Outline of the Project
Overall Goal
Conditions of roads and bridges administered by DPWH are improved.
Project Purpose
Road and bridge maintenance management works of DPWH are improved.
Outputs
Output-1:Capability of concerned engineers of all ROs/DEOs on road maintenance management is enhanced.
Output-2:Capability of concerned engineers of all ROs/DEOs on bridge maintenance management is enhanced.
Output-3:Capability of concerned engineers of ROs/DEOs in target Regions (II, III, VII, VIII, and XIII) on special bridge maintenance management is enhanced.
Output-4:Database system to be utilized for road and bridge maintenance management is developed.
Activities
Activity 1:Technical Improvement of Road Maintenance Management
1.1: Assist conducting seminars/OJTs on road maintenance management by Sustainability Program for concerned engineers of all ROs/DEOs.
1.2: Assist implementing pilot projects on road slope stability and relevant OJTs.
1.3: Monitor and evaluate situations of road maintenance management by ROs/DEOs
1.4: Review manuals on road maintenance management and construction supervision developed and/or revised by the Phase-II and make their necessary revisions.
Activity 2:Technical Improvement of Bridge Maintenance Management
2.1: Assist conducting seminars/OJTs on bridge maintenance management by Sustainability Program for concerned engineers of all ROs/DEOs.
2.2: Assist conducting seminars/OJTs on bridge engineering inspections by Sustainability Program for concerned engineers of all ROs/DEOs.
2.3: Assist implementing pilot projects on bridge repair and relevant OJTs.
2.4: Monitor and evaluate situations of bridge maintenance and engineering inspections by ROs/DEOs.
2.5: Review manuals on bridge maintenance management and construction supervision developed and/or revised by the Phase-II and make their necessary revisions.
Activity 3:Technical Improvement of Special Bridge Maintenance Management
3.1: Develop special bridge maintenance and management manual.
3.2: Conduct seminars/OJTs on special bridge maintenance management for concerned engineers of target ROs/DEOs.
3.3: Assist conducting seminars/OJTs on special bridge inspections by Sustainability Program for concerned engineers of target ROs/DEOs (conduct OJT for RO-VIII).
3.4: Assist implementing pilot projects on special bridge repair and relevant OJTs.
3.5: Monitor and evaluate situations of special bridge inspections by ROs/DEOs.
3.6: Review special bridge inspection manuals developed by the Phase-II and make their necessary revisions
Activity 4: Improvement of Database System for Road and Bridge Maintenance Management
4.1: Review current filing situation of documents/data related to road and bridge maintenance management and identify issues to be improved.
4.2: Prepare the basic plan (framework, necessary entry data, operation manner, selection of model RO, etc.) for developing the database system.
4.3: Develop the database system based on the basic plan.
4.4: Enter necessary data and make trial operations of the system at model RO.
4.5: Improve the system in consideration of the results of trial operations at model RO.
4.6: Prepare relevant manuals including operation manner.
4.7: Conduct seminars on the database system and its relevant manuals.