Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
September 2, 2021 FY2021 WIN1E02562 310108100566000 April 13, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Secondary Roads

Rizal - Dakak - Dapitan Coastal Loop Rd - K1852+210 - K1852+250, K1852+530 - K1852+580, K1822+500 - K1823+200, K1827+400 - K1827+881

CW1: Construction of Slope Protection Structure
Physical Target: 6,521.0 Sq. M.
Unit Cost: Php 16,101.08665/sq. m.
ROW Acquisition: 939.9415 Sq. M. (Php 281,982.46)
EAO: Php 3,674,831.51
Total Allocation: Php 108,952,000.00
September 2, 2021 FY2021 WIN1E02440 310205100731000 April 19, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads

Sindangan - Bayog - Lakewood Road, Package 1, Zamboanga del Norte

CW1: Construction of Concrete Road
Physical Target: 3.596 Lane Km.
Unit Cost: Php 27,869,938.92/lane km.
EAO: Php 139,699.63
Total Allocation: Php 104,000,000.00
September 2, 2021 FY2021 WIN1E02471 310205100733000 April 19, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads

Sindangan - Bayog - Lakewood Road, Package 2, Zamboanga del Norte

CW1: Construction of Concrete Road
Physical Target: 1.26 Lane Km.
Unit Cost: Php 66,296,896.37/lane km.
EAO: Php 3,035,025.00
Excess: Php 145,885.57
Total Allocation: Php 86,715,000.00
August 31, 2021 FY2021 WIN1B01143 300116203731000 April 17, 2021 Region IX Regional Office IX
Local - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Timbangan to Pantao Road, Barangay Timbangan, Indanan, Sulu.

CW1: Construction of Concrete Road
Physical Target: 4.40 Lane Km.
Unit Cost: Php 14,255,013.70/lane km.
EAO: Php 2,195,272.11
Excess: Php 82,667.62
Total Allocation: Php 65,000,000.00
August 31, 2021 FY2021 WIN1E02274 310204101155000 April 12, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Road

Zamboanga City Diversion Road, Zamboanga City

CW1: Road Widening
Physical Target (Road): 6.06 Lane Km.
Unit Cost (Road): Php 12,438,392.49/lane km.
CW2: Construction of Concrete Bridge
Physical Target (Bridge): 352.026 Sq. M.
Unit Cost (Bridge): Php 65,830.5527/sq.m.
EAO: Php 3,449,275.36
Total Allocation: Php 102,000,000.00
August 31, 2021 FY2021 WIN1B01144 300116203730000 April 17, 2021 Region IX Regional Office IX
Local - National Roads and Bridges - National Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Jolo-Buansa Road, Barangay Buansa, Indanan, Sulu

CW1: Construction of Concrete Road
Physical Target: 10.20 Lane Km.
Unit Cost: Php 13,234,242.44/lane km.
EAO: Php 4,900,000.00
Excess: Php 110,727.08
Total Allocation: Php 140,000,000.00
August 31, 2021 FY2021 WIN1B01139 310105100506000 April 17, 2021 Region IX Regional Office IX
Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

Jolo-Indanan-Parang-Silangkan Rd - K0012+0000 - K0013+690

CW1: Rehabilitation of Paved Road
Physical Target: 3.38 Lane Km.
Unit Cost: Php 17,122,798.65/lane km.
EAO: Php 2,025,627.08
Excess: Php 99,313.47
Total Allocation: Php 60,000,000.00
August 31, 2021 FY2021 WIN1B01145 310105100508000 April 17, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

Jolo-Taglibi-Tiptipon Rd - K0008+000 - K0008+507

CW1: Rehabilitation of Paved Road
Physical Target: 1.014 Lane Km.
Unit Cost: Php 23,709,243.18/lane km.
EAO: Php 841,441.04
Excess: Php 17,386.38
Total Allocation: Php 24,900,000.00
August 31, 2021 FY2021 WIN1B01138 310202100726000 April 17, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Road

Camp Andres-Sucuban Rd - Sta. 6+480 - Sta. 8+180

CW1: Road Widening
Physical Target: 3.40 Lane Km.
Unit Cost: Php 21,164,164.33/lane km.
ROW Acquisition: 1,744.352467 Sq. M. (Php 523,305.74)
EAO: Php 2,518,535.55
Total Allocation: Php 75,000,000.00
August 31, 2021 FY2021 WIN1B01142 310202100727000 April 17, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Road

Karungdong-Kulay-Kulay Rd - Sta. 6+480 - Sta. 8+045

CW1: Road Widening
Physical Target: 3.13 Lane Km.
Unit Cost: Php 18,241,795.49/lane km.
ROW Acquisition: 1,012.971 Sq. M. (Php 304,791.41)
EAO: Php 1,998,388.70
Total Allocation: Php 59,400,000.00
August 31, 2021 FY2021 WIN1E02244 300117210043000 April 17, 2021 Region IX Regional Office IX
Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program - Construction of Tandu-Bato-Kan Allayon Road, Luuk, Sulu

CW1: Construction of Concrete Road
Physical Target: 1.76 Lane Km.
Unit Cost: Php 14,045,301.35
EAO: Php 250,000.00
Excess: Php 30,269.62
Total Allocation: Php 25,000,000.00
August 31, 2021 FY2021 WIN1E02242 300117210043000 April 17, 2021 Region IX Regional Office IX
Local Program - Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program - Construction of Suligpang-Garid Road, Luuk, Sulu

CW1: Construction of Concrete Road
Physical Target: 1.90 Lane Km.
Unit Cost: Php 13,000,013.88/lane km.
EAO: Php 250,000.00
Excess: Php 49,973.63
Total Allocation: Php 25,000,000.00
August 31, 2021 2021 WIN1E02809 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. : 300116203510000
Project ID: P00550690MN

Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Construction of Bunawan - Varuela Road (Phase 4), Bunawan, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 12.151 Lane Km

Allocation:
TOTAL: P 130,000,000
CW1: P 125,450,000
EAO: P 4,550,000

Unit Cost:
CW1: P 10,324,253.15 / Lane Km

TO:

Construction of Bunawan - Veruela Road (Phase 4), Bunawan, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Slope Protection Structure

Physical Target:
CW1- 2.54 Lane Km
CW2- 16,205.2 Square meters

Allocation:
TOTAL: P 130,000,000
CW1: P 105,170,193.55
CW2: P 20,279,806.45
EAO: P 4,550,000

Unit Cost:
CW1: P 41,405,588.01 / Lane Km
CW2: P 1,251.44 /Square meters
August 31, 2021 2021 WIN1E02808 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. : 300116203511000
Project ID: P00550691MN

Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Construction of Bunawan - Varuela Road (Phase 5), Bunawan, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 12.151 Lane Km

Allocation:
TOTAL: P 130,000,000
CW1: P 125,450,000
EAO: P 4,550,000

Unit Cost:
CW1: P 10,324,253.15 / Lane Km

TO:

Construction of Bunawan - Veruela Road (Phase 5), Bunawan, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Slope Protection Structure

Physical Target:
CW1- 2.633 Lane Km
CW2- 11,716.85 Square meters

Allocation:
TOTAL: P 130,000,000
CW1: P 108,192,373.11
CW2: P 17,257,626.89
EAO: P 4,550,000

Unit Cost:
CW1: P 41,090,912.69 / Lane Km
CW2: P 1,472.89 /Square meters
August 31, 2021 FY2021 WIN1E02240 300116203722000 April 17, 2021 Region IX Regional Office IX
Local - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure - including Local Projects

Construction/Re-blocking of Romandier Camp Andres-Tandu Bato National Road, Km 26+000.00 - Km 27+000.00, Km 44+000.00 - Km 45+510.00, 2nd District, Sulu

CW1: Preventive Maintenance of Road (Concrete Reblocking)
Physical Target: 5.020 Lane Km.
Unit Cost: Php 19,192,180.64/lane km.
EAO: Php 3,500,000.00
Excess: Php 155,253.17
Total Allocation: Php 100,000,000.00
August 31, 2021 FY2021 WIN1E02239 300112200190000 April 17, 2021 Region IX Regional Office IX
Local - National Roads and Bridges - National Bridge - Local Infrastructure Program - Reblocking of Camp Andres Lahing-Lahing Road, Luuk, Sulu

Km 04+000 - Km 07+080

CW1: Preventive Maintenance of Road (Concrete Reblocking)
Physical Target: 6.16 Lane Km.
Unit Cost: Php 11,235,827.97/lane km.
EAO: Php 700,000.00
Excess: Php 87,299.73
Total Allocation: Php 70,000,000.00
August 31, 2021 FY2021 WIN1E02238 300111200355000 April 17, 2021 Region IX Regional Office IX
Local - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects - Widening of Jolo-Taglibi-Tiptipo National Road, Panamao, Sulu

CW1: Road Widening
Physical Target: 5.920 Lane Km.
Unit Cost: Php 16,227,552.91/lane km.
ROW Acquisition: 1,901.792 Sq. M. (Php 570,537.83)
EAO: Php 3,362,348.96
Total Allocation: Php 100,000,000.00
August 31, 2021 FY2021 WIN1B01150 300116204458000 April 17, 2021 Region IX Regional Office IX
Local Program - Local - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects - Construction/ Concreting of Kan-Imbas Road Camp Andres, Luuk, Sulu

CW1: Construction of Concrete Road
Physical Target: 1.160 Lane Km.
Unit Cost: Php 16,773,738.42/lane km.
EAO: Php 500,000.00
Excess: Php 42,463.43
Total Allocation: Php 20,000,000.00
August 31, 2021 FY2021 WIN1B01149 310105100507000 April 17, 2021 Region IX Regional Office IX
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads

Jolo-Taglibi-Tiptipon Road, K0002+000 - K0003+035

CW1: Rehabilitation of Paved Road
Physical Target: 2.070 Lane Km.
Unit Cost: Php 16,325,626.26/lane km.
EAO: Php 1,182,791.62
Excess: Php 23,162.02
Total Allocation: Php 35,000,000.00
August 31, 2021 FY2021 WIN1B01151 300116203723000 April 17, 2021 Region IX Regional Office IX
Local Program - Local - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects

Construction/Concreting of Kan-Bah-Kan Bulak Road, Luuk, Sulu

CW1: Construction of Concrete Road
Physical Target: 5.020 Lane Km.
Unit Cost: Php 17,969,967.08/lane km.
EAO: Php 2,800,000.00
Excess: Php 48,456.79
Total Allocation: Php 80,000,000.00
August 31, 2021 FY2021 WIN1B01152 300117210035000 April 17, 2021 Region IX Regional Office IX
Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program - Concreting of Road at Salimbangun, Barangay Pandan Niog, Pangutaran, Sulu

CW1: Construction of Concrete Road
Physical Target: 0.930 Lane Km.
Unit Cost: Php 10,645,161.29
EAO: Php 100,000.00
Total Allocation: Php 10,000,000.00
August 31, 2021 FY2021 WIN1B01153 300117210012000 April 17, 2021 Region IX Regional Office IX
Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program - Concreting of Road at Barangay Bangas Likud, Hadji Panglima Tahil, Sulu

CW1: Construction of Concrete Road
Physical Target: 0.834 Lane Km.
Unit Cost: Php 11,870,503.60/lane km.
EAO: Php 100,000.00
Total Allocation: Php 10,000,000.00
August 31, 2021 FY2021 WIN1E02272 310201100680000 April 12, 2021 Region IX Regional Office IX
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads

Dipolog-Punta-Dansullan-S Osmeña Rd, Zamboanga del Norte/Sur Bdry Rd - K1882+220 - K1885+560

CW1: Road Widening
Physical Target: 6.72 Lane Km.
Unit Cost: Php 15,417,758.34/lane km.
ROW Acquisition: 9,221.357 Sq. M. (Php 2,766,407.20)
EAO: Php 3,626,256.76
Total Allocation: Php 110,000,000.00
August 27, 2021 FY 2021 WIN1C04227 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320101106861000
Project ID: P00526227LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Mitigation and Drainage Systems – Rehabilitation/Improvement of Flood Control Structures along Laniton Bridge in Barangay Laniton, Basud, Camarines Norte
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 522 Lineal Meters
Allocation: Php 43,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Mitigation and Drainage Systems – Rehabilitation/Improvement of Flood Control Structures along Laniton Bridge in Barangay Laniton, Basud, Camarines Norte
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 380 Lineal Meters
Allocation: Php 43,000,000.00
August 27, 2021 FY 2021 GAA WIN1E02721 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Daang Maharlika (MN) - K1377+(-201) - K1377+(-198),
K1377+655 - K1377+665, K1377+683 - K1378+000
Physical Target:
CW1: 3.654 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 21,876,000.00
CW1: P 21,438,480.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 437,520.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Daang Maharlika (MN) - K1392+287 - K1392+872
Physical Target:
CW1: 3.510 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 21,876,000.00
CW1: P 21,438,480.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 437,520.00
August 27, 2021 FY 2021 WIN1C04016 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320101106855000
Project ID: P00526221LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Barangay Taba-Taba to Barangay Mangcamagong, Basud, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 190 Lineal Meters
Allocation: Php 43,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Barangay Taba-Taba to Barangay Mangcamagong, Basud, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 190 Lineal Meters
Allocation: Php 43,000,000.00
August 27, 2021 FY 2021 WIN1C04205 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320101106856000
Project ID: P00526222LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Phase I, Barangay Cayucyucan, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 190 Lineal Meters
Allocation: Php 43,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Phase I, Barangay Cayucyucan, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 210 Lineal Meters
Allocation: Php 43,000,000.00
August 27, 2021 2021 WIN1E02766 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Butuan City District Engineering Office
UACS No. : 300204101157000
Project ID: P00537703MN

Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones

FROM:

Road connecting Brgys. Mat-i and E.G. Montilla, Butuan City, Agusan del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 0.843 Lane Km

Allocation:
TOTAL: P 10,000,000
CW1: P 9,800,000
EAO: P 200,000

Unit Cost:
CW1: P 4,694,610.78/Lane Km

TO:

Road Connecting Brgys. Mat-i and E.G. Montilla, Las Nieves, Agusan del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 0.843 Lane Km

Allocation:
TOTAL: P 10,000,000
CW1: P 9,800,000
EAO: P 200,000

Unit Cost:
CW1: P 4,694,610.78/Lane Km
August 27, 2021 FY 2021 WIN1C04304 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320102104344000
Project ID: P00526488LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Flood Control Project along Daet River (Brgy. 1 Section), Daet, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 75.819 Lineal Meters
Allocation: Php 17,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Flood Control Project along Daet River (Brgy. 1 Section), Daet, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 73.00 Lineal Meters
Allocation: Php 17,000,000.00
August 27, 2021 2021 WIN1E02737 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 310109100733000
Project ID: P00509865MN

OO1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

FROM:

Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1133 + 360 - K1133 + 428

Type of Work:
CW1- Construction of Road Slope Protection Structure

Physical Target:
CW1- 0.000 Square meters

Allocation:
TOTAL: P 45,000,000
CW1: P 44,100,000
EAO: P 900,000

Unit Cost:
CW1: P -

TO:

Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1134+300 - K1134+590, K1134+700 – K1134+860

Type of Work:
CW1- Construction of Road Slope Protection Structure

Physical Target:
CW1- 2,946.50 Square meters

Allocation:
TOTAL: P 45,000,000
CW1: P 44,100,000
EAO: P 900,000

Unit Cost:
CW1: P 14,966.91/ Square meters
August 27, 2021 2021 WIN1E02725 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 300211100240000
Project ID: P00533131MN

Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239

FROM:

Asset Preservation - Preventive Maintenance - Tertiary Roads - Asphalt Overlay along Surigao - San Juan Coastal Road, K1116+059.00 - K119+816, Brgy. Sabang, Surigao

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 2.359 Lane Km

Allocation:
TOTAL: P 40,000,000
CW1: P 38,600,000
EAO: P 1,400,000

Unit Cost:
CW1: P 16,362,865.62/Lane Km

TO:

Asset Preservation - Preventive Maintenance - Tertiary Roads - Asphalt Overlay along Surigao - San Juan Coastal Road, K1116+059.00 – K1117+000, K1117+171 - K1117+582.37, Brgy. Sabang, Surigao

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 2.727 Lane Km

Allocation:
TOTAL: P 40,000,000
CW1: P 38,600,000
EAO: P 1,400,000

Unit Cost:
CW1: P 14,154,748.81/Lane Km
August 27, 2021 2021 WIN1E02757 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 300116204631000
Project ID: P00550981MN

Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Rehabilitation/Concreting of Road, from Barangay Pili to Barangay Karihatag, Malimono, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 1.812 Lane Km

Allocation:
TOTAL: P 33,000,000
CW1: P 32,340,000
EAO: P 660,000

Unit Cost:
CW1: P 17,847,682.12/Lane Km

TO:

Rehabilitation/Concreting of Road, from Barangay Pili to Barangay Karihatag, Malimono, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure

Physical Target:
CW1- 1.423 Lane Km
CW2- 483.29 Square meters

Allocation:
TOTAL: P 33,000,000
CW1: P 29,026,530
CW2: P 3,313,470
EAO: P 660,000

Unit Cost:
CW1: P 2,398,123.68/Lane Km
CW2: P 6,856.07/Square meters
August 27, 2021 FY 2021 WIN1C04084 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320102104345000
Project ID: P00526489LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Mabulao River Control Structure, Barangay Calasgasan – Magang Section, Daet, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 290 Lineal Meters
Allocation: Php 43,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Mabulao River Control Structure, Barangay Calasgasan – Magang Section, Daet, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 239 Lineal Meters
Allocation: Php 43,000,000.00
August 27, 2021 FY 2021 GAA WIN1F06521 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Regional Office IV-B
UACS No. : 310205100728000
Project ID : P00506139LZ

001 : Ensure Safe and Reliable National Road System

Network Development - Construction of Missing Links/New Roads

FROM :

Mindoro Island Circumferential Road (Puerto Galera - Abra De Ilog)
Occidental Mindoro
Physical Target - CW1 - Construction of Concrete Road :
0.546 Lane Km
- CW2 - Construction of Concrete Bridge :
1,436.724 Square Meters
Allocation : Php 110.00 Million

TO :

Mindoro Island Circumferential Road (Puerto Galera - Abra De Ilog)
Occidental Mindoro
Physical Target - CW1 - Construction of Gravel Road :
0.934 Lane Km
Allocation : Php 110.00 Million
August 27, 2021 FY 2021 WIN1C04303 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300107200973000
Project ID: P00561592LZ
AS PER GAA:
Local Program – Flood Control and Drainage – Flood Control Structures/Facilities – Local Infrastructure Program – Construction of Flood Control Structure (River Bank Stabilization), Brgy. Bakiad, Labo, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 1,267.664 Lineal Meters
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program – Flood Control and Drainage – Flood Control Structures/Facilities – Local Infrastructure Program – Construction of Flood Control Structure (River Bank Stabilization), Brgy. Bakiad, Labo, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 388.0 Lineal Meters
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04280 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300107200982000
Project ID: P00561598LZ
AS PER GAA:
Local Program – Flood Control and Drainage – Flood Control Structures/Facilities – Local Infrastructure Program – Improvement of River Bank in Brgy. Dalas, Labo, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 1,267.664 Lineal Meters
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program – Flood Control and Drainage – Flood Control Structures/Facilities – Local Infrastructure Program – Improvement of River Bank in Brgy. Dalas, Labo, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 399.0 Lineal Meters
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04203 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300116203521000
Project ID: P00561929LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Divresion Road, Brgy. Exciban, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 7.98 Lane Km
Allocation: Php 93,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Divresion Road, Brgy. Exciban, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.25278 Lane Km
CW2 - Construction of Road Slope Protection Structure – 3,622.04 Square meters
Allocation: Php 93,000,000.00
August 27, 2021 FY 2021 WIN1C04131 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300116203522000
Project ID: P00561930LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Bypass Road, Brgy. Anahaw, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 7.98 Lane Km
Allocation: Php 93,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Construction/Repair/ Rehabilitation/Improvement of Various Infrastructure including Local Projects – Construction of Bypass Road, Brgy. Anahaw, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.816 Lane Km
CW2 - Construction of Road Slope Protection Structure – 4,818.40 Square meters
Allocation: Php 93,000,000.00
August 27, 2021 FY 2021 WIN1C04113 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300116203727000
Project ID: P00561995LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Road with Seawall (Cong. Eming Panotes Boulevard) Barangay Mambungalon, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 9.904 Lane Km
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Road with Seawall (Cong. Eming Panotes Boulevard) Barangay Mambungalon, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.89 Lane Km
CW2 - Construction of Road Slope Protection Structure – 2,202.75 Square meters
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04085 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300116203733000
Project ID: P00561998LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of By-pass Road with Seawall at Brgy. Parang – South Poblacion, Jose Panganiban, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 9.904 Lane Km
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of By-pass Road with Seawall at Brgy. Parang – South Poblacion, Jose Panganiban, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.87 Lane Km
CW2 - Construction of Road Slope Protection Structure – 2,175 Square meters
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04097 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300116204253000
Project ID: P00562514LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Seawall with Roads (cong. Elmer Panotes Blvd.), Leading to Cory Aquino Blvd., Lanot Section, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 2.476 Lane Km
Allocation: Php 25,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Seawall with Roads (cong. Elmer Panotes Blvd.), Leading to Cory Aquino Blvd., Lanot Section, Mercedes, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.24 Lane Km
CW2 - Construction of Road Slope Protection Structure – 564 Square meters
Allocation: Php 25,000,000.00
August 27, 2021 FY 2021 WIN1C04086 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300117207600000
Project ID: P00562560LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Opening/Concreting of Road, Lukbanan, Capalonga Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0 Lane Km
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Opening/Concreting of Road, Lukbanan, Capalonga Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 3.406Lane Km
CW2 - Construction of Road Slope Protection Structure – 5,359.93 Square meters
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04087 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300117209236000
Project ID: P00564789LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Opening/Concreting of Road, Purok 3 to Purok 5, Barangay San Antonio to Barangay Bautista, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 1.592 Lane Km
Allocation: Php 10,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Opening/Concreting of Road, Purok 3 to Purok 5, Barangay San Antonio to Barangay Bautista, Labo, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 1.752 Lane Km
Allocation: Php 10,000,000.00
August 27, 2021 FY 2021 WIN1C04265 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 310108100528000
Project ID: P00505991LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Secondary Roads – Masbate-Milagros Rd – K0004+743 – K0004+994
Physical Target: CW1- Construction of Road Slope Protection Structure – 2,133.50 Square meters
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Secondary Roads – Masbate-Milagros Rd – K0004+743 – K0004+994, K0007+775 – K0007+890
Physical Target: CW1- Construction of Road Slope Protection Structure – 1,259 Square meters
Allocation: Php 10,000,000.00
August 27, 2021 FY 2021 WIN1C04008 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 310105100570000
Project ID: P00505784LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction Upgrading of Damaged Paved Roads - Secondary Roads – Masbate-Milagros Rd – K0011+483 – K0011+612
Physical Target: CW1- Reconstruction of Concrete Pavement – 0.258 Lane Km
Allocation: Php 5,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction Upgrading of Damaged Paved Roads - Secondary Roads – Masbate-Milagros Rd – K0011+483 – K0011+554
Physical Target: CW1- Reconstruction of Concrete Pavement – 0.142 Lane Km
Allocation: Php 5,000,000.00
August 27, 2021 FY 2021 WIN1C03946 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 320101106882000
Project ID: P00526248LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation and Drainage Systems – Construction of Tinapian River Control, Masbate City
Physical Target: CW1- Construction of Flood Mitigation Structure – 676 Lineal Meters
Allocation: Php 50,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation and Drainage Systems – Construction of Tinapian River Control, Baleno, Masbate
Physical Target: CW1- Construction of Flood Mitigation Structure – 676 Lineal Meters
Allocation: Php 50,000,000.00
August 27, 2021 FY 2021 WIN1C03754 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 300117209330000
Project ID: P00564883LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Concreting of Road, Junction National Road, Masbate Institute of Fisheries and Tech., Masbate City, Masbate
Physical Target: CW1- Construction of Concrete Road – 0.162 Lane Km
Allocation: Php 3,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Road Concreting of Road, Junction National Road, Masbate Institute of Fisheries and Tech., Milagros, Masbate
Physical Target: CW1- Construction of Concrete Road – 0.162 Lane Km
Allocation: Php 3,000,000.00
August 27, 2021 FY 2021 WIN1C04110 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 300117209327000
Project ID: P00564880LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Concreting of Road, Junction National Road – Sitio Kabas-an, Barangay Paraiso, Milagros Masbate
Physical Target: CW1- Construction of Concrete Road – 0.37 Lane Km
Allocation: Php 5,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Concreting of Road, Junction National Road – Sitio Luacan, Barangay Paraiso, Milagros Masbate
Physical Target: CW1- Construction of Concrete Road – 0.37 Lane Km
Allocation: Php 5,000,000.00
August 27, 2021 FY 2021 WIN1C04042 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 310205100581000
Project ID: P00506283LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads – Malubi – Cabangcalan – Dayhagan – Mataba Road, Masbate
Physical Target: CW1- Construction of Concrete Road – 3.3 Lane km.
Allocation: Php 100,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads – Malubi – Cabangcalan – Dayhagan – Mataba Road, Masbate
Physical Target: CW1- Construction of Concrete Road – 2.32 Lane km.
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04013 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 310205100583000
Project ID: P00506284LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads – Mandaon – Dayhagan Road, Masbate
Physical Target: CW1- Construction of Concrete Road – 3.2 Lane km.
Allocation: Php 100,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads – Mandaon – Dayhagan Road, Masbate
Physical Target: CW1- Construction of Concrete Road – 2.64 Lane km.
Allocation: Php 100,000,000.00
August 27, 2021 FY 2021 WIN1C04309 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 2nd District Engineering Office
UACS No.: 310202100836000
Project ID: P00505299LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Masbate-Cataingan-Placer Rd – K0009+803 – K0010+265
Physical Target: CW1- Road Widening – 0.922 Lane km.
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Masbate-Cataingan-Placer Rd – K0008+723 – K0008+859
Physical Target: CW1- Road Widening – 0.272 Lane km.
Allocation: Php 10,000,000.00
August 26, 2021 FY 2021 WIN1C04120 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 310107100255000
Project ID: P00505798LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Primary Roads – Daang Maharlika (LZ) – K0359+800 – K0359+850, K0360+100 – K0360+150, K0364+638 – K0364+748
Physical Target: CW1- Construction of Road Slope Protection Structure – 2,000 Square meters
Allocation: Php 20,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Primary Roads – Daang Maharlika (LZ) – K0359+800 – K0360+024, K0360+100 – K0360+150, K0364+638 – K0364+748
Physical Target: CW1- Construction of Road Slope Protection Structure – 1,176 Square meters
Allocation: Php 20,000,000.00
August 26, 2021 FY 2021 WIN1C04329 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300203101667000
Project ID: P00532255LZ
AS PER GAA:
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations - Daet – Vinzons leading to Mantigbi – Sula – Sabang – Aguit-it Beach, Quinamanukan Island, Vinzons, Camarines Norte
Physical Target: CW1- Construction of Concrete Bridge – 95.238 Square meters
Allocation: Php 10,000,000.00

AS MODIFIED:
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations - Daet – Vinzons leading to Mantigbi – Sula – Sabang – Aguit-it Beach, Quinamanukan Island, Vinzons, Camarines Norte
Physical Target: CW1- Construction of Revetment – 342.99 Square meters
CW2- Construction of Concrete Road – 0.0416 Lane km.
Allocation: Php 10,000,000.00
August 26, 2021 FY 2021 WIN1C04001 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 300203101669000
Project ID: P00532256LZ
AS PER GAA:
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Pinagtigasan to Mahabang Buhangin Road leading to White Sand Beaches Calaguas Island, Brgy. Pinagtigasan, Vinzons, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.302 Lane km.
Allocation: Php 10,000,000.00

AS MODIFIED:
Convergence and Special Support Program – Construction/Improvement of Access Roads leading to Declared Tourism Destinations – Pinagtigasan to Mahabang Buhangin Road leading to White Sand Beaches Calaguas Island, Brgy. Pinagtigasan, Vinzons, Camarines Norte
Physical Target: CW1- Construction of Concrete Road – 0.392 Lane km.
Allocation: Php 10,000,000.00
August 26, 2021 FY 2021 GAA WIN1F06461 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 3001162044221000
Project ID : P00562482LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Concreting of Road,
Bansud, Oriental Mindoro
Physical Target - CW1 - Construction of Concrete Road -
6.00 Lane Km
Allocation : Php 36.00 Million

TO :

Concreting of Road,
Bansud, Oriental Mindoro
Physical Target - CW1 - Construction of Concrete Road -
5.0874 Lane Km
Allocation : Php 36.00 Million
August 26, 2021 FY 2021 WIN1C04196 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Norte District Engineering Office
UACS No.: 320102106857000
Project ID: P00526223LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Tambo Section, Barangay Taba-Taba, Basud, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 191.778 Lineal Meters
Allocation: Php 43,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Construction of Seawall with Road (Cong. Elmer E. Panotes Boulevard leading to Cory Aquino Boulevard) Tambo Section, Barangay Taba-Taba, Basud, Camarines Norte
Physical Target: CW1- Construction of Flood Mitigation Structure – 179 Lineal Meters
Allocation: Php 43,000,000.00
August 26, 2021 FY 2021 GAA WIN1F06524 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 300103203539000
Project ID : P00557166LZ

LOCAL PROGRAM

Buildings and Other Structures - Multipurpose/Facilities -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Construction/Rehabilitation of Multi-Purpose Building
(Evacuation Center), Brgy. Poblacion and Brgy. Cabalwa,
Mansalay, Oriental Mindoro
Physical Target - CW1 - Construction of Multi-Purpose Building
1.00 No. of Building
Allocation : Php 6.00 Million

TO :

Construction/Rehabilitation of Multi-Purpose Building
(Evacuation Center), Brgy. Poblacion and Brgy. Cabalwa,
Mansalay, Oriental Mindoro
Physical Target - CW1 - Construction of Multi-Purpose Building
2.00 No. of Building
Allocation : Php 6.00 Million

August 26, 2021 2021 WIN1F06710 GAA FY 2021 January 1, 2021 Region VIII Biliran District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Secondary Roads

AS PER GAA/ORIGINAL:

Biliran Circumferential Rd - K1099 + 704 - K1100 + 097

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 7.7077 M
Asphalt Overlay: 0.722 Lane Km

EAO P 0.1573 M

Total P 7.865 M

AS MODIFIED:

Biliran Circumferential Rd - K1099 + 704 - K1100 + 009

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 7.7077 M
Asphalt Overlay: 0.546 Lane Km

EAO P 0.1573 M

Total P 7.865 M
August 26, 2021 FY 2021 GAA WIN1F06483 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 310102100693000
Project ID : P00505618LZ

001 : Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Secondary Roads

FROM :

Calapan South Road,
K0127 + 402 - K0127 + 560
Physical Target - Preventive Maintenance - 0.538 Lane Km
Allocation : Php 5.442 Million

TO :

Calapan South Road,
K0127 + 094 - K0127 + 218.50
Physical Target - Preventive Maintenance - 0.498 Lane Km
Allocation : Php 5.442 Million
August 26, 2021 FY 2021 GAA WIn1F06458 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Mindoro Occidental District Engineering Office
UACS No. : 310209100313000
Project ID : P00505126LZ

001 : Ensure Safe and Reliable National Road System

Off-Carriageway Improvement - Tertiary Roads

FROM :

Jct MWCR (Sn Isidro) - Penal Colony - Jct Yapang Road,
K0307 + 318 - K0307 + 535,
K0307 + 604 - K0310 + 049
Physical Target - CW1 - Off-Carriageway Improvement :
Shoulder Paving/Construction -
10,458 square meters
Allocation : Php 28.76 Million

TO :

Jct. MWCR (Sn Isidro) - Penal Colony - Jct Yapang Road,
K0310 + 547 - K0312 + 149,
K0312 + 602 - K0313 + 690
Physical Target - CW1 - Off-Carriageway Improvement :
Shoulder Paving/Construction -
13,125 square meters
Allocation : Php 28.76 Million

August 26, 2021 FY 2021 GAA Win1F06455 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Mindoro Occidental District Engineering Office
UACS No. : 300116204148000
Project ID : P00562409LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Upgrading/Improvement of JNR to Lourdes P/R in
San Jose, Occidental Mindoro
Physical Target - CW1 - Rehabilitation of Concrete Road -
5.482 Lane Km
Allocation : Php 48.00 Million

TO :

Upgrading/Improvement of JNR to Lourdes P/R in
Magsaysay, Occidental Mindoro
Physical Target - CW1 - Rehabilitation of Concrete Road -
5.482 Lane Km
Allocation : Php 48.00 Million
August 26, 2021 FY 2021 GAA WIN1E02789 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction (Completion) of Asico Bridge (Asico Village) Matina Pangi, Davao (Phase 2)
Physical Target:
CW1: 000.00 sq. m. (Construction of Bridge)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Bridge)
EAO: P 800,000.00

TO: Local Program - Local Roads and Bridges - Local Bridges - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction (Completion) of Asico Bridge (Asico Village) Matina Pangi, Davao (Phase 2)
Physical Target:
CW1: 1,940.60 sq. m. (Construction of Bridge)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Construction of Bridge)
EAO: P 800,000.00
August 26, 2021 2021 WIN1F06709 GAA FY 2021 January 1, 2021 Region VIII Biliran District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Secondary Roads

AS PER GAA/ORIGINAL:

Naval-Caibiran Cross Country Rd - K1029 + 745 - K1029+ 883

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 5.90646 M
Asphalt Overlay: 0.552 Lane Km

EAO P 0.12054 M

Total P 6.027 M

AS MODIFIED:

Naval-Caibiran Cross Country Rd - K1029 + 745 - K1029+ 849

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 5.90646 M
Asphalt Overlay: 0.416 Lane Km

EAO P 0.12054 M

Total P 6.027 M
August 26, 2021 FY 2021 GAA WIN1E02789 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Barangay Maduao-Barangay Tagpore, Panabo City, Davao del Norte
Physical Target:
CW1: 7.090 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 58,000,000.00
CW1: P 55,970,000.00 (Construction of Concrete Road)
EAO: P 2,030,000.00

TO: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Concreting of Road, Barangay Maduao-Barangay Tagpore, Panabo City, Davao del Norte
Physical Target:
CW1: 2.897 lane km (Construction of Concrete Road)
CW2: 238.50 sq. m. (Replacement of Bridge)
Allocation:
TOTAL: P 58,000,000.00
CW1: P 33,965,346.00 (Construction of Concrete Road)
CW2: P 22,004,654.00 (Replacement of Bridge)
EAO: P 2,030,000.00
August 26, 2021 FY 2021 GAA WIN1E02800 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Secondary Roads
Dacudao Rd - K1507+(-660) - K1507+(-068)
Physical Target:
CW1: 592.000 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 20,060,000.00
CW1: P 19,658,800.00 (Construction of Drainage Structure along Road)
EAO: P 401,200.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Secondary Roads
Dacudao Rd - K1507+(-419) - K1507+(-068)
Physical Target:
CW1: 351.000 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 20,060,000.00
CW1: P 19,658,800.00 (Construction of Drainage Structure along Road)
EAO: P 401,200.00
August 26, 2021 FY 2021 GAA WIN1E02802 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao de Oro 1st District Engineering Office
MODIFICATION:

FROM: Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Road from Purok 13 to Purok 9 Barangay Pasian, Monkayo, Davao de Oro
Physical Target:
CW1: 1.842 Lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 21,500,000.00
CW1: P 21,285,000.00 (Construction of Concrete Road)
EAO: P 215,000.00

TO: Local Program - Local Roads and Bridges - Local Roads - Local Infrastructure Program
Construction of Road from Purok 13 to Purok 9 Barangay Pasian, Monkayo, Davao de Oro
Physical Target:
CW1: 0.760 Lane km (Construction of Concrete Road)
CW2: 146.400 sq. m. (Construction of Concrete Bridge)
Allocation:
TOTAL: P 21,500,000.00
CW1: P 11,989,116.74 (Construction of Concrete Road)
CW2: P 9,295,883.26 (Construction of Concrete Bridge)
EAO: P 215,000.00
August 26, 2021 FY 2021 GAA WIN1F06459 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Mindoro Occidental District Engineering Office
UACS No. : 300202100194000
Project ID : P00531942LZ

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Seaports

FROM :

Access Road leading to Caminawit Port,
Rizal, Occidental Mindoro
Physical Target - CW1 - Construction of Concrete Road :
0.678 Lane Km
Allocation : Php 10.00 Million

TO :

Access Road leading to Caminawit Port,
San Jose, Occidental Mindoro
Physical Target - CW1 - Construction of Concrete Road -
0.300 Lane Km
Allocation : Php 10.00 Million
August 26, 2021 FY 2021 GAA P00562395LZ FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Marinduque District Engineering Office
UACS No. : 300116204134000
Project ID : P00562395LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Repair/Restoration of Road with Slips, Road Collapse,
and Landslide
Marinduque Circumferential Road,
K0022 + 080 - K0022 + 140,
Lamesa, Santa Cruz, Marinduque
Physical Target - CW1 - Rehabilitation/Major Repair of Road Slope
Protection Structure - 1,200 square meters
Allocation : Php 20.00 Million

TO :

Repair/Restoration of Road with Slips, Soil Collapse and
Landslide,
Marinduque Circumferential Road
K0022 + 137 - K0022 + 407,
Lamesa, Santa Cruz, Marinduque
Physical Target - CW1 - Rehabilitation/Major Repair of Road Slope
Protection Structure - 2,480 square meters
Allocation : Php 20.00 Million
August 26, 2021 FY 2021 GAA WIN1F06548 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Mindoro Oriental District Engineering Office
UACS No. : 320102104116000
Project ID : P00526332LZ

002 : Protect Lives and Properties Against major Floods

Construction/Maintenance of Flood Mitigation Structure
and Drainage Systems

FROM :

Construction of Calapan River Control along
Ibaba Section, Calapan City, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
608.40 Lineal meters
Allocation : Php 70.00 Million

TO :

Construction of Calapan River Control along
Ibaba Section. Calapan City, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure
217.60 Lineal Meters
Allocation : Php 70.00 Million
August 26, 2021 2021 WIN1C04429 FY 2021 GAA December 28, 2020 Region III Regional Office III
Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as R. A. 11239

Installation of Road Safety Devices and Lighting Facilities along Gov JJ Linao Road (S04821LZ), (S04822LZ)
August 26, 2021 2021 WIN1C04413 FY 2021 GAA December 28, 2020 Region III Regional Office III
Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as R. A. 11239

Improvement of Signages along Various Intersections of Roman Expressway

August 25, 2021 FY 2021 GAA WIN1F06488 FY 2021 GAA DPWH Infra Projects December 28, 2020 Region IV-B Southern Mindoro Engineering District Office
UACS No. : 310108100638000
Project ID : P00505927LZ

001 : Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/Reconstruction of
National Roads with Slips, Slope Collapse, and Landslides -
Secondary Roads

FROM :

Calapan South Road,
K0114 + 600 - K0114 + 691
Physical Target - CW1 - Construction of Road Slope
Protection Structure : 910 sq. m.
Allocation : Php 15.30 Million

TO :

Calapan South Road,
K0114 + 527.80 - K0114 + 563,
K0114 + 600 - K0114 + 695.60
Physical Target - CW1 - Construction of Road Slope
Protection Structure : 1,046.40 sq.m.
Allocation : Php 15.30 Million

August 25, 2021 FY 2021 WIN1C04252 FY 2021 GAA RA 11518 March 27, 2021 Region V Sorsogon 2nd District Engineering Office
UACS No.: 310109100662000
Project ID: P00505799LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slip, Slope Collapse and Landslide – Tertiary Roads
– Ariman-Casiguran Rd – K0607+400 – K0607+500
Physical Target: CW1- Construction of Road Slope Protection Structure – 1,000.0 Square meters
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slip, Slope Collapse and Landslide – Tertiary Roads
– Ariman-Casiguran Rd – K0607+400 – K0607+492, K0607+535 – K0607+635, K0608+100 – K0608+225, K0608+310 – K0608+430
Physical Target: CW1- Construction of Road Slope Protection Structure – 1,311.0 Square meters
Allocation: Php 10,000,000.00
August 25, 2021 FY 2021 WIN1C04305 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 1st District Engineering Office
UACS No.: 320101106172000
Project ID: P00525692LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Mababoy Shore Protection, Sitio Mababoy, Barangay Guinhadap, Monreal, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 438.058 Lineal Meters
Allocation: Php 55,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Mababoy Shore Protection, Sitio Mababoy, Barangay Guinhadap, Monreal, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 220.0 Lineal Meters
Allocation: Php 55,000,000.00
August 25, 2021 FY 2021 WIN1C04306 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 1st District Engineering Office
UACS No.: 320101106180000
Project ID: P00525700LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Shore Protection Structure, Barangay Sitio Busdak, Bartolobac, San Jacinto, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 438.058 Lineal Meters
Allocation: Php 55,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Shore Protection Structure, Barangay Sitio Busdak, Bartolobac, San Jacinto, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 203.0 Lineal Meters
Allocation: Php 55,000,000.00
August 25, 2021 FY 2021 WIN1C04325 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 1st District Engineering Office
UACS No.: 320101106181000
Project ID: P00525701LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Sitio Dalakit Shore Protection, Sitio Dalakit, Barangay McArthur, Monreal, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 438.058 Lineal Meters
Allocation: Php 55,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Sitio Dalakit Shore Protection, Sitio Dalakit, Barangay McArthur, Monreal, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 218.0 Lineal Meters
Allocation: Php 55,000,000.00
August 25, 2021 FY 2021 WIN1C04210 FY 2021 GAA RA 11518 March 27, 2021 Region V Masbate 1st District Engineering Office
UACS No.: 320101106182000
Project ID: P00525702LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Sitio Guiwanon Shore Protection, Sitio Guiwanon, Barangay Danao, San Jacinto, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 438.058 Lineal Meters
Allocation: Php 55,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction of Sitio Guiwanon Shore Protection, Sitio Guiwanon, Barangay Danao, San Jacinto, Masbate
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 215.0 Lineal Meters
Allocation: Php 55,000,000.00
August 25, 2021 FY 2021 WIN1C04296 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 1st District Engineering Office
UACS No.: 310104100272000
Project ID: P00505455LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction Upgrading of Damaged Paved Roads – Primary Roads – Daang Maharlika (LZ) – K0373+300 – K0374+721
Physical Target: CW1- Reconstruction of Concrete Pavement – 2.844 Lane Km
Allocation: Php 55,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction Upgrading of Damaged Paved Roads – Primary Roads – Daang Maharlika (LZ) – K0387+000 – K0387+400, K0395+000 – K0396+461
Physical Target: CW1- Reconstruction of Concrete Pavement – 1.4286 Lane Km
CW2 - Construction of Drainage Structure along Road – 1,360.70 Lineal meters
Allocation: Php 55,000,000.00
August 25, 2021 FY 2021 WIN1C04101 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 2nd District Engineering Office
UACS No.: 320102104353000
Project ID: P00526497LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Rehabilitation of Riverwall along Libmanan River within Bicol River Basin, Barangay Alimbuyog, Milaor, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure - 170.00 Lineal Meters
Allocation: Php 35,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Rehabilitation of Riverwall along Bicol River within Bicol River Basin, Barangay Alimbuyog, Milaor, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure - 170.00 Lineal Meters
Allocation: Php 35,000,000.00
August 25, 2021 FY 2021 WIN1C04291 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 1st Engineering Office
UACS No.: 320101106169000
Project ID: P00525689LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Bulawan Flood Control, San Francisco Section, Malilipot, Albay
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 461.952 Lineal Meters
Allocation: Php 58,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Bulawan Flood Control, San Francisco Section, Malilipot, Albay
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 152.0 Lineal Meters
Allocation: Php 58,000,000.00
August 25, 2021 FY 2021 WIN1C04297 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 1st Engineering Office

UACS No.: 320101106170000
Project ID: P00525690LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Bulawan Flood Control, San Jose Section, Malilipot, Albay
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 461.952 Lineal Meters
Allocation: Php 58,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitation/Improvement of Bulawan Flood Control, San Jose Section, Malilipot, Albay
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 152.0 Lineal Meters
Allocation: Php 58,000,000.00
August 25, 2021 FY 2021 WIN1C04298 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 1st Engineering Office
UACS No.: 3201011068110000
Project ID: P00526177LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction/Extension Seawall, Pawa, Tabaco City
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 200.698 Lineal Meters
Allocation: Php 45,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Maintenance of Flood Mitigation Structures and Drainage Systems – Construction/Extension Seawall, Pawa, Tabaco City
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 103.56 Lineal Meters
Allocation: Php 45,000,000.00
August 25, 2021 FY 2021 WIN1C04287 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 2nd Engineering Office
UACS No.: 310109100656000
Project ID: P00505984LZ
AS PER GAA:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Tertiary Roads – Comun-Inarado-Peñafrancia Rd – K0530+912 – K0530+980
Physical Target: CW1- Construction of Road Slope Protection Structure – 1,400.0 Square meters
Allocation: Php 7,000,000.00

AS MODIFIED:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Tertiary Roads – Comun-Inarado-Peñafrancia Rd – K0519+370 – K0519+502, K0523+183 – K0523+210
Physical Target: CW1- Construction of Road Slope Protection Structure – 814.08 Square meters
Allocation: Php 7,000,000.00
August 25, 2021 FY 2021 WIN1C04344 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 2nd Engineering Office
UACS No.: 310109100645000
Project ID: P00505579LZ
AS PER GAA:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Secondary Roads – Legazpi City-Punta de Jesus Rd – K0561+720 – K0562+120
Physical Target: CW1- Construction of Road Slope Protection Structure – 0 Square meters
Allocation: Php 4,000,000.00

AS MODIFIED:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide - Secondary Roads – Legazpi City-Punta de Jesus Rd – K0561+720 – K0562+120
Physical Target: CW1- Construction of Road Slope Protection Structure – 511.70 Square meters
Allocation: Php 4,000,000.00
August 25, 2021 FY 2021 WIN1C04331 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 2nd Engineering Office
UACS No.: 310202100830000
Project ID: P00505273LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Road Widening - Secondary Roads – Daang Maharlika Jct-Legazpi-Sto. Domingo-Tabaco-Camarines Sur Bdry Rd – K0535+160 – K0535+710
Physical Target: CW1- Road Widening – 1.10 Lane Km
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Road Widening - Secondary Roads – Daang Maharlika Jct-Legazpi-Sto. Domingo-Tabaco-Camarines Sur Bdry Rd – K0535+000 – K0535+080
Physical Target: CW1- Road Widening – 0.16 Lane Km
ROW - ROW Acquisition – 710.0 Square meters
Allocation: Php 10,000,000.00
August 25, 2021 FY 2021 WIN1C04316 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 2nd Engineering Office
UACS No.: 300117207615000
Project ID: P00562571LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Buhatan-Gaba Toruism Ridge View/Cross Country Road, Rapu-Rapu, Albay
Physical Target: CW1- Construction of Concrete Road - 8.581 lane Km
Allocation: Php 100,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Buhatan-Gaba Toruism Ridge View/Cross Country Road, Rapu-Rapu, Albay
Physical Target: CW1- Construction of Concrete Road – 4.80 lane Km
Allocation: Php 100,000,000.00
August 25, 2021 FY 2021 WIN1C04294 FY 2021 GAA RA 11518 March 27, 2021 Region V Albay 2nd Engineering Office
UACS No.: 300107201205000
Project ID: P00561821LZ
AS PER GAA:
Local Program -Flood Control and Drainage – Flood Control Structures / Facilities – Local Infrastructure Program – Construction of Mangagat Flood Control System, Barangay Galicia, Rapu-Rapu, Albay
Physical Target: CW1- Construction of Flood Mitigation Structure – 361.165 Lineal Meters
Allocation: Php 35,000,000.00

AS MODIFIED:
Local Program -Flood Control and Drainage – Flood Control Structures / Facilities – Local Infrastructure Program – Construction of Mangagat Flood Control System, Barangay Galicia, Rapu-Rapu, Albay
Physical Target: CW1- Construction of Flood Mitigation Structure – 145.0 Lineal Meters
Allocation: Php 35,000,000.00
August 25, 2021 FY 2021 WIN1C04138 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 5th District Engineering Office
UACS No.: 310104100305000
Project ID: P00505453LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction /Upgrading of Damage Paved Roads – Primary Roads – Daang Maharlika (LZ) – K0456+(-692) – K0456+(-627)
Physical Target: CW1- Reconstruction of Concrete Pavement – 0.26 Lane Km
Allocation: Php 5,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction /Upgrading of Damage Paved Roads – Primary Roads – Daang Maharlika (LZ) – K0461+103 – K0461+210, K0464+273-K0464+445
Physical Target: CW1- Reconstruction of Concrete Pavement – 0.082 Lane Km
CW2 – Rehabilitation/Major Repair of Drainage Structure along Road – 331.0 Lineal meters
Allocation: Php 5,000,000.00
August 25, 2021 FY 2021 WIN1C04209 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 5th District Engineering Office
UACS No.: 310202100832000
Project ID: P00505008LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Secondary Roads – Iriga City-Sn Isidro-Sagrada-Sn Ramon-Hanawan Rd - K0477+000 – K0477+333
Physical Target: CW1- Road Widening – 0.666 Lane Km
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Secondary Roads – Iriga City-Sn Isidro-Sagrada-Sn Ramon-Hanawan Rd - K0477+000 – K0477+235
Physical Target: CW1- Road Widening – 0.47 Lane Km
Allocation: Php 10,000,000.00
August 25, 2021 FY 2021 WIN1C04283 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 5th District Engineering Office
UACS No.: 320102104129000
Project ID: P00526345LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and principal Rivers – Rehabilitation of Flood Control Structure along Bicol River – Santiago Old Nabua Section, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 540.0 Lineal Meters
Allocation: Php 80,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and principal Rivers – Rehabilitation of Flood Control Structure along Barit River – Santiago Old Nabua Section, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 582.50 Lineal Meters
Allocation: Php 80,000,000.00
August 25, 2021 FY 2021 WIN1C034228 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 5th District Engineering Office
UACS No.: 320102104131000
Project ID: P00526347LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Rehabilitation /Improvement of Revetment along Bicol River Downstream of Sto. Domingo Bridge, Right Side, Brgy. Topas, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 540.0 Lineal Meters
Allocation: Php 80,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Rehabilitation /Improvement of Revetment along Bicol River Downstream of Sto. Domingo Bridge, Right Side, Brgy. Sto. Domingo, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 553.0 Lineal Meters
Allocation: Php 80,000,000.00
August 25, 2021 FY 2021 WIN1C04062 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 5th District Engineering Office
UACS No.: 320102104373000
Project ID: P00526517LZ
AS PER GAA:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Rehabilitation/Improvement along Barit River Downstream of Sto. Domingo Bridge, Right Side, Brgy. Sto. Domingo, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 340.0 Lineal Meters
Allocation: Php 50,000,000.00

AS MODIFIED:
OO2: Protect Lives and Properties Against Major Floods - Construction /Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers – Rehabilitation/Improvement along Bicol River Downstream of Sto. Domingo Bridge, Right Side, Brgy. Sto. Domingo, Nabua, Camarines Sur
Physical Target: CW1- Rehabilitation/Major Repair of Flood Control Structure – 340.0 Lineal Meters
Allocation: Php 50,000,000.00
August 25, 2021 FY 2021 WIN1C04339 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310108100531000
Project ID: P00505988LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide – Secondary Roads – Tigaon-Goa-Sn Jose-Lagonoy-Guijalo via Sn Vicente Rd – K0553+090 – K0553+122, K0533+230 – K0553+260, K0555+719 – K0555+800, K0556+1053 – K0556+1080, K0556+967 – K0556+999, K0559+865 – K0559+910, K0563+700 – K0563+817
Physical Target: CW1- Construction of Road Slope Protection Structure – 5,865.0 Square meters
Allocation: Php 51,635,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation – Rehabilitation/Reconstruction of National Roads with Slip, Slope Collapse and Landslide – Secondary Roads – Tigaon-Goa-Sn Jose-Lagonoy-Guijalo via Sn Vicente Rd – K0553+090 – K0553+122, K0533+230 – K0553+260, K0555+719 – K0555+800, K0556+1053 – K0556+1080, K0556+967 – K0556+999, K0559+865 – K0559+910, K0563+700 – K0563+817, K0568+107 – K0568+150
Physical Target: CW1- Construction of Road Slope Protection Structure – 4,086.20 Square meters
Allocation: Php 51,635,000.00
August 25, 2021 FY 2021 WIN1C04039 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 300116203423000
Project ID: P00561894LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Construction. Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects – Construction of Scout Fuentabella-Tamban-Mabini road, Goa, Camarines Sur
Physical Target: CW1- Construction of Concrete Road – 5.814 Lane km.
Allocation: Php 34,500,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Construction. Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects – Construction of Scout Fuentabella-Tamban-Mabini road, Goa, Camarines Sur
Physical Target: CW1- Construction of Concrete Road – 5.8088 Lane km.
Allocation: Php 34,500,000.00
August 25, 2021 FY 2021 WIN1C04260 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 300117209279000
Project ID: P00564832LZ
AS PER GAA:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Road, Nato, Sagñay, Camarines Sur
Physical Target: CW1- Construction of Concrete Road – 0.259 Lane km.
Allocation: Php 2,000,000.00

AS MODIFIED:
Local Program - Local Roads and Bridges – Local Roads – Local Infrastructure Program – Construction of Road, Nato, Sagñay, Camarines Sur
Physical Target: CW1- Construction of Concrete Road – 0.518 Lane km.
Allocation: Php 2,000,000.00
August 25, 2021 FY 2021 WIN1C04048 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310208100357000
Project ID: P00505285LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Pili-Tigaon-Albay Bdry Rd – K0493+523 – K0494+457, K0494+543 – K0494+610, K0494+666 – K0495+228
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 4,488.75 Square meters
Allocation: Php 13,533,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Pili-Tigaon-Albay Bdry Rd – K0493+523 – K0494+142, K0494+195 – K0494+457, K0494+543 – K0494+610, K0494+666 – K0495+228
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 4,368.99 Square meters
Allocation: Php 13,533,000.00
August 25, 2021 FY 2021 WIN1C04015 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310208100359000
Project ID: P00505287LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Secondary Roads – Tigaon-Goa-Sn Jose-Lagonoy-Guijalo via Sn Vicente Rd
– K0552+245 – K0552+400, K0553+1074 – K0554+102, K0554+312 – K0554+366, K0555+724 – K0555+867
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 1,820 Square meters
Allocation: Php 5,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Secondary Roads – Tigaon-Goa-Sn Jose-Lagonoy-Guijalo via Sn Vicente Rd
– K0552+245 – K0552+400, K0553+1074 – K0554+102, K0554+312 – K0554+366, K0555+724 – K0555+840
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 1,8284 Square meters
Allocation: Php 5,000,000.00
August 25, 2021 FY 2021 WIN1C04041 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310209100315000
Project ID: P00505289LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Jct Digdigon (Goa)-Tinambac Rd – K0502+269 – K0503+280
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 3,333 Square meters
Allocation: Php 10,000,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Jct Digdigon (Goa)-Tinambac Rd – K0502+269 – K0502+815.7, K0502+815.7 – K0503+121, K0503+121 – K0503+241
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 3,3477.4 Square meters
Allocation: Php 10,000,000.00
August 25, 2021 FY 2021 WIN1C04072 FY 2021 GAA RA 11518 March 27, 2021 Region V Camarines Sur 4th District Engineering Office
UACS No.: 310209100316000
Project ID: P00505290LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Jct Teres-Garchitorena Rd – K0545+(-180) – K0545+(-044), K0546+041 – K0546+144, K0547+887 – K0548+000
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 1,068 Square meters
Allocation: Php 3,204,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Tertiary Roads – Jct Teres-Garchitorena Rd – K0545+(-180) – K0545+(-044), K0546+041 – K0546+144, K0547+887 – K0547+924
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 828 Square meters
Allocation: Php 3,204,000.00
August 25, 2021 FY 2021 WIN1C04271 FY 2021 GAA RA 11518 March 27, 2021 Region V Catanduanes District Engineering Office
UACS No.: 310208100361000
Project ID: P00505295LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Secondary Roads – Catanduanes Cir Rd – K0198+578 – K0200+411
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 1,727 Square meters
Allocation: Php 7,840,000.00

AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program – Off-Carriageway Improvement – Secondary Roads – Catanduanes Cir Rd – K0199+569 – K0199+965
Physical Target: CW1- Off-Carriageway Improvement: Shoulder Paving/Construction – 606 Square meters
ROW - ROW Acquisition – 8,940 Square meters
Allocation: Php 7,840,000.00

Pages