Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
August 12, 2025 2025 WIN5XY00577 SR2025-03-008365 April 21, 2025 Region IV-A Regional Office IV-A
UACS: 310204103002000
Project ID: P00900664LZ
Amount: ₱150,000,000.00

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of By-Pass and Diversion Roads

Change in Physical Target and Scope of Work

Original:
Construction of Concrete Road - 15.00 Lane km

Approved Modification:
Construction of Gravel Road - 0.666 Lane km
Construction of Road Slope Protection Structure - 1260 square meters
August 12, 2025 2025 P00909494MN SR2025-02-001515 February 3, 2025 Region XII Regional Office XII
Contract ID: 25M00109
UACS: 310201101636000

OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening - Primary Roads

Project Name:
From: Maharlika Highway( Marbel-Allah Valley-Cotabato Rd) - K1822 + (-910) - K1822 + (-906), K1822 + (-878.50) - K1822 + 090, K1822 + 111 - K1826 + 704, K1826 + 726.80 - K1828 + 669

To: Maharlika Highway (Marbel-Allah Valley-Cotabato Rd) - K1821+160 - K1821 + 854, K1822 + (-292) - K1822 + 000, K1822 + 000 - K1823 + 791, K1822 + 070 - K1823 + 795, K1826 + 905.5 - K1827 + 000, K1827 + 069 + K1827 + 240, K1829 + 090 - K1829 + 470, K1830 + 241 - K1831 + 000, K1831 + 489 - K1831 + 530, K1836 + 066 - K1936 + 189, K1837 + 829 - K1837 + 928, K1843 + 998.17 - K1844 + 056.290, K1844 + 056.920 - K1844 + 112.12, K1844 + 112.12 - K1844 + 641.330

Type of Work/ Physical Target:
From: CW 1- Road Widening : 21.076 Lane km
To: CW 1- Road Widening: 5.537 Lane km, CW 2 – Rehabilitation of Paved Road: 5.1945 Lane km



August 12, 2025 2025 P00920114MN SR2025-02-001941 February 3, 2025 Region XII Regional Office XII
Contract ID:
UACS: 320101113456000

OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

Project Name: Construction of Riverbank Protection (Phase II), Datu Piang, Maguindanao
Type of Work: CW1-Construction of Flood Mitigation Structure
Physical target:
From: 317.619 Lineal meters
To: 245 lineal meters

August 12, 2025 2025 P00909493MN SR2025-02-001495 February 3, 2025 Region XII Regional Office XII
UACS No. 310201101635000


OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening - Primary Roads


Project Name:
From: Maharlika Highway( Cotabato-Lanao Rd) - K1867 + 445 - K1872 + 366, K1873 + 263 - K1876 + 207, K1876 + 223.22 - K1877 + 404, K1877 + 441.70 - K1879 + 000, K1879 + 425 - K1881 + 150
To: Maharlika Highway (Cotabato-Lanao Rd) - K1888 + 080 - K1892 + 847, K1893 + 527 - K1893 + 592.8, K1893 + 592.8 - K1894 + 124

Type of Work/ Physical Target:
From: CW1- Road Widening: 40.800 Lane km
To: CW1- Road Widening: 10.6614 Lane km
August 12, 2025 2025 P00935701MN SR2025-02-002169 February 3, 2025 Region XII Regional Office XII
Contract ID:
UACS No. 300221107419000

Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities


Project Name:
Construction of Road, Barangay Gang, Sultan Kudarat, Maguindanao del Norte
Type of Work: CW1- Construction of Concrete Road

Physical target:
From: 3.879 Lane km
To: 2.000 Lane km
August 12, 2025 2025 WIN5XY00539 SR2025-02-000365 February 1, 2025 Region IV-A Batangas 2nd District Engineering Office
UACS: 310102102025000
Project ID: P00915430LZ
Amount: ₱100,000,000.00


ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads

Change in Station Limits and Physical Target

Original:
Batangas-Lobo Rd - K0133 + 150 - K0135+000
Preventive Maintenance - 7.452 Lane Km

Approved Modification:
Batangas-Lobo Rd - K0133 + 684 - K0135+000
Preventive Maintenance - 5.316 Lane Km
August 12, 2025 2025 WIN5XY00499 SR2025-02-000399 February 1, 2025 Region IV-A Batangas 2nd District Engineering Office
UACS: 310102102063000
Project ID: P00915432LZ
Amount: ₱100,000,000.00


ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads

Change in Station Limits and Physical Target

Original:
Batangas-Tabangao-Lobo Rd - K0123 + 000 - K0125 + 600
Preventive Maintenance - 6.516 Lane Km

Approved Modification:
Batangas-Tabangao-Lobo Rd - K0123 + 000 - K0124 + 665
Preventive Maintenance - 5.232 Lane Km
August 12, 2025 2025 WIN5XY00540 SR2025-02-000407 February 1, 2025 Region IV-A Batangas 2nd District Engineering Office
UACS: 310102102064000
Project ID: P00915433LZ
Amount: ₱100,000,000.00

Change in Station Limits and Physical Target

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads

Original:
Batangas-Tabangao-Lobo Rd - K0126 + 600 - K0129 + 000, K0140 + 176 - K0141 + 455

Approved Modification:
Batangas-Tabangao-Lobo Rd - K0126 + 800 - K0129 + 000, K0140 + 176 - K0141 + 400
August 12, 2025 2025 WIN5XY00540 SR2025-05-015655 May 10, 2025 Region IV-A Batangas 2nd District Engineering Office
UACS: 300221108114000
Project ID: P00949206LZ
Amount: ₱10,000,000.00

CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Basic Infrastruture Program (BIP)
Access Roads and/or Bridges from the National Roads leading to Major/ Strategic Public Buildings/ Facilities


Change in Project Description

FROM:
Concreting of Road Sitio Papaya Centro-Malapad na at Brgy Bulacan, Mabini, Batangas

TO:
Concreting of Road Sitio Payapa Centro-Mapalad na at Brgy Bulacan, Mabini, Batangas
August 11, 2025 2025 310101101615000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation - Preventive Maintenance - Primary Roads - Maharlika Highway - K0211 + 000 - K0211 + 520, K0212 + 625 - K0213 + 168, K0218 + 138 - K0218 + 758, K0218 + 758 - K0218 + 810, K0218 + 810 - K0218 + 960, K0218 + 960 - K0219 + 000, K0219 + 000 - K0219 + 173

TO:

Asset Preservation - Preventive Maintenance - Primary Roads - Maharlika Highway - K0211 + 000 - K0211 + 520, K0212 + 625 - K0213 + 168, K0218 + 138 - K0218 + 758, K0218 + 758 - K0218 + 810, K0218 + 810 - K0218 + 960, K0218 + 960 - K0219 + 000
August 11, 2025 2025 310101101616000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation - Preventive Maintenance - Primary Roads - Maharlika Highway - K0287 + 500 - K0288 + 000, K0291 + 000 - K0291 + 900

TO:

Asset Preservation - Preventive Maintenance - Primary Roads - Maharlika Highway - K0287 + 500 - K0288 + 000, K0291 + 000 - K0291 + 789
August 11, 2025 2025 320101112665000 FY2025 GAA January 2, 2025 Region II Isabela 4th District Engineering Office
FROM:

Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Sinalugan Flood Control Drainage Structure Sta. 0+000 - Sta. 1+620, San Guillermo, Isabela

TO:

Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Sinalugan Flood Control Drainage Structure Sta. 0+000 - Sta. 0+620, San Guillermo, Isabela
August 11, 2025 FY 2025 310101101757000 May 26, 2025 Region IX Regional Office IX
UACS No. 310101101757000
Project ID: P00909581MN

OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Maharlika Highway (Lanao-Pagadian-Zamboanga City Rd) - K1813+842 - K1849+000 - K1850+780
CW1- Preventive Maintenance of Road: Asphalt Overlay: 1.56 Lane-km
Unit Cost: ₱ 16,087,257.64/ Lane-km CW2- Preventive Maintenance of Road/ Concrete Reblocking: 0.98112 Lane-km Unit Cost: ₱ 8,632,453.80/ Lane-Km
EAO: ₱ 1,217,405.00
Allocation: ₱ 34,783,000.00
August 11, 2025 FY 2025 310101101751000 June 20, 2025 Region IX Regional Office IX
UACS No. 310101101751000
Project ID: P00909573MN

OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Maharlika Highway (Pagadian-Zamboanga City Rd) - K1665+500 - K1666+804, K1667+516 - K1667+623
CW1- Preventive Maintenance of Road: Asphalt Overlay: 6.644 Lane-km
Unit Cost: ₱ 11,183,774.83/ Lane-km
EAO: ₱ 2,695,000.00
Allocation: ₱ 77,000,000.00
August 11, 2025 FY 2025 WIN5E0373 310201101578000 April 23, 2025 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310201101578000
Project ID: P00900587MN

OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Primary Roads
Jct Aurora-Monte Alegre-Jct Labangan Rd - K1650+939 - K1652+000

CW1- Road Widening: 2.122 Lane-Km
Unit Cost: ₱ 14,776,635.25/ Lane-Km CW2- Construction of Road Slope Protection Structure: 1,340.78 sq.m.
Unit Cost: ₱ 4,806.143/ sq.m. ROW: 10,610.00 sq.m.
EAO: ₱ 1,400,000.00
Allocation: ₱ 40,000,000.00
August 11, 2025 FY 2025 310107100798000 April 23, 2025 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310107100798000
Project ID: P00900570MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Jct. Aurora - Ozamis City Rd - K1631+100 - K1631+140, K1631+170 - K1631+210, K1631+320 - K1631+456

CW1- Construction of Road Slope Protection Structure: 3,190.36 sq.m.
Unit Cost: ₱ 9,215.261/ sq.m.
EAO: ₱ 600,000.00
Allocation: ₱ 30,000,000.00
August 11, 2025 FY 2025 WIN5E03786 310203100912000 April 23, 2025 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310203100912000
Project ID: P00900574MN

OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Tertiary Roads
Jct Switch-Jct Monte Alegre Rd - K1647+500 - K1648+588

CW1- Road Widening: 2.18 Lane-Km
Unit Cost: ₱ 22,619,136.70/ Lane-Km CW2- Construction of Road Slope Protection Structure: 9,720.00 sq.m.
Unit Cost: ₱ 1,246.428/ sq.m. ROW: 10,900.00 sq.m.
EAO: ₱ 2,275,000.00
Allocation: ₱ 65,000,000.00
August 11, 2025 FY 2025 310107100797000 April 23, 2025 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310107100797000
Project ID: P00909022MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1638+800 - K1638+862.86, K1640+100 - K1640+160, K1642+118 - K1642+180

CW1- Construction of Road Slope Protection Structure: 2,155.55 sq.m.
Unit Cost: ₱ 10,992.294/ sq.m.
EAO: ₱ 483,560.00
Allocation: ₱ 24,178,000.00
August 11, 2025 FY 2025 WIN5E03749 310201101579000 April 23, 2025 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310201101579000
Project ID: P00900573MN

OO1: Ensure Safe and Reliable National Road System – Network Development - Road Widening - Primary Roads
Jct Switch-Jct Monte Alegre-Jct Labangan Rd - K1655+187 - K1655+975

CW1- Road Widening: 1.576 Lane-Km
Unit Cost: ₱ 14,910,156.09/ Lane-Km CW2- Construction of Road Slope Protection Structure: 3,570.00 sq.m.
Unit Cost: ₱ 4,230.138/ sq.m.
EAO: ₱ 1,400,000.00
Allocation: ₱ 40,000,000.00
August 11, 2025 FY 2025 300221108888000 May 5, 2025 Region IX Zamboanga del Sur 2nd District Engineering Office
UACS No. 300221108888000
Project ID: P00938380MN

Convergence and Special Support Program (CSSP) – Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Improvement of MECoPark to Purok Pinadayag, Mecolong to Baga Barangay Road, Dumalinao, Zamboanga del Sur
CW1- Rehabilitation of Paved Road: 1.508 Lane-Km
Unit Cost: ₱ 6,564,986.74/ Lane-km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00
August 11, 2025 FY 2025 300221108889000 May 5, 2025 Region IX Zamboanga del Sur 2nd District Engineering Office
UACS No. 300221108889000
Project ID: P00938381MN

Convergence and Special Support Program (CSSP) – Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Rehabilitation of ARCP 2 Junction National Highway of Barangay Maruing to Barangay Linok Madalum, Lapuyan, Zamboanga del Sur
CW1- Rehabilitation of Paved Road: 0.754 Lane-Km
Unit Cost: ₱ 6,564,986.74/ Lane-km
EAO: ₱ 50,000.00
Allocation: ₱ 5,000,000.00
August 11, 2025 2025 WIN5XY00588 GAA 2025 January 31, 2025 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

AS PER GAA/ORIGINAL:

Calbayog - Catarman Rd - K0792 + 148 - K0792 + 230, K0793 + 073 - K0793 + 153, K0793 + 378 - K0793 + 400

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 8.024240 M
Structure: 428.00 Square meters

ROW-ROW Acquisition: 428.00 Square meters P 0.599760 M

EAO P 0.176000 M

Total P 8.800 M

AS MODIFIED:

Calbayog - Catarman Rd - K0792 + 148 - K0792 + 230, K0792 + 378 - K0792 + 400, K0793 + 073 - K0793 + 153

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 5.83626747 M
Structure: 428.00 Square meters

CW2-Road Widening: 0.226 Lane Km P 2.18773253 M

ROW-ROW Acquisition: 106.97 Square meters P 0.600000M

EAO P 0.176000 M

Total P 8.800 M

August 11, 2025 2025 SR2025-07-019287 July 7, 2025 Cordillera Administrative Region CAR - Regional Office
"Project ID: P00947410LZ
UACS: 300215105256000

FROM:
Project Name:
Construction of Palsuguan Bridge including approaches, Lagayan, Abra
Type of Work:
CW1 - Construction of Bridge
Physical Target:
CW1 - 2249.818 Square meters
Allocation:
Php 300,000,000

TO:
Project Name:
Construction of Palsuguan Bridge including approaches, Lagayan, Abra
Type of Work:
CW1 - Construction of Steel Bridge
Physical Target:
CW1 - 2681.69 Square meters
Allocation:
Php 300,000,000"
August 8, 2025 FY 2025 310302100569000 June 20, 2025 Region IX Regional Office IX
UACS No. 310302100569000
Project ID: P00909928MN

OO1: Ensure Safe and Reliable National Road System - Bridges - Replacement of Permanent Weak Bridges
Bayao Br. (B01201MN) along Maharlika Highway (Lanao-Pagadian-Zamboanga City Rd)

CW1- Replacement of Bridge: 294.79 sq.m.
Unit Cost: ₱ 98,205.50/ sq.m.
EAO: ₱ 1,050,000.00
Allocation: ₱ 30,000,000.00
August 8, 2025 2025 WIN5XY00583 FY2025 GAA December 20, 2024 Region III Regional Office III
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Primary Roads

Maharlika Highway - K0037+000 - K0037+242, K0037+242 - K0037+540
August 8, 2025 2025 WIN5XY00580 GAA 2025 January 31, 2025 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

AS PER GAA/ORIGINAL:

Calbayog-Catarman Rd - K0786 + 746 - K0786 + 935, K0792 + 137 - K0792 + 307, K0793 + 407 - K0793 + 462, K0793 + 616 - K0794 + 818

Physical Target: Allocation:

CW1-Road Widening: 3.104 Lane Km P 34.857620 M

EAO P 0.711380 M

Total P 35.569 M

AS MODIFIED:

Calbayog-Catarman Rd - K0786 + 364 - K0786 + 927

Physical Target: Allocation:

CW1-Road Widening: 0.727 Lane Km P 20.63947015 M

CW2-Construction of Road Slope Protection P 10.83814985 M
Structure: 1,173.50 Square meters

ROW-ROW Acquisition: 1,140.53 Square meters P 3.380000 M

EAO P 0.711380 M

Total P 35.569 M
August 8, 2025 FY 2025 WIN5E03767 310108102181000 May 5, 2025 Region IX Zamboanga del Norte 2nd District Engineering Office
UACS No. 310108102181000
Project ID: P00909010MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Sindangan-Siayan-Dumingag-Mahayag Rd (Sindangan-Siayan Sect) - K1931+770 - K1931+820, K1932+710 - K1932+720, K1951+514 - K1951+520

CW1- Rehabilitation/ Major Repair of Road Slope Protection Structure: 609.38 sq.m.
Unit Cost: ₱ 12,865.54/ sq.m.
EAO: ₱ 160,000.00
Allocation: ₱ 8,000,000.00
August 8, 2025 FY 2025 310109101767000 May 5, 2025 Region IX Zamboanga del Norte 2nd District Engineering Office
UACS No. 310109101767000
Project ID: P00909014MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Sindangan-Bayog-Lakewood Rd - K1930+320 - K1930+390, K1933+035 - K1933+070

CW1- Construction of Road Slope Protection Structure: 1,152.48 sq.m.
Unit Cost: ₱ 12,755.10/ sq.m.
EAO: ₱ 300,000.00
Allocation: ₱ 15,000,000.00
August 8, 2025 FY 2025 WIN5E03765 310110100634000 April 29, 2025 Region IX Zamboanga del Norte 2nd District Engineering Office
UACS No. 310110100634000
Project ID: P00909006MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Cpnstruction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
Dipolog - Sindangan - Liloy Rd - K1892+010.90 - K1892+211

CW1- Construction of Drainage Structure along Road: 200.10 ln.m.
Unit Cost: ₱ 24,487.76/ ln.m.
EAO: ₱ 100,000.00
Allocation: ₱ 5,000,000.00
August 8, 2025 FY 2025 WIN5E03764 310108102180000 April 29, 2025 Region IX Zamboanga del Norte 2nd District Engineering Office
UACS No. 310108102180000
Project ID: P00909009MN

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Sindangan-Siayan-Dumingag-Mahayag Rd (Sindangan-Siayan Sect) - K1948+860 - K1948+890, K1951+420 - K1951+430, K1951+460 - K1951+514

CW1- Rehabilitation/ Major Repair of Road Slope Protection Structure: 814.36 sq.m.
Unit Cost: ₱ 12,033.99/ sq.m.
EAO: ₱ 200,000.00
Allocation: ₱ 10,000,000.00
August 7, 2025 2025 WIN5XY00579 SR2025-02-002652 February 3, 2025 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Network Development Program - Road Widening - Primary Roads

AS PER GAA/ORIGINAL:

Maharlika Highway (Sn Isidro-Sn Juanico Br) - K0741 + 820 - K0741 + 913, K0741 + 914 - K0742 + 012

Physical Target: Allocation:

CW1-Road Widening: 0.386 Lane Km P 4.268195 M

EAO P 0.154805 M

Total P 4.423 M

AS MODIFIED:

Maharlika Highway (Sn Isidro-Sn Juanico Br) - K0768 + 862 - K0768 + 998

Physical Target: Allocation:

CW1-Road Widening: 0.272 Lane Km P 4.268195 M

EAO P 0.154805 M

Total P 4.423 M
August 7, 2025 2025 WIN5XY00578 SR2025-02-002623 February 3, 2025 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Network Development Program - Road Widening - Primary Roads


AS PER GAA/ORIGINAL:

Maharlika Highway (Sn Isidro-Sn Juanico Br) - K0716 + 789 - K0716 + 985, K0720 + 386 - K0720 + 485, K0720 + 672 - K0720 + 710, K0720 + 721 - K0720 + 732, K0721 + 158 - K0721 + 181, K0721 + 287 - K0721 + 377, K0721 + 655 - K0721 + 737, K0729 + 282 - K0729 + 437, K0730 + 056 - K0730 + 361, K0730 + 468 - K0730 + 509, K0730 + 584 - K0730 + 742, K0730 + 762 - K0730 + 796, K0730 + 809 - K0730 + 913, K0730 + 935 - K0731 + 521, K0731 + 592 - K0731 + 619, K0731 + 842 - K0731 + 872, K0731 + 906 - K0732 + 090, K0732 + 122 - K0732 + 249, K0732 + 669 - K0732 + 710, K0732 + 711 - K0732 + 780, K0734 + 000 - K0734 + 189, K0734 + 303 - K0734 + 312, K0734 + 532 - K0734 + 563, K0734 + 573.03 - K0734 + 578, K0734 + 949 - K0734 + 959, K0735 + 101 - K0735 + 164, K0735 + 526 - K0735 + 684, K0735 + 853 - K0736 + 000, K0741 + 576 - K0741 + 580, K0741 + 596 - K0741 + 600, K0745 + 553 - K0745 + 633, K0748 + 347 - K0749 + 152, K0753 + 284 - K0753 + 288, K0753 + 326 - K0753 + 330, K0769 + 000 - K0769 + 146

Physical Target: Allocation:

CW1-Road Widening: 4.341 Lane Km P 95.172160 M

EAO P 3.451840 M

Total P 98.624 M

AS MODIFIED:

Maharlika Highway (Sn Isidro - Sn Juanico Br) - K0716 + 376 - K0716 + 428, K0716 + 941 - K0716 + 982, K0720 + 386 - K0720 + 485, K0720 + 672 - K0720 + 710, K0720 + 721 - K0720 + 732, K0721 + 158 - K0721 + 181, K0721 + 287 - K0721 + 377, K0729 + 282 - K0729 + 437, K0730 + 056 - K0730 + 361, K0730 + 468 - K0730 + 509, K0730 + 584 - K0730 + 742, K0730 + 762 - K0730 + 796, K0730 + 809 - K0730 + 913, K0730 + 935 - K0731 + 521, K0731 + 592 - K0731 + 619, K0731 + 842 - K0731 + 872, K0731 + 906 - K0732 + 090, K0732 + 122 - K0732 + 249, K0734 + 000 - K0734 + 189, K0734 + 303 - K0734 + 312, K0734 + 532 - K0734 + 563, K0734 + 949 - K0734 + 959, K0735 + 101 - K0735 + 164, K0735 + 526 - K0735 + 684, K0735 + 833 -K0736 + 000, K0741 + 576 - K0741 + 580, K0741 + 596 - K0741 + 600, K0745 + 553 - K0745 + 633, K0748 + 347 - K0749 + 152, K0753 + 284 - K0753 + 288, K0753 + 326 - K0753 + 330, K0755 + 160 - K0755 + 515

Physical Target: Allocation:

CW1-Road Widening: 4.513 Lane Km P 67.78332771 M

CW2-Construction of Road Slope Protection P 27.38883229 M
Structure: 4,908.00 Square meters

EAO P 3.451840 M

Total P 98.624 M
August 7, 2025 2025 SR2025-03-008266 March 12, 2025 Region IV-A Regional Office IV-A
OO1: Ensure Safe and Reliable National Road System - Asset reservation Program - Preventive Maintenance - Primary Roads

GAA 2025 - AIP:
Maharlika Highway - K0054 + 018 - K0054 + 105, K0055 + 000 - K0056 + 255

Approved Modification:
Maharlika Highway - K0054 + 018 - K0054 + 105, K0055 + 000 - K0056 + 000, K0056 + 255 - K0056 + 581
August 7, 2025 2025 WN5F08557 SR2025-03-008365 March 12, 2025 Region IV-A Regional Office IV-A
UACS: 310101101676000
Project ID: P00918174LZ
Amount: 81,613,000.00

OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads

GAA 2025 - AIP:
Maharlika Highway (Manila South Road) - K0036 + 150 - K0036 + 860

Approved Modification:
Maharlika Highway (Manila South Road) - K0037 + 739 - K0037 + 1036, K0038 + 447 - K0038 + 725, K0041 + 680 - K0041 + 806
August 7, 2025 2025 310104100890000 FY2025 GAA January 2, 2025 Region II Isabela 2nd District Engineering Office
FROM:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Santiago-Tuguegarao Rd - K0366 + 470 - K0367 + 364

TO:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Santiago-Tuguegarao Rd - K0372 + 105 - K0373 + 084
August 6, 2025 FY 2025 P00909120MN SR2025-03-009398 May 17, 2025 Region XII Cotabato 3rd District Engineering Office
Contract ID: 25MI0030
UACS: 310108102048000
Amount: ₱ 82,250,000

​​OO1: Ensure Safe and Reliable National Road System​ - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

Project Name:
From: ​​Bukidnon-Cotabato Rd - K1630 + 150 - K1630+ 300​
To: ​Bukidnon-Cotabato Rd - K1630 + 100 - K1630 + 300
Type of Work: ​​Construction of Road Slope Protection Structure​
Physical Target:
From: ​​2,350.00​ Square Meters
To: 5,605.69​ Square Meters
August 6, 2025 FY 2025 P00909121MN SR2025-02-000605 February 1, 2025 Region XII Cotabato 3rd District Engineering Office
Contract ID: 25MI0031
UACS: 310108102049000
Amount: ₱ 109,620,000.00

​OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

Project Name:
From: Bukidnon-Cotabato Rd - K1629 + 705 - K1629 + 905
To: ​​Bukidnon-Cotabato Rd - K1629 + 625 – K1629 + 905​
Type of Work: ​Construction of Road Slope Protection Structure
Physical Target:
From: 3,132.00 Square Meters
To: 5,740.50 Square Meters
August 6, 2025 FY 2025 P00909117MN SR2025-02-000597 February 1, 2025 Region XII Cotabato 3rd District Engineering Office
Contract ID: 25MI0056
UACS: 310108102045000
Amount: ₱ 139,500,000.00

​OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

Project Name:
From: Bukidnon-Cotabato Rd - K1612 + 944 - K1613 + 081
To: ​​Bukidnon - Cotabato Rd - K1612 + 656 - K1613 + 000​
Type of Work: ​​Construction of Road Slope Protection Structure​
Physical Target:
From: ​3,985.71 Square Meters
To: 4,000.72 Square Meters
August 6, 2025 FY 2025 P00909123MN SARO-BMB-A-25-0008278 March 11, 2025 Region XII Cotabato 3rd District Engineering Office
Contract ID: 25MI0057
UACS: 310109101782000
Amount: ₱ 31,400,000.00

​OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

Project Name:
From: ​​Kidapawan-Calunasan-Mlang Rd - K1634 + 775 - K1634 + 812​
To: ​​Kidapawan-Calunasan-Mlang Rd - K1634 + 775 - K1634 + 900​
Type of Work: Construction of Road Slope Protection Structure
Physical Target:
From: 1,256.00 Square Meters
To: 1,375.00 Square Meters
August 6, 2025 2025 FY 2025 GAA, RA 12116 December 30, 2024 Region XIII Surigao del Sur 1st District Engineering Office
UACS No. : 300221109144000
Project ID: P00938553MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Roads leading to Major/ Strategic Public Buildings/ Facilities

FROM:

Rehabilitation of Road, Brgy. San Juan, Madrid, Surigao del Sur

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 2.198 Lane Km

Allocation:
TOTAL: P 30,000,000
CW1: P 29,700,000
EAO: P 300,000

Unit Cost:
CW1: P 13,512,283.89/Lane Km

TO:

Rehabilitation of Road, Brgy. San Juan, Madrid, Surigao del Sur

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 4.329 Lane Km

Allocation:
TOTAL: P 30,000,000
CW1: P 29,700,000
EAO: P 300,000

Unit Cost:
CW1: P 6,860,706.86/Lane Km
August 6, 2025 2025 FY 2025 GAA, RA 12116 December 30, 2024 Region XIII Surigao del Sur 1st District Engineering Office
UACS No. : 300214102174000
Project ID: P00935189MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239

FROM:

Construction of Pedestrian Overpass at Surigao-Davao Coastal Rd - K1302 + 641

Type of Work:
CW1- Road Safety: Pedestrian Overpass

Physical Target:
CW1- 1.0 Number of Pedestrian Overpass

Allocation:
TOTAL: P 22,795,000
CW1: P 22,339,100
EAO: P 455,900

Unit Cost:
CW1: P 22,339,100/ Number of Pedestrian Overpass

TO:

Construction of Pedestrian Overpass at Surigao-Davao Coastal Rd - K1302 + 641 and K1303 + 014

Type of Work:
CW1- Road Safety: Pedestrian Overpass

Physical Target:
CW1- 2.0 Number of Pedestrian Overpass

Allocation:
TOTAL: P 22,795,000
CW1: P 22,339,100
EAO: P 455,900

Unit Cost:
CW1: P 11,169,550/ Number of Pedestrian Overpass
August 6, 2025 2025 FY2025 GAA December 20, 2024 Region III Pampanga 1st District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Jose Abad Santos Ave (JASA) - K0085+088.50 - K0086+000, K0086+592.30 - K0087+464.70
August 6, 2025 FY 2025 GAA WIN5E03864 FY 2025 GAA RA 12116 January 1, 2025 Region XI Regional Office XI
WIN5E03864 (Regional Office XI_13)
UACS No. 310204103232000
Project ID: P00910153MN

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Jct. Daang Maharlika-Eliong-Jct. Acacia Road, Davao City
Physical Target:
CW1: 1,042.00 sq. m. (Construction of Road Slope Protection Structure)
CW2: 4,573.00 sq. m. (Construction of Drainage Structure along Road)
CW3: 0.508 lane km (Reconstruction to Concrete Pavement)
ROW: 414.80 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 19,182,270.00 (Construction of Road Slope Protection Structure)
CW2: P 17,792,670.00 (Construction of Drainage Structure along Road)
CW3: P 6,450,060.00 (Reconstruction to Concrete Pavement)
ROW: P 4,825,000.00 (ROW Acquisition)
EAO: P 1,750,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Jct. Daang Maharlika-Eliong-Jct. Acacia Road, Davao City
Physical Target:
CW1: 1,028.20 sq. m. (Construction of Road Slope Protection Structure)
CW2: 4,071.347 sq. m. (Construction of Drainage Structure along Road)
CW3: 0.313 lane km (Reconstruction to Concrete Pavement)
ROW: 329.40 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 19,851,128.00 (Construction of Road Slope Protection Structure)
CW2: P 18,854,122.00 (Construction of Drainage Structure along Road)
CW3: P 5,684,750.00 (Reconstruction to Concrete Pavement)
ROW: P 3,860,000.00 (ROW Acquisition)
EAO: P 1,750,000.00
August 6, 2025 FY 2025 GAA WIN5E03859 FY 2025 GAA RA 12116 January 1, 2025 Region XI Regional Office XI
WIN5E03859 (Regional Office XI_14)
UACS No. 310107100763000
Project ID: P00909181MN

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way - K1726 + 460 - K1726 + 580, K1726 + 900 - K1726 + 980
Physical Target:
CW1: 3,000.00 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Road Slope Protection Structure)
EAO: P 2,100,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way - K1727 + 340 - K1727 + 480
Physical Target:
CW1: 1,303.445 sq. m. (Construction of Road Slope Protection Structure)
CW2: 0.280 lane km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 53,246,817.00 (Construction of Road Slope Protection Structure)
CW2: P 4,653,183.00 (Reconstruction to Concrete Pavement)
ROW: P 2,100,000.00 (ROW Acquisition)
EAO: P 1,750,000.00
August 6, 2025 FY 2025 GAA P00938000MN FY 2025 GAA RA 12116 January 1, 2025 Region XI Regional Office XI
P00938000MN (Regional Office XI_15)
UACS No. 300215106034000
Project ID: P00938000MN

MODIFICATION:

FROM: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Construction of Road, Barangay San Antonio to Sitio Danao, Barangay Balet, Babak District, Island Garden City of Samal, Davao del Norte
Physical Target:
CW1: 1.400 lane km (Construction of Concrete Road)
CW2: 1,400.00 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 17,954,720.00 (Construction of Concrete Road)
CW2: P 10,995,280.00 (Construction of Drainage Structure along Road)
EAO: P 1,050,000.00

TO: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Construction of Road, Barangay San Antonio to Sitio Danao, Barangay Balet, Babak District, Island Garden City of Samal, Davao del Norte
Physical Target:
CW1: 1.600 lane km (Construction of Concrete Road)
CW2: 1,220.00 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 21,309,553.00 (Construction of Concrete Road)
CW2: P 7,640,447.00 (Construction of Drainage Structure along Road)
EAO: P 1,050,000.00
August 6, 2025 FY 2025 GAA P00938036MN FY 2025 GAA RA 12116 January 1, 2025 Region XI Davao del Norte 2nd District Engineering Office
P00938036MN (Davao del Norte 2nd District Engineering Office_01)
UACS No. 300215106069000
Project ID: P00938036MN

MODIFICATION:

FROM: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Improvement of Jct. Panabo City Coastal Road to Jct. Tagum to Sto. Tomas Diversion Road, Package 2, Carmen, Davao del Norte
Physical Target:
CW1: 51,233.30 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Road Slope Protection Structure)
EAO: P 5,250,000.00

TO: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Improvement of Jct. Panabo City Coastal Road to Jct. Tagum to Sto. Tomas Diversion Road, Package 2, Carmen, Davao del Norte
Physical Target:
CW1: 44,266.67 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Road Slope Protection Structure)
EAO: P 5,250,000.00
August 6, 2025 FY 2025 GAA P00938000MN FY 2025 GAA RA 12116 January 1, 2025 Region XI Regional Office XI
P00938006MN (Regional Office XI_16)
UACS No. 300215106040000
Project ID: P00938006MN

MODIFICATION:

FROM: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Construction of Road, Barangay Tagbitan-ag to Sitio Tayapoc, Barangay Aundanao, Island Garden City of Samal, Davao del Norte
Physical Target:
CW1: 3.200 lane km (Construction of Concrete Road)
CW2: 3,200.00 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 44,024,564.00 (Construction of Concrete Road)
CW2: P 23,525,437.00 (Construction of Drainage Structure along Road)
EAO: P 2,450,000.00

TO: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major Strategic Public Buildings/Facilities
Construction of Road, Barangay Tagbitan-ag to Sitio Tayapoc, Barangay Aundanao, Island Garden City of Samal, Davao del Norte
Physical Target:
CW1: 2.730 lane km (Construction of Concrete Road)
CW2: 3,280.00 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 43,608,080.00 (Construction of Concrete Road)
CW2: P 23,941,920.00 (Construction of Drainage Structure along Road)
EAO: P 2,450,000.00
August 5, 2025 2025 GAA FY 2025 January 31, 2025 Region VIII Samar 1st District Engineering Office
Organizational Outcome 1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads

AS PER GAA/ORIGINAL:

Gomez St - (S00079SM) Chainage 055 - Chainage 192

Physical Target: Allocation:
CW1- Rehabilitation of Paved Road: P 3.580920 M
0.274 Lane Km
EAO P .73080 M
Total P 3.654 M

AS MODIFIED:

Gomez St - (S00079SM) Chainage 051 - Chainage 188

Physical Target: Allocation:
CW1- Rehabilitation of Paved Road: P 3.580920 M
0.274 Lane Km
EAO P .73080 M
Total P 3.654 M
August 5, 2025 2025 WIN5E03865 SR2025-03-008562 March 12, 2025 Cordillera Administrative Region CAR - Regional Office
"Project ID: P00922647LZ
UACS: 320101112546000

FROM:
Project Name:
Construction of Apayao River Flood Control, Sta. 78+847 - Sta. 79 + 797 (L/S), Barangay Laco, Kabugao, Apayao
Type of Work:
CW1 - Construction of Flood Mitigation Structure
Physical Target:
CW1 - 950 Lineal meters
Allocation:
Php 100,000,000

TO:
Project Name:
Construction of Apayao River Flood Control, Sta. 78+850 - Station 79+187, Sta. 0+000 - Sta. 0+324 (L/S), Barangay Laco, Kabugao, Apayao
Type of Work:
CW1 - Construction of Flood Mitigation Structure
Physical Target:
CW1 - 655 Lineal meters
Allocation:
Php 100,000,000"
August 5, 2025 FY 2025 P00920427MN SR2025-03-009691 March 18, 2025 Region XII South Cotabato 1st District Engineering Office
Contract ID: 25MB0083
UACS: 320102107931000
Amount: ₱ 15,000,000.00

OO2: Protect Lives and Properties Against Major Floods - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Project Name: Construction of Conel CIS Protection Works of Main Canal along bank, General Santos City
Type of Work: Construction of Flood Mitigation Structure
Physical Target:
From: 196.161 Lineal meters
To: 106.00 Lineal meters
August 5, 2025 2025 WIN5E03783 GAA 2025 January 21, 2025 Cordillera Administrative Region Mountain Province 2nd District Engineering Office
"Project ID: P00922916LZ
UACS: 320101000000000

FROM:
Project Name:
Construction of Flood Control Structure, Butigue, Sta. 92+799 - Sta. 92+959, Paracelis, Mountain Province
Type of Work:
CW1 - Construction of Flood Mitigation Structure
Physical Target:
CW1 - 160 Lineal meters
Allocation:
Php 15,000,000

TO:
Project Name:
Construction of Flood Control Structure, Butigue, Sta. 95+439 - Sta. 95+599, Paracelis, Mountain Province
Type of Work:
CW1 - Construction of Flood Mitigation Structure
Physical Target:
CW1 - 160 Lineal meters
Allocation:
Php 15,000,000"
August 5, 2025 2025 P00901622MN SR2025-03-009484 March 17, 2025 Region X Regional Office X
P00901622MN
310204103123000
OO1:Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads

FROM:
Manolo Fortich - Misamis Oriental Alternate/Bypass Road, Package 15, Bukidnon
Type of Work:
CW1-Construction of Concrete Road
Physical Target:
CW1-20.00 Lane Km
Allocation:
Total: Php 200,000,000.00
CW1: Php 193,000,000.00
EAO: Php 7,000,000.00

TO:
Manolo Fortich - Misamis Oriental Alternate/Bypass Road, Package 15, Bukidnon
Type of Work:
CW1-Construction of Gravel Road
Physical Target:
CW1-10.00 Lane Km
Allocation:
Total: Php 200,000,000.00
CW1: Php 193,000,000.00
EAO: Php 7,000,000.00
August 5, 2025 2025 P00901537MN GAA2025 January 3, 2025 Region X Bukidnon 3rd District Engineering Office
P00901537MN
310103101891000

OO1: Ensure Safe and Reliable National Road System, Asset Preservation Program - Preventive Maintenance - Tertiary Roads

FROM:
Jct SH-Aglayan-Alanib-Ticalaan Road (Ticalaan-Paganan Sect) - K1503 + 200 - K5014 + 754, K1506 + 910 - K1507 + 000, K1511 + 000 - K1512 + 000

Type of Work:
CW1- Preventive Maintenance - Asphalt Overlay
Physical Target:
CW1- 10.688 Lane Km
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00

TO:
Jct SH-Aglayan-Alanib-Ticalaan Road (Ticalaan-Paganan Sect) - K1503 + 200 - K1504 + 754, K1506 + 910 - K1507 + 000, K1507 + 000 - K1508 + 000

Type of Work:
CW1- Preventive Maintenance - Asphalt Overlay
Physical Target:
CW1- 5.360 Lane Km
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
August 5, 2025 2025 P00910562MN SR2025-02-001228 February 1, 2025 Region X Regional Office X
P00910562MN
310204103131000
OO1:Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads

FROM:
Construction of Mangima-Agusan Acanyon Bypass Road, Package 3, Bukidnon
Type of Work:
CW1-Construction of Concrete Road
Physical Target:
CW1-20.00 Lane Km
Allocation:
Total: Php 200,000,000.00
CW1: Php 193,000,000.00
EAO: Php 7,000,000.00

TO:
Construction of Mangima-Agusan Canyon Bypass Road, Package 3, Bukidnon
Type of Work:
CW1-Construction of Gravel Road
Physical Target:
CW1-0.85 Lane Km
Allocation:
Total: Php 200,000,000.00
CW1: Php 193,000,000.00
EAO: Php 7,000,000.00
August 5, 2025 2025 P00901536MN GAA2025 January 3, 2025 Region X Bukidnon 3rd District Engineering Office
P00901537MN
310103101891000

OO1: Ensure Safe and Reliable National Road System, Asset Preservation Program - Preventive Maintenance - Tertiary Roads

FROM:
Jct SH-Aglayan-Alanib-Ticalaan Road (Ticalaan-Paganan Sect) - K1533 + 000 - K1534 + 461, K1535 + 000 - K1535 +731, K1536 + 000 - K1537 + 227

Type of Work:
CW1- Preventive Maintenance - Asphalt Overlay
Physical Target:
CW1- 8.556 Lane Km
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00

TO:
Jct SH-Aglayan-Alanib-Ticalaan Road (Ticalaan-Paganan Sect) - K1504+754 - K1506+910, K1508 + 000 - K1508 +364

Type of Work:
CW1- Preventive Maintenance - Asphalt Overlay
Physical Target:
CW1- 5.116 Lane Km
Allocation:
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
August 5, 2025 2025 P00910174MN SR2025-02-001458 February 3, 2025 Region X Regional Office X
P00910174MN
310204103156000
OO1:Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads

FROM:
Misamis Oriental-Bukidnon Bypass Road (PHIVIDEC-Alae), Package 7, Bukidnon
Type of Work:
CW1-Construction of Concrete Road
Physical Target:
CW1-6.058 Lane Km
Allocation:
Total: Php 50,000,000.00
CW1: Php 48,250,000.00
EAO: Php 1,750,000.00

TO:
Misamis Oriental-Bukidnon Bypass Road (PHIVIDEC-Alae), Package 7, Bukidnon
Type of Work:
CW1-Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1-3.90 Lane Km
Allocation:
Total: Php 50,000,000.00
CW1: Php 48,250,000.00
EAO: Php 1,750,000.00
August 5, 2025 2025 310203100933000 FY 2025 GAA January 2, 2025 Region II Quirino District Engineering Office
FROM:

Network Development - Road Widening - Tertiary Roads - Echague-Jones-Madella Rd (Villa Norte-Panang Sect) - K0383 + 000 - K0383 + 107, K0385 + 109 - K0385 + 300

TO:

Network Development - Road Widening - Tertiary Roads - Echague-Jones-Maddela Rd (Villa Norte-Panang Sect) - K0383 + 000 - K0383 + 155, K0385 + 109 - K0385 + 540
August 5, 2025 2025 310104100798000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Maharlika Highway - K0346 + 694 - K0347 + 282, K0347 + 430 - K0347 + 993, K0350 + 700 - K0351 + 561, K0352 + 000 - K0352 + 338, K0352 + 534 - K0354 + 246

FROM:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads - Maharlika Highway - K0346 + 694 - K0347 + 282, K0347 + 430 - K0347 + 993, K0350 + 700 - K0351 + 561, K0352 + 000 - K0352 + 338, K0352 + 534 - K0353 + 434.50
August 5, 2025 2025 300214101445000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

CSSP: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Preventive Maintenance - Primary Roads along Maharlika Highway - K0340 + 623 - K0342 + 038, K0342 + 588 + K0342 + 764, K0342 + 794 - K0342 + 916

TO:

CSSP: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Preventive Maintenance - Primary Roads along Maharlika Highway - K0340 + 623 - K0341 + 985
August 5, 2025 2025 300214101447000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Preventive Maintenance - Primary Roads along Maharlika Highway - K0220 + 576 - K0222 + 290, K0237+ 627 - K0237 + 804, K0238 + 147 - K0238 + 420

TO:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Preventive Maintenance - Primary Roads along Maharlika Highway - K0220 + 576 - K0222 + 115.70, K0237+ 627 - K0237 + 804, K0238 + 147 - K0238 + 540
August 5, 2025 2025 300214101431000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads along Maharlika Highway - K0423 + 239 - K0423 + 356, K0459 + 243 - K0459 + 628, K0460 + 270 - K0460 + 323

TO:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads along Maharlika Highway - K0459 + 243 - K0459 + 628, K0460 + 270 - K0460 + 375
August 5, 2025 2025 P00910171MN SR2025-02-001410 February 3, 2025 Region X Regional Office X
P00910171MN
310204103153000
OO1:Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads

FROM:
Mangima-Agusan Canyon Bypass Road, Bukidnon
Type of Work:
CW1-Construction of Concrete Road
Physical Target:
CW1-4.00 Lane Km
Allocation:
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00

TO:
Mangima-Agusan Canyon Bypass Road, Bukidnon
Type of Work:
CW1-Construction of Gravel Road
Physical Target:
CW1-0.486 Lane Km
Total: Php 100,000,000.00
CW1: Php 96,500,000.00
EAO: Php 3,500,000.00
August 5, 2025 2025 310104100796000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads – Maharlika Highway - K0259 + 000 - K0260 + 024, K0265 + 530 - K0265 + 991, K0305 + 152 - K0306 + 677

TO:

Asset Preservation Program – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads – Maharlika Highway - K0259 + 000 - K0260 + 024, K0265 + 530 - K0265 + 991, K0301 + 550 - K0301 + 942.70, K0305 + 152 - K0306 + 468.50
August 5, 2025 2025 310101101618000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0382 + 000 - K0382 + 644, K0382 + 826 - K0383 + 003, K0390 + 847 - K0391 + 050

TO:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0382 + 000 - K0382 + 575, K0382 + 826 - K0383 + 003, K0390 + 830 - K0390 + 923
August 5, 2025 2025 310101101617000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0304 + 245 - K0304 + 700

TO:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0304 + 245 - K0304 + 673
August 5, 2025 2025 300214101443000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads along Maharlika Highway ( Cagayan Valley Rd) - K0461 + 489 - K0461 + 707, K0462 + (-113) - K0462 + (-43), K0469 + 780 - K0469 + 898

TO:

Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239 - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads along Maharlika Highway ( Cagayan Valley Rd) - K0461 + 322.50 - K0461 + 707, K0462 + (-113) - K0462 + (-043), K0469 + 780 - K0469 + 946.50
August 5, 2025 2025 310201101500000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Network Development Program – Road Widening - Primary Roads – Manila North Rd - K0668 + 1006 - K0669 + 000, K0675 + 367 - K0675 + 392

TO:

Network Development Program – Road Widening - Primary Roads – Manila North Rd - K0668 + 994.20 - K0668 + 1017.20
August 5, 2025 2025 310204101026000 FY2025 GAA January 2, 2025 Region II Regional Office II
Network Development Program – Construction of By-Pass and Diversion Roads - Santiago Circumferential Road, Isabela
August 5, 2025 2025 310101101613000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Jct Logac-Magapit Rd - K0705 + (-113) - K0705 + 417.5

TO:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Jct Logac-Magapit Rd - K0705 + (-113) - K0705 + 344.50
August 5, 2025 2025 310104100797000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads – Maharlika Highway (Cagayan Valley Rd) - K0515 + 910 - K0516 + 000, K0534 + 142.8 - K0534 + 483

TO:

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads – Maharlika Highway (Cagayan Valley Rd) - K0528 + 655 - K0529 + 008, K0534 + 142.8 - K0534 + 483
August 5, 2025 2025 310101101612000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway (Cagayan Valley Rd) - K0516 + 000 - K0516 + 339, K0530 + 143.1 - K0530 + 869, K0530 + 922 - K0531 + 000, K0536 + 000 - K0536 + 964.7, K0541 + 14.6 - K0541 + 533, K0548 + 000 - K0548 + 341.3, K0549 + 000 - K0549 + 940, K0550 + 094 - K0550 + 828

TO:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway (Cagayan Valley Rd) - K0541 + 000 - K0541 + 533, K0548 + 000 - K0548 + 920, K0549 + 050 - K0549 + 940, K0550 + 094 - K0550 + 605.50
August 5, 2025 2025 310101101614000 FY2025 GAA January 2, 2025 Region II Regional Office II
FROM:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0367 + 506 - K0367 + 871, K0368 + 534 - K0369 + 000, K0370 + 000 - K0370 + 105, K0371 + 574 - K0372 + 417

TO:

Asset Preservation Program – Preventive Maintenance - Primary Roads – Maharlika Highway - K0367 + 506 - K0367 + 871, K0368 + 594.40 - K0369 + 000, K0370 + 000 - K0370 + 105, K0371 + 574 - K0372 + 103.55
August 4, 2025 FY 2025 P00909496MN SR2025-02-003033 February 3, 2025 Region XII Regional Office XII
Contract ID: 25M00011
UACS: 310201101638000
Amount: ₱ 3,461,000.00

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Project Name:
From: Maharlika Highway( Digos-Makar Rd) - (S01505MN) Chainage 000 - Chainage 095, Chainage 095 - Chainage 097, Chainage 097 - Chainage 109, Chainage 130 - Chainage 201
To: Maharlika Highway( Digos-Makar Rd) - (S01505MN) - Chainage 000 - Chainage 081
Type of Work:
From: CW1 - Road Widening
To: CW1 - Road Widening, CW-2- Construction of Drainage Structure along Road
Physical Target:
From: CW1 - 0.180 Lane Km
To: CW1 - 0.243 Lane Km, CW2 - 162 Lineal Meters
August 4, 2025 FY 2025 P00909546MN SR2025-02-001097 February 1, 2025 Region XII Regional Office XII
Contract ID: 25M00163
UACS: 310104100871000
Amount: ₱ 36,448,000.00

OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads

Project Name:
From: Maharlika Highway (Marbel-Allah Valley-Cotabato Rd) - K1809 + 914 - K1810 + 1500, K1812 + 900 - K1813 + 009
To: Maharlika Highway (Marbel-Allah Valley-Cotabato Rd) - K1806+1781 - K1809+751
Type of Work: Reconstruction to Concrete Pavement
Physical Target:
From: 3.372 Lane Km
To: 3.94 Lane Km
August 4, 2025 FY 2025 GAA WIN5E03848 FY 2025 GAA RA 12116 January 1, 2025 Region XI Davao Oriental 1st District Engineering Office
WIN5E03848 (Davao Oriental 1st District Engineering Office_02)
UACS No. 310101101809000
Project ID: P00901457MN

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Surigao del Sur - Davao Oriental Coastal Rd - K1550 + 000 - K1550 + 951, K1551 + 240 - K1551 + 320,
K1552 + 000 - K1553 + 000, K1554 + 000 - K1554 + 649, K1554 + 734 - K1554 + 935,
K1555 + 260 - K1556 + 000, K1559 + K1556 + 000, K1559 + K1560 + 000
Physical Target:
CW1: 15.238 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 3,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Surigao del Sur - Davao Oriental Coastal Rd - K1552 + 000 - K1553 + 000, K1554 + 000 - K1554 + 449,
K1554 + 449 - K1554 + 935, K1555 + 260 - K1556 + 000
Physical Target:
CW1: 8.228 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 3,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
August 4, 2025 2025 WIN5E03837 FY 2025 GAA, RA 12116 December 30, 2024 Region XIII Regional Office XIII
UACS No. : 310201101652000
Project ID: P00909428MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

FROM:

Maharlika Highway (Agusan-Davao Sect) - K1257 + 373 - K1257 + 481, K1257 + 721.40 - K1257 + 779

Type of Work:
CW1- Road Widening

Physical Target:
CW1- 0.331 Lane Km

Allocation:
TOTAL: P 4,514,000
CW1: P 4,356,010
EAO: P 157,990

Unit Cost:
CW1: P 13,160,151.06/Lane Km

TO:

Maharlika Highway (Agusan - Davao sect) K1257 + 004 - K1257 + 120

Type of Work:
CW1- Road Widening
ROW- ROW Acquisition

Physical Target:
CW1- 0.232 Lane Km
ROW- 2236.8 Square meters

Allocation:
TOTAL: P 4,514,000
CW1: P 4,302,935
ROW: P 53,075
EAO: P 157,990

Unit Cost:
CW1: P 18,547,133.62/Lane Km
ROW: -
August 1, 2025 2025 WIN5E03844 SR2025-03-008698 March 12, 2025 Cordillera Administrative Region CAR - Regional Office
"Project ID: P00900585LZ
UACS: 310108101977000

FROM:
Project Name:
Mt Prov-Ilocos Sur via Tue Rd - K0388 + 500 - K0388 + 635
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 - 10,000 Square meters
Allocation:
Php 100,000,000

TO:
Project Name:
Mt Prov-Ilocos Sur via Tue Rd - K0388 + 500 - K0388 + 635
Type of Work:
CW1 - Construction of Road Slope Protection Structure
Physical Target:
CW1 - 4335 Square meters
Allocation:
Php 100,000,000"
August 1, 2025 2025 FY 2025 GAA January 1, 2025 Region IV-B Marinduque District Engineering Office
PROJECT ID NO. P00914756LZ

OO1: Ensure Safe and Reliable National Road System

From:
Asset Preservation Program - Rehabilitation / Reconstruction of Roads with Slips, Slope Collapse and Landslide - Secondary Roads - Marinduque Circumferential Road - K0015 + 891 - K0015 + 931

To:
Asset Preservation Program - Rehabilitation / Reconstruction of Roads with Slips, Slope Collapse and Landslide - Secondary Roads - Marinduque Circumferential Road - K0015 + 888 - K0015 + 929
August 1, 2025 2025 SR2025-03-008207 March 12, 2025 Region IV-B Marinduque District Engineering Office
PROJECT ID NO. P00919034LZ

OO1: Ensure Safe and Reliable National Road System

From:
Asset Preservation Program - Preventive Maintenance - Secondary Roads- Mogpog-Balanacan Port Rd - K0008 + (-147) - K0011 + 000

To:
Asset Preservation Program - Preventive Maintenance - Secondary Roads- Mogpog-Balanacan Port Rd - K0008 + (-147) - K0009 + 000, K0009 + 585 - K0010 + 228
August 1, 2025 2025 SARO-BMB-A-25-0008151 March 7, 2025 Region IV-B Marinduque District Engineering Office
PROJECT ID NO. P00919036LZ

OO1: Ensure Safe and Reliable National Road System

From:
Asset Preservation Program - Rehabilitation /Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Dr. Damian Reyes Road (Boac Side) - K0023+012 - K0023+0720

To:
Asset Preservation Program - Rehabilitation /Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Dr. Damian Reyes Road (Boac Side) - K0023+012 - K0023+072
August 1, 2025 2025 SARO-BMB-A-25-0008146 January 1, 2025 Region IV-B Mindoro Occidental District Engineering Office
PROJECT ID NO. P00915783LZ

OO1: Ensure Safe and Reliable National Road System

From:
Mindoro West Coastal Rd (Section 7) (S00121MR) – K0427+716 – K0428+000

To:
Mindoro West Coastal Rd (Section 7) (S00121MR) – K0410+957 – K0411+670
August 1, 2025
August 1, 2025 2025 SR2025-03-0007589 March 6, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919047LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa North Rd - K0085 + 100 - K0085 + 163, K0085 + 165 - K0085 + 215, K0086 + 800 - K0086 + 818, K0093 + 200 - K0096 + 250, K0095 + 930 - K0095 + 980, K0096 + 060 - K0096 + 110, K0097 + 019 - K0097 + 100, K0131 + 650 - K0131 + 655, K0138 + 300 - K0138 + 350, K0138 + 660 - K0138 + 670, K0141 + 450 - K0141 + 509, K0156 + 990 - K0157 + 000

To:
Puerto Princesa North Rd - K0085+100 - K0085+163, K0085+165 - K0085+215, K0086+800 - K0086+818, K0093+200 - K0093+250, K0095+930 - K0095+980, K0096+060 - K0096+110, K0097+019 - K0097+100, K0131+650 - K0131+655, K0138+300 - K0138+350, K0138+660 - K0138+670, K0141+450 - K0141+509, K0156+990 - K0157+000
August 1, 2025 2025 SARO-BMB-A-0008148 March 7, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919044LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa North Rd - K0115 + 063 - K0116 + 221

To:
Puerto Princesa North Road - K0115+063 - K0115+905
August 1, 2025 2025 SR2025-03-0008212 March 12, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919043LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa North Rd - K0263 + 000 - K0265 + 023

To:
Puerto Princesa North Road - K0263+000 - K0264+975
August 1, 2025 2025 SR2025-03-0008224 March 12, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919045LZ

OO1: Ensure Safe and Reliable National Road System

From:
Roxas Diversion Rd - K0134 + (-711) - K0134 + 630

To:
Roxas Diversion Rd - K0134+(-711) - K0134+264
August 1, 2025 2025 SR2025-03-0008387 March 12, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919046LZ

OO1: Ensure Safe and Reliable National Road System

From:
PPNR Jct-Taytay Poblacion Rd - K0208 + 116 - K0210 + 000

To:
PPNR Jct - Taytay Poblacion Road K0208+116 - K0209+579
August 1, 2025 2025 SR2025-03-0008585 March 12, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00915174LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa North Rd - K0149 + 000 - K0151 + 000

To:
Puerto Princesa North Rd - K0149+000 - K0150+559
August 1, 2025 2025 SARO-BMB-A-0008148 March 7, 2025 Region IV-B Palawan 1st District Engineering Office
PROJECT ID NO. P00919053LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa North Rd - K0174 + 174 -K0174 + 928, K0175 + 047 - K0175 + 596, K0175 + 756 - K0176 + 140, K0176 + 320 - K0177 + 617

To:
Puerto Princesa North Rd - K0174+174 -K0174+928, K0175+047 - K0175+596, K0175+756 - K0176+140, K0176+320 - K0176+714
August 1, 2025 2025 SR2025-03-008540 March 12, 2025 Region IV-B Palawan 2nd District Engineering Office
PROJECT ID NO. P00919056LZ

OO1: Ensure Safe and Reliable National Road System

From:
Aramaywan-Berong-Pto Princesa Road K0093 + 809 - K0094 + 164, K0096 + 040 - K0096 + 457 Quezon, Palawan

To:
Aramaywan-Berong-Pto Princesa Road K0093 + 809 - K0094 + 164, K0096 + 040 - K0096 + 437 Quezon, Palawan
August 1, 2025 2025 FY 2025 GAA January 1, 2025 Region IV-B Palawan 2nd District Engineering Office
PROJECT ID NO. P00915175LZ

OO1: Ensure Safe and Reliable National Road System

From:
Puerto Princesa South Rd - K0107 + 463 - K0108 + 960

To:
Puerto Princesa South Rd - K0107 + 983 - K0108 + 960
August 1, 2025 2025 SR2025-03-008687 March 12, 2025 Region IV-B Palawan 2nd District Engineering Office
PROJECT ID NO. P00951337LZ

OO1: Ensure Safe and Reliable National Road System

From:
Construction of Pedestrian Overpass -Puerto Princesa South Road K091 + 295

To:
Construction of Pedestrian Overpass -Puerto Princesa South Road K090 + 1075
August 1, 2025 2025 SARO-BMB-A-25-0008156 March 7, 2025 Region IV-B Romblon District Engineering Office
PROJECT ID NO. P00914774LZ

OO1: Ensure Safe and Reliable National Road System

From:
Tablas Circumferential Rd - K0127 + 760 - K0127 + 898.50, K0127 + 902.90 - K0127 + 898.50

To:
Tablas Circumferential Rd - K0127 + 760 - K0127 + 898.50, K0127 + 902.90 - K0128 + 022.00
August 1, 2025 2025 FY 2025 GAA January 1, 2025 Region IV-B Romblon District Engineering Office
PROJECT ID NO. P00914615LZ

OO1: Ensure Safe and Reliable National Road System

From:
Dapawan-Torrel Rd - K0002 + 046 - K0003 + 085

To:
Dapawan-Torrel Rd - K0002 + 046 - K0002 + 691.50
August 1, 2025 2025 FY 2025 GAA January 1, 2025 Region IV-B Romblon District Engineering Office
PROJECT ID NO. P00914773LZ

OO1: Ensure Safe and Reliable National Road System

From:
Looc (Cogon Tulay)-Odiongan Rd - K0103 + 315 - K0103 + 708, K0123 + 300 - K0123 + 360

To:
Looc (Cogon Tulay)-Odiongan Rd - K0103 + 315 - K0103 + 563, K0123 + 300 - K0123 + 402
August 1, 2025 2025 SARO-BMB-A-25-0008156 March 7, 2025 Region IV-B Romblon District Engineering Office
PROJECT ID NO. P00916284LZ

OO1: Ensure Safe and Reliable National Road System

From:
Sibuyan Circumferential Rd - K0031 + 421 - K0031 + 461, K0031 + 592 - K0031 + 632, K0039 + 079 - K0039 + 095

To:
Sibuyan Circumferential Rd - K0031 + 421 - K0031 + 461, K0031 + 592 - K0031 + 632, K0039 + 013 - K0039 + 033.40
August 1, 2025 2025 SR2025-03-007910 March 6, 2025 Region IV-B Romblon District Engineering Office
PROJECT ID NO. P00915182LZ

OO1: Ensure Safe and Reliable National Road System

From:
Tablas Circumferential Rd - K0098 + 820 - K0099 + 214, K0099 + 234.77 - K0100 + 804, K0100 + 952 - K0101 + 000

To:
Tablas Circumferential Rd - K0098 + 820 - K0099 + 199.90, K0099 + 231.13 - K0100 + 341.23
August 1, 2025 2025 SR2025-04-013095 March 6, 2025 Region IV-B Mindoro Occidental District Engineering Office
PROJECT ID NO. P00900350LZ

OO1: Ensure Safe and Reliable National Road System

From:
Mindoro West Coastal Rd (Section 3) (S00117MR) – K0340+000 – K0343+073

To:
Mindoro West Coastal Rd (Section 3) (S00117MR) – K0381+751 – K0382+891
August 1, 2025 FY 2025 P00909497MN SR2025-02-003033 February 3, 2025 Region XII Regional Office XII
Contract ID: 25M00012
UACS: 310201101639000
Amount: ₱ 1,905,000.00

OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Project Name:
From: Maharlika Highway( Digos-Makar Rd) - (S01506MN) Chainage 000 - Chainage 020, Chainage 020 - Chainage 037, Chainage 037 - Chainage 056, Chainage 056 - Chainage 067, Chainage 067 - Chainage 070, Chainage 092 - Chainage 094, Chainage 094 - Chainage 149
To: Maharlika Highway( Digos-Makar Rd) - (S01506MN) Chainage 000 - Chainage 051
Type of Work:
From: CW1 - Road Widening
To: CW1 - Road Widening, CW2 - Construction of Road Slope Protection Structure
Physical Target:
From: CW1 - 0.198 Lane Km
To: CW1 - 0.102 Lane Km, CW2 - 135 Square Meters
August 1, 2025 FY 2025 P00909987MN SR2025-02-003204 February 3, 2025 Region XII Regional Office XII
Contract ID: 25M00016
UACS: 310305102398000
Amount: ₱ 42,000,000.00

OO1: Ensure Safe and Reliable National Road System: Bridge Program - Widening of Permanent Bridges

Project Name: Banate II Br. (B01765MN) along Maharlika Highway( Digos-Makar Rd)
Type of Work:Widening of Bridge
Physical Target:
From: 333.9 Square meters
To: 381.6 Square meters