Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
May 12, 2018 FY 2018 WIN8C02708 310204100219000 May 3, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 310204100219000
Project ID: P00201349MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of By-Pass and Diversion Roads

NRJ Poblacion Tambulig-Tungawan-Pasingkalan Road

Physical Target:
CW-1 - Construction of Concrete Road: 2.82 lane km.
Unit Cost: P 17,356,310.00/lane km.
EAO: P 1.7752 M
Allocation: P 50.720 M
May 12, 2018 FY 2018 WIN8G02060 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310209100015000
Project ID: P00201615LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Off-Carriageway Improvement - Tertiary Roads - Jct Donsol-Banuang Gurang Rd - K0571+(-475) - K0574+210, K0574+235 - K0577+700
Physical Target - CW1- Off-Carriageway Improvement; Shoulder Paving/Construction/ 15,989.58 sq.m.
CW2- Construction of Drainage Structure along Road/ 4,754.68 lm.
CW3- Construction of Slope Protection Structure/ 15,319.83 sq.m.
Unit Cost: CW1- Php 3,414.78/sq,m.
CW2- Php 6,409.97/lm
CW3- Php 2,399.99/sq.m.
Estimated Cost: Php 126.265M
(As Modified)
May 12, 2018 FY 2018 WIN8G02021 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310209100016000
Project ID: P00201616LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Off-Carriageway Improvement - Tertiary Roads - Jct Putiao-Pilar-Donsol Rd – K0561+(-1073) – K0564+006, K0564+042.50 – K0565+500
Physical Target - CW1- Off-Carriageway Improvement; Shoulder Paving/Construction/ 21,633.00 sq.m.
CW2- Construction of Drainage Structure along Road/ 5,491.00 lm.
CW3- Construction of Slope Protection Structure/ 10,120.39sq.m.
Unit Cost: CW1- Php 3,015.19/sq,m.
CW2- Php 8,456.76/lm
CW3- Php 3,269.28/sq.m.
Estimated Cost: Php 150.00M
(As Modified)

May 12, 2018 FY 2018 WIN8C02737 300117201960000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201960000
Project ID: P00251828MN

Local Program:

Local Roads and Bridges - Local Roads Local Infrastructure

Concreting of Road at Camp Arturo Enrile, Malagutay, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 1.55 lane km.
Unit Cost: P 6,387,096.77/lane km.
EAO: P 100,000.00
Allocation: P 10,000,000.00
May 12, 2018 FY 2018 GAA WIN8C02762 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Jct. Davao-Cotabato Road (Bangkal Section)-Catalunan Grande Road-Jct. Davao-Bukidnon Road (Mintal Section), incl. ROW and Bridge, Davao City
Physical Target:
CW1: 1 number of bridge (Construction of Substructure)
ROW: 2,917.181 sq. m.
Allocation:
TOTAL: P 117,498,000.00
CW1: P 94,085,570.00 (Construction of Substructure)
ROW: P 19,300,000.00
EAO: P 4,112,430.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Jct. Davao-Cotabato Road (Bangkal Section)-Catalunan Grande Road-Jct. Davao-Bukidnon Road (Mintal Section), incl. ROW and Bridge, Davao City
Physical Target:
CW1: 1 number of bridge (Construction of Substructure)
CW2: 1.384 Lane Km (Construction of Gravel Road)
ROW: 18,883.00 sq. m.
Allocation:
TOTAL: P 117,498,000.00
CW1: P 32,982,727.33 (Construction of Substructure)
CW2: P 10,010,917.67 (Construction of Gravel Road)
ROW: P 70,391,925.00
EAO: P 4,112,430.00
May 12, 2018 FY 2018 WIN8G02035 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310204100157000
Project ID: P00201075LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Constructiong of By-Pass and Diversion Roads - Juban-Bulan Diversion Road (Juban section), incl. ROW, Sorsogon
Physical Target - CW1- Construction of Concrete Road/ 2.88 lane-km
CW2- Construction of Drainage Structure along Road/ 4,390.86 lm.
ROW Acquisition: 28,822. sq.m.
Unit Cost: CW1- Php 16.472M/lane-km.
CW2- Php 5,480/lm
ROW- Php 867.39/sq.m.
Estimated Cost: Php 100.0M
(As Modified)

May 12, 2018 FY 2018 WIN8C02761 300117201965000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201965000
Project ID: P00250056MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Brgy. Bolong, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.37 lane km.
Unit Cost: P 5,351,351.35/lane km.
EAO: P 20,000.00
Allocation: P 2,000,000.00
May 12, 2018 FY 2018 WIN8G02129 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310209100018000
Project ID: P00201617LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Off-Carriageway Improvement - Tertiary Roads – Juban-Magallanes Rd – K0613+815 – K0616+647, K0616+660 – K0619+147, K0619+161 – K0623+546, K0623+562 – K0624+486
Physical Target - CW1- Off-Carriageway Improvement; Shoulder Paving/Construction/ 42,160.00 sq.m.
Unit Cost: Php 3.43T/sq.m.
Estimated Cost: Php 150.0M
(As Modified)
May 12, 2018 FY 2018 WIN8C02707 300117201968000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201968000
Project ID: P00250059MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Brgy. Pasobolong, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.17 lane km.
Unit Cost: P 8,735,294.12/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 12, 2018 FY 2018 WIN8G 01868 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300203100101000
Project ID: P00230386LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Ligao-Pioduran-Donsol Road Leading to Butanding Site, Albay
Physical Target - CW1- Reconstruction from Paved to Concrete/ 9.75 lane-km
Unit Cost: Php 9.897M/lane-km
Estimated Cost: Php 100.0M
(As Modified)

May 12, 2018 FY 2018 GAA WIN8C02782 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Jct. Davao City Diversion Road-Buhangin-Tigatto Road (Buhangin Gallera Section), incl. ROW, Davao City
Physical Target:
CW1: 0.756 Lane Km (Construction of Concrete Road)
ROW: 6,562.00 sq. m.
Allocation:
TOTAL: P 60,540,000.00
CW1: P 20,427,120.00 (Construction of Concrete Road)
ROW: P 37,993,980.00
EAO: P 2,118,900.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Jct. Davao City Diversion Road-Buhangin-Tigatto Road (Buhangin Gallera Section), incl. ROW, Davao City
Physical Target:
CW1: 0.808 Lane Km (Construction of Gravel Road)
ROW: 6,562.00 sq. m.
Allocation:
TOTAL: P 60,540,000.00
CW1: P 20,427,120.00 (Construction of Gravel Road)
ROW: P 37,993,980.00
EAO: P 2,118,900.00
May 12, 2018 FY 2018 WIN8C02666 300117201970000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201970000
Project ID: P00250088MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Brgy. Tolosa, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.18 lane km.
Unit Cost: P 8,250,000.00/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 12, 2018 FY 2018 WIN8G02026 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 300202100088000
Project ID: P00201390LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Secondary Roads - Masbate-Cataingan-Placer Rd - K0024+350 - K0024+763, K0025+000 - K0025+201
Physical Target - CW1- Road Widening/ 1.228 lane-km
CW2- Construction of Slope Protection Structure/ 3,084sq.m.
Unit Cost: CW1- Php 10.94M/lane-km
CW2- Php 25.93T/sq.m.
Estimated Cost: Php 96.79M
(As Modified)


May 12, 2018 FY 2018 WIN8C02665 300117201973000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No. 300117201973000
Project ID: P00250089MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Concreting of Road, Brgy. Victoria, Zamboanga City

Physical Target:
CW-1 - Construction of Concrete Road: 0.19 lane km.
Unit Cost: P 7,815,789.47/lane km.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 12, 2018 FY 2018 WIN8G02004 FY 2018 GAA R.A. 10964 December 28, 2017 Region V Regional Office V
UACS No.: 300202100089000
Project ID: P00201391LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Road Widening – Secondary Roads - Masbate-Cataingan-Placer Rd - K0075+872 - K0077+160, K0079+850 - K0081+182, K0083+390 - K0084+730, K0088+000 - K0088+834, K0089+000 - K0089+356
Physical Target - CW1-Road Widening/10.324 lane-km
Unit Cost: Php 15.42M/lane-km
Estimated Cost: Php 165.01m
(As Modified)

May 12, 2018 FY 2018 GAA WIN8C02733 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Upper Tibanban-Oregon-Magdug Road, incl. ROW and Bridge, Davao Oriental
Physical Target:
CW1: 4.570 Lane Km (Construction of Concrete Road)
CW2: 334.00 sq. m. (Construction of Concrete Bridge)
ROW: 22,842.105 sq. m.
Allocation:
TOTAL: P 108,517,000.00
CW1: P 71,822,055.00 (Construction of Concrete Road)
CW2: P 27,708,750.00 (Construction of Concrete Bridge)
ROW: P 4,188,100.00
EAO: P 3,798,095.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Upper Tibanban-Oregon-Magdug Road, incl. ROW and Bridge, Davao Oriental
Physical Target:
CW1: 1.694 Lane Km (Construction of Concrete Road)
CW2: 429.30 sq. m. (Construction of Concrete Bridge)
CW3: 1.080 Lane Km (Construction of Gravel Road)
ROW: 22,842.105 sq. m.
Allocation:
TOTAL: P 108,517,000.00
CW1: P 53,384,068.99 (Construction of Concrete Road)
CW2: P 40,458,522.49 (Construction of Concrete Bridge)
CW3: P 6,688,213.52 (Construction of Gravel Road)
ROW: P 4,188,100.00
EAO: P 3,798,095.00
May 12, 2018 FY 2018 GAA WIN8C02783 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Replacement of Permanent Weak Bridges
Lipadas Br. (B00012MN) along Davao-Cotabao Rd (Davao City-Jct. Digos Sect)
Physical Target:
CW1: 669.60 sq. m. (Replacement of Bridge)
Allocation:
TOTAL: P 95,504,000.00
CW1: P 92,161,360.00 (Replacement of Bridge)
EAO: P 3,342,640.00

TO: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Replacement of Permanent Weak Bridges
Lipadas Br. (B00012MN) along Davao-Cotabao Rd (Davao City-Jct. Digos Sect)
Physical Target:
CW1: 626.203 sq. m. (Replacement of Bridge)
Allocation:
TOTAL: P 95,504,000.00
CW1: P 92,161,360.00 (Replacement of Bridge)
EAO: P 3,342,640.00
May 12, 2018 FY 2018 GAA WIN8C02691 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Widening of Permanent Bridges
Kingking Br. (B00197MN) along Surigao-Davao Coastal Rd incl. ROW
Physical Target:
CW1: 1,886.70 sq. m. (Widening of Bridge)
ROW: 10,204.082 sq. m.
Allocation:
TOTAL: P 270,250,000.00
CW1: P 259,826,250.00 (Widening of Bridge)
ROW: P 965,000.00
EAO: P 9,458,750.00

TO: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Widening of Permanent Bridges
Kingking Br. (B00197MN) along Surigao-Davao Coastal Rd incl. ROW
Physical Target:
CW1: 1,897.84 sq. m. (Widening of Bridge)
ROW: 10,204.082 sq. m.
Allocation:
TOTAL: P 270,250,000.00
CW1: P 259,826,250.00 (Widening of Bridge)
ROW: P 965,000.00
EAO: P 9,458,750.00
May 12, 2018 FY 2018 GAA WIN8C02735 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Mawab-Maragusan-Caraga Road, Package C, incl. ROW, Davao Oriental
Physical Target:
CW1: 9.682 Lane Km (Construction of Concrete Road)
ROW: 22,727,273 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 191,552,500.00 (Construction of Concrete Road)
ROW: P 1,447,500.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Mawab-Maragusan-Caraga Road, Package C, incl. ROW, Davao Oriental
Physical Target:
CW1: 10.664 Lane Km (Construction of Concrete Road)
ROW: 22,727,273 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 191,552,500.00 (Construction of Concrete Road)
ROW: P 1,447,500.00
EAO: P 7,000,000.00
May 12, 2018 FY 2018 GAA WIN8C02863 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Maragusan-Pantukan Road (Pantukan Section), Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 19.032 Lane Km (Construction of Gravel Road)
ROW: 147,959.184 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 275,507,500.00 (Construction of Gravel Road)
ROW: P 13,992,500.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Maragusan-Pantukan Road (Pantukan Section), Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 12.79372 Lane Km (Construction of Concrete Road)
ROW: 147,959.184 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 275,507,500.00 (Construction of Concrete Road)
ROW: P 13,992,500.00
EAO: P 10,500,000.00
May 12, 2018 FY 2018 GAA WIN8C02772 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Local Program – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Nabunturan-Laak Road, Compostela Valley
Physical Target:
CW1: 2.034 Lane Km (Construction of Concrete Road)
CW2: 334 sq. m. (Construction of Concrete Bridge)
ROW: 15,255 sq. m.
Allocation:
TOTAL: P 60,000,000.00
CW1: P 29,442.150.00 (Construction of Concrete Road)
CW2: P 27,020,000.00 (Construction of Concrete Bridge)
ROW: P 1,437,850.00
EAO: P 2,100,000.00

TO: Local Program – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Nabunturan-Laak Road, Compostela Valley
Physical Target:
CW1: 1.75712 Lane Km (Construction of Gravel Road)
CW2: 333.90 sq. m. (Construction of Concrete Bridge)
ROW: 15,255 sq. m.
Allocation:
TOTAL: P 60,000,000.00
CW1: P 24,577,394.09 (Construction of Gravel Road)
CW2: P 31,884,755.91 (Construction of Concrete Bridge)
ROW: P 1,437,850.00
EAO: P 2,100,000.00
May 12, 2018 FY 2018 GAA WIN8C02880 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Preventive Maintenance – Secondary Roads
Davao City Div Rd – K1508+772 – K1512+221
Physical Target:
CW1: 20.472 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 200,639,000.00
CW1: P 193,616,635.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 7,022,365.00

TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Preventive Maintenance – Secondary Roads
Davao City Div Rd – K1508+772 – K1511+936.987
Physical Target:
CW1: 18.738 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 200,639,000.00
CW1: P 193,616,635.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 7,022,365.00
May 12, 2018 FY 2018 GAA WIN8C02909 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Paving of Unpaved Road – Secondary Roads
Davao-Sarangani Coastal Rd (Malalag-Malita-JAS-G), incl. ROW –
K1733+267 – K1733+451, K1733+486 – K1733+624, K1777+000 – K1777+220,
K1777+305 – K1777+500, K1784+420 – K1784+456, K1784+620 – K1786+000,
K1786+609 – K1786+710, K1786+803 – K1786+830, K1787+560 – K1787+1179
Physical Target:
CW1: 5.800 Lane Km (Paving of Unpaved Roads)
ROW: 29,000.00 sq. m.
Allocation:
TOTAL: P 122,190,000.00
CW1: P 116,948,350.00 (Paving of Unpaved Roads)
ROW: P 965,000.00
EAO: P 4,276,650.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Paving of Unpaved Road – Secondary Roads
Davao-Sarangani Coastal Rd (Malalag-Malita-JAS-Glan), incl. ROW –
K1733+267 – K1733+451, K1733+486 – K1733+624, K1777+000 – K1777+220,
K1777+305 – K1777+500, K1784+420 – K1784+456, K1784+620 – K1786+000,
Physical Target:
CW1: 3.438 Lane Km (Paving of Unpaved Roads)
ROW: 29,000.00 sq. m.
Allocation:
TOTAL: P 122,190,000.00
CW1: P 73,340.00 (Paving of Unpaved Roads)
ROW: P 965,000.00
EAO: P 2,695,000.00
EXC: P 45,190,000.00 (Excess)
May 11, 2018 FY - 2018 WIN8F05439 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Off-Carriageway Improvement
- Secondary Roads

FROM:
Calapan South Road
K0012+400 - K0013+020,
K0018+000 - K0019+206,
K0023+560 - K0024+824,
K0028+016 - K0029+000,
K0033+550 - K0034+123.50

CW1: 27,261 sq.m. ( Off-Carriageway Improvement:
Shoulder Paving/Construction )
Allocation: 147,207,000 Php

TO:
Calapan South Road
K0012+400 - K0012+960,
K0015+162 - K0015+791,
K0017+210 -K0019+206,
K0023+560 - K0024+985,
K0024+1000 - K0025+535,
K0028+016 - K0028+954,
K0033+550 - K0034+123

CW1: 40,656.00 sq.m. ( Off-Carriageway Improvement:
Shoulder Paving/Construction )
Allocation: 147,207,000 Php
May 11, 2018 FY - 2018 WIN8F05348 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities

FROM:
Construction of Brgy. Catubugan Flood Control
Boac, Marinduque

CW1: 298.00 lin.m. ( Construction of Revetment )
Allocation: 10,000,000 Php

TO:
Construction of Catubugan Fllod Control
Boac, Marinduque

CW1: 200.00 lin.m. ( Construction of Revetment )
Allocation: 10,000,000 Php
May 11, 2018 FY - 2018 WIN8F05329 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 1.8 km. Kay Duke - Albon road,
Barangay Kay Duke, Torrijos, Marinduque

CW1: 1.583 Lane km ( Construction of Concrete Road )
Allocation: 9,000,000 Php

TO:
Concreting of 1.80 lane km Kay Duke - Albon road,
Barangay Kay Duke, Torrijos, Marinduque

CW1: 1.800 Lane km ( Construction of Concrete Road )
Allocation: 9,000,000 Php

May 11, 2018 FY - 2018 WIN8F05335 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 500 m. Matuyatuya to Manuhay road,
Barangay Matuyatuya, Torrijos, Marinduque

CW1: 0.440 Lane km ( Construction of Concrete Road )
Allocation: 2,500,000 Php

TO:
Concreting of 500 lane km. Matuyatuya to Mabuhay road
Barangay Matuyatuya, Torrijos, Marinduque

CW1: 0.500 Lane km ( Construction of Concrete Road )
Allocation: 2,500,000 Php
May 11, 2018 FY - 2018 WIN8F05345 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Road, Brgy. Tabionan,
Gasan, Marinduque

CW1: 0.352 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 php

TO:
Construction of Road, Brgy. Tabionan,
Gasan, Marinduque

CW1: 0.488 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
May 11, 2018 FY - 2018 WIN8F05346 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Road, Brgy. Kay Duke,
Torrijos, Marinduque

CW1; 0.652 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php

TO:
Construction of Road, Brgy. Kay Duke,
Torrijos, Marinduque

CW1: 0.600 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
May 11, 2018 2018 WIN8C02752 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Dumlan-Concepcion Road connecting to Maco Public Transport Terminal and Banana Flour Processing Plant, Maco, Compostela Valley
Physical Target:
CW1: 7.584 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 94,800,000.00
CW1: P 91,482,000.00
EAO: P 3,318,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Dumlan-Concepcion Road connecting to Maco Public Transport Terminal and Banana Flour Processing Plant, Maco, Compostela Valley
Physical Target:
CW1: 11.581 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 94,800,000.00
CW1: P 91,482,000.00
EAO: P 3,318,000.00
May 11, 2018 FY - 2018 WIN8F05338 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Construction of Road, Brgy. Mahinhin,
Boac, Marinduque

CW1: 0.352 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php

TO:
Construction of Road, Brgy. Mahinhin,
Boac, Marinduque

CW1: 0.600 Lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
May 11, 2018 2018 WIN8C02758 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program
Local - Buidings and Other Structures - Multipurpose/Facilities - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Gym at Mampisig, Mabini, Compostela Valley
Physical Target:
CW1: 1 Number of Building (Construction of Multipurpose Building)
ALLOCATION:
TOTAL: P 1,500,000.00
CW1: P 1,470,000.00
EAO: P 30,000.00

TO: Local Program
Local - Buidings and Other Structures - Multipurpose/Facilities - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Gym at Mampising, Mabini, Compostela Valley
Physical Target:
CW1: 1 Number of Building (Construction of Multipurpose Building)
ALLOCATION:
TOTAL: P 1,500,000.00
CW1: P 1,470,000.00
EAO: P 30,000.00
May 11, 2018 FY - 2018 WIN8F05391 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repiar/rehabilitation/Improvement of
Various Infrastructures including Local Projects
- Flood Control Structures/Facilities

FROM:
Construction of Brgy. Ogbac Flood Control,
Boac, Marinduque

CW1: 119.00 lin.m ( Construction of Revetment )
Allocation: 4,000,000 Php

TO:
Construction of Brgy. Ogbac Flood Control,
Boac, Marinduque

CW1: 90.00 lin.m. ( Construction of Revetment )
Allocation: 4,000,000 Php
May 11, 2018 FY - 2018 WIN8F0388 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities

FROM:
Construction of Brgy. Sumangga Flood Control,
Mogpog, Marinduque

CW1: 149.00 lin.m. ( Construction of Revetment )
Allocation: 5,000,000 Php

TO:
Construction of Brgy. Sumangga Flood Control,
Mogpog, Marinduque

CW1: 110.00 lin.m. ( Construction of Revetment )
Allocation: 5,000,000 Php

May 11, 2018 FY - 2018 WIN8F05387 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Local Infrastructure Program -
- Flood Control Structures/Facilities

FROM:
Construction of Flood Control, Brgy. Daypay,
Boac, Marinduque

CW1: 45.00 lin.m. ( Construction of Revetment )
Allocation: 1,500,000 Php

TO:
Construction of Flood Control, Brgy. Daypay,
Boac, Marinduque

CW1: 140.00 lin.m. ( Construction of Revetment )
Allocation: 1,500,000 Php
May 11, 2018 FY - 2018 WIN8F05397 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 1.5 km Makawayan to Gumamela road,
Barangay Makawayan, Torrijos, Marinduque

CW1: 1.319 Lane km ( Construction of Concrete Road )
Allocation: 7,500,000 Php

TO:
Concreting of 1.5 lane km Makawayan to Gumamela road,
Barangay Makawayan, Torrijos, Marinduque

CW1: 1.50 Lane km ( Construction of Concrete Road )
Allocation: 7,500,000 Php
May 11, 2018 2018 WIN8C02881 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Mainit Road leading to Mainit Hotspring of Mainit Protected Landscpae, Brgy. Mainit, Nabunturan, Compostela Valley
Physical Target:
CW1 - 1.642 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1 - P 19,600,000.00
EAO - P 400,000.00

TO: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Mainit Road leading to Mainit Hotspring of Mainit Protected Landscpae, Brgy. Mainit, Nabunturan, Compostela Valley
Physical Target:
CW1 - 2.477 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1 - P 19,600,000.00
EAO - P 400,000.00
May 11, 2018 FY - 2018 WIN8F05390 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
001 - Ensure safe and Reliable National Road System

Retrofitting/Strengthening of Permanent Bridges

FROM:
Marlangga Br. ( B00008MQ ) along
Mogpog - Balanacan Port Road

CW1: 1.000 Bridge ( retrofitting/Strengthening )
Allocation: 3,500,000 Php

TO:
Marlangga br. ( B00008MQ ) along
Marinduque Circumferential Road

CW1: 1.000 Bridge ( Retrofitting/Strengthening )
Allocation: 3,500,000 Php
May 11, 2018 2018 WIN8C02901 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Revetment along Hijo River, Barangay Bucana, Maco, Compostela Valley
Physical Target:
CW1: 350 lm (Construction of Revetment)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 48,057,000.00 (Construction of Revetment)
ROW: P 193,000.00
EAO: P 1,750,000.00

TO: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Revetment along Hijo River, Barangay Bucana, Maco, Compostela Valley
Physical Target:
CW1: 412.20 lm (Construction of Revetment)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 48,057,000.00 (Construction of Revetment)
ROW: P 193,000.00
EAO: P 1,750,000.00
May 11, 2018 FY - 2018 WIN8F05372 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of Brgy Agot, Boac, Marinduque

CW1: 0.528 Lane km ( Construction of Concrete Road )
Allocation; 3,000,000 Php

TO;
Concreting of Brgy. Agot, Road, Boac, Marinduque

CW1: 0.747 Lane km ( Construction of Concrete Road )
Allocation; 3,000,000 Php


May 11, 2018 2018 WIN8C02884 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
Montevista-Compostela-Mati Bdry Rd-K1473 + 771 - K1473 + 780
Physical Target:
CW1 - 64.00 Lineal meters (Construction of Drainage Structure along Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1 - P 4,900,000.00
EAO - P 100,000.00

TO: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads
Montevista-Compostela-Mati Bdry Rd-K1473 + 620 - K1473 + 774, K1473 + 777 - K1473 + 835, K1473 + 837 - K1473 + 840
Physical Target:
CW1 - 215.78 Lineal meters (Construction of Drainage Structure along Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1 - P 4,900,000.00
EAO - P 100,000.00
May 11, 2018 2018 WIN8C02892 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Daang Maharlika (MN) - K1382+137-K1382+272, K1385+000-K1385+671
Physical Target:
CW1: 1.612 Lane Km (Reconstruction from Paved to Concrete)
ALLOCATION:
TOTAL: P 20,150,000.00
CW1: P 19,747,000.00
EAO: P 403,000.00

TO: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Daang Maharlika (MN) - K1378+000-K1378+287, K1381+669-K1382+272, K1382+308-K1382+508
Physical Target:
CW1: 2.164 Lane Km (Reconstruction from Paved to Concrete)
ALLOCATION:
TOTAL: P 20,150,000.00
CW1: P 19,747,000.00
EAO: P 403,000.00
May 11, 2018 FY 2018 WIN8C02615 UACS No. 300117201993000 April 24, 2018 Region IX Zamboanga del Norte 1st District Engineering Office
UACS No. 300117201993000
Project ID: P00251621MN
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road from Sitio Capis to Laitan, Palaranan Manukan, Zamboanga del Norte
Physical Target:
CW-1- Construction of Concrete Road: 0.400 Lane km
Unit Cost: P 3,588,750/lane km
EAO: P 14,500.00
Allocation: P 1,450,000.00
May 11, 2018 FY 2018 WIN8C02513 UACS No. 320101102187000 April 10, 2018 Region IX Zamboanga Sibugay 1st District Engineering Office
UACS No. 320101102187000
Project ID: P00220279MN
OO2: Protect Lives and Properties
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Concrete Protection Dike, Sta. 01+841 - Sta. 02+020 & Sta. 00+666 - Sta. 00+784.80, Brgy. Bulawan, Payao, Zamboanga Sibugay
Physical Target:
CW-1- Construction of Dike: 297.80 lineal meters
Unit Cost: P 65,815.98/lineal meters
EAO: P 400,000.00
Allocation: P 20,000,000.00
May 11, 2018 FY 2018 WIN8C02522 UACS No. 320101102186000 April 10, 2018 Region IX Zamboanga Sibugay 1st District Engineering Office
UACS No. 320101102186000
Project ID: P00220280MN
OO2: Protect Lives and Properties
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Concrete Protection Dike, Sta. 00+(-002) - Sta. 00+156.50, Brgy.Guiwan, Payao, Zamboanga Sibugay
Physical Target:
CW-1- Construction of Dike: 158.50 lineal meters
Unit Cost: P 123,659.31/lineal meters
EAO: P 400,000.00
Allocation: P 20,000,000.00
May 10, 2018 FY 2018 GAA WIN8C02650 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package B, Compostela Valley
Physical Target:
CW1: 10.942 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 184,797,500.00
ROW: P 8,202,500.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package B, Compostela Valley
Physical Target:
CW1: 12.114 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 184,797,500.00
ROW: P 8,202,500.00
EAO: P 7,000,000.00
May 10, 2018 FY 2018 GAA WIN8C02639 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Mahayag-Gatungan-Callawa Diversion Road, incl. ROW, Davao City
Physical Target:
CW1: 2.214 Lane Km (Construction of Gravel Road)
CW2: 6.154 Lane Km (Construction of Concrete Road)
CW3: 333.2 sq. m. (Additional Lane Width)
CW4: 8.484 Lane Km (Reconstruction from Paved to Concrete)
ROW: 129,325.00 sq. m.
Allocation:
TOTAL: P 380,000,000.00
CW1: P 42,730,200.00 (Construction of Gravel Road)
CW2: P 103,925,675.00 (Construction of Concrete Road)
CW3: P 1,891,400.00 (Additional Lane Width)
CW4: P 143,273,550.00 (Reconstruction from Paved to Concrete)
ROW: P 74,879,175.00
EAO: P 13,300,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Mahayag-Gatungan-Callawa Diversion Road, incl. ROW, Davao City
Physical Target:
CW1: 2.387 Lane Km (Construction of Gravel Road)
CW2: 4.803 Lane Km (Construction of Concrete Road)
CW3: 9.527 Lane Km (Reconstruction from Paved to Concrete)
ROW: 129,325.00 sq. m.
Allocation:
TOTAL: P 380,000,000.00
CW1: P 31,532,908.50 (Construction of Gravel Road)
CW2: P 143,114,617.19 (Construction of Concrete Road)
CW3: P 117,173,299.31 (Reconstruction from Paved to Concrete)
ROW: P 74,879,175.00
EAO: P 13,300,000.00
May 10, 2018 2018 WIN8C02771 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW - K1427 + 391 - K1430 + 144
Physical Target:
CW1: 5.534 Lane Km (Road Widening)
ROW: 10,549.565 sq.m.
ALLOCATION:
TOTAL: P 95,142,000.00
CW1: P 80,104,650.00
ROW: p 11,707,380.00
EAO: P 3,329.970.00

TO: OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW - K1427 + 391 - K1430 + 044
Physical Target:
CW1: 5.285 Lane Km (Road Widening)
ROW: 10,549.565 sq.m.
ALLOCATION:
TOTAL: P 95,142,000.00
CW1: P 80,104,650.00
ROW: p 11,707,380.00
EAO: P 3,329.970.00
May 10, 2018 FY 2018 GAA WIN8C02651 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package A, Compostela Valley
Physical Target:
CW1: 10.942 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 184,797,500.00 (Construction of Concrete Road)
ROW: P 8,202,500.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package A, Compostela Valley
Physical Target:
CW1: 11.754 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 184,797,500.00 (Construction of Concrete Road)
ROW: P 8,202,500.00
EAO: P 7,000,000.00
May 10, 2018 FY 2018 GAA WIN8C02593 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package C, Compostela Valley
Physical Target:
CW1: 10.942 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 184,797,500.00 (Construction of Concrete Road)
ROW: P 8,202,500.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Laak-Malaybalay City Road, Package C, Compostela Valley
Physical Target:
CW1: 9.698 Lane Km (Construction of Concrete Road)
ROW: 83,734.694 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 162,795,500.00 (Construction of Concrete Road)
ROW: P 8,202,500.00
EAO: P 6,202,000.00
EXC: P 22,800,000.00 (Excess Funds)
May 10, 2018 2018 WIN8C02741 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO1: Ensure and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW - K1430 + 578 - K1431 + 585
Physical Target:
CW1 - 2.022 Lane Km (Road Widening)
ROW - 6,086.957 sq. m.
ALLOCATION:
TOTAL: P 37,330,000.00
CW1: P 29,723,400.00 (Road Widening)
ROW: P 6,860,000.00
EAO: P 746,600.00

TO: OO1: Ensure and Reliable National Road System
Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW - K1430 + 578 - K1431 + 585
Physical Target:
CW1 - 1.850 Lane Km (Road Widening)
ROW - 6,086.957 sq. m.
ALLOCATION:
TOTAL: P 37,330,000.00
CW1: P 29,723,400.00 (Road Widening)
ROW: P 6,860,000.00
EAO: P 746,600.00
May 10, 2018 2018 WIN8C02768 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Butuan City District Engineering Office
OO1- Organizational Outcome 1
Network Development – Road Widening – Tertiary Roads

FROM:

Butuan City-Malaybalay Rd incl. ROW – K1242 + 786 – K1247 + 190

Scope of Work: Road Widening
ROW Acquisition

Physical Target: 8.80 Lane km
58,520.00 Square meters

Amount : Php 99,237,000.00 (Total)
Php 93,526,705.00 (Road Widening)
Php 2,237,000.00 (ROW Acquisition)
Php 3,473,295.00 (EAO)

TO:

Butuan City-Malaybalay Rd incl. ROW – K1245 + 130 - K1247 + 190, K1249 + 451 - K1251 + 050

Scope of Work: Road Widening
ROW Acquisition

Physical Target: 7.408 Lane km
49,263.20 Square meters

Amount : Php 99,237,000.00 (Total)
Php 93,526,705.00 (Road Widening)
Php 2,237,000.00 (ROW Acquisition)
Php 3,473,295.00 (EAO)
May 10, 2018 2018 WIN8C02763 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Butuan City District Engineering Office
OO2- Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

FROM:

Improvement of Bank Protection along Agusan River Basin, Amparo Section, Tungao, Butuan City

Scope of Work: Construction of Flood Mitigation Structure
ROW Acquisition

Physical Target: 40.00 Lineal meters
400.00 Square meters

Amount : Php 30,000,000.00 (Total)
Php 29,008,000.00 (Flood Control)
Php 392,000.00 (ROW Acquisition)
Php 600,000.00 (EAO)

TO:

Improvement of Bank Protection along Agusan River Basin, Dankias Section, Tungao, Butuan City

Scope of Work: Construction of Flood Mitigation Structure
ROW Acquisition

Physical Target: 34.80 Lineal meters
400.00 Square meters

Amount : Php 30,000,000.00 (Total)
Php 29,000,000.00 (Flood Control)
Php 400,000.00 (ROW Acquisition)
Php 600,000.00 (EAO)
May 10, 2018 2018 WIN8C02692 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
San Jose Road leading to Awao Falls, Brgy. San Jose, Monkayo, Compostela Valley
Physical Target:
CW1: 1.650 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
San Jose Road leading to Awao Falls, Brgy. San Jose, Monkayo, Compostela Valley
Physical Target:
CW1: 2.032 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00
May 10, 2018 2018 WIN8C02770 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Butuan City District Engineering Office
OO2- Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

FROM:

Rechanneling of Sanghay Creek, De Oro Section, Agusan Del Norte

Scope of Work: Construction of Flood Mitigation Structure

Physical Target: 500.00 Lineal meters

Amount : Php 30,000,000.00 (Total)
Php 29,400,000.00 (Flood Control)
Php 600,000.00 (EAO)

TO:

Rechanneling of De Oro Creek, De Oro Section, Agusan del Norte

Scope of Work: Construction of Flood Mitigation Structure
ROW Acquisition

Physical Target: 650.00 Lineal meters
6,500.00 Square meters

Amount : Php 30,000,000.00 (Total)
Php 29,200,000.00 (Flood Control)
Php 200,000.00 (ROW Acquisition)
Php 600,000.00 (EAO)
May 10, 2018 FY 2018 GAA WIN8C02588 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Nabunturan-New Bataan Diversion Road, Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 9.600 Lane Km (Construction of Concrete Road)
ROW: 81,632,653 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 185,280,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Nabunturan-New Bataan Diversion Road, Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 12.62216 Lane Km (Construction of Concrete Road)
ROW: 81,632,653 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 185,280,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 7,000,000.00
May 10, 2018 2018 WIN8C02798 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
OO1- Organizational Outcome 1
Network Development - Road Widening - Secondary Roads

FROM:

Dapa-Jct Cancohoy Rd – K0001 + (-1019) – K0001 + (-021.4)

Project ID: P00201540MN
Scope of Work: Road Widening
Physical Target: 1.995 Lane Km

Amount : Php 51,399,000.00 (Total)
: Php 49,600,035.00 (Road)
: Php 1,798,965.00 (EAO)

TO:

Dapa-Jct Cancohoy Road – K0001 + (-1019) – K0002 + 000

Project ID: P00201540MN
Scope of Work: Road Widening
Physical Target: 3.982 Lane Km

Amount : Php 51,399,000.00 (Total)
: Php 49,600,035.00 (Road)
: Php 1,798,965.00 (EAO)
May 10, 2018 FY 2018 GAA WIN8C02594 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Davao del Norte-Compostela Valley-Agusan del Sur Road Leading to Various Tourism Sites, San Isidro, Davao del Norte
Physical Target:
CW1: 11.067 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Davao del Norte-Compostela Valley-Agusan del Sur Road Leading to Various Tourism Sites, San Isidro, Davao del Norte
Physical Target:
CW1: 9.244 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00
May 10, 2018 2018 WIN8C02727 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Covergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Tuboran Road leading to Camp Manuel T. Yan Sr. Economility Park, Brgy. Tuboran, Mawab, Compostela Valley
Physical Target:
CW1 - 2.930 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 35,000,000.00
CW1- P 34,300,000.00
EAO - P 700,000.00

TO: Covergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Tuboran Road leading to Camp Manuel T. Yan Sr. Economility Park, Brgy. Tuboran, Mawab, Compostela Valley
Physical Target:
CW1 - 3.981 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 35,000,000.00
CW1- P 34,300,000.00
EAO - P 700,000.00
May 10, 2018 2018 WIN8C02797 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
OO1- Organizational Outcome 1
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

FROM:

Jct Del Carmen-Sta Monica-Sn Isidro Rd – K0040 + (-673) – K0040 + (-432)

Project ID: P00200287MN
Scope of Work: Construction of Road Slope Protection Structure
Physical Target: 3,856 square meters

Amount : Php 69,112,000.00 (Total)
: Php 66,693,080.00 (Slope)
: Php 2,418,920.00 (EAO)

TO:

Jct Del Carmen-Sta Monica-San Isidro Road – K0039 + 330 - K0039 + 571

Project ID: P00200287MN
Scope of Work: Construction of Road Slope Protection Structure
Physical Target: 3,694.34 square meters

Amount : Php 69,112,000.00 (Total)
: Php 66,693,080.00 (Slope)
: Php 2,418,920.00 (EAO)
May 10, 2018 FY 2018 GAA WIN8C02601 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Monkayo-Compostela Road, Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 13.656 Lane Km (Construction of Concrete Road)
ROW: 112,244.898 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 230,635,000.00
ROW: P 10,615,000.00
EAO: P 8,750,000.00

TO: OO1: Ensure Safe Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Monkayo-Compostela Road, Package B, incl. ROW, Compostela Valley
Physical Target:
CW1: 17.397 Lane Km (Construction of Concrete Road)
ROW: 112,244.898 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 230,635,000.00
ROW: P 10,615,000.00
EAO: P 8,750,000.00
May 10, 2018 FY 2018 GAA WIN8C02579 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Widening of Permanent Bridges
Maniki Br. (B00182MN) along Tagum-Panabo Circum Rd (Phase I), incl. ROW
Physical Target:
CW1: 1,697.630 sq. m. (Widening of Bridge)
ROW: 6,430.00 sq. m.
Allocation:
TOTAL: P 191,000,000.00
CW1: P 183,350,000.00
ROW: P 965,000.00
EAO: P 6,685,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Bridge Program
Widening of Permanent Bridges
Maniki Br. (B00182MN) along Tagum-Panabo Circum Rd (Phase I), incl. ROW
Physical Target:
CW1: 1,696.613 sq. m. (Widening of Bridge)
ROW: 6,430.00 sq. m.
Allocation:
TOTAL: P 191,000,000.00
CW1: P 183,350,000.00
ROW: P 965,000.00
EAO: P 6,685,000.00
May 10, 2018 2018 WIN8C02753 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Pasian Road leading to Agrotourism Complex, Brgy. Pasian, Monkayo, Compostela Valley
Physical Target:
CW1 - 1.218 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1 - P 14,700,000.00 (Construction of Concrete Road)
EAO - 300,000.00

TO: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Pasian Road leading to Agrotourism Complex, Brgy. Pasian, Monkayo, Compostela Valley
Physical Target:
CW1 - 1.910 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1 - P 14,700,000.00 (Construction of Concrete Road)
EAO - 300,000.00
May 10, 2018 FY 2018 GAA WIN8C02577 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Construction/Upgrading/Rehabilitation of Drainage along National Roads
Tagum-Panabo Circum Rd – K1459+850 – K1462+558
Physical Target:
CW1: 5,190.00 Lineal Meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 124,569,000.00
CW1: P 120,209,085.00
EAO: P 4,359,915.00

TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Construction/Upgrading/Rehabilitation of Drainage along National Roads
Tagum-Panabo Circum Rd – K1459+850 – K1462+660
Physical Target:
CW1: 5,389.60 Lineal Meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 124,569,000.00
CW1: P 120,209,085.00
EAO: P 4,359,915.00
May 10, 2018 FY 2018 GAA WIN8C02574 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development System
Road Widening – Primary Roads
Daang Maharlika (MN) incl. ROW –
K1505+000 – K1506+000, K1506+104 – K1506+417,
(S01460MN) Chainage 1302 – Chainage 1673
Physical Target:
CW1: 2.997 Lane Km (Road Widening)
ROW: 3,927.50 sq. m.
Allocation:
TOTAL: P 116,000,000.00
CW1: P 89,199,775.00
ROW: P 22,740,225.00
EAO: P 4,060,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development System
Road Widening – Primary Roads
Daang Maharlika (MN) incl. ROW –
K1505+000 – K1506+004, K1506+118 – K1506+428,
(S01460MN) Chainage 1302 – Chainage 1673, K1503+771 – K1504+579
Physical Target:
CW1: 4.068 Lane Km (Road Widening)
ROW: 4,927.50 sq. m.
Allocation:
TOTAL: P 116,000,000.00
CW1: P 83,149,225.00
ROW: P 28,790,775.00
EAO: P 4,060,000.00
May 10, 2018 2018 WIN8C02709 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO2: Protect lives and Properties
Flood Management
Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment of Hijo Bridge 1, Hijo River, Maco (Downstream), Compostela Valley
Physical Target:
CW1 - 800.00 Lineal meters (Construction of Revetment)
ROW - 1,143 square meters
ALLOCATION:
TOTAL: P 45,000,000.00
CW1 - P 43,904,000.00 (Construction of Revetment
ROW - P 196,000.00
EAO - P 900,000.00

TO: OO2: Protect lives and Properties
Flood Management
Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment of Hijo Bridge 1, Hijo River, Maco (Downstream), Compostela Valley
Physical Target:
CW1 - 786.00 Lineal meters (Construction of Revetment)
ROW - 1,143 square meters
ALLOCATION:
TOTAL: P 45,000,000.00
CW1 - P 43,904,000.00 (Construction of Revetment
ROW - P 196,000.00
EAO - P 900,000.00
May 10, 2018 2018 WIN8C02743 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Trades, Industries and Economic Zones
San Roque - San Isidro Road connecting to Nabunturan Public Transport Terminal and Prk 5, San Isidro Food Terminal, Nabunturan, Compostela Valley
Physical Target:
CW1 - 3.402 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 42,530,000.00
CW1 - P 41,679,400.00
EAO - P 850,600.00

TO: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Trades, Industries and Economic Zones
San Roque - San Isidro Road connecting to Nabunturan Public Transport Terminal and Prk 5, San Isidro Food Terminal, Nabunturan, Compostela Valley
Physical Target:
CW1 - 2.963 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 42,530,000.00
CW1 - P 41,679,400.00
EAO - P 850,600.00
May 10, 2018 2018 WIN8C02764 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
Local Program - National Roads and Bridges - Local Roads Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Concreting of Brgy. Navarro - Lobo - Inyaran Road, Socorro, Bucas Grande, Surigao del Norte

Project ID No. P00257833MN
Scope of Work: Construction of Concrete Road
Physical Target: 6.40 Lane Km

Allocation - Php 80,000,000.00 (Total)
- Php 77,200,000.00 (Road)
- Php 2,800,000.00 (EAO)

TO:

Concreting of Brgy. Navarro - Lobo - Inyaran Road, Socorro, Bucas Grande, Surigao del Norte

Project ID No. P00257833MN
Scope of Work: Construction of Concrete Road
Physical Target: 5.60 Lane Km

Allocation - Php 80,000,000.00 (Total)
- Php 77,200,000.00 (Road)
- Php 2,800,000.00 (EAO)
May 10, 2018 2018 WIN8C02757 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Structures and Drainage Systemss
Rechanneling/Construction of Revetment with Steel Sheet Pile of Kingking River, Balanban Section R/S, Pantukan, Compostela Valley
Physical Target:
CW1: 414 lm (Construction of Revetment)
CW2: 275 cm (Channelization)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 32,540,456.00 (Construction of Revetment)
CW2: P 1,563,444.00 (Channelization)
ROW: P 196,000.00
EAO: P 700,000.00

TO: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Structures and Drainage Systemss
Rechanneling/Construction of Revetment with Steel Sheet Pile of Kingking River, Balanban Section R/S, Pantukan, Compostela Valley
Physical Target:
CW1: 413.13 lm (Construction of Revetment)
CW2: 708.00 cm (Channelization)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 32,866,935.00 (Construction of Revetment)
CW2: P 1,237,064.00 (Channelization)
ROW: P 196,000.00
EAO: P 700,000.00
May 10, 2018 2018 WIN8C02766 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
Local Program - National Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Concreting of Esperanza - Katsawan- Katipunan Road, Brgy. Esperanza, Del Carmen, Siargao, Surigao del Norte

Project ID No. P00257836MN
Scope of Work: Construction of Concrete Road
Physical Target: 6.40 Lane Km

Allocation - Php 80,000,000.00 (Total)
- Php 77,200,000.00 (Road)
- Php 2,800,000.00 (EAO)

TO:

Concreting of Esperanza - Katsawan- Katipunan Road, Brgy. Esperanza, Del Carmen, Siargao, Surigao del Norte

Project ID No. P00257836MN
Scope of Work: Construction of Concrete Road
Physical Target: 5.60 Lane Km

Allocation - Php 80,000,000.00 (Total)
- Php 77,200,000.00 (Road)
- Php 2,800,000.00 (EAO)
May 10, 2018 2018 WIN8C02711 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation / Reconstruction of National Roads with Slips Collapse, and Landslide - Secondary Roads
Compostela-Cateel Rd (Compostela Side) - K1586 + 500 - K1586 + 718, K1587 + 140 - K1587 + 180, K1587 + 949 - K1587 + 960, K1588 + 200 - K1588 + 215, K1589 + 200 - K1589 + 511, K1591 + 950 - K1592 + 020, K1592 + 200 - K1592 + 218, K1592 + 400 - K1592 + 450, K1592 + 500 - K1592 + 520, K1594 + 200 - K1594 + 252, K1594 + 900 - K1594 + 984, K1598 + 200 - K1598 + 250, K1599 + 100 - K1599 + 140, K1601 + 500 - K1601 + 562, K1601 + 810 - K1601 + 830, K1602 + 200 - K1602 + 262, K1603 + 000 - K1603 + 022, K1604 + 750 - K1604 + 780
Physical Target:
CW1 - 9,106.00 sq. m. (Construction of Road Slope Protection Structure)
ALLOCATION:
TOTAL: P 76,500,000.00
CW1 - P 73,822,500.00
EAO - P 2,677,500.00

TO: OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation / Reconstruction of National Roads with Slips Collapse, and Landslide - Secondary Roads
Compostela-Cateel Rd (Compostela Side) - K1586 + 620 - K1586 + 680, K1586 + 695 - K1586 + 735, K1587 + 136 - K1587 + 175, K1588 + 135 - K1588 + 166, K1589 + 200 - K1589 + 511, K1589 + 335 - K1589 + 373, K1592 + 270 - K1592 + 305, K1592 + 406 - K1592 + 580, K1592 + 545 - K1592 + 582, K1594 + 900 - K1595 + 000, K1598 + 200 - K1598 + 250, K1599 + 100 - K1599 + 140, K1603 + 000- K1603 + 058, K1603 + 120 - K1603 + 200, K1605 + 513 - K1605 + 544, K1606 + 280 - K1606 + 380, K1606 + 680 - K1607 + 000
Physical Target:
CW1 - 8,260.135 sq. m. (Construction of Road Slope Protection Structure)
ALLOCATION:
TOTAL: P 76,500,000.00
CW1 - P 73,822,500.00
EAO - P 2,677,500.00
May 10, 2018 2018 WIN8C02747 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Structures and Drainage Systems
Construction of Revetment along Hijo River, Brgy. Hijo, Maco, Compostela Valley
Physical Target:
CW1: 250 lm (Construction of Revetment)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 34,104,000.00 (Construction of Revetment)
ROW: P 196,000.00
EAO: P 700,000.00

TO: OO2: Protect Lives and Properties - Flood Management
Construction/Rehabilitation of Flood Mitigation Structures and Drainage Systems
Construction of Revetment along Hijo River, Brgy. Hijo, Maco, Compostela Valley
Physical Target:
CW1: 239.40 lm (Construction of Revetment)
ROW: 1,143 sq.m.
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 34,104,000.00 (Construction of Revetment)
ROW: P 196,000.00
EAO: P 700,000.00
May 10, 2018 2018 WIN8C02767 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
Local Program - National Roads and Bridges - Local Roads -
Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Concreting of Nueva Estrella - San Roque Road, Socorro, Bucas Grande, Surigao del Norte

Project ID : P00257838MN
Scope of Work: Construction of Concrete Road
Physical Target: 6.40 Lane Km

Allocation: Php 80,000,000.00 (Total)
Php 77,200,000.00 (Road)
Php 2,800,000.00 (EAO)

TO:

Concreting of Nueva Estrella - San Roque Road, Socorro, Bucas Grande, Surigao del Norte

Project ID : P00257838MN
Scope of Work: Construction of Concrete Road
Physical Target: 5.60 Lane Km

Allocation: Php 80,000,000.00 (Total)
Php 77,200,000.00 (Road)
Php 2,800,000.00 (EAO)
May 10, 2018 2018 WIN8C02745 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Magnaga Road Circuit leading to various Beach Resorts, Brgy. Magnaga, Pantukan, Compostela Valley
Physical Target:
CW1: 1.672 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Magnaga Road Circuit leading to various Beach Resorts, Brgy. Magnaga, Pantukan, Compostela Valley
Physical Target:
CW1: 3.016 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00
May 10, 2018 2018 WIN8C02746 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Building and Other Structures - Multipurpose/Facilities
Construction of Covered Court, Brgy. Sawangan, Andili,Mawab, Compostela Valley
Physical Target:
CW1 - 1 number of building (Const. of Multipurpose building)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1 - P 2,970,000.00
EAO - P 30,000.00

TO: Local Program
Building and Other Structures - Multipurpose/Facilities
Construction of Covered Court, Brgy. Sawangan, Mawab, Compostela Valley
Physical Target:
CW1 - 1 number of building (Const. of Multipurpose building)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1 - P 2,970,000.00
EAO - P 30,000.00
May 10, 2018 FY 2018 GAA WIN8C02585 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Sur District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Astorga-Brgy. Jose Rizal Road connecting Sitio Central Rizal in support of Coffee Processing Production, Sta. Cruz, Davao del Sur
Physical Target:
CW1: 3.058 Lane Km (Construction of Concrete Road)
CW2: 3,951.948 sq. m. (Additional Lane Width)
Allocation:
TOTAL: P 99,453,000.00
CW1: P 55,442,145.00 (Construction of Concrete Road)
CW2: P 40,530,000.00 (Additional Lane Width)
EAO: P 3,480,855.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Astorga-Brgy. Jose Rizal Road connecting Sitio Central Rizal in support of Coffee Processing Production, Sta. Cruz, Davao del Sur
Physical Target:
CW1: 4.738 Lane Km (Construction of Concrete Road)
CW2: 6,233.80 sq. m. (Additional Lane Width)
Allocation:
TOTAL: P 99,453,000.00
CW1: P 55,442,145.00 (Construction of Concrete Road)
CW2: P 40,530,000.00 (Additional Lane Width)
EAO: P 3,480,855.00
May 10, 2018 2018 WIN8C02769 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 2nd District Engineering Office
OO1- Organizational Outcome 1
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

FROM:

Jct Osmeña –Pilar Rd – K0020 + 070 – K0020 + 167, K0020 + 218 – K0020 + 339

Project ID: P00201548MN
Scope of Work: Construction of Road Slope Protection Structure
Physical Target: 2,484 square meters

Amount : Php 46,888,000.00 (Total)
: Php 45,950,240.00 (Slope)
: Php 937,760.00 (EAO)

TO:

Jct Osmeña –Pilar Rd – K0020 + 070 – K0020 + 167, K0020 + 218 – K0020 + 339

Project ID: P00201548MN
Scope of Work: Construction of Road Slope Protection Structure
Physical Target: 2,526.74 square meters

Amount : Php 46,888,000.00 (Total)
: Php 45,950,240.00 (Slope)
: Php 937,760.00 (EAO)
May 10, 2018 FY 2018 GAA WIN8C02592 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Sur District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Construction of Concrete Road – Access Road leading to Lao Integrated Farms-Mt. Apo Trail-Balutakay Waterfalls, Brgy. Eman, Bansalan, Davao del Sur
Physical Target:
CW1: 3.000 Km / 6.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 85,000,000.00
CW1: P 82,025,000.00 (Construction of Concrete Road)
EAO: P 2,975,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Construction of Concrete Road – Access Road leading to Lao Integrated Farms-Mt. Apo Trail-Balutakay Waterfalls, Brgy. Eman, Bansalan, Davao del Sur
Physical Target:
CW1: 3.6166 Km / 7.2332 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 85,000,000.00
CW1: P 82,025,000.00 (Construction of Concrete Road)
EAO: P 2,975,000.00
May 10, 2018 FY 2018 GAA WIN8C02570 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Sur District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development
Road Widening – Primary Road
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) incl. ROW –
K1568+200 – K1568+491, K1568+529 – K1569+197, K1569+230 – K1569+338,
K1569+600 – K1569+727, K1581+434 – K1581+927, K1581+959 – K1582+027,
K1582+118 – K1583+259, (S00165MN) Chainage 000 – Chainage 201,
(S00165MN) Chainage 239 – Chainage 296, (S01465MN) Chainage 000 – Chainage 188,
(S01465MN) Chainage 226 – Chainage 316, (S01466MN) Chainage 000 – Chainage 197,
(S01466MN) Chainage 230 – Chainage 337
Physical Target:
CW1: 5.174 Lane Km (Road Widening)
ROW: 19,030 sq. m.
Allocation:
TOTAL: P 100,000,000.00
CW1: P 88,780,000.00 (Road Widening)
ROW: P 7,720,000.00
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development
Road Widening – Primary Road
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) incl. ROW –
K1568+200 – K1568+491, K1568+529 – K1569+197, K1569+230 – K1569+338,
K1569+600 – K1569+727, K1581+434 – K1581+927, K1581+959 – K1582+027,
K1582+118 – K1583+259, (S00165MN) Chainage 000 – Chainage 201,
(S00165MN) Chainage 239 – Chainage 296, (S01465MN) Chainage 000 – Chainage 188,
(S01465MN) Chainage 226 – Chainage 316, (S01466MN) Chainage 000 – Chainage 197,
(S01466MN) Chainage 230 – Chainage 337
Physical Target:
CW1: 5.662 Lane Km (Road Widening)
ROW: 19,030 sq. m.
Allocation:
TOTAL: P 100,000,000.00
CW1: P 88,780,000.00 (Road Widening)
ROW: P 7,720,000.00
EAO: P 3,500,000.00
May 10, 2018 FY 2018 GAA WIN8C02656 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 1st District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Access Road Connecting Junction Tagduan Section, Brgy. San Jose to Sitio Lib-og, Brgy. Mercedes in support of Abaca and Coconut Industries, Caraga, Davao Oriental
Physical Target:
CW1: 8.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00

TO: Convergence and Special Support
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Access Road Connecting Junction Tagduan Section, Brgy. San Jose to Sitio Lib-og, Brgy. Mercedes in support of Abaca and Coconut Industries, Caraga, Davao Oriental
Physical Target:
CW1: 6.240 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
May 10, 2018 FY 2018 GAA WIN8C02657 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 1st District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Road Connecting Sitio Mahayahay to Sitio Buko Buko sa Anay in support to Coffee, Cacao, Abaca & Coconut Industries, Boston, Davao Oriental
Physical Target:
CW1: 7.200 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Construction of Concrete Road)
EAO: P 3,150,000.00

TO: Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Road Connecting Sitio Mahayahay to Sitio Buko Buko sa Anay in support to Coffee, Cacao, Abaca & Coconut Industries, Boston, Davao Oriental
Physical Target:
CW1: 6.588 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Construction of Concrete Road)
EAO: P 3,150,000.00
May 10, 2018 FY 2018 GAA WIN8C02655 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 1st District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment on Sheet Piles Foundation, Caraga, Davao Oriental
Physical Target:
CW1: 160 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 29,000,000.00
CW1: P 28,420,000.00 (Construction of Revetment)
EAO: P 580,000.00

TO: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment on Sheet Piles Foundation, Caraga, Davao Oriental
Physical Target:
CW1: 217.64 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 29,000,000.00
CW1: P 28,420,000.00 (Construction of Revetment)
EAO: P 580,000.00
May 10, 2018 FY 2018 GAA WIN8C02658 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 1st District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry - Davao Or Costal Rd incl. ROW -
K1690 + 263 - K1693 + 341
Physical Target:
CW1: 6.156 Lane Km (Road Widening)
ROW: 27,000.00 Square Meters
Allocation:
TOTAL: P 96,120,000.00
CW1: P 89,108,100.00 (Road Widening)
EAO: P 3,364,200.00
ROW: P 3,647,700.00

TO: OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry - Davao Or Costal Rd incl. ROW -
K1690 + 700 - K1693 + 341
Physical Target:
CW1: 5.19708 Lane Km (Road Widening)
ROW: 27,000.00 Square Meters
Allocation:
TOTAL: P 96,120,000.00
CW1: P 89,108,100.00 (Road Widening)
EAO: P 3,364,200.00
ROW: P 3,647,700.00
May 10, 2018 FY 2018 GAA WIN8C02600 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 1st District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment on Sheet Piles Foundation, Caraga River Bank Protection, Caraga, Davao Oriental
Physical Target:
CW1: 200.00 Lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00 (Construction of Revetment)
CW1: P 34,300,000.00
EAO: P 700,000.00

TO: OO2: Protect Lives and Properties Against Major Floods
Flood Management Program - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment on Sheet Piles Foundation, Caraga River Bank Protection, Caraga, Davao Oriental
Physical Target:
CW1: 136.20 Lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00 (Construction of Revetment)
CW1: P 34,300,000.00
EAO: P 700,000.00
May 10, 2018 FY 2018 GAA WIN8C02653 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 2nd District Engineering Office

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development
Paving of Unpaved Roads - Secondary Roads
Mati - Maragusan Rd -
K1502+120 - K1502+241, K1502+337 - K1503+660, K1504+518 - K1505+300
Physical Target:
CW1: 4.446 Lane Km (Paving of Unpaved Roads)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Paving of Unpaved Roads)
EAO: P 3,500,000.00

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development
Paving of Unpaved Roads - Secondary Roads
Mati - Maragusan Rd -
K1502+120 - K1502+241, K1502+337 - K1503+135, K1504+518 - K1505+300
Physical Target:
CW1: 3.609 Lane Km (Paving of Unpaved Roads)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Paving of Unpaved Roads)
EAO: P 3,500,000.00
May 10, 2018 FY 2018 GAA WIN8C02730 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Occidental District Engineering Office

MODIFICATION:

FROM: Local Program – Local Road and Bridges – Local Roads
Local Infrastructure Program
Construction of Roads, Sitio Mote, Brgy. Pinalpalan, Malita, Davao Occidental
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 6,500,000.00
CW1: P 6,435,000.00 (Construction of Concrete Road)
EAO: P 65,000.00

TO: Local Program – Local Road and Bridges – Local Roads
Local Infrastructure Program
Construction of Roads, Sitio Mote, Brgy. Pinalpalan, Malita, Davao Occidental
Physical Target:
CW1: 1.262 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 6,500,000.00
CW1: P 6,435,000.00 (Construction of Gravel Road)
EAO: P 65,000.00
May 10, 2018 FY 2018 GAA WIN8C02885 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Occidental District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Butulan, Jose Abad Santos, Davao Occidental
Physical Target:
CW1: 1,000.00 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 34,300,000.00 (Construction of Revetment)
EAO: P 700,000.00

TO: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Butulan, Jose Abad Santos, Davao Occidental
Physical Target:
CW1: 741.20 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 34,270,000.00 (Construction of Revetment)
ROW: P 30,000.00
EAO: P 700,000.00
May 10, 2018 FY 2018 GAA WIN8C02895 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Occidental District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Buhangin, Malita, Davao Occidental
Physical Target:
CW1: 1,000.00 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 34,300,000.00 (Construction of Revetment)
EAO: P 700,000.00

TO: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Buhangin, Malita, Davao Occidental
Physical Target:
CW1: 1,051.82 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 34,280,000.00 (Construction of Revetment)
ROW: P 20,000.00
EAO: P 700,000.00
May 10, 2018 FY 2018 GAA WIN8C02914 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Occidental District Engineering Office

MODIFICATION:

FROM: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Lamidan, Don Marcelino, Davao Occidental
Physical Target:
CW1: 860.00 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Revetment)
EAO: P 600,000.00

TO: OO2: Protect Lives and Properties – Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Concrete Revetment (RC Cut-off Wall), Lamidan, Don Marcelino, Davao Occidental
Physical Target:
CW1: 984.07 Lineal Meters (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,370,000.00 (Construction of Revetment)
ROW: P 30,000.00
EAO: P 600,000.00
May 10, 2018 FY 2018 GAA WIN8C02904 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Occidental District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction /Improvement of Access Roads leading to Declared Tourism Destinations
Brgy. Pangyan Road leading to Tudaya Falls, Pangyan, Malita, Davao Occidental
Physical Target:
CW1: 2.000 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: 49,000,000.00 (Construction of Gravel Road)
EAO: P 1,000,000.00

TO: Convergence and Special Support Program
Construction /Improvement of Access Roads leading to Declared Tourism Destinations
Brgy. Pangyan Road leading to Tudaya Falls, Pangyan, Malita, Davao Occidental
Physical Target:
CW1: 1.630 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: 49,000,000.00 (Construction of Concrete Road)
EAO: P 1,000,000.00
May 9, 2018 2018 310209100034000 GAA FY 2018 January 1, 2018 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development - Off-Carriageway Improvement -Tertiary Roads -

Claveria-Diaballo-Luzon-Cagayan Bdry Rd-K0619+601-K0619+761
May 9, 2018 2018 300203100236000 GAA FY 2018 January 1, 2018 Region II Cagayan 2nd District Engineering Office
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations

Pacac-Binubongan Road leading to Pader Falls, Incl. Bridge, Brgy. Binobongan, Allacapan, Cagayan
May 9, 2018 2018 WIN8C02696 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Araibo Road leading to Salvosa Falls, Brgy. Araibo, Pantukan, Compostela Valley
Physical Target:
CW1: 1.600 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

TO: Convergence and Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Araibo Road leading to Salvosa Falls, Brgy. Araibo, Pantukan, Compostela Valley
Physical Target:
CW1: 1.247 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00
May 9, 2018 2018 WIN8C02693 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program - Buildings and Other Structures - Multipurpose/Facilities - Local Infrastructure Program
Completion of Covered Court, Brgy. Katagan, Laak, Compostela Valley
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00 (Construction of Multi-Purpose Building)

TO: Local Program - Buildings and Other Structures - Multipurpose/Facilities - Local Infrastructure Program
Completion of Covered Court, Brgy. Kapatagan, Laak, Compostela Valley
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 1,000,000.00
CW1: P 1,000,000.00 (Construction of Multi-Purpose Building)
May 9, 2018 2018 WIN8C02774 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Mapawa Road leading to Rafflesia Conservation Site, Brgy. Mapawa, Maragusan, Compostela Valley
Physical Target:
CW1: 0.980 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

TO: Convergence and Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Mapawa Road leading to Rafflesia Conservation Site, Brgy. Mapawa, Maragusan, Compostela Valley
Physical Target:
CW1: 2.190 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00
May 9, 2018 2018 WIN8C02740 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure Including Local Projects
Concreting of Road at Brgy. Nuevo Iloco to Brgy. Bawani Section Mawab, Compostele Valley
Physical Target:
CW1 - 1.500 Lane Km (Construction of Concrete Road)
ALLOCATION
TOTAL: P 15,000,000.00
CW1 - P 14,700,000.00 (Construction of Concrete Road)
EAO - P 300,000.00

TO: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure Including Local Projects
Concreting of Road at Brgy. Nuevo Iloco, Mawab, Compostele Valley
Physical Target:
CW1 - 2.200 Lane Km (Construction of Concrete Road)
ALLOCATION
TOTAL: P 15,000,000.00
CW1 - P 14,700,000.00 (Construction of Concrete Road)
EAO - P 300,000.00
May 9, 2018 2018 WIN8C02697 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program
Local - Buildings and Other Structures - Multipurpose/Facilities - Local Infrastructure Program
Construction of Multi-Purpose Building (Mini Gym) at Banbanan ES, Laak, Compostela Valley
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 1,600,000.00
CW1: P 1,584,000.00
EAO: P 16,000.00

TO: Local Program
Local - Buildings and Other Structures - Multipurpose/Facilities - Local Infrastructure Program
Construction of Multi-Purpose Building (Mini Gym) at Banbanon ES, Laak, Compostela Valley
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 1,600,000.00
CW1: P 1,584,000.00
EAO: P 16,000.00
May 9, 2018 2018 WIN8C02694 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program
Local - Buildings and Other Structures - School Buildings - Local Infrastructure Program
Construction of Two (2) Classroom School Building with CR, Madrasah, Brgy. Bongabong, Pantukan, Compostela Valley
Physical Target:
CW1: 2 number of classrooms (Construction of Classrooms)
ALLOCATION
TOTAL: P 2,500,000.00
CW1: P 2,475,000.00
EAO: P 25,000.00

TO: Local Program
Local - Buildings and Other Structures - School Buildings - Local Infrastructure Program
Construction of Two (2) Classroom School Building with CR, Madrasah, Brgy. Bongbong, Pantukan, Compostela Valley
Physical Target:
CW1: 2 number of classrooms (Construction of Classrooms)
ALLOCATION
TOTAL: P 2,500,000.00
CW1: P 2,475,000.00
EAO: P 25,000.00
May 9, 2018 2018 WIN8C02700 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Local Program
Local - Buildings and Other Structure - Multipurpose / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of MPB (Brgy. Hall) Tambongan, Pantukan, Compostela
Physical Target:
CW1 - 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 4,500,000.00
CW1 - P 4,410,000.00 (Construction of Multi-Purpose Building)
EAO - P 90,000.00

TO: Local Program
Local - Buildings and Other Structure - Multipurpose / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of MPB (Brgy. Hall) Tambongon, Pantukan, Compostela
Physical Target:
CW1 - 1 number of buildings (Construction of Multi-Purpose Building)
ALLOCATION
TOTAL: P 4,500,000.00
CW1 - P 4,410,000.00 (Construction of Multi-Purpose Building)
EAO - P 90,000.00
May 9, 2018 2018 WIN8C02775 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Linda Road leading to Ecotourism Park, Brgy. Linda, Nabunturan, Compostela Valley
Physical Target:
CW1: 1.638 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Linda Road leading to Ecotourism Park, Brgy. Linda, Nabunturan, Compostela Valley
Physical Target:
CW1: 2.784 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00
EAO: P 400,000.00

Pages