P2.1B access road, to connect ports of Agusan del Norte

The Department of Public Works and Highways (DPWH) is constructing an access road that will directly connect Nasipit International Port to Masao National Port Road in Agusan del Norte.

Costing P2.1 billion, the ongoing Nasipit – Buenavista – Masao Port Coastal Road project now 23 percent completed is a 5.79-kilometer road opening and 18.90-kilometer road upgrading from Nasipit Road to Butuan City - Masao Port Road, with provision of drainage, slope protection, and road safety devices.

P2.1B access road, to connect ports of Agusan del Norte

The Department of Public Works and Highways (DPWH) is constructing an access road that will directly connect Nasipit International Port to Masao National Port Road in Agusan del Norte.

Costing P2.1 billion, the ongoing Nasipit – Buenavista – Masao Port Coastal Road project now 23 percent completed is a 5.79-kilometer road opening and 18.90-kilometer road upgrading from Nasipit Road to Butuan City - Masao Port Road, with provision of drainage, slope protection, and road safety devices.

DPWH to complete 2 bridge widening projects in Santa Cruz, Occidental Mindoro in Q2

Works are ongoing for the widening from two (2) lanes to four (4) lanes of Pola and Aribugan Bridges along Mindoro West Coast Road in the town of Sta. Cruz, Occidental Mindoro Province.

DPWH Mindoro Occidental District Engineer Josefino M. Melgar Jr. reported that the ongoing bridge widening projects located at Barangays Barahan and Poblacion I are being fast-tracked for completion by the second quarter of 2020.

DPWH to complete 2 bridge widening projects in Santa Cruz, Occidental Mindoro in Q2

Works are ongoing for the widening from two (2) lanes to four (4) lanes of Pola and Aribugan Bridges along Mindoro West Coast Road in the town of Sta. Cruz, Occidental Mindoro Province.

DPWH Mindoro Occidental District Engineer Josefino M. Melgar Jr. reported that the ongoing bridge widening projects located at Barangays Barahan and Poblacion I are being fast-tracked for completion by the second quarter of 2020.

Cale Bridge widening in Iloilo nearing completion

The Department of Public Works and Highways (DPWH) Iloilo 2nd District Engineering Office (DEO) posted 75 percent completion rate for the widening of Cale Bridge in Barangay Naslo, Pototan, Iloilo.

DPWH Iloilo 2nd DEO District Engineer Sanny Boy O. Oropel reported that the 25.5-lineal meter Cale Bridge along Pototan-Tina-Lambunao Road presently undergoes widening from two (2) to four (4) lanes with abutment on reinforced concrete piles foundation, an asphalt overlay both on the newly constructed and existing sides, and construction of concrete and slope protection.

Cale Bridge widening in Iloilo nearing completion

The Department of Public Works and Highways (DPWH) Iloilo 2nd District Engineering Office (DEO) posted 75 percent completion rate for the widening of Cale Bridge in Barangay Naslo, Pototan, Iloilo.

DPWH Iloilo 2nd DEO District Engineer Sanny Boy O. Oropel reported that the 25.5-lineal meter Cale Bridge along Pototan-Tina-Lambunao Road presently undergoes widening from two (2) to four (4) lanes with abutment on reinforced concrete piles foundation, an asphalt overlay both on the newly constructed and existing sides, and construction of concrete and slope protection.

Drainage project along Buenavista-Bunaguit Road, now completed

The Department of Public Works and Highways (DPWH) has completed the construction of drainage canals along a section of Buenavista – Bunaguit Road in Agusan del Norte.

In his report, DPWH Agusan del Norte District Engineer Edmund V. Opinion said that the P14.6 million project involves construction of 1,108 lineal meter concrete drainage/line canal with provision of gravel road widening.

Drainage project along Buenavista-Bunaguit Road, now completed

The Department of Public Works and Highways (DPWH) has completed the construction of drainage canals along a section of Buenavista – Bunaguit Road in Agusan del Norte.

In his report, DPWH Agusan del Norte District Engineer Edmund V. Opinion said that the P14.6 million project involves construction of 1,108 lineal meter concrete drainage/line canal with provision of gravel road widening.

Improvement of San Jose – Llanera Road in N. Ecija almost complete

Rehabilitation works on the San Jose – Llanera Road in the municipality of Llanera, Nueva Ecija is now 90 percent complete.

According to Department of Public Works and Highways (DPWH) Region 3 Director Roseller A. Tolentino, the improvement of the 3.472- kilometer road started in June 2019 will provide better travel experience for motorists.

“The quality of the road has been greatly affected by the volume of vehicles passing through the road everyday, thus the need to rehabilitate it to guarantee safer and smoother travel,” said Director Tolentino.

Improvement of San Jose – Llanera Road in N. Ecija almost complete

Rehabilitation works on the San Jose – Llanera Road in the municipality of Llanera, Nueva Ecija is now 90 percent complete.

According to Department of Public Works and Highways (DPWH) Region 3 Director Roseller A. Tolentino, the improvement of the 3.472- kilometer road started in June 2019 will provide better travel experience for motorists.

“The quality of the road has been greatly affected by the volume of vehicles passing through the road everyday, thus the need to rehabilitate it to guarantee safer and smoother travel,” said Director Tolentino.