January 5, 2021 |
FY 2020 GAA |
WIN0G02887 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Sta. 3+365 to Sta. 3+620, Davao City
Physical Target:
CW1: 195.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 38,600,000.00 (Construction of Revetment)
EAO: P 1,400,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Sta. 4+292 to Sta. 4+480, Davao City
Physical Target:
CW1: 188.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 38,600,000.00 (Construction of Revetment)
EAO: P 1,400,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02882 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Aplaya Section, Right Bank, Davao City
Physical Target:
CW1: 160.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 24,500,000.00 (Construction of Flood Mitigation Structure)
EAO: P 500,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Aplaya Section, Right Bank, Davao City
Physical Target:
CW1: 123.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 24,500,000.00 (Construction of Flood Mitigation Structure)
EAO: P 500,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02883 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 0+512 to Sta. 0+852, Davao City
Physical Target:
CW1: 100.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 1+013 to Sta. 1+095, Davao City
Physical Target:
CW1: 82.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02886 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving along Jct. Daang Maharlika Rd.-Iñigo St.-Jct. Dacudao, Davao City
Physical Target:
CW1: 2,032.73 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 8,640,000.00
CW1: P 8,467,000.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 172,800.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving along Jct. Daang Maharlika Rd.-Iñigo St.-Jct. Dacudao, Davao City
Physical Target:
CW1: 854.40 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: 0.320 lane km (Road Widening)
Allocation:
TOTAL: P 8,640,000.00
CW1: P 6,834,177.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: P 1,633,023.00 (Road Widening)
EAO: P 172,800.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02880 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bunawan River, Sta. 5+060 to Sta. 5+282, Davao City
Physical Target:
CW1: 250.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bunawan River, Sta. 5+260 to Sta. 5+482, Davao City
Physical Target:
CW1: 444.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02879 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Matina Pangi Bridge Upstream Section, Davao City
Physical Target:
CW1: 245.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Revetment)
EAO: P 800,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Matina Pangi Bridge Upstream Section, Davao City
Physical Target:
CW1: 203.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Revetment)
EAO: P 800,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02881 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Bridge Upstream, Matina Pangi Section, Left Bank, Davao City
Physical Target:
CW1: 150.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 24,500,000.00 (Construction of Revetment)
EAO: P 500,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Bridge Upstream, Matina Pangi Section, Left Bank, Davao City
Physical Target:
CW1: 125.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 25,000,000.00
CW1: P 24,500,000.00 (Construction of Revetment)
EAO: P 500,000.00 |
January 5, 2021 |
FY 2020 GAA |
WIN0G02878 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Sta. 2+983 to Sta. 3+173, Davao City
Physical Target:
CW1: 115.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 27,000,000.00
CW1: P 26,055,000.00 (Construction of Revetment)
EAO: P 945,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Sta. 4+071 to Sta. 4+186, Davao City
Physical Target:
CW1: 115.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 27,000,000.00
CW1: P 26,055,000.00 (Construction of Revetment)
EAO: P 945,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00953 |
300113200026000 |
October 1, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200026000
Project ID: P00442692MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Ukilan Bridge along Jolo - Taglibi - Tiptipon Road K19+829.08 - K19+839.92
Physical Target:
CW-1 - Replacement of Bridge: 103.41 sq.m.
Unit Cost: P 113,212.62/sq.m.
EAO: P 292,682.93
Allocation: P 12,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00968 |
300113200025000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200025000
Project ID: P00442691MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Tumarikin Bridge along Jolo - Taglibi - Tiptipon Road K17+638.08 - K17+648.92
Physical Target:
CW-1 - Replacement of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00966 |
300111200015000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200015000
Project ID: P00442700MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Bridge Widening of Pang II Bridge (Sta. 43+966.38 - Sta. 43+977.22)
Physical Target:
CW-1 - Widening of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00970 |
300113200023000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200023000
Project ID: P00442687MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Taung Bridge along Jolo - Taglibi - Tiptipon Road K16+419.08 - K16+427.92
Physical Target:
CW-1 - Replacement of Bridge: 84.3336 sq.m.
Unit Cost: P 104,051.0544/sq.m.
EAO: P 225,000.00
Allocation: P 9,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00954 |
300111200012000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200012000
Project ID: P00442703MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Bridge Widening of Bulingbuling Bridge (Sta. 22+955.08 - Sta. 22+965.92)
Physical Target:
CW-1 - Widening of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00951 |
300113200018000 |
October 1, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200018000
Project ID: P00442688MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Binuang Bridge along Jolo - Taglibi - Tiptipon Road K17+093.08 - K17+051.92
Physical Target:
CW-1 - Replacement of Bridge: 122.4936 sq.m.
Unit Cost: P 111,504.08/sq.m.
EAO: P 341,463.41
Allocation: P 14,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00952 |
300113200021000 |
October 5, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200021000
Project ID: P00442686MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Lubluban Gadja Bridge along Jolo - Taglibi - Tiptipon Road K15+008.08 - K15+020.92
Physical Target:
CW-1 - Replacement of Bridge: 122.4936 sq.m.
Unit Cost: P 103,539.51/sq.m.
EAO: P 317,073.17
Allocation: P 13,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00967 |
3001112001267000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 3001112001267000
Project ID: P00444701MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Slope Protection Along Seit - Tayungan National Road Km 39+520 - 40+870.00, Km 38+000 - Km41+660 (with exemption), Sulu
Physical Target:
CW-1 - Construction of Slope Protection: 22,143.33 sq.m.
Unit Cost: P 1,968.80939/sq.m.
CW-2 - Preventive Maintenance of Road: Concrete Reblocking: 3.04 Lane km
Unit Cost: P 17,377,704.03/Lane km
ROW: 669.79 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 3,374,847.57
Allocation: P 100,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00962 |
300111200014000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200014000
Project ID: P00442699MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Bridge Widening of Pang I Bridge along Seit-Pang-Camp Andres Road
Physical Target:
CW-1 - Widening of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00950 |
300107200933000 |
August 19, 2020 |
Region IX |
Regional Office IX |
UACS No. 300107200933000
Project ID: P00444669MN
Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Local Infrastructure Program
Construction of Seawall from Brgy. Tanduh Bagua to Brgy. Umangay, Patikul, Sulu
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 91.00 Ln.m.
Unit Cost: P 21,758.24/Ln.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00961 |
300111200016000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200016000
Project ID: P00442701MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Bridge Widening of Sapah Biray Bridge (Sta. 35+156.58 - Sta. 35+167.42)
Physical Target:
CW-1 - Widening of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B00959 |
300113200022000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200022000
Project ID: P00442690MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Lumukan Bridge along Jolo - Taglibi - Tiptipon Road K18+108.08 - K18+118.92
Physical Target:
CW-1 - Replacement of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B01103 |
300113200024000 |
October 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200024000
Project ID: P00442689MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Tuburan Bridge along Jolo - Taglibi - Tiptipon Road K17+339.08 - K17+351.92
Physical Target:
CW-1 - Replacement of Bridge: 122.4963 sq.m.
Unit Cost: P 111,504.08/sq.m.
EAO: P 341,463.41
Allocation: P 14,000,000.00 |
December 30, 2020 |
FY 2020 |
WIN0B01104 |
300111200203000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200203000
Project ID: P00442698MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening along Punay Road
Physical Target:
CW-1 - Road Widening: 5.26 lane km
Unit Cost: P 16,482,853.87/lane km
ROW: 885.65 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 3,034,493.40
Allocation: P 90,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00939 |
300111200100000 |
March 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200100000
Project ID: P00442712MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Missing Links - Tonggusong - Tubig Indangan National Road
Physical Target:
CW-1 - Road Upgrading Gravel to Paved: 1.685 lane km
Unit Cost: P 15,280,999.47/lane km
ROW: 1,167.73 Sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 901,196.94
Excess: P 28,000,000.00
Allocation: P 55,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00925 |
300111200194000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200194000
Project ID: P00442680MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo Port - Bud Daho - Romandier Road, K5+140.00 - K7+310.00
Physical Target:
CW-1 - Reconstruction to Concrete Pavement: 4.34 lane km
Unit Cost: P 17,773,500.65/lane km
ROW: 544.04 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 2,699,794.75
Allocation: P 80,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00927 |
300111200200000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200200000
Project ID: P00442694MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening along Camp Andres - Sucuban Road
Physical Target:
CW-1 - Road Widening: 5.58 lane km
Unit Cost: P 15,546,969.90/lane km
ROW: 705.28 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 3,036,323.22
Allocation: P 90,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00934 |
300111200201000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200201000
Project ID: P00442697MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening along Karungdong - Kulay-Kulay Road
Physical Target:
CW-1 - Road Widening: 5.28 lane km
Unit Cost: P 16,432,055.05/lane km
ROW: 673.69 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 3,036,643.77
Allocation: P 90,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00916 |
300116202154000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300116202154000
Project ID: P00443222MN
Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Concrete Road - Concreting of Lower Patibulan - Lubhang Road, Phase I, Old Panamao, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 8.92 lane km
Unit Cost: P 16,217,455.19/Lane km
EAO: P 5,063,089.51
Excess: P 277,210.21
Allocation: P 150,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00944 |
300111200193000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200193000
Project ID: P00442679MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo Port - Bud Daho - Romandier Road, K0+000 - K2+510
Physical Target:
CW-1 - Reconstruction from Paved to Concrete: 5.02 lane km
Unit Cost: P 16,314,609.29/lane km
EAO: P 2,866,476.85
Excess: P 234,184.50
Allocation: P 85,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00946 |
300117207258000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207258000
Project ID: P00443951MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Concrete Road - Concreting of Road along Gulangan Ipil Road, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 0.95 lane km
Unit Cost: P 15,237,986.39/Lane km
EAO: P 144,760.87
Excess: P 379,152.06
Allocation: P 15,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00948 |
300116202252000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300116202252000
Project ID: P00443443MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Slope Protection Along Seit-Tanguyan National Road, Sulu, Km 38+000 - 39+520
Physical Target:
CW-1 - Construction of Concrete Road: 3.04 lane km
Unit Cost: P 25,375,422.16/lane km
EAO: P 2,699,944.92
Excess: P 158,771.70
Allocation: P 80,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00945 |
300117205331000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117205331000
Project ID: P00443757MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Bypass Road from Barangay Limook Emergency Hospital-Barangay Maligaya Isla Verde-Barangay Maganda Junction National Highway, Lamitan City, Basilan
Physical Target:
CW-1- Construction of Concrete Road: 2.728 lane km
Unit Cost: P 21,250,371.90/Lane km
EAO: P 579,710.14
Excess: P 1,449,275.37
Allocation: P 60,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00949 |
300107200934000 |
August 19, 2020 |
Region IX |
Regional Office IX |
UACS No. 300107200934000
Project ID: P00444670MN
Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Local Infrastructure Program
Construction of Seawall from Brgy. Bangas, Hadji Panglima Tahil, Sulu
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 90.00 Ln.m.
Unit Cost: P 22,000.00/Ln.m.
EAO: P 20,000.00
Allocation: P 2,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00947 |
300111200199000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200199000
Project ID: P00442693MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening along Camp Andres - Lahing-Lahing
Physical Target:
CW-1 - Road Widening: 5.28 lane km
Unit Cost: P 16,438,144.71/lane km
ROW: 562.76 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 3,037,769.14
Allocation: P 90,000,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02872 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Aplaya Section, Left Bank, Davao City
Physical Target:
CW1: 180.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Flood Mitigation Structure)
EAO: P 600,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Matina River, Matina Aplaya Section, Left Bank, Davao City
Physical Target:
CW1: 146.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Flood Mitigation Structure)
EAO: P 600,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02866 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Lasang River, Sta. 2+149 to Sta. 2+585, Davao City
Physical Target:
CW1: 170.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Revetment)
EAO: P 800,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Lasang River, Sta. 2+075 to Sta. 2+245, Davao City
Physical Target:
CW1: 170.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Revetment)
EAO: P 800,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02864 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Jct. F. Torres-Mt. Mayon-E. Quirino Road, Davao City
Physical Target:
CW1: 350.000 lm (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Drainage Structure)
EAO: P 600,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Jct. F. Torres-Mt. Mayon-E. Quirino Road, Davao City
Physical Target:
CW1: 947.000 lm (Construction of Drainage Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Drainage Structure)
EAO: P 600,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00960 |
300111200126000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200126000
Project ID: P00444700MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Slope Protection Along Camp Andres Romandier National Road, KM 29+000.00 - KM31+220.00, KM 29+000 - KM 34+000 (with exemption), Sulu
Physical Target:
CW-1 - Construction of Slope Protection: 20,830 sq.m.
Unit Cost: P 2,495.69/sq.m.
CW-2 - Preventive Maintenance of Road: Concrete Reblocking: 7.40 Lane km
Unit Cost: P 12,559,779.55/Lane km
EAO: P 5,072,463.77
Allocation: P 150,000,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02863 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Jct. Davao-Cotabato Old Road (Bago Gallera Section) Leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 4.120 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Concrete Road)
EAO: P 3,500,000.00
TO: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Jct. Davao-Cotabato Old Road (Bago Gallera Section) Leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 2.210 lane km (Road Widening)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Road Widening)
EAO: P 3,500,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02869 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 3+632 to Sta. 3+821, Davao City
Physical Target:
CW1: 150.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 2+680, Sta. 2+687 to Sta. 2+782 Sta. 2+850, Davao City
Physical Target:
CW1: 184.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02861 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Talomo River, Sta. 3+110 to Sta. 3+365, Davao City
Physical Target:
CW1: 230.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Talomo River, Sta. 3+340 to Sta. 3+455, Davao City
Physical Target:
CW1: 230.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 49,000,000.00 (Construction of Revetment)
EAO: P 1,000,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02865 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Generoso Bridge Downstream Section, Right Bank, Davao City
Physical Target:
CW1: 125.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Revetment)
EAO: P 600,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Generoso Bridge Downstream Section, Right Bank, Davao City
Physical Target:
CW1: 107.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Revetment)
EAO: P 600,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02874 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 3+065 to Sta. 3+440, Davao City
Physical Target:
CW1: 120.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Davao River, Sta. 3+566 to Sta. 3+686, Davao City
Physical Target:
CW1: 120.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Revetment)
EAO: P 1,050,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00957 |
300111200290000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200290000
Project ID: P00442705MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction from Paved to Concrete - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Mahalu - Boki Road
Physical Target:
CW-1 - Construction of Concrete Road: 2.13 lane km
Unit Cost: P 16,947,211.72/lane km
EAO: P 902,439.02
Allocation: P 37,000,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02870 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Control Structures for Datu Loho Creek, Davao City
Physical Target:
CW1: 1,000.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Flood Mitigation Structure)
EAO: P 300,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Control Structures for Datu Loho Creek, Davao City
Physical Target:
CW1: 87.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Flood Mitigation Structure)
EAO: P 300,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02871 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Taloma River, NHA Bangkal Section, Left Bank, Davao City
Physical Target:
CW1: 215.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Flood Mitigation Structure)
EAO: P 400,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure along Talomo River, NHA Bangkal Section, Left Bank, Davao City
Physical Target:
CW1: 163.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Flood Mitigation Structure)
EAO: P 400,000.00 |
December 29, 2020 |
FY 2020 GAA |
WIN0G02867 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Road Widening & Replacement of Bridge along Jct. Davao-Cotabato Old Road (Bago Gallera Section) Leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 4.290 lane km (Road Widening)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Road Widening)
EAO: P 3,500,000.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Road Widening & Replacement of Bridge along Jct. Davao-Cotabato Old Road (Bago Gallera Section) Leading to Philippine Coconut Authority (PCA), Davao City
Physical Target:
CW1: 0.394 lane km (Road Widening)
CW2: 715.68 sq.m. (Replacement of Bridge)
CW3: 0.724 lane km (Reconstruction to Concrete Pavement)
CW4: 591.60 sq.m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 6,465,500.00 (Road Widening)
CW2: P 63,979,500.00 (Replacement of Bridge)
CW3: P 14,475,000.00 (Reconstruction to Concrete Pavement)
CW4: P 11,580,000.000 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00958 |
300113200020000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200020000
Project ID: P00442683MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Kaunayan Bridge along Jolo - Taglibi - Tiptipon Road K8+889.08 - K8+897.92
Physical Target:
CW-1 - Replacement of Bridge: 84.3336 sq.m.
Unit Cost: P 104,051.0544/sq.m.
EAO: P 225,000.00
Allocation: P 9,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00963 |
300111200289000 |
December 9, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200289000
Project ID: P00442704MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Lupa pula - Umus Mataha Road
Physical Target:
CW-1 - Reconstruction from Paved to Concrete: 2.07 lane km
Unit Cost: P 16,956,521.74/lane km
EAO: P 877,500.00
Excess: P 22,500.00
Allocation: P 36,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00956 |
300113200019000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300113200019000
Project ID: P00442684MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Replacement of Permanent Weak Bridges - Duana Bridge along Jolo - Taglibi - Tiptipon Road K8+788.08 - K8+796.82
Physical Target:
CW-1 - Replacement of Bridge: 84.3336 sq.m.
Unit Cost: P 86,709.21199/sq.m.
EAO: P 187,500.00
Allocation: P 7,500,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00965 |
300111200294000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200294000
Project ID: P00442709MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening - Sikub - Kompang Road
Physical Target:
CW-1 - Construction of Concrete Road: 0.866 lane km
Unit Cost: P 28,146,651.27/lane km
EAO: P 625,000.00
Allocation: P 25,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00955 |
300111200013000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200013000
Project ID: P00442702MN
Local Program - National Roads and Bridges - National Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Bridge Widening of Kan Munih Bridge along Camp Andres - Lahing-Lahing Road
Physical Target:
CW-1 - Widening of Bridge: 103.4136 sq.m.
Unit Cost: P 94,281.60319/sq.m.
EAO: P 250,000.00
Allocation: P 10,000,000.00 |
December 29, 2020 |
FY 2020 |
WIN0B00964 |
300117207267000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207267000
Project ID: P00442449MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Rehabilitation of Concrete Road - Rehabilitation of Main Road to Lahi, Maimbung, Sulu
Physical Target:
CW-1- Rehabilitation of Concrete Road: 0.970 lane km
Unit Cost: P 10,206,185.57/Lane km
EAO: P 100,000.00
Allocation: P 10,000,000.00 |
December 29, 2020 |
GAA CY 2020 |
WIN0F06038 |
UACS No. 300108200149000 |
April 15, 2020 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300108200149000
Project ID.: P0044873LZ
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Sta. Ana, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 200 l.m.
Unit Cost (P’000) = P 965.00 / l.m.
Allocation (P’000) = P 193,000.00
EAO (P’000)= P 7,000.00
Total (P’000) = P 200,000.00
As Modified
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Sta. Ana, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 6,650 sq.m.
CW2 = Construction of Concrete Road = 500 lane km.
Unit Cost (P’000) = P 22.30 / sq.m.
= P 89.44/ lane km.
Allocation (P’000) = P 148,282.29
= P 44,717.71
EAO (P’000) = P 7,000.00
Total (P’000) = P 200,00.00
WIN0F06038
|
December 28, 2020 |
FY 2020 |
WIN0B00935 |
300117207261000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207261000
Project ID: P00443958MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road along Langgal Maas, Matatal to Anak Jati, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.92 lane km
Unit Cost: P 15,062,690.04/Lane km
EAO: P 289,203.65
Excess: P 790,431.47
Allocation: P 30,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00917 |
300117207256000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207256000
Project ID: P00441133MN
Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Concrete Road - Concreting of Tabuh Batu Road, Maimbung, Sulu
Physical Target:
CW-1 - Construction of Concrete Road: 0.940 lane km
Unit Cost: P 10,531,914.89/lane km
EAO: P 100,000.00
Allocation: P 10,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00933 |
300117207268000 |
August 17, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207268000
Project ID: P00443963MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction/Rehabilitation of Jolo-Buansa Road, Brgy. Buansa, Indanan, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 0.98 lane km
Unit Cost: P 10,102,040.82/Lane km
EAO: P 100,000.00
Allocation: P 10,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00919 |
300117207263000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207263000
Project ID: P00442454MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Improvement/Construction/Concreting of Kan-Dayok-Bagsak Road, Panamao, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.00 lane km
Unit Cost: P 9,900,000.00/Lane km
EAO: P 100,000.00
Allocation: P 10,000,000.00 |
December 28, 2020 |
2020 |
WIN0C04098 |
FY 2020 GAA |
January 7, 2020 |
Region III |
Regional Office III |
Local Roads and Bridges - Local Roads
Construction of Mabiga - Morong - Subic Port Road to connect to Hermosa Ecozone, Clark International Airport, Subic Port and Airport and Bataan Techno Park, Phase I, Hermosa, Bataan |
December 28, 2020 |
2020 |
WIN0C04105 |
FY 2020 GAA |
January 7, 2020 |
Region III |
Regional Office III |
Flood Control and Drainage - Flood Control Structures / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction / Rehabilitation / Construction of Flood Control Structures along Rio Chico River, Sta. 4+000 - Sta. 4+480.25, Brgy. Macarse, Zaragoza, Nueva Ecija |
December 28, 2020 |
FY 2020 |
WIN0B00936 |
300117207260000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207260000
Project ID: P00443956MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road along Pagasinan - Luuk Tulay, Pata, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 0.92 lane km
Unit Cost: P 15,725,267.15/Lane km
EAO: P 144,672.46
Excess: P 388,081.77
Allocation: P 15,000,000.00 |
December 28, 2020 |
2020 |
WIN0C04103 |
FY 2020 GAA |
January 7, 2020 |
Region III |
Regional Office III |
Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including local Projects
Construction of San Ildefonso - San Miguel Bypass Road with ROW |
December 28, 2020 |
FY 2020 |
WIN0B00924 |
300117207257000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207257000
Project ID: P00443948MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road along Langhub Road, Patikul, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 0.94 lane km
Unit Cost: P 15,390,637.03/Lane km
EAO: P 144,671.99
Excess: P 388,129.20
Allocation: P 15,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00914 |
300117207258000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207258000
Project ID: P00443951MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road along Gulangan Ipil Road, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 0.95 lane km
Unit Cost: P 15,237,986.39/Lane km
EAO: P 144,760.88
Excess: P 379,152.05
Allocation: P 15,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00922 |
300117207255000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207255000
Project ID: P00441131MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Main Road to Bualo, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.12 lane km
Unit Cost: P 13,784,613.95/Lane km
EAO: P 154,387.68
Excess: P 406,844.70
Allocation: P 16,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00943 |
300117207265000 |
July 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207265000
Project ID: P00442452MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Rehabilitation of Main Road to Kulasi, Maimbung, Sulu
Physical Target:
CW-1- Rehabilitation of Paved Road: 1.44 lane km
Unit Cost: P 13,397,719.94/Lane km
EAO: P 192,927.17
Excess: P 514,356.11
Allocation: P 20,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00920 |
300117207266000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207266000
Project ID: P00442451MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Rehabilitation of Main Road to Labah, Maimbung, Sulu
Physical Target:
CW-1- Rehabilitation of Paved Road: 1.52 lane km
Unit Cost: P 12,694,995.62/Lane km
EAO: P 192,963.93
Excess: P 510,642.73
Allocation: P 20,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00941 |
300117207270000 |
July 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207270000
Project ID: P00442450MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Rehabilitation of Main Road to Tandoh Patong, Maimbung, Sulu
Physical Target:
CW-1- Rehabilitation of Paved Road: 1.306 lane km
Unit Cost: P 14,780,316.39/Lane km
EAO: P 193,030.93
Excess: P 503,875.86
Allocation: P 20,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00942 |
300117207254000 |
July 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207254000
Project ID: P00441132MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Duhul Kabbun Road, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.35 lane km
Unit Cost: P 14,298,301.72/Lane km
EAO: P 193,027.07
Excess: P 504,265.61
Allocation: P 20,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00923 |
300117207259000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207259000
Project ID: P00443953MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road along Taboh Bato, Maimbung, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.40 lane km
Unit Cost: P 13,402,255.88/Lane km
EAO: P 192,992.48
Excess: P 507,759.04
Allocation: P 20,000,000.00 |
December 28, 2020 |
GAA CY 2020 |
WIN0F06034 |
UACS No.300104213392000 |
April 15, 2020 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300104213392000
Project ID.: P00447247LZ
Local Program
Local – Buildings and Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of New VALPOLY Campus, Brgy. Parada, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building = 1.00 No. of Bldg.
Unit Cost (P’000) = P 422,284.00 / No. of Building
Allocation = P 422,284.00
EAO = P 15,316.00
Total (P’000) = P 437,600.00
As Modified
Local Program
Local – Buildings and Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of New VALPOLY Campus, Brgy. Parada, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building = 5.00 No. of Bldg.
Unit Cost (P’000) = P 84,456.80 / No. of Building
Allocation = P 422,284.00
EAO = P 15,316.00
Total (P’000) = P 437,600.00
WIN0F06034
|
December 28, 2020 |
GAA CY 2020 |
WIN0F06032 |
UACS No. 300108200151000 |
April 15, 2019 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300108200151000
Project ID.: P00448740LZ
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Ususan, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 200 l.m.
Unit Cost (P’000) = P 965.00 / l.m.
Allocation (P’000) = P 193,000.00
EAO (P’000)= P 7,000.00
Total (P’000) = P 200,000.00
As Modified
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Ususan, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 6,650 sq.m.
CW2 = Construction of Concrete Road = 500 lane km.
Unit Cost (P’000) = P 22.23 / sq.m.
= P 90.33/ lane km.
Allocation (P’000) = P 147,834.00
= P 45,165.60
EAO = P 7,000.00
Total (P’000) = P 200,00.00
WIN0F06032
|
December 28, 2020 |
GAA CY 2020 |
WIN0F06033 |
UACS No. 300108200152000 |
April 15, 2020 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 300108200152000
Project ID.: P00448741LZ
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Wawa, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 360 l.m.
Unit Cost (P’000) = P 536.11 / l.m.
Allocation (P’000) = P 193,000.00
EAO (P’000)= P 7,000.00
Total (P’000) = P 200,000.00
As Modified
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Wawa, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 6,783 sq.m.
CW2 = Construction of Concrete Road = 510 lane km.
Unit Cost (P’000) = P 22.26 / sq.m.
= P 82.39/ lane km.
Allocation (P’000) = P 150,980.00
= P 42,019.05
EAO (P'000) = P 7,000.00
Total (P’000) = P 200,00.00
WIN0F06033
|
December 28, 2020 |
GAA CY 2020 |
WIN0F06036 |
UACS No. 300108200150000 |
April 15, 2020 |
National Capital Region |
NCR - Regional Office |
As per GAA/Original
UACS No. 3001082001500000
Project ID.: P00448739LZ
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Tuktukan, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 3.50 l.m.
Unit Cost (P’000) = P 551.43 / l.m.
Allocation = P 193,000,000.00
EAO = P 7,000,000.00
Total (P’000) = P 200,000.00
As Modified
Local Program
Local – Flood Control and Drainage – Drainage / Protection Works – Construction / Repair / Rehabilitation /
Improvement of Various of Infrastructure including Local Projects
Construction of Slope Protection and Linear Parks along Taguig River, Brgy. Tuktukan, Taguig City
Physical Target: CW1 = Construction of Drainage Structure = 3.50 l.m.
CW2 = Construction of Concrete Road = 500 lane km.
Unit Cost (P’000) = P 21.62 / sq.m.
= P 98.43/ lane km.
Allocation = P 143,784,790.00
= P 49,215,210.00
EAO = P 7,000,000.00
Total (P’000) = P 200,000.00
WIN0F06036
|
December 28, 2020 |
FY 2020 |
WIN0B00926 |
300207100133000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300207100133000
Project ID: P00431769MN
CSSP: Convergence and Special Support Program - Construction/ Improvement of Various Infrastructure in Support of National Security
Road Concreting (Gravel to Concrete) Airport Access Road, Camp Bautista, Brgy. Busbus, Jolo, Sulu
CW1 - Construction of Concrete Road: 1.26 lane km.
Unit Cost: P 15,264,834.26/lane km.
EAO: P 673,179.19
Excess: P 93,129.65
Allocation: P 20,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00918 |
300111200291000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200291000
Project ID: P00442708MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening - Iruk-Iruk - Bikad National Road
Physical Target:
CW-1 - Construction of Concrete Road: 0.866 lane km
Unit Cost: P 28,146,651.27/lane km
EAO: P 625,000.00
Allocation: P 25,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00932 |
300117207264000 |
December 2, 2020 |
Region IX |
Regional Office IX |
UACS No. 300117207264000
Project ID: P00442455MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction/Concreting of Kan-Izquierdo-Junction Sucuban Road, Luuk, Sulu
Physical Target:
CW-1- Construction of Concrete Road: 1.84 lane km
Unit Cost: P 15,737,817.40/Lane km
EAO: P 289,575.84
Excess: P 752,840.14
Allocation: P 30,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00940 |
300111200287000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200287000
Project ID: P00442678MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo-Taglibi - Tiptipon Road, K16+000 - K16+935.00
Physical Target:
CW-1 - Reconstruction to Concrete Pavement: 1.87 lane km
Unit Cost: P 15,487,664.80/lane km
EAO: P 724,048.33
Excess: P 314,018.48
Allocation: P 30,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00931 |
300111200285000 |
December 3, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200285000
Project ID: P00442681MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo-Indanan-Parang-Silangkan Road, Sulu
K0+660 - K1+587
Physical Target:
CW-1 - Reconstruction to Concrete Pavement: 1.854 lane km
Unit Cost: P 15,614,212.40/lane km
EAO: P 723,718.74
Excess: P 327,531.47
Allocation: P 30,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00915 |
300111200286000 |
June 29, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200286000
Project ID: P00442676MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo-Taglibi - Tiptipon Road, K0+840.00 - K1+874.00
Physical Target:
CW-1 - Construction of Concrete Road: 2.068 lane km
Unit Cost: P 16,341,943.40/lane km
EAO: P 844,878.47
Excess: P 359,982.57
Allocation: P 35,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00929 |
300111200282000 |
June 14, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200282000
Project ID: P00442713MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Missing Links - Banaran - Tonggusong National Road
K0+000.00 - K0+500.00,
K3+600.00 - K4+033.00
Physical Target:
CW-1 - Road Upgrading Gravel to Paved: 1.866 lane km
Unit Cost: P 18,087,354.46/lane km
ROW:225.70 Sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 843,775.09
Excess: P 337,510.03
Allocation: P 35,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00928 |
300111200288000 |
March 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200288000
Project ID: P00442706MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Rehabilitation/Reconstruction/ Upgrading of Damaged Paved Roads - Laum - Likud Sikubong Road
Physical Target:
CW-1 - Road Upgrading Gravel to Paved: 2.1416 lane km
Unit Cost: P 14,766,655.65/lane km
ROW: 1,439.51 Sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 891,906.00
Allocation: P 37,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00937 |
300111200284000 |
October 9, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200284000
Project ID: P00442715MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Missing Links - Nalil - Sikiat Road
Physical Target:
CW-1 - Road Upgrading Gravel to Paved: 2.570 lane km
Unit Cost: P 17,071,984/lane km
EAO: P 1,096,875.00
Excess: P 28,125.00
Allocation: P 45,000,000.00 |
December 28, 2020 |
FY 2021 |
WIN0B00921 |
300111200283000 |
March 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200283000
Project ID: P00442714MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Missing Links - Marangmarang - Bakung Road, K5+488.00 - K6+440.00
Physical Target:
CW-1 - Road Upgrading Gravel to Paved: 1.904 lane km
Unit Cost: P 25,285,169.00/lane km
ROW: 2,178.21 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 1,203,574.04
Allocation: P 50,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00930 |
300111200293000 |
March 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200293000
Project ID: P00442710MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening - Sibutu - Ligayan National Road
Physical Target:
CW-1 - Road Widening: 5.706 lane km
Unit Cost: P 8,442,814.35/lane km
ROW: 2,069.78 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 1,204,367.47
Allocation: P 50,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00879 |
300111200292000 |
March 20, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200292000
Project ID: P00442711MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Road Widening - Pagasinan - Karungdung Road
K187+700.05 - K188+913.00
Physical Target:
CW-1 - Road Widening: 2.426 lane km
Unit Cost: P 19,870,577.39/lane km
ROW: 355.90 sq.m.
Unit Cost: P 300.00/sq.m.
EAO: P 1,687,210.73
Allocation: P 50,000,000.00 |
December 28, 2020 |
FY 2020 |
WIN0B00938 |
300111200191000 |
June 15, 2020 |
Region IX |
Regional Office IX |
UACS No. 300111200191000
Project ID: P00442682MN
Local Program - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Reconstruction/Upgrading of Damaged Paved Roads along Jolo-Indanan-Parang-Silangkan Road, K10+000 - K11+360
Physical Target:
CW-1 - Reconstruction from Paved to Concrete: 2.72 lane km
Unit Cost: P 18,223,972.13/lane km
EAO: P 1,734,922.15
Excess: P 195,873.66
Allocation: P 51,500,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03235 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bunawan River, Sta. 4+605 to Sta. 5+050, Davao City
Physical Target:
CW1: 375.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bunawan River, Sta. 4+605 to Sta. 5+050, Davao City
Physical Target:
CW1: 445.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03242 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Daang Maharlika (MN) -
K1508+769, K1510+400 - K1510+700, K1510+625
Physical Target:
CW1: 3,100.00 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Drainage Structure along Road)
EAO: P 3,500,000.00
TO: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Daang Maharlika (MN) -
K1510+201, K1510+625
Physical Target:
CW1: 3,100.00 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Drainage Structure along Road)
EAO: P 3,500,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03240 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Magsaysay Avenue -
K1510+063, K1510+178, K1510+303
Physical Target:
CW1: 1,200.00 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 44,250,000.00
CW1: P 43,365,000.00 (Construction of Drainage Structure along Road)
EAO: P 885,000.00
TO: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage along Magsaysay Avenue -
(S01445MN) Chainage 171 to Outfall
Physical Target:
CW1: 1,458.00 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 44,250,000.00
CW1: P 43,365,000.00 (Construction of Drainage Structure along Road)
EAO: P 885,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03233 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads (Asphalt to Concrete) along Davao-Bukidnon Rd -
K1699+583 - K1699+764, K1699+764 - K1701+708
Physical Target:
CW1: 6.500 lane km (Rehabilitation of Paved Road)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Rehabilitation of Paved Road)
EAO: P 3,150,000.00
TO: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads (Asphalt to Concrete) along Davao-Bukidnon Rd -
K1699+(-629) - K1701+200
Physical Target:
CW1: 2.490 lane km (Rehabilitation of Paved Road)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Rehabilitation of Paved Road)
EAO: P 3,150,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03244 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving along Davao-Cotabato Rd (Davao City-Jct. Digos Sect.) -
K1514+265 - K1514+530 (R/S)
Physical Target:
CW1: 2,200.81 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 9,351,000.00
CW1: P 9,163,980.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 187,020.00
TO: Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving along Davao-Cotabato Rd (Davao City-Jct. Digos Sect.) -
K1514+265 - K1514+530, K1521+235 - K1521+415
Physical Target:
CW1: 575.05 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: 0.265 lane km (Road Widening)
CW3: 270.00 sq.m. (Off-Carriageway Improvement: Construction of Median/Center Island)
Allocation:
TOTAL: P 9,351,000.00
CW1: P 1,783,600.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: P 3,185,000.00 (Road Widening)
CW3: P 4,195,380.00 (Off-Carriageway Improvement: Construction of Median/Center Island)
EAO: P 187,020.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03237 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bago River, Sta. 2+835 to Sta. 2+920, Sta. 2+930 to Sta. 3+215
Physical Target:
CW1: 150.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,300,000.00 (Construction of Flood Mitigation Structure)
EAO: P 700,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Flood Mitigation Structure, Bago River, Sta. 3+673 to Sta. 3+848, Sta. 3+851 to Sta. 3+876, Sta. 3+880 to Sta. 3+897, Sta. 3+901 to Sta. 3+990, Davao City
Physical Target:
CW1: 306.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,300,000.00 (Construction of Flood Mitigation Structure)
EAO: P 700,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03234 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Libby Creek Flood Control (B/B), Davao City
Physical Target:
CW1: 832.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 67,550,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,450,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Libby Creek Flood Control (B/B), Davao City
Physical Target:
CW1: 943.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 67,550,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,450,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03238 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Alternate Rd. from Region XI to Region X, (Jct Davao City Diversion Rd-Catalunan Grande-Talandag-Sumimao-Panalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Davao City
Physical Target:
CW1: 0.400 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 48,550,000.00
CW1: P 46,850,750.00 (Construction of Concrete Road)
EAO: P 1,699,250.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Alternate Rd. from Region XI to Region X, (Jct Davao City Diversion Rd-Catalunan Grande-Talandag-Sumimao-Pañalum-Tapak-Cabanglasan-Aglayan, Malaybalay), Davao City
Physical Target:
CW1: 1.470 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 48,550,000.00
CW1: P 46,850,750.00 (Construction of Concrete Road)
EAO: P 1,699,250.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03236 |
FY 2020 GAA RA 11465 |
January 1, 2020 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Talomo River, Sta. 5+575 to Sta. 5+830, Davao City
Physical Target:
CW1: 190.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Talomo River, Sta. 3+455 to Sta. 3+542, Davao City
Physical Target:
CW1: 174.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Flood Mitigation Structure)
EAO: P 800,000.00 |
December 28, 2020 |
FY 2020 GAA |
WIN0G03243 |
FY 2020 GAA RA 11465 |
January 1, 2019 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving / Construction, Jct. Daang Maharlika Rd-Iñigo St.-Jct. Dacudao, Davao City
Physical Target:
CW1: 2,352.700 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,650,000.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
EAO: P 350,000.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Shoulder Paving / Construction, Jct. Daang Maharlika Rd-Iñigo St.-Jct. Dacudao, Davao City
Physical Target:
CW1: 818.09 sq.m. (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: 876.00 sq.m. (Additional Lane Width)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 7,500,945.00 (Off-Carriageway Improvement: Shoulder Paving/Construction)
CW2: P 2,149,055.00 (Additional Lane Width)
EAO: P 350,000.00 |
December 23, 2020 |
FY 2020 |
WIN0G03161 |
310106100526000 |
July 15, 2020 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS NO. 310106100526000
Project ID: P00400628MN
Organizational Outcome 1:
Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Crossing Sta. Clara - Sandayong Rd
K1790+(-884) - K1790+(-763),
K1795+516 - K1795+558
CW1 - Reconstruction to Concrete Pavement: 0.326 lane km.
Unit Cost: P 18,786,993.87/lane km.
ROW: 5,235.00 sq. m.
Unit Cost: P 299.98/sq. m.
EAO: P 122,491.20
Excess: 34,553.50
Allocation: P 7,852,000.00 |
December 23, 2020 |
FY 2020 |
WIN0G03154 |
300116203191000 |
July 14, 2020 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 300116203191000
Project ID: P00442886MN
Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Completion of Causeway Approach - Phase III of the Kaliantana Bridge, Naga, Zamboanga Sibugay
Physical Target:
CW-1 - Construction of Concrete Road: 0.32684 lane km.
Unit Cost: P 23,196,270.16/lane km.
CW-2 - Construction of Road Slope Protection Structures: 2,598 sq.m.
Unit Cost: P 15,942.47/sq.m.
EAO: P 1,000,000.00
Allocation: P 50,000,000.00 |
December 23, 2020 |
FY 2020 |
WIN0G03160 |
300117207295000 |
July 8, 2020 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 300117207295000
Project ID: P00443998MN
Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Local Roads, Dipolog City, Zamboanga del Norte
Physical Target:
CW-1- Construction of Concrete Road: 0.428 lane km
Unit Cost: P 6,939,252.34/Lane km
EAO: P 30,000.00
Allocation: P 3,000,000.00 |
December 23, 2020 |
FY 2020 |
WIN0G03170 |
310109100477000 |
July 15, 2020 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 310109100477000
Projects ID: P00400077MN
Organizational Outcome 1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Tertiary Roads
Crossing Sta. Clara - Sandayong Rd.
K1809+860 - K1810+020,
K1810+240 - K1810+270,
K1810+280 - K1810+320
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 1,976 sq.m.
Unit Cost: P 6,019.86/sq.m
EAO: P 242,760.00
Allocation: P 12,138,000.00 |