Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
May 23, 2018 FY 2018 GAA WIN8C03043 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Island Garden City of Samal (IGACOS) Circumferential Road (West Side), Package 2, Davao del Norte
Physical Target:
CW1: 15.308 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 450,000,000.00
CW1: P 434,250,000.00 (Construction of Concrete Road)
EAO: P 15,750,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Island Garden City of Samal (IGACOS) Circumferential Road (West Side), Package 2, Davao del Norte
Physical Target:
CW1: 213798 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 450,000,000.00
CW1: P 434,250,000.00 (Construction of Concrete Road)
EAO: P 15,750,000.00
May 23, 2018 FY 2018 GAA WIN8C03049 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides – Secondary Roads
Davao-Sarangani Coastal Rd (Malalag-Malita-JAS-G) – K1672 + 675 - K1672 + 705,
K1673 + 600 - K1673 + 700, K1675 + 475 - K1679 + 048
Physical Target:
CW1: 3,900.00 sq. m. (Construction of Road Slope Protection Structure)
CW2: 6.860 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 145,878,000.00
CW1: P 87,815,000.00 (Construction of Road Slope Protection Structure)
CW2: P 52,957,270.00 (Asphalt Overlay)
EAO: P 5,105,730.00

TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides – Secondary Roads
Davao-Sarangani Coastal Rd (Malalag-Malita-JAS-Glan) –
K1670 + 650 - K1670 + 860, K1670 + 740 - K1670 + 760, K1672 + 660 - K1672 + 705,
K1673 + 600 - K1673 + 700, K1673 + 860 - K1673 + 960, K1675 + 475 - K1677 + 000
Physical Target:
CW1: 3,000.00 sq. m. (Construction of Road Slope Protection Structure)
CW2: 3.04744 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 145,878,000.00
CW1: P 100,301,497.80 (Construction of Road Slope Protection Structure)
CW2: P 40,470,772.22 (Asphalt Overlay)
EAO: P 5,105,730.00
May 23, 2018 FY 2018 GAA WIN8C03038 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Bayabas - Handurumog Road Nabunturan, Compostela Valley
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Bayabas - Handurumog Road Nabunturan, Compostela Valley
Physical Target:
CW1: 1.498 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
May 23, 2018 FY 2018 GAA WIN8C03033 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Bukidnon-Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon-Laak-Compostela Valley), Package 5, incl. ROW, Davao del Norte
Physical Target:
CW1: 13.428 Lane Km (Construction of Concrete Road)
ROW: 100,710.00 sq. m.
Allocation:
TOTAL: P 312,000,000.00
CW1: P 291,555,450.00 (Construction of Concrete Road)
ROW: P 9,524,550.00
EAO: P 10,920,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Bukidnon-Compostela Valley Road (Brgy. Namnam, San Fernando, Bukidnon-Laak-Compostela Valley), Package 5, incl. ROW, Davao del Norte
Physical Target:
CW1: 8.49298 Lane Km (Construction of Concrete Road)
CW2: 821.2032 sq. m. (Construction of Concrete Bridge)
CW3: 381.60 sq. m. (Construction of Concrete Bridge)
ROW: 100,710.00 sq. m.
Allocation:
TOTAL: P 312,000,000.00
CW1: P 177,771,295.75 (Construction of Concrete Road)
CW2: P 80,450,661.34 (Construction of Concrete Bridge)
CW3: P 33,333,492.91 (Construction of Concrete Bridge)
ROW: P 9,524,550.00
EAO: P 10,920,000.00
May 23, 2018 FY 2018 GAA WIN8C03048 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Road-Talandang-Sumimao-Pañalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Package B, incl. ROW and Bridge, Davao del Norte
Physical Target:
CW1: 8.560 Lane Km (Construction of Gravel Road)
CW2: 286.20 sq. m. (Construction of Concrete Bridge)
CW3: 286.20 sq. m. (Construction of Concrete Bridge)
CW4: 286.20 sq. m. (Construction of Concrete Bridge)
CW5: 286.20 sq. m. (Construction of Concrete Bridge)
ROW: 65,535.60 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 103,225,000.00 (Construction of Gravel Road)
CW2: P 28,226,250.00 (Construction of Concrete Bridge)
CW3: P 28,226,250.00 (Construction of Concrete Bridge)
CW4: P 28,226,250.00 (Construction of Concrete Bridge)
CW5: P 28,226,250.00 (Construction of Concrete Bridge)
ROW: P 6,272,500.00
EAO: P 8,750,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Road-Talandang-Sumimao-Pañalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Package B, incl. ROW and Bridge, Davao del Norte
Physical Target:
CW1: 4.714 Lane Km (Construction of Gravel Road)
CW2: 429.30 sq. m. (Construction of Concrete Bridge)
CW3: 429.30 sq. m. (Construction of Concrete Bridge)
ROW: 65,535.60 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 140,000,544.17 (Construction of Gravel Road)
CW2: P 51,720,653.19 (Construction of Concrete Bridge)
CW3: P 43,234,302.64 (Construction of Concrete Bridge)
ROW: P 6,272,500.00
EAO: P 8,750,000.00
May 23, 2018 FY 2018 GAA WIN8C03041 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Apalaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 1, incl. Bridge, Davao City
Physical Target:
CW1: 2.380 Lane Km (Construction of Asphalt Road)
CW2: 3,460.00 sq. m. (Construction of Road Slope Protection Structure)
CW3: 292.95 sq. m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 250,000,000.00
CW1: P 172,445,500.00 (Construction of Asphalt Road)
CW2: P 49,504,500.00 (Construction of Road Slope Protection Structure)
CW3: P 19,300,000.00 (Construction of Concrete Bridge)
EAO: P 8,750,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Davao City Coastal Bypass Road at Jct. Davao-Cotabato Road-Bago Apalaya-Talomo-Matina Aplaya-Roxas Avenue-Sta. Ana Wharf-R. Castillo (Bago Aplaya-Times Beach), Package 1, incl. Bridge, Davao City
Physical Target:
CW1: 2.636Lane Km (Construction of Concrete Road)
CW2: 1,376.86 sq. m. (Construction of Road Slope Protection Structure)
CW3: 243.22 sq. m. (Construction of Concrete Bridge)
CW4: 1.028 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 250,000,000.00
CW1: P 179,640,110.18 (Construction of Asphalt Road)
CW2: P 23,337,474.65 (Construction of Road Slope Protection Structure)
CW3: P 35,313,018.57 (Construction of Concrete Bridge)
CW4: P 2,959,396.60 (Construction of Gravel Road)
EAO: P 8,750,000.00
May 23, 2018 FY 2018 GAA WIN8C03037 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program - Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Bongkilaton Road leading to Mandaya Village, Pansan Falls, Bongkilaton Cave and Tagbubunlas Falls, Brgy. Ngan, Compostela Valley
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,0000.00 (Construction of Concrete Road)
EAO: P 400,000.00

TO: Convergence and Special Support Program - Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Bongkilaton Road leading to Mandaya Village, Pansan Falls, Bongkilaton Cave and Tagbubunlas Falls, Brgy. Ngan, Compostela Valley
Physical Target:
CW1: 1.403 Lane Km (Construction of Concrete Road)
CW2: 348.000 Lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 14,787,930.00 (Construction of Concrete Road)
CW2: P 4,812,070.00 (Construction of Revetment)
EAO: P 400,000.00
May 23, 2018 FY 2018 GAA WIN8C03025 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Road-Talandang-Sumimao-Pañalum-Tapak-Cabanglasan-Aglayan, Malaybalay, Package A, incl. ROW and Bridge, Davao City
Physical Target:
CW1: 2.500 Lane Km (Construction of Concrete Road)
CW2: 1,908.00 sq. m. (Construction of Concrete Bridge)
ROW: 11,627.907 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 48,250,000.00 (Construction of Concrete Road)
CW2: P 231,600,000.00 (Construction of Concrete Bridge)
ROW: P 9,650,000.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Road-Talandang-Sumimao-Pañalum-Tapak-Cabanglasan-Aglayan, Malaybalay, Package A, incl. ROW and Bridge, Davao City
Physical Target:
CW1: 2.500 Lane Km (Construction of Concrete Road)
CW2: 381.60 sq. m. (Construction of Concrete Bridge)
CW3: 429.30 sq. m. (Construction of Concrete Bridge)
CW4: 10.34678 Lane Km (Construction of Gravel Road)
ROW: 11,627.907 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 56,183,759.92 (Construction of Concrete Road)
CW2: P 33,336,090.22 (Construction of Concrete Bridge)
CW3: P 39,477,236.29 (Construction of Concrete Bridge)
CW4: P 150,852,913.58 (Construction of Gravel Road)
ROW: P 9,650,000.00
EAO: P 10,500,000.00
May 23, 2018 FY 2018 WIN8G02165 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 300203100319000
Project ID: P00230346LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Access Road from Virac to Bagamanoc leading to Paday Falls, Bagamanoc, Catanduanes
Physical Target - CW1 – Construction of Concrete Road/ 0.94 lane-km
Unit Cost: CW1 – Php 16.68M /lane-km
Estimated Cost: Php 16.0M
(As Modified)
May 23, 2018 FY 2018 WIN8G01912 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 300203100320000
Project ID: P00230399LZ
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – San Andres-Pandan-Hiyop Access Road leading to Hiyop Highlands and Su-nog Sea Cave, San Andres, Catanduanes
Physical Target - CW1 – Construction of Concrete Road/ 2.275 lane-km
Unit Cost: CW1 – Php 14.215M /lane-km
Estimated Cost: Php 33.0M
(As Modified)
May 23, 2018 FY 2018 WIN8G02167 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 300117201439000
Project ID: P00255760LZ
Local Program – Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Road, Brgy. Rizal, Viga, Catanduanes
Physical Target - CW1 – Construction of Concrete Road/ 0.2814 lane-km
Unit Cost: CW1 – Php 10.55M /lane-km
Estimated Cost: Php 3.0M
(As Modified)

May 23, 2018 FY 2018 GAA WIN8C03028 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement/Concreting of Jct. Davao-Bukidnon Rd (Calinan Section)-Wangan-Subasta-Tagakpan-Tungkalan-Tagarano-Bayabas-Catigan-Baracatan-Sibulan Road, Davao City
Physical Target:
CW1: 6.220 Lane Km (Construction of Concrete Road)
CW2: 773.00 sq. m. (Construction of Concrete Bridge)
ROW: 24,105.00 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 91,573,675.00 (Construction of Concrete Road)
CW2: P 78,165,000.00 (Construction of Concrete Bridge)
ROW: P 23,261,325.00
EAO: P 7,000,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement/Concreting of Jct. Davao-Bukidnon Rd (Calinan Section)-Wangan-Subasta-Tagakpan-Tungkalan-Tagurano-Bayabas-Catigan-Baracatan-Sibulan Road, Davao City
Physical Target:
CW1: 3.774 Lane Km (Construction of Concrete Road)
CW2: 429.30 sq. m. (Construction of Concrete Bridge)
CW3: 200.34 sq. m. (Replacement of Bridge)
CW4: 0.591 Lane Km (Construction of Gravel Road)
ROW: 24,105.00 sq. m.
Allocation:
TOTAL: P 200,000,000.00
CW1: P 99,782,383.82 (Construction of Concrete Road)
CW2: P 44,040,342.13 (Construction of Concrete Bridge)
CW3: P 23,079,631.49 (Replacement of Bridge)
CW4: P 2,836,317.56 (Construction of Gravel Road)
ROW: P 23,261,325.00
EAO: P 7,000,000.00
May 23, 2018 FY 2018 WIN8G01913 FY 2018 GAA R.A. 10964 December 29, 2016 Region V Catanduanes District Engineering Office
UACS No.: 320101101708000
Project ID: P00220672LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Drainage Structure along Sibanhan River, Sta. 0+000 - Sta.0+952, Virac, Catanduanes
Physical Target - CW - Construction of Drainage Structure/ 952.0 lm.
Unit Cost: CW1 - Php 30,882.35/lm
Estimated Cost: Php 30.0M
(As Modified)
May 23, 2018 FY 2018 WIN8G02173 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 320101101720000
Project ID: P00223411LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of River Protection, Brgy. San Nicolas, Panganiban, Catanduanes
Physical Target - CW1 - Construction of Flood Mitigation Structure/ 452 lm
Unit Cost: Php 43,363/lm
Estimated Cost: Php 20.0M
(As Modified)
May 23, 2018 FY 2018 WIN8G01871 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310111100045000
Project ID: P00202645LZ
OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program - Construction/Upgrading/Rehabilitation of Drainage along National Roads –Secondary Roads – Catanduanes Cir Rd - K0121+000 - K0122+000, K0122+000 - K0122+540
Physical Target - CW1 - Construction of Drainage Structure along Road/ 1,545.59 lm.
Unit Cost: CW1 – Php 11,316.11/lm.
Estimated Cost: Php 17.847M
(As Modified)
May 23, 2018 FY 2018 GAA WIN8C03026 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Carmen-Tagum City Coastal Road, incl. ROW, Carmen, Tagum City, Davao del Norte
Physical Target:
CW1: 9.596 Lane Km (Construction of Gravel Road)
ROW: 71,970.00 sq. m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 138,916,575.00 (Construction of Gravel Road)
ROW: P 5,833,425.00
EAO: P 5,250,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Carmen-Tagum City Coastal Road, incl. ROW, Carmen, Tagum City, Davao del Norte
Physical Target:
CW1: 5.184 Lane Km (Construction of Gravel Road)
CW2: 861.27 sq. m. (Construction of Concrete Bridge)
ROW: 71,970.00 sq. m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 37,115,676.61 (Construction of Gravel Road)
CW2: P 101,800,898.39 (Construction of Concrete Bridge)
ROW: P 5,833,425.00
EAO: P 5,250,000.00
May 23, 2018 FY 2018 WIN8G02049 FY 2018 GAA R.A. 10964 November 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310111100046000
Project ID: P00202644LZ
OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program - Construction/Upgrading/Rehabilitation of Drainage along National Roads – Secondary Roads – Catanduanes Cir Rd – K0201+000 – K0201+811
Physical Target - CW1 - Construction of Drainage Structure along Road/ 115.58 lm.
Unit Cost: CW1 – Php 63,159.89/lm.
Estimated Cost: Php 7.449M
(As Modified)
May 23, 2018 FY 2018 WIN8G01911 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310209100069000
Project ID: P00202648LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Off-Carriageway Improvement - Tertiary Roads - Jct Bato-Baras Rd incl. ROW - K0008+-003 - K0008+579, K0012+000 - K0012+940
Physical Target - CW1 - Off-Carriageway improvement: Shoulder Paving/Construction/ 6,566.00 sq.m.
Right-of-Way Acquisition (ROW)/ 3,492 sq.m.
Unit Cost: CW1 – Php 7,401.49/sq.m.
ROW Acquisition – Php 103.84/sq.m.
Estimated Cost: Php 49.960M
(As Modified)
May 23, 2018 FY 2018 GAA WIN8C03032 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office

MODIFICATION:

FROM: Local Roads - Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Kao-Cabacungan-Dauis Road Phase 1, Nabunturan, Compostela Valley
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Roads - Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Kao-Cabacungan-Dauis Road Phase 1, Nabunturan, Compostela Valley
Physical Target:
CW1: 1.187 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
May 23, 2018 FY 2018 WIN8G01872 FY 2018 GAA R.A. 10964 November 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310212100060000
Project ID: P00202650LZ
OO1: Ensure Safe and Reliable National Road System – Network Development Program - Paving of Unpaved Roads - Tertiary Roads - Baras-Gigmoto-Viga Rd - K0056+031.50 - K0056+146.50, K0056+502.62 - K0056+530.92, K0064+155 - K0064+582.50
Physical Target - CW1 - Paving of unpaved Roads/1.1416 lane-km
Unit Cost: CW1 - Php 13.091M/ lane-km
Estimated Cost: Php 15.25 M
(As Modified)
May 23, 2018 FY 2018 WIN8G01870 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310109100088000
Project ID: P00200936LZ
OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse and Landslide - Tertiary Roads - Baras-Gigmoto-Viga Rd - K0031+700 - K0032+052, K0081+440 - K0081+590
Physical Target - CW1 - Construction of Road Slope Protection Structure/ 4,057.09 sq.m.
Unit Cost: Php 4,831.05/sq.m.
Estimated Cost: Php 20.0M
(As Modified)

May 23, 2018 FY 2018 WIN8G02051 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Catanduanes District Engineering Office
UACS No.: 310106100148000
Project ID: P00202641LZ
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation Program - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads - Baras-Gigmoto-Viga Rd - K0027+185 - K0027+499, K0027+522 - K0027+651, K0040+900 - K0041+000, K0041+243 - K0041+473, K0083+550 - K0083+600
Physical Target - CW1 -Rehabilitation of Paved Road/ 1.44 lane-km
Unit Cost: Php 9.403 M/lane-km
Estimated Cost: Php 13.855M
(As Modified)
May 22, 2018 FY 2018 WIN8C02997 300203100521000 May 10, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No. 300203100521000
Project ID: P00230026MN

CSSP: Convergence and Special Support Program -
Construction/Improvement of Access Roads leading to Declared Tourism Destination
NRJ leading to Philippine Eagle Sanctuary, Brgy. Dakayakan, Midsalip, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Concrete Road: 1.60 lane km
Unit Cost: CW-1 - Construction of Concrete Road: P 13.781M/lane km
EAO: P 0.45M
Allocation: 22.5M
May 22, 2018 FY 2018 WIN8C02862 300204100202000 May 7, 2018 Region IX Zamboanga del Sur 1st District Engineering Office
UACS No: 300204100202000
Project ID: P00230034MN

CSSP: Convergence and Special Support Program -
Construction/Improvement of Acces Roads leading to Trades, Industries and Economic Zones
NRJ to Brgy. Upper Timonan - Marangan - Kahayagan - Palili - Timbaboy in Support of Abaca Handicraft Processing, Zamboanga del Sur
Physical Target:
CW-1 - Construction of Concrete Road: 2.286 lane km
Unit Cost: CW-1 - Construction of Concrete Road: P 8,573,930/lane km
EAO: P 0.40M
Allocation: P 20.0M
May 22, 2018 FY 2018 WIN8C02683 310101100111000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No: 310101100111000
Project ID: P00200007MN

OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
Lanao - Pagadian - Zamboanga City Rd
K1786+786.00 - K1786+804.00, K1786+813.00 - K1786+826.50, K1786+890.50 - K1786+908.50, K1786+926.50 - K1786+967.00, K1787+004.50 - K1787+036.00, K1787+049.50 - K1787+103.50, K1787+113.50 - K1787+190.00, K1787+204.50 - K1787+213.50, K1787+218.00 - K1787+245.00, K1808+004.50 - K1808+067.50, K1808+085.50 - K1808+209.00, K1808+209.00 - K1808+227.00, K1808+227.00 - K1808+243.00, K1808+254.00 - K1808+263.00, K1808+288.00 - K1808+360.00, K1808+364.50 - K1808+387.00, K1808+400.50 - K1808+495.00, K1808+513.00 - K1808+576.00, K1808+667.50 - K1808+676.50, K1808+700.00 - K1808+704.50, K1808+726.00 - K1808+789.00, K1808+818.00 - K1808+863.00, K1808+874.50 - K1808+897.00, K1808+951.00 - K1808+973.50, K1810+460.00 - K1811+000.00, K1812+332.00 - K1812+458.00, K1812+471.50 - K1812+489.50, K1812+489.50 - K1812+507.50, K1812+507.50 - K1812+611.00, K1812+611.00 - K1812+665.00, K1812+692.00 - K1812+867.50, K1812+881.00 - K1812+890.00, K1812+894.50 - K1812+912.50, K1812+930.50 - K1813+000.00
Physical Target:
CW-1 - Concrete Reblocking: 3.3185 lane km
Unit Cost: CW-1 - Concrete Reblocking: P 9,261,642.31/lane km
EAO: P 0.62724M
Allocation: P 31.362M
May 22, 2018 FY 2018 WIN8C02721 300117201989000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No: 300117201989000
Project ID: P00251836MN

Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Road Concreting, Brgy. Cawit, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road: 0.34 lane km
Unit Cost: CW-1 - Construction of Concrete Road: P 8,735,294.12 lane km
EAO: P 30,000.00
Allocation: P 3,000,000.00
May 22, 2018 FY 2018 WIN8C02935 300109200208000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No: 300109200208000
Project ID: P00250071MN

Local Program:
Local - Flood Control and Drainage -
Drainage/Protection Works - Local Infrastructure Program
Construction of Drainage System, Sta. Catalina, Zamboanga City
Physical Target:
CW-1: Construction of Drainage System: 156.00 l.m.
Unit Cost: CW-1: Construction of Drainage System: P 9,519.23/l.m.
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 22, 2018 FY 2018 WIN8C02674 300107200217000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No: 300107200217000
Project ID: P00251832MN

Local Program:
Flood Control and Drainage - Flood Control Structures/Facilities - Local Infrastructure Program
Construction of Drainage Facilities at San Roque, Zamboanga City
Physical Target:
CW-1: Construction of Drainage Structure: 164.00 lm
Unit Cost: CW-1: Construction of Drainage Structure: P 18,109.76/lm
EAO: P 30,000.00
Allocation: P 3,000,000.00
May 22, 2018 FY 2018 WIN8C02702 300202100069000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No: 300202100069000
Project ID: P00230005MN

Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Seaports
Acces Road leading to Panubigan Wharf, Zamboanga City
Physical Target:
CW-1: Construction of Concrete Road: 1.40 lane km
Unit Cost: CW-1: Construction of Concrete Road: P 17,220,000.00/lane km
EAO: P 492,000.00
Allocation: P 24,600,000.00
May 22, 2018 FY 2018 WIN8C02704 300117201975000 May 3, 2018 Region IX Zamboanga City 2nd District Engineering Office
UACS No: 300117201975000
Project ID: P00250076MN

Local Program:
Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road, Cabaluay, Zamboanga City
Physical Target:
CW-1: Construction of Concrete Road: 0.21 lane km
Unit Cost: CW-1: Construction of Concrete Road: P 7,071.43/lane km
EAO: P 15,000.00
Allocation: P 1,500,000.00
May 21, 2018 FY - 2018 WIN8F05458 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
001 - Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Puerto Princesa North Rd
K0111+200 - K0112+284

CW1: 4.36 lane km ( Road Widening )
Allocation: 89,462,000 Php

TO:
Puerto Princesa North Rd
K0111+200 - K0112+878

CW1: 6.74 lane km ( Road Widening )
Allocation: 89,462,000 Php

May 21, 2018 FY - 2018 WIN8F05457 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
001 - Ensure Safe and Reliable National Road System

Network Development - Off-Carriageway Improvement
- Secondary Road

FROM:
El Nido -Jct. New Ibahay Rd
K0273+583 - K0276+168,
K0276+337 - K0277+000

CW1: 7,440 sq.m. ( Off-Carriageway Improvement
Shoulder Paving/Construction )
Allocation: 66,960,000 Php

TO:
El Nido - Jct New Ibahay Rd
K0273+235.3 - K0276+168,
K0276+337.0 - K0277+000

CW1: 15,776030 sq.m. ( Off-Carriageway Improvement
Shoulder Paving/Construction )
Allocation: 66,960,000 Php
May 21, 2018 FY - 2018 WIN8F05461 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
002 - Protect Lives and Properties Against Major Floods

Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage Systems

FROM:
Construction of Flood Control Structure at Tapiken Bridge,
CBNR, Palawan

CW1: 260 lm ( Construction of Flood Control Mitigation
Structure )
Allocation: 10,000,000 Php

TO:
Construction of Flood Control Structure at Tapiken Bridge,
CBNR, Busuanga, Palawan

CW1: 227 lm ( Construction of Flood Mitigation Structure )
Allocation: 10,000,000 Php


May 21, 2018 FY - 2018 WIN8F05459 FY _ 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
001 - Endure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Puerto Princesa North Rd.
K0220 + 000 - K02220 + 000

CW1: 4.008 lane km ( Road Widening )
Allocation: 75,818,000 Php

TO:
Puerto Princesa North Rd
K0219 + 015 - K0222 + 000

CW1: 6 lane km ( Road Widening )
Allocation: 75,818,00 Php
May 21, 2018 FY - 2018 WIN8F05462 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
Convergence Special Support Program

Convergence and Special Support -
Construction/Improvement of Access Roads leading to
Declared Tourism Destinations

FROM:
Mampio Road from Seaport to Cagayancillo Poblacion,
Brgy. Mampio, Cagayancillo, Palawan

CW1: 20 lane km ( Construction of Concrete Road )
Allocation : 60,000,000 Php

TO:
Mampio Road from Seaport to Cagayancillo Poblacion,
Brgy. Mampio, Cagayancillo, Palawan

CW1: 4.84 lane km ( Construction of Concrete Road )
Allocation: 60,000,000 Php
May 21, 2018 FY - 2018 WIN8F05463 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
002 - Protect Lives and Properties against Major Floods

Flood Management - Construction/Maintenance of Flood
Mitigation Structures and Drainage Systems

FROM:
Construction of Flood Control Structure at Caramay Bridge,
PPNR, Palawan

CW1: 715 lm ( Construction of Flood Mitigation Structure )
Allocation: 20,000,000 Php

TO:
Construction of Flood Control Structure at Caramay Bridge,
PPNR, Roxas, Palawan

CW1: 530 lm ( Construction of Flood Mitigation Structure )
Allocation: 20,000,000 Php
May 21, 2018 FY 2018 GAA WIN8C02989 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Samal Bridge leading to San Remigio, Samal Island, Davao City
Physical Target:
CW1: 19.430 Lane Km (Construction of Concrete Road)
ROW: 97,150.00
Allocation:
TOTAL: P 300,000,000.00
CW1: P 281,249,250.00 (Construction of Concrete Road)
ROW: P 8,250,750.00
EAO: P 10,500,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Samal Bridge leading to San Remigio, Samal Island, Davao del Norte
Physical Target:
CW1: 17.388 Lane Km (Construction of Concrete Road)
ROW: 97,150.00
Allocation:
TOTAL: P 300,000,000.00
CW1: P 281,249,250.00 (Construction of Concrete Road)
ROW: P 8,250,750.00
EAO: P 10,500,000.00
May 21, 2018 FY - 2018 WIN8F05464 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
002 - Protect Lives and Properties against Major Floods

Flood Management - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

FROM: Construction of Flood Control Structure at Dipuyai Bridge, Coron - Busuanga Road, Palawan

CW1: 261 lm ( Construction of Flood Mitigation Structure )
Allocation: 10,000,000 Php

TO:
Construction of Flood Control Structure at Dipuyai Bridge, Coron - Busuanga Road, Coron, Palawan

CW1: 209.50 lm ( Construction of Flood Mitigation
Structure )
Allocation: 10,000,000 Php
May 21, 2018 FY 2018 GAA WIN8C03003 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Fatima-Malabog Road to Mabuhay-Pañalum-Paquibato Road, Package B, incl. ROW, Davao City
Physical Target:
CW1: 8.760 Lane Km (Construction of Concrete Road)
CW2: 2.654 Lane Km (Reconstruction from Paved to Concrete)
ROW: 9,096.00 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 231,327,870.00 (Construction of Concrete Road)
CW2: P 53,783,310.00 (Reconstruction from Paved to Concrete)
ROW: P 4,388,820.00
EAO: P 10,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Fatima-Malabog Road to Mabuhay-Pañalum-Paquibato Road, Package B, incl. ROW, Davao City
Physical Target:
CW1: 6.754 Lane Km (Construction of Concrete Road)
CW2: 2.213 Lane Km (Reconstruction from Paved to Concrete)
ROW: 9,096.00 sq. m.
Allocation:
TOTAL: P 300,000,000.00
CW1: P 147,061,491.59 (Construction of Concrete Road)
CW2: P 41,549,688.41 (Reconstruction from Paved to Concrete)
ROW: P 4,388,820.00
EAO: P 7,000,000.00
EXC: P 100,000,000.00 (Excess)
May 21, 2018 FY 2018 GAA WIN8C03000 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Grande-Talandag-Sumimao-Panalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Package A, incl. ROW and Bridge, Davao del Norte
Physical Target:
CW1: 10.320 Lane Km (Construction of Gravel Road)
CW2: 763.20 sq. m. (Construction of Concrete Bridge)
ROW: 78,163.20 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 124,485,000.00 (Construction of Gravel Road)
CW2: P 109,045,000.00 (Construction of Concrete Bridge)
ROW: P 7,720,000.00
EAO: P 8,750,000.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Alternate Road from Region XI to Region X (Jct. Davao City Diversion Road-Catalunan Grande-Talandag-Sumimao-Panalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Package A, incl. ROW and Bridge, Davao del Norte
Physical Target:
CW1: 12.212 Lane Km (Construction of Gravel Road)
CW2: 429.30 sq. m. (Construction of Concrete Bridge)
ROW: 78,163.20 sq. m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 194,396,985.49 (Construction of Gravel Road)
CW2: P 39,133,014.51 (Construction of Concrete Bridge)
ROW: P 7,720,000.00
EAO: P 8,750,000.00
May 21, 2018 FY 2018 GAA WIN8C02991 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides – Tertiary Road
Fatima-Malabog Rd – K1502 + 781 - K1502 + 811, K1503 + 100 - K1503 + 140,
K1503 + 950 - K1503 + 998, K1504 + 260 - K1504 + 300,
K1504 + 409 - K1504 + 436, K1504 + 800 - K1504 + 846
Physical Target:
CW1: 9,840.00 sq. m. (Construction of Slope Protection)
Allocation:
TOTAL: P 233,430,000.00
CW1: P 225,259,950.00
EAO: P 8,170,050.00

TO: OO1: Ensure Safe and Reliable National Road System – Asset Preservation Program
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides – Tertiary Road
Fatima-Malabog Rd – K1502 + 840 - K1502 + 886.3, K1503 + 797 - K1503 + 842.5,
K1504 + 132 - K1504 + 192, K1504 + 292 - K1504 + 310,
K1504 + 492 - K1504 + 579, K1504 + 595 - K1504 + 625,
K1504 + 723 - K1504 + 776
Physical Target:
CW1: 5,610.38 sq. m. (Construction of Slope Protection)
Allocation:
TOTAL: P 233,430,000.00
CW1: P 225,259,950.00
EAO: P 8,170,050.00
May 21, 2018 FY 2018 GAA WIN8C03002 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Demoloc-Little Baguio-Alabel Road, incl. ROW, Davao Occidental
Physical Target:
CW1: 8.474 Lane Km (Construction of Gravel Road)
ROW: 42,370.00 sq. m.
Allocation:
TOTAL: P 163,032,000.00
CW1: P 155,395,880.00 (Construction of Gravel Road)
ROW: P 1,930,000.00
EAO: P 5,706,120.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Missing Links/New Roads
Demoloc-Little Baguio-Alabel Road, incl. ROW, Davao Occidental
Physical Target:
CW1: 4.39112 Lane Km (Construction of Gravel Road)
CW2: 333.90 sq. m. (Construction of Concrete Bridge)
ROW: 42,370.00 sq. m.
Allocation:
TOTAL: P 163,032,000.00
CW1: P 127,739,390.00 (Construction of Gravel Road)
CW2: P 27,656,490.00 (Construction of Concrete Bridge)
ROW: P 1,930,000.00
EAO: P 5,706,120.00
May 21, 2018 FY 2018 GAA WIN8C03004 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement/Concreting of Jct. Calinan-Baguio-Cadalian Road (Baguio Proper-Wines-Magpet Bdry.), Davao City
Physical Target:
CW1: 15.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Improvement/Concreting of Jct. Calinan-Baguio-Cadalian Road (Baguio Proper-Wines-Magpet Bdry.), Davao City
Physical Target:
CW1: 3.150 Lane Km (Construction of Concrete Road)
CW2: 666.00 sq. m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 21,582,910.00 (Construction of Concrete Road)
CW2: P 74,917,090.00 (Construction of Concrete Bridge)
EAO: P 3,500,000.00
May 21, 2018 FY 2018 GAA WIN8C02994 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 2nd District Engineering Office

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Road from Junction Brgy. Sainz connecting to Sitio Licop in support of Cacao, Coffee, Corn and Mango Industries, Mati City, Davao Oriental
Physical Target:
CW1: 2.898 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 36,226,000.00
CW1: P 35,501,480.00 (Construction of Concrete Road)
EAO: P 724,520.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Road from Junction Brgy. Sainz connecting to Sitio Licop in support of Cacao, Coffee, Corn and Mango Industries, Mati City, Davao Oriental
Physical Target:
CW1: 0.940 Lane Km (Construction of Concrete Road)
CW2: 0.940 Lane Km (Construction of Gravel Road)
Allocation:
TOTAL: P 36,226,000.00
CW1: P 35,501,480.00 (Construction of Concrete Road)
CW2: P 18,859,070.00 (Construction of Gravel Road)
EAO: P 724,520.00
May 21, 2018 FY 2018 GAA WIN8C02987 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao del Norte District Engineering Office

MODIFICATION:

FROM: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Construction of Road, Brgy. Malinawon, Tagum City
Physical Target:
CW1: 2.220 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Program – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Construction of Road, Brgy. Malinawon, Tagum City
Physical Target:
CW1: 1.502 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
May 18, 2018 FY - 2018 WIN8F05460 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Mindoro West Coastal Rd
K0409+000 - K0414+000

CW1: 9.99 lane km ( Road Widening )
Allocation: 150,000,000 Php

TO:
Mindoro West Coastal Rd
K0409+000 - K0410+056,
K0410+095 - K0413+676,
K0413+695 - K0414+000

CW1: 9.874 LANE KM ( Road Widening )
Allocation: 150,000,000 Php



May 18, 2018 FY - 2018 WIN8F05455 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Construction of Missing Links/
New Roads

FROM:
Palawan Circumferential Road ( Latud - Canipaan Section )
Package B, Palawan

CW1: 33 lane km
Allocation: 150,000,000 Php

TO:
Palawan Circumferential Road ( Latud - Canipaan Section )
Package B, Palawan

CW1: 16.6376 lane km ( Construction of Gravel Road )
CW2: 493.568 sq.m. ( Construction of Steel Bridge )
Allocation: 150,000,000 Php
May 18, 2018 FY - 2018 WIN8F05453 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development -Road Widening - Secondary Roads

FROM:
Calapan South Road
K0072+026 - K0072+178,
K0072+191 - K0072+443,
K0072+822 - K0075+252,
K0075+283 - K0076+849,
K0077+348 - K0078+269,
K0078+466 - K0079+745

CW1: 13.220 lane km ( Road Widening )
Allocation: 160,000,000 Php

TO:
Calapan South Road
K0074+640 - K0075+239,
K0075+275 - K0079+714,
K0079+820 - K0080+609,
K0080+613 - K0082+639,
K0082+651 - K0083+114,
K0083+140 - K0083+511,
K0083+532 - K0084+064

CW1: 18.322 lane km ( Road Widening )
Allocation: 160,000,000 Php
May 18, 2018 FY - 2018 WIN8F05456 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
01 - Ensure Safe and Reliable National Road System

Network Development - Off-Carriageway Improvement
- Secondary Roads

FROM:
Tablas Circumferential Rd
K0006+454-0K0007+000,
K0008+158 - K0009+000,
K0013+000-k0013+693,
K0015+000 - K0016+098,
K0016+528 - K0016912,
K0024+708 - K0025+597,
K0030+000 - K0030+934,
K0031+854 - K0032+570,
K0038+500 - K0038+700,
K0041+000 - k0042+000

CW1: 21,696 square meters
( Off-Carriageway Improvement :Shoulder Paving/
Construction )
Allocation; 69,878,000 Php

TO:
Tablas Circumferential Rd.
K0006+454.00 - K0007+000.00,
K0008+000.00 - K0008+984.09,
K0013+000.00 - K0013+580.00,
K0013+612.75 - K0013+672.75,
K0015+000.00 - K0016+086.15,
K0016+522.11 - K0016+920.00,
K0024+833.03 - K0025+594.27,
K0029+990.52 - K0030+686.70,
K0030+700.00 - K0030+940.00,
K0031+853.58 - K0032+572.25,
K0038+500.00 - K0038+700.00,
K0041+000.00 - K0041+958.02

CW1: 22,481.12 square meters
( Off-Carriageway Improvement: Shoulder Paving/
Construction )
Allocation: 69,878,000 Php
May 18, 2018 2018 WIN8C02984 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Anibongan-Pangi Road, Maco, Compostela Valley
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Anibongan-Pangi Road, Maco, Compostela Valley
Physical Target:
CW1: 1.549 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Concrete Road)
EAO: P 200,000.00
May 18, 2018 2018 WIN8C02979 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling/Construction of Revetment with Sheet Pile of Kingking River, Cebulida L/S, Pantukan, Compostela Valley
Physical Target:
CW1: 320 Lineal Meters (Construction of Revetment)
CW2: 17,697 Cubic Meters (Channelization)
ROW: 356 Square Meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 28,933,909.00 (Construction of Revetment)
CW2: P 4,778,091.00 (Channelization)
ROW: P 588,000.00
EAO: P 700,000.00

TO: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling/Construction of Revetment with Sheet Pile of Kingking River, Cebulida L/S, Pantukan, Compostela Valley
Physical Target:
CW1: 718.17 Lineal Meters (Construction of Revetment)
CW2: 15,055 Cubic Meters (Channelization)
ROW: 356 Square Meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1: P 29,736,949.00 (Construction of Revetment)
CW2: P 3,975,050.00 (Channelization)
ROW: P 588,000.00
EAO: P 700,000.00
May 18, 2018 2018 WIN8C02971 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: 001 Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Montevista-Compostela-Mati Bdry Rd - K1456 + 250 - K1456 + 830
Physical Target:
CW1 - 1.160 Lane Km (Reconstruction from Paved to Concrete)
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 34,300,000.00 (Reconstruction from Paved to Concrete)
EAO - P 700,000.00

TO: 001 Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Montevista-Compostela-Mati Bdry Rd - K1456 + 140 - K1456 + 934
Physical Target:
CW1 - 1.589 Lane Km (Reconstruction from Paved to Concrete)
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 34,300,000.00 (Reconstruction from Paved to Concrete)
EAO - P 700,000.00
May 18, 2018 2018 WIN8C02980 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Aguinaldo, Laak, Compostela Valley
Physical Target:
CW1: 0.300 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1: P 2,940,000.00 (Construction of Concrete Road)
EAO: P 60,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Aguinaldo, Laak, Compostela Valley
Physical Target:
CW1: 0.340 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 3,000,000.00
CW1: P 2,940,000.00 (Construction of Concrete Road)
EAO: P 60,000.00
May 18, 2018 2018 WIN8C02973 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Kalamokan Creek, Barangay Poblacion, New Bataan, Compostela Valley
Physical Target:
CW1: 750 Lineal Meters (Construction of Revetment)
CW2: 53,000 Cubic Meters (Channelization)
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 20,555,726.00
CW2: P 28,444,274.00
EAO: P 1,000,000.00

TO: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Kalamokan Creek, Barangay Poblacion, New Bataan, Compostela Valley
Physical Target:
CW1: 2,276 Lineal Meters (Construction of Revetment)
CW2: 66,007 Cubic Meters (Channelization)
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 37,161,352.00
CW2: P 11,838.648.00
EAO: P 1,000,000.00
May 18, 2018 2018 WIN8C02981 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Anislagan Road, Maco, Compostela Valley
Physical Target:
CW1 - 0.600 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,000,000.00
CW1 - P 5,880,000.00 (Construction of Concrete Road)
EAO - P 120,000.00

TO : Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Concreting of Anislagan Road, Maco, Compostela Valley
Physical Target:
CW1 - 0.666 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,000,000.00
CW1 - P 5,880,000.00
EAO - P 120,000.00
May 18, 2018 2018 WIN8C02972 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Circumferential Road, Magading, Nabunturan, Compostela Valley
Physical Target:
CW1: 0.500 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Construction of Concrete Road)
EAO: P 100,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Circumferential Road, Magading, Nabunturan, Compostela Valley
Physical Target:
CW1: 0.716 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 5,000,000.00
CW1: P 4,900,000.00 (Construction of Concrete Road)
EAO: P 100,000.00
May 18, 2018 2018 WIN8C02993 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Tan-awan Road, Malinawon, Mawab, Compostela Valley
Physical Target:
CW1 - 0.650 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,500,000.00
CW1 - P 6,370,000.00 (Construction of Concrete Road)
EAO - P 130,000.00

TO: Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Tan-awan Road, Malinawon, Mawab, Compostela Valley
Physical Target:
CW1 - 0.842 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 6,500,000.00
CW1 - P 6,370,000.00 (Construction of Concrete Road)
EAO - P 130,000.00
May 18, 2018 2018 WIN8C02999 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road, Langtud to National Highway, Laak, Compostela Valley
Physical Target:
CW1: 1.200 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 12,000,000.00
CW1: P 11,580,000.00 (Construction of Concrete Road)
EAO: P 420,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Road, Langtud to National Highway, Laak, Compostela Valley
Physical Target:
CW1: 1.324 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 12,000,000.00
CW1: P 11,580,000.00 (Construction of Concrete Road)
EAO: P 420,000.00
May 18, 2018 2018 WIN8C02978 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment, Brgy. Napnapan, Pantukan, Compostela Valley
Physical Target:
CW1 - 1,050 Lineal meters (Construction of Revetment)
CW2 - 3,500 cubic meters (Channelization)
ROW - 2,343 square meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 31,734,487.00 (Construction of Revetment)
CW2 - P 2,163,713.00 (Channelization)
ROW - P 401,800.00
EAO - P 700,000.00

TO: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment, Brgy. Napnapan, Pantukan, Compostela Valley
Physical Target:
CW1 - 687.28 Lineal meters (Construction of Revetment)
CW2 - 1,463 cubic meters (Channelization)
ROW - 2,343 square meters
ALLOCATION:
TOTAL: P 35,000,000.00
CW1 - P 32,540,500.00 (Construction of Revetment)
CW2 - P 1,357,700.00 (Channelization)
ROW - P 401,800.00
EAO - P 700,000.00
May 18, 2018 2018 WIN8C02992 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Manat River, Barangay Banagbanag, Montevista, Compostela Valley
Physical Target:
CW1: 337 Lineal Meters (Construction of Revetment)
CW2: 4,267 Cubic Meters (Channelization)
ROW: 1,714 Square Meters
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 44,733,834.00 (Construction of Revetment)
CW2: P 3,972,166.00 (Channelization)
ROW: P 294,000.00
EAO: P 1,000,000.00

TO: OO2 Protect Lives and Properties
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Rechanneling and Construction of Revetment along Manat River, Barangay Banagbanag, Montevista, Compostela Valley
Physical Target:
CW1: 674.40 Lineal Meters (Construction of Revetment)
CW2: 4,267 Cubic Meters (Channelization)
ROW: 1,714 Square Meters
ALLOCATION:
TOTAL: P 50,000,000.00
CW1: P 46,382,278.00 (Construction of Revetment)
CW2: P 2,323,721.00 (Channelization)
ROW: P 294,000.00
EAO: P 1,000,000.00
May 18, 2018 2018 WIN8C02985 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road at Brgy. Dumlan to Brgy. Libaylibay Section Maco, Compostela Valley
Physical Target:
CW1: 1.500 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00

TO: Local Program
Local – Local Roads and Bridges – Local Roads – Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road at Brgy. Dumlan to Brgy. Libaylibay Section Maco, Compostela Valley
Physical Target:
CW1: 2.282 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00
May 18, 2018 2018 WIN8C02986 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment at Manat River, Olaycon Section, Monkayo, Compostela Valley
Physical Target:
CW1 - 360 Lineal meters (Construction of Revetment)
CW2 - 55,000 cubic meters (Channelization)
ROW - 1,286 square meters
ALLOCATION:
TOTAL: P 85,000,000.00
CW1 - P 57,214,850.00 (Construction of Revetment)
CW2 - P 24,520,650.00 (Channelization)
ROW - P 289,500.00
EAO - P 2,975,000.00

TO: 002: Protect Lives and Properties
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment at Manat River, Olaycon Section, Monkayo, Compostela Valley
Physical Target:
CW1 - 373.6 Lineal meters (Construction of Revetment)
CW2 - 61,208 cubic meters (Channelization)
ROW - 1,286 square meters
ALLOCATION:
TOTAL: P 85,000,000.00
CW1 - P 71,107,054.00 (Construction of Revetment)
CW2 - P 10,628,446.00 (Channelization)
ROW - P 289,500.00
EAO - P 2,975,000.00
May 18, 2018 2018 WIN8C03005 FY 2018 GAA R.A 10964 January 1, 2018 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION

FROM: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Magsaysay Road leading to Aqualime Mountain Resort, Brgy. Magsaysay, Nabunturan, Compostela Valley
Physical Target:
CW1 – 2.525 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 30,000,000.00
CW1 - P 29,400,000.00 (Construction of Concrete Road)
EAO - P 600,000.00

TO: Convergence and Special Support Program
Construction / Improvement of Access Roads leading to Declared Tourism Destinations
Magsaysay Road leading to Aqualime Mountain Resort, Brgy. Magsaysay, Nabunturan, Compostela Valley
Physical Target:
CW1 – 2.273 Lane Km (Construction of Concrete Road)
ALLOCATION:
TOTAL: P 30,000,000.00
CW1 - P 29,400,000.00 (Construction of Concrete Road)
EAO - P 600,000.00
May 17, 2018 FY - 2018 WIN8F05436 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
001 - Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/Reconstruction/Upgrading
of Damaged Paved Roads - Secondary Roads

FROM:
Tablas Circumferential Rd
K0084+315 - K0084+560

CW1:0.490 Lane Km ( Reconstruction from Paved
to Concrete )
Allocation: 6,600,000 Php

TO:
Tablas Circumferential Rd
K0077+220 - K0077+420

CW1: 0.40 Lane Km ( Reconstruction from Paved
to Concrete )
Allocation: 6,600,000 Php
May 17, 2018 FY - 2018 WIN8F05432 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
001 - Ensure Safe and Reliable National Road System

Network Development - Off-Carriageway Improvement
- Secondary Roads

FROM:
Tablas Circumferential Rd
K0050+000 - K0052+485,
K0054+000 - K0055+125,
K0083+000 - K0083+398,
K0083+541 - K0084+315,
K0084+560 - K0087+000,
K0091+048 - K0091+670,
K0096+000 - K0097+233,
K0102+894 - K0103+052

CW1: 27,747 square meters
( Off-Carriageway Improvement: Shoulder Paving/
Construction )
Allocation: 89,377,000 Php

TO:
Tablas Circumferential Rd.
K0050+000 - K0052+477,
K0054+000 - K0055+134,
K0083+000 - K0083+990,
K0084+560 - K0086+792,
K0091+048 - K0091+670,
K0096+000 - K0097+254,
K0102+894 - K0103+.45.70

CW1: 28,123.26 square meters
( Off-Carriageway Improvement: Shoulder Paving/
Construction )
Allocation: 89,377,000 Php
May 17, 2018 FY - 2018 WIN8F05442 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
Convergence Special Support Program

Convergence and Special Support - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones

FROM:
Access Road leading to Fishing Industry
Taytay, Palawan

CW1: 4 lane km ( Construction of Concrete Road )
Allocation: 50,000,000 Php

TO:
Access Road leading to Fishing Induatry
Taytay, Palawan

CW1: 3.556 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php

May 17, 2018 FY - 2018 WIN8F05435 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
Convergence Special Support Program

Convergence and Special Support -
Construction/Improvement of Access Roads leading to
Trades, Industries and Economic Zones

FROM:
Access Road leading to Mussel Production and
Fishing Industry, Taytay, Palawan

CW1: 4 lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php

TO:
Access Road leading to Mussel Production and
Fishing Industry, Taytay, Palawan

CW1: 3.4136 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
May 17, 2018 FY 2018 WIN8C02688 320101102199000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102199000
Project ID: P00221451MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Flood Control Project Phase I in Metro Brgys. of Ipil, (Don Andres - Bangkerohan, Lower Taway, ), Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 784.84 lineal meters
Unit Cost: P 36,185.72/lineal meter
ROW Acquisition: 3,333.33 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.6 M
Allocation: P 30 M
May 17, 2018 FY - 2018 WIN8F05433 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
Convergence Special Support Program

Convergence and Special Support -
Construction/Improvement of Access Roads leading to
Trades, Industries and Economic Zones

FROM:
Access Road leading to Seaweed Plantations in
Brgy. Sta. Teresita, Dumaran, Palawan

CW1: 4 lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php

TO:
Access Road leading to Seaweed Plantation in
Brgy. Sta. teresita, Dumaran, Palawan

CW1: 3.054 Lane Km ( Construction of Concrete Road )
Allocation: 50,000,000 Php
May 17, 2018 FY 2018 WIN8C02686 300116201168000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 300116201168000
Project ID: P00240256MN

Local Program:

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects

Improvement/Construction/Concreting of Labasan - Camaga Road, Siay, Zamboanga Sibugay (Phase II)
Sta. 3+111.00 - Sta. 3+745.12,
Sta. 4+045.84 - Sta. 5+378.00
Physical Target:
CW-1 - Construction of Concrete Road:
3.93256 lane km.
Unit Cost: P 7,476,046.14/lane km.
EAO: P 0.600 M
Allocation: P 30 M
May 17, 2018 FY 2018 WIN8C02685 300117202015000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 300117202015000
Project ID: P00251466MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Construction of Barangay Road, Brgy. Don Andres, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road:
0.19 lane km.
Unit Cost: P 5,263,157.89/lane km.
Allocation: P 1 M
May 17, 2018 FY - 2018 WIN8F05431 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Palawan 1st District Engineering Office
001 - Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads -
Secondary Roads

FROM:
El Nido - Jct New ibahay Rd.
K0276+168 - K0276+268,
K0276+287 - K0276+337

CW1: 0.30 lane Km ( Paving of Unpaved Road )
Allocation: 5,100,000 Php

TO:
El Nido - New Ibahay Rd
K0276+168.00 - K0276+264.50,
K0276+291.00 - K0276+330.00

CW1: 0.2712 lane Km ( Paving of Unpaved Road )
Allocation: 5,100,000 Php
May 17, 2018 FY 2018 WIN8C02682 320101102193000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102193000
Project ID: P00220661MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control, Brgy. Guintolan, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 510 lineal meters
Unit Cost: P 47,303.92/lineal meter
ROW Acquisition: 1,250 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.5 M
Allocation: P 30 M
May 17, 2018 FY - 2018 WIN8F05434 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Mindoro Oriental District Engineering Office
002 - Protect Lives and Properties against Major Floods

Flood Management - Construction/Rehabilitation of
Flood Mitigation Facilities along Major River Basins
and Principal Rivers

FROM:
Rehabilitation/Reconstruction of Alag Gabions,
Baco, Oriental Mindoro

CW1:36.40 l. m. ( Construction of Flood Control
Mitigation Structure )
Allocation: 4,530,000 Php

TO:
Rehabilitation/Reconstruction Of Alag Gabions,
Baco, Oriental Mindoro

CW1: 126.00 l. m. ( Construction of Flood
Mitigation Structure )
Allocation: 4,530,000 Php
May 17, 2018 FY 2018 WIN8C02681 320101102188000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102188000
Project ID: P00220109MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Comprehensive Drainage System within Metro Ipil Area, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 985.66 lineal meters
Unit Cost: P 24,247.71/lineal meter
ROW Acquisition: 2,000.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5 M
Allocation: P 25 M
May 17, 2018 FY - 2018 WIN8F05454 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Buildings and Other Structures

FROM:
Concreting of Brgy. Libtangin MPB,
Gasan marinduque

CW1: 1 Bldg ( Construction of Multi Purpose Building )
Allocation; 4,000,000 Php

TO:
Construction / (Completion) of Brgy. Libtangin MPB,
Gasan, Marinduque

CW1: 1 Bldg ( Construction of Multi Purpose Building )
Allocation: 4,000,000 Php
May 17, 2018 FY 2018 WIN8C02677 320101102189000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102189000
Project ID: P00220411MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control along Kabasalan River, FL Pena, Kabasalan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 380.00 lineal meters
Unit Cost: P 63,486.84/lineal meter
ROW Acquisition: 1,250.00 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 0.5 M
Allocation: P 25 M
May 17, 2018 FY 2018 WIN8C02673 320101102194000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102194000
Project ID: P00220662MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control, Brgy. Poblacion, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 499.30 lineal meters
Unit Cost: P 48,317.64/lineal meter
ROW Acquisition: 1,250.00 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.5 M
Allocation: P 25 M
May 17, 2018 FY 2018 WIN8C02672 320101102195000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102195000
Project ID: P00220664MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control, Brgy. Sta. Clara, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 656 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 44,131.10/lineal meter
ROW Acquisition: 1,500 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.6 M
Allocation: P 30 M
May 17, 2018 FY 2018 WIN8C02671 320101102192000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102192000
Project ID: P00221059MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control Structure along Sanito River, Brgy. Sanito, Ipil, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 161.50 lineal meters
Unit Cost: P 115,170.28/lineal meter
ROW Acquisition: 3,333.33 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 1.00 M
Allocation: P 20 M
May 17, 2018 FY 2018 WIN8C02670 300117202014000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 300117202014000
Project ID: P00251472MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program

Construction of Barangay Road, Brgy. Concepcion, Kabasalan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road:
0.305 lane km.
Unit Cost: P 4,852,941.18/lane km.
EAO: P 0.015 M
Allocation: P 1.5 M
May 17, 2018 FY 2018 WIN8C02669 320102100517000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320102100517000
Project ID: P00221747MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management -
Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

Construction of Flood Control Structure along Sibuguey River (Phase VI), Siay, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 618 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 62,459.55/lineal meter
ROW Acquisition: 2,000 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.8 M
Allocation: P 40 M
May 17, 2018 FY 2018 WIN8C02668 320101102198000 May 3, 2018 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 320101102198000
Project ID: P00222748MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Upper Tungawan Flood Control Structure along Tungawan River, Tungawan, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 183.50 lineal meters
Unit Cost: CW-1 - Construction of Flood Mitigation Structure: P 36,811.99/lineal meter
ROW Acquisition: 350.00 square meters
Unit Cost: P 300.00/square meter
EAO: P 0.140 M
Allocation: P 7.0 M
May 17, 2018 FY - 2018 WIN8F05441 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 1,865 m. Dampulan - Mabilog road,
Barangay Dampulan, Torrijos, Marinduque

CW1: 1.640 Lane km ( Construction of Concrete Road )
Allocation: 9,325,000 Php

TO:
Concreting of 1.865 lane km Dampulan - Mabilog road,
Barangay Dampulan, Torrijos, Marinduque

CW1: 1.865 Lane Km ( Construction of Concrete Road )
Allocation: 9,325,000 Php
May 17, 2018 FY 2018 WIN8G02183 FY 2018 GAA January 4, 2018 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation Program – Preventive Maintenance – Secondary Roads – San Jose City – Rizal Rd via Pinili – Porais – Villa Joson (Palarilla) Rd, K0165+128.70 – K0165+515, K0167+000 – K0168+000, K0172+000 – K0172+067, K0172+737 – K0173+508, K0174+477 – K0174+912.70
May 17, 2018 FY 2018 WIN8G02188 FY 2018 GAA January 4, 2018 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation Program - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads – Secondary Roads – Bongabon – Rizal – Aurora Rd, K0152+560 – K0152+740, K0152+740 – K0153+197
May 16, 2018 FY - 2018 WIN8F05373 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of Brgy. Pili Road,
Mogpog, Marinduque

CW1: 1.055 Lane Km ( Construction of Concrete Road )
Allocation: 6,000,000 Php

TO:
Concreting of Brgy. Pili Road,
Mogpog, Martinduque

CW1: 1.404 lane Km ( Construction of Concrete Road )
Allocation: 6,000,000 Php
May 16, 2018 FY - 2018 WIN8F05389 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities

FROM:
Construction of Brgy. Bamban Flood Control,
Boac, marinduque

CW1: 179.00 lin.m. ( Construction of Revetment )
Allocation: 6,000,000 Php

TO:
Construction of brgy. Bamban Flood Control,
Boac, Marinduque

CW1: 108.00 lin.m. ( Construction of Revetment )
Allocation: 6,000,000 Php
May 16, 2018 FY - 2018 WIN8F05399 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
- Flood Control Structures/Facilities

FROM:
Construction of brgy. Duyay Flood Control,
Boac, Marinduque

CW1: 89.00 lin.m. ( Construction of Revetment )
Allocation: 3,000,000 Php

TO:
Construction of Brgy. Duyay Flood Control,
Boac, Marinduque

CW1: 54.00 lin.m. ( Construction of Revetment )
Allocation: 3,000,000 Php
May 16, 2018 FY - 2018 WIN8F05400 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of Brgy. Maligaya,
Boac, Marinduque

CW1: 0.352 Lane Km ( Construction of Concrete Road )
Allocation: 2,000,000 Php

TO:
Concreting of Brgy. Maligaya,
Boac, Marinduque

CW1: 0.495 Lane Km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
May 16, 2018 FY - 2018 WIN8F05375 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 2 km. Bayanan to Sampalukan road,
Barangay Marlangga, Torrijos, Marinduque

CW1: 1.759 Lane Km ( Construction of Concrete Road )
Allocation: 10,000,000 Php

TO:
Concreting of 2 lane km Bayanan to Sampalukan road,
Barangay Marlanga, Torrijos, Marinduque

CW1: 2.00 Lane Km ( Construction of Concrete Road )
Allocation: 10,000,000 Php
May 16, 2018 FY - 2018 WIN8F05414 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Marinduque District Engineering Office
Local Program

Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Concreting of 2.5 km Bangwayin-Pakaskasan road,
Barangay Bangwayin, Torrijos, Marinduque

CW1: 2.199 Lane Km ( Construction of Concrete Road )
Allocation; 12,500,000 Php

TO:
Concreting of 2.5 lane km Bangwayin-Pakaskasan road,
Barangay Bangwayin, Torrijos, Marinduque

CW1: 2.500 Lane Km ( Construction of Concrete Road )
Allocation: 12,500,000 Php
May 16, 2018 FY 2018 WIN8C02995 310208100126000 April 5, 2018 Region IX Zamboanga del Norte 3rd District Engineering Office
UACS No. 310208100126000
Project ID: P00200812MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Off-Carriageway Improvement - Secondary Roads

Rizal-Dakak-Dapitan Coastal Loop Rd including RROW
K1860+254.00 - K1868+570.74
Physical Target:
CW-1 - Off-Carriageway Improvement: Shoulder Paving/Construction
11,883.89 sq.m.
Unit Cost: P 1,615.63/sq.m.
ROW: 267 sq.m.
Unit Cost: P 1,498.13/sq.m.
EAO: P 400,000
Allocation: P 20,000,000.00
May 16, 2018 FY 2018 WIN8C02967 300116200128000 May 9, 2018 Region IX Regional Office IX
UACS No. 300116200128000
Project ID: P00257849MN

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects

Construction of Boulevard, Liloy, Zamboanga del Norte
Physical Target:
CW-1 - Paving of Unpaved Roads:
3.06 lane km.
Unit Cost: P 18,167,808.19/lane km
CW-2 - Embankment: 58,533.1917 cu.m.
Unit Cost: P 698.86/cu.m.
EAO: P 3,500,000.00
Allocation: P 100,000,000.00
May 16, 2018 FY 2018 WIN8C02968 300204100002000 May 9, 2018 Region IX Regional Office IX
UACS No. 300204100002000
Project ID: P00230001MN

CSSP: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones

Access Road at Sitio Anuling, Pamucutan to Sta. Rita in support of High Value Crops (Abaca, Cacao, Rubber and Coffee), Upper La Paz, Zamboanga City

Physical Target:
CW-1 - Const. of Concrete Road:
2.56 lane km.
Unit Cost: P 47,119,140.63/lane km.
EAO: P 4,375,000.00
Allocation: P 125,000,000.00
May 16, 2018 FY - 2018 WIN8F05443 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
001 - Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance
- Secondary Roads

FROM:
Tablas Circumferential Rd
K0098+100 - K0098+240

CW1: .280 Lane Km ( Preventive Maintenance of Road )
Allocation 1,247,000 Php

TO:
Tablas Circumferential Rd
K0098+100 - K0098+181.50

CW1: 0.163 Lane Km ( Preventive maintenance of Road )
Allocation: 1,247,000 Php
May 16, 2018 FY 2018 WIN8C02969 310212100036000 May 9, 2018 Region IX Regional Office IX
UACS No. 310212100036000
Project ID: P00200864MN

OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads

Sindangan-Bayog-Lakewood Rd - (S01059MN) -
Sta. 1938+722.00 - Sta. 1938+810.00,
Sta. 1945+740.00 - Sta. 1946+460.00
Physical Target:
CW-1 - Paving of Unpaved Road:
1.62 lane km.
Unit Cost: P 93,775,921.98/lane km.
ROW: 8,276.69 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 5,600,000.00
Allocation: P 160,000,000.00
May 16, 2018 FY - 2018 WIN8F05437 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Romblon District Engineering Office
001 - Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads
- Tertiary Roads

FROM:
Lubi - Binoog Rd
K0065+836 - K0068+319

CW1: 4.884 Lane Km ( Paving of Unpaved Roads )
Allocation: 100,000,000 Php

TO:
Lubi - Binoog Rd
K0065+836 - K0067+661.87

CW1: 3.42774 Lane Km ( Paving of Unpaved Road )
Allocation: 100,000,000 Php
May 16, 2018 FY 2018 WIN8C02965 320101100070000 May 9, 2018 Region IX Regional Office IX
UACS No. 320101100070000
Project ID: P00220517MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Construction of Flood Control Structure along Dipolog River Basin, Dipolog City, Zamboangna del Norte
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 479.04 lm.
Unit Cost: P 241,583.88/lm
ROW: 238.86 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 4,200,000.00
Allocation: P 120,000,000.00
May 16, 2018 FY 2018 WIN8C02964 320101100236000 May 9, 2018 Region IX Regional Office IX
UACS No. 320101100236000
Project ID: P00221447MN

OO2: Protect Lives and Properties Against Major Floods-Flood Management
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems

Extension of Flood Control Structure along Siocon River (Downstream), Siocon, Zamboanga del Norte
Physical Target:
CW-1 - Construction of Flood Mitigation Structure: 569.50 lm
Unit Cost: P 184,950.83/lm
ROW: 203.48 sq.m.
Unit Cost: P 300/sq.m.
EAO: P 3,822,455.00
Allocation: P 109,213,000.00