱ 190,382.52
Allocation: ₱ 170,000,000.00 |