March 3, 2024 |
FY2023 |
|
300215102759000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102759000
Project ID: P00733819MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/
Facilities
Construction of Concrete Road along Siay - Godod Road, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 3.814 lane km
Unit Cost: ₱ 17,049,657.45 /lane km
CW2 - Construction of Road Slope Protection Structure: 5,567 sq.m.
Unit Cost: ₱ 3,919.99 /sq.m.
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102758000 |
April 17, 2022 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102758000
Project ID: P00733818MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Concrete Road along Sandayong - Godod - Salug Road (Sandayong - Miampic Section), Zamboanga Sibugay
CW1 - Construction of Concrete Road : 5.06034 lane km
Unit Cost: ₱ 20,580,568.72 /lane km
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102757000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102757000
Project ID: P00733817MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Concrete Road along Salug - Godod - Kabasalan Road, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 4.266 lane km
Unit Cost: ₱ 17,989,005.91 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,579 sq.m.
Unit Cost: ₱ 3,919.7 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102756000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102756000
Project ID: P00733816MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Concrete Road along Naga (Bulansing) - Titay (Palomoc) Road, ZamboangaSibugay
CW1 - Construction of Concrete Road : 5.0 lane km
Unit Cost: ₱ 15,618,813.69 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,234 sq.m.
Unit Cost: ₱ 3,919.4 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102754000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102754000
Project ID: P00733814MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Concrete Road along Ipil - Labason Road (Via Titay and Kalawit), Zamboanga Sibugay
CW1 - Construction of Concrete Road : 4.88 lane km
Unit Cost: ₱ 14,868,972.72 /lane km
CW2 - Construction of Road Slope Protection Structure: 3,646 sq.m.
Unit Cost: ₱ 3,919.2 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102753000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102753000
Project ID: P00733813MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading to Barangay Silingan - Barangay Taruc, R.T. Lim, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 4.4191lane km
Unit Cost: ₱ 17,873,405.41 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,007 sq.m.
Unit Cost: ₱ 3,919.1 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.0 |
March 3, 2024 |
FY2023 |
|
300215102752000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102752000
Project ID: P00733812MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading to Barangay Silingan - Barangay Palmera, R.T. Lim, Zamboanga Sibugayy
CW1 - Construction of Concrete Road : 3.75 km
Unit Cost: ₱ 20,630,034.88 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,420 sq.m.
Unit Cost: ₱ 3,920.4 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102751000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102751000
Project ID: P00733811MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading to Barangay Logan - Barangay Upper Pangi, Ipil, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 3.88 lane km
Unit Cost: ₱ 18,312,449.44 /lane km
CW2 - Construction of Road Slope Protection Structure: 4,030 sq.m.
Unit Cost: ₱ 3,920.02 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102750000 |
April 19, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102750000
Project ID: P00733810MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading to Barangay Banker - Barangay Sininan, Kabasalan, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 3.97 lane km
Unit Cost: ₱ 19,551,445.71 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,355 sq.m.
Unit Cost: ₱ 3,919.64 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
300215102749000 |
April 17, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.300215102749000
Project ID: P00733809MN
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or
Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Access Road leading Barangay Upper Pangi - Barangay Logan, Ipil, Zamboanga Sibugay
CW1 - Construction of Concrete Road : 5.0989 lane km
Unit Cost: ₱ 14,862,725.83 /lane km
CW2 - Construction of Road Slope Protection Structure: 2,823 sq.m.
Unit Cost: ₱ 3,920.1 /sq.m
EAO: ₱ 3,150,000.00
Allocation: ₱ 90,000,000.00 |
March 3, 2024 |
FY2023 |
|
310109101368000 |
March 14, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.310109101368000
Project ID: P00706400MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Ipil-Magdaup Wharf Rd - K2015+153 - K2015+260, K2016+490 - K2016+700
CW1 - Construction of Road Slope Protection Structure: 4,490 sq.m.
Unit Cost: ₱ 3,895.05 /sq.m
CW2 - Road Widening : 0.634 lane km
Unit Cost: ₱ 16,421,461.72 /lane km
ROW Acquisition: ₱ 5,000 sq.m
Unit Cost: ₱ 300.00 /sq.m.
EAO: ₱ 600,000.00
Allocation: ₱ 30,000,000.00 |
March 3, 2024 |
FY2023 |
|
310107100570000 |
March 13, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.310107100570000
Project ID: P00706399MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Ipil-Liloy-Sindangan Rd- K2000+560 - K2000+860, K2004+095 - K2004+220, K2004+560 - K2004+600, K2004+640 - K2004+650, K2005+000 - K2005+060, K2011+178 - K2011+834
CW1 - Construction of Road Slope Protection Structure: 6,200 sq.m.
Unit Cost: ₱ 3,927.88 /sq.m
CW2 - Road Widening : 1.312 lane km
Unit Cost: ₱ 12,032,861.51 /lane km
ROW Acquisition: 6,666.7 sq.m
Unit Cost: ₱ 300.00 /sq.m.
EAO: ₱ 860,000.00
Allocation: ₱ 43,000,000.00 |
March 3, 2024 |
FY2023 |
|
310104100493000 |
March 13, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.310104100493000
Project ID: P00706253MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1706+037.87 - K1766+164.45, K1770+475 - K1770+588.24, K1773+313 - K1773+383, K1776+950 - K1777+026.37, K1778+580.83 - K1778+661.86, K1781+435 - K1782+200, K1783+195 - K1783+958, K1788+800 - K1789+195, K1975+390 - K1796+460, K1801+655 - K1802+127, K1807+000 - K1807+560
CW1 - Reconstruction to Concrete Pavement: 7.7808 lane km
Unit Cost: ₱ 10,953,200.89 /lane km
CW2 - Road Widening : 0.43888 lane km
Unit Cost: ₱ 9,468,828.65 /lane km
ROW Acquisition: 1,000 sq.m
Unit Cost: ₱ 300.00 /sq.m.
EAO: ₱ 3,252,655.00
Allocation: ₱ 92,933,000.00 |
March 3, 2024 |
FY2023 |
|
310101101083000 |
March 13, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.310101101083000
Project ID: P00706090MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1811 + 712- K1812 + 000
CW1 - Preventive Maintenance of Road: Asphalt Overlay: 0.568 lane km
Unit Cost: ₱ 6,052,535.211 lane km
EAO: ₱ 70,160.00
Allocation: ₱ 3,508,000.00 |
March 3, 2024 |
FY2023 |
|
310101101082000 |
March 13, 2023 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No.310101101082000
Project ID: P00706089MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1803 + 000 - K1803 + 538
CW1 - Preventive Maintenance of Road: Asphalt Overlay: 2.152 lane km
Unit Cost: ₱ 5,461,951.67 lane km
EAO: ₱ 239,880.00
Allocation: ₱ 11,994,000.00 |
March 2, 2024 |
FY 2023 |
|
300221102349000 |
May 29, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS NO. 300221102349000
Project ID: P00735037MN
Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Concreting of Road at Brgy. Tandu Patong, Maimbung, Sulu
CW1: Construction of Concrete Road: 0.530 lane km
Unit Cost: ₱ 11,927,710.80 / lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300221102351000 |
May 29, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS NO. 300221102351000
Project ID: P00735039MN
Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Concreting of Road at Brgy. Bangkal, Patikul, Sulu
CW1: Construction of Concrete Road: 0.838 lane km
Unit Cost: ₱ 11,813,842.48 / lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300221102353000 |
May 29, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS NO. 300221102353000
Project ID: P00735041MN
Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Concreting of Road at Brgy. Anuling, Patikul, Sulu
CW1: Construction of Concrete Road: 0.83 lane km
Unit Cost: ₱ 11,927,710.84/ lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300222100127000 |
May 24, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS NO. 300222100127000
Project ID: P00732417MN
Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Construction of Road, Sitio Arakan - Sitio Mosque, Barangay Tandu Patong, Maimbung Sulu
CW1: Construction of Concrete Road: 0.87 lane km
Unit Cost: ₱ 11,379,310.34 /lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300222100128000 |
May 24, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS NO. 300222100128000
Project ID: P00732418MN
Convergence and Special Support Program (CSSP) - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Construction of Road, Tandu Patong - Kabbun Maas, Barangay Tandu Patong, Maimbung, Sulu
CW1: Construction of Concrete Road: 0.736 lane km
Unit Cost: ₱ 13,451,086.95 /lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
310107100562000 |
March 21, 2023 |
Region IX |
Zamboanga del Norte 2nd District Engineering Office |
UACS No. 310107100562000
Project ID: P00706386MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Dipolog-Sindangan-Liloy Rd (S01057MN) - K1874 + 155 - K1874 + 494
CW1- Construction of Road Slope Protection Structure/ 2,622.56 sq. m.
Unit Cost: ₱ 18,684.03/ sq. m.
EAO: ₱ 1,000,000.00
Allocation: ₱50,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300222100120000 |
May 29, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS No. 300222100120000
Project ID: P00732410MN
Convergence and Special Support Program (CSSP): Basic Infrastructure Program (BIP): Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Construction of Road, Ipil - Patao, Barangay Patao, Maimbung, Sulu
CW1: Construction of Concrete Road: 0.530 lane km
Unit Cost: ₱ 12,375,000.00 /lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300215102737000 |
May 29, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS No. 300215102737000
Project ID: P00735018MN
Convergence and Special Support Program (CSSP): Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction/Improvement of Road, Indanan-Maimbung, Maimbung, Sulu
CW1: Construction of Concrete Road: 2.65 lane km
Unit Cost: ₱ 10,924,528.3 /lane km
EAO: ₱ 1,050,000.00
Allocation: ₱ 30,000,000.00 |
March 2, 2024 |
FY 2023 |
|
310305101838000 |
March 21, 2023 |
Region IX |
Zamboanga del Norte 2nd District Engineering Office |
UACS No. 310305101838000
Project ID: P00706604MN
OO1: Ensure Safe and Reliable National Road System – Bridge - Widening of Permanent Bridges
Piao Br. (B00429MN) along Dipolog-Sindangan-Liloy Rd
CW1- Widening of Bridge: 723.51 Square Meters
Unit Cost: ₱ 78,794.83/Square Meters
ROW Acquisition 2,506.08 sq.m.
Unit Cost: ₱ 368.492/sq.m.
EAO: ₱ 2,067,678.51
Allocation: ₱ 60,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300215102735000 |
April 24, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Tawi-Tawi District Engineering Office |
UACS No. 300215102735000
Project ID: P00735016MN
Convergence and Special Support Program (CSSP): Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Road, Sapa-Sapa-Kohec National Highway, Sapa-Sapa, Tawi-Tawi
CW1: Construction of Concrete Road: 7.98 lane km
Unit Cost: ₱ 21,162,280.7 /lane km
EAO: ₱ 6,125,000.00
Allocation: ₱ 175,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300222100119000 |
May 24, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS No. 300215102735000
Project ID: P00735016MN
Convergence and Special Support Program (CSSP): Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Construction of Road, Sitio Pasil - Sitio Tau Luuk, Barangay Ipil, Maimbung, Sulu
CW1: Construction of Concrete Road: 0.90 lane km
Unit Cost: ₱ 11,000,000.00 /lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
300222100126000 |
May 24, 2023 |
Bangsamoro Autonomous Region in Muslim Mindanao |
Sulu 1st District Engineering Office |
UACS No. 300215102735000
Project ID: P00735016MN
Convergence and Special Support Program (CSSP): Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Roads connecting to Indigenous People (IP) Communities
Construction of Road, Sitio Lakahan - Sitio Pitak, Barangay Matatal, Maimbung, Sulu
CW1: Construction of Concrete Road: 0.88 lane km
Unit Cost: ₱ 11,250,000.00 /lane km
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00 |
March 2, 2024 |
FY 2023 |
|
310202101481000 |
April 12, 2023 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310202101481000
Project ID: P00705451MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Liloy-Siocon Rd - K2005 + 944 - K2006 + 380, K2006 + 655 - K2007 + 307
CW1 - Road Widening: 2.186 Lane km
Unit Cost: ₱ 15,690,759.38/ Lane km
EAO: ₱ 700,000.00
Allocation: ₱ 35,000,000.00 |
March 2, 2024 |
FY 2023 |
|
310109101366000 |
March 27, 2023 |
Region IX |
Zamboanga del Sur 2nd District Engineering Office |
UACS No. 310109101366000
Project ID: P00706379MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Jct Dumalinao-Margosatubig Rd - K1682 + 990 - K1683 + 035, K1701 + 850 - K1701 + 905, K1701 + 911 - K1701 + 941, K1716 + 320 - K1716 + 335
CW1- Construction of Road Slope Protection Structure/ 1,350.00 sq. m.
Unit Cost: ₱ 9,800.00/ sq. m.
EAO: ₱ 270,000.00
Allocation: ₱13,500,000.00 |
March 2, 2024 |
FY 2023 |
|
310109101363000 |
March 27, 2023 |
Region IX |
Zamboanga del Sur 2nd District Engineering Office |
UACS No. 310109101363000
Project ID: P00706397MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Sindangan-Bayog-Lakewood Rd - K1744 + 110 - K1744 + 130, K1746 + 930 - K1746 + 983,
CW1- Construction of Road Slope Protection Structure: 3,000.00 sq. m.
Unit Cost: ₱ 9,800.00/ sq. m.
EAO: ₱ 600,000.00
Allocation: ₱ 30,000,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E02637 |
310201101101000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310201101101000
Project ID: P00705438MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1627 + 200 - K1629 + 320
CW1 - Road Widening: 4.24 Lane km
Unit Cost: ₱ 18,884,433.96/ Lane km
ROW Acquisition 21,200 sq.m.
Unit Cost: ₱ 92.217/sq.m.
EAO: ₱ 2,975,000.00
Allocation: ₱ 85,000,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E02640 |
310201101212000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310201101212000
Project ID: P00705461MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1651 + 724 - K1652 + 047, K1656 + 460 - K1657 + 007
CW1 - Road Widening: 1.742 Lane km
Unit Cost: ₱ 10,947,967.85/ Lane km
ROW Acquisition 8,710 sq.m.
Unit Cost: ₱ 45.617/sq.m.
EAO: ₱ 397,320.00
Allocation: ₱ 19,866,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E03024 |
310203100737000 |
May 29, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310203100737000
Project ID: P00705944MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Jct Switch-Jct Monte Alegre Rd - K1642 + (-135) - K1642 + 351
CW1 - Road Widening: 0.972 Lane km
Unit Cost: ₱ 19,855,967.08/ Lane km
ROW Acquisition 4,860.00 sq.m.
Unit Cost: ₱ 61.728/sq.m.
EAO: ₱ 400,000.00
Allocation: ₱ 20,000,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E02638 |
310203100649000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310203100649000
Project ID: P00705943MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Jct Aurora-Monte Alegre-Jct Labangan Rd - K1653 + 466 - K1655 + 187
CW1 - Road Widening: 3.442 Lane km
Unit Cost: ₱ 12,689,581.29/ Lane km
CW2 - Construction of Slope Protection Structure: 2,985.50 sq.m
Unit Cost: ₱ 9,235.443/ sq.m
ROW Acquisition 11,530.00 sq.m.
Unit Cost: ₱ 97.57/sq.m.
EAO: ₱ 2,625,000.00
Allocation: ₱ 75,000,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E02661 |
310203100738000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310203100738000
Project ID: P00705945MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Jct Switch-Jct Monte Alegre Rd - K1647 + 000 - K1647 + 500
CW1 - Road Widening: 1.00 Lane km
Unit Cost: ₱ 21,181,720.00/ Lane km
EAO: ₱ 432,280.00
Allocation: ₱ 21,614,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E03003 |
310104100596000 |
May 29, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310104100596000
Project ID: P00706239MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1649 + 220 - K1651 + 007
CW1 - Reconstruction to Concrete Pavement: 3.78 Lane Km
Unit Cost: ₱ 12,962,962.96
EAO: ₱ 1,000,000.00
Allocation: ₱ 50,000,000.00
|
March 2, 2024 |
FY 2023 |
|
310104100598000 |
April 12, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310104100598000
Project ID: P00706240MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Jct Aurora-Ozamis City Rd - K1651 + 385 - K1652 + 569
CW1 - Reconstruction to Concrete Pavement: 2.368 Lane Km
Unit Cost: ₱ 11,057,280.41/Lane Km
EAO: ₱ 534,360.00
Allocation: ₱ 26,718,000.00 |
March 2, 2024 |
FY 2023 |
|
310105100968000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310105100968000
Project ID: P00706241MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Sindangan-Siayan-Dumingag-Mahayag Rd (Mahayag-Dumingag Sect) - K1661 + (-699) - K1661 + (-516.46), K1661 + (-043) - K1661 + 300, K1670 + 521 - K1670 + 763.37, K1670 + 898 - K1671 + 823.80
CW1 - Rehabilitation of Paved Road: 3.3838 Lane km
Unit Cost: ₱ 13,032,685.15/ Lane km
EAO: ₱ 900,000.00
Allocation: ₱ 45,000,000.00 |
March 2, 2024 |
FY 2023 |
WIN3E02664 |
310106101000000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310106101000000
Project ID: P00706244MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
Eastern Bobongan-Sominot-Midsalip-Dumingag Rd - Chainage 1115 - Chainage 1690.40, Chainage 510 - Chainage 1115
CW1 - Rehabilitation of Paved Road: 2.361 Lane km
Unit Cost: ₱ 15,067,344.35
EAO: ₱ 726,000.00
Allocation: ₱ 36,300,000.00
|
March 2, 2024 |
FY 2023 |
|
310107100566000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310107100566000
Project ID: P00706392MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Tucuran Jct-Karomatan Jct Rd - K1652 + 940 - K1653 + 050
CW1 - Construction of Road Slope Protection Structure: 819.82 sq.m.
Unit Cost: ₱ 4,781.537
EAO: ₱ 80,000.00
Allocation: ₱ 4,000,000.00 |
March 2, 2024 |
FY 2023 |
|
310107100567000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310107100567000
Project ID: P00706393MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Tucuran Jct-Karomatan Jct Rd - K1652 + 920.84 - K1653 + 147.80
CW1 - Construction of Road Slope Protection Structure: 757.722 sq.m.
Unit Cost: ₱ 6,466.75
EAO: ₱ 100,000.00
Allocation: ₱ 5,000,000.00
|
March 2, 2024 |
FY 2023 |
|
310107100568000 |
March 13, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 310107100568000
Project ID: P00706394MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Jct Blancia-Molave-Josefina Rd - K1684 + (-050) - K1684 + (-020), K1684 + (-210) - K1684 + (-120), K1686 + 160 - K1686 + 308
CW1 - Construction of Road Slope Protection Structure: 3,816.62 sq.m.
Unit Cost: ₱ 5,135.434
EAO: ₱ 400,000.00
Allocation: ₱ 20,000,000.00
|
March 2, 2024 |
FY 2023 |
|
310108101635000 |
June 26, 2023 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No.310108101635000
Project ID: P00706395MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Sindangan-Siayan-Dumingag-Mahayag Rd (Mahayag-Dumingag Sect) - K1680 + 780 - K1680 + 940
CW1 - Construction of Road Slope Protection Structure: 1,254.10 sq.m.
Unit Cost: ₱ 3,485.889/sq.m.
CW2 - Off Carriageway Improvement: Shoulder Paving/Construction: 924.00 sq.m.
Unit Cost: ₱ 1,102.105/sq.m.
EAO: ₱ 110,000.00
Allocation: ₱ 5,500,000.00 |
March 2, 2024 |
2023 |
WIN3E03209 |
SR2023-03-006981 |
March 15, 2023 |
Cordillera Administrative Region |
Abra District Engineering Office |
"From:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0416 + 400 - K0426 + 500;
Type of Work: Road Safety: Pavement markings;
Physical Target: 15.951 Lane Km;
Allocation: Php 100,000,000.000"
"To:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0416 + 938 - K0426 + 392;
Type of Work:
CW1: Road Safety: Guardrails
CW2: Road Safety: Roadway Lighting;
Physical Target:
CW1: 501 meters
CW2: 212 units ;
Allocation: Php 100,000,000.000"
|
March 2, 2024 |
2023 |
WIN3E03220 |
SR2023-03-006983 |
March 15, 2023 |
Cordillera Administrative Region |
Abra District Engineering Office |
"From:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0427 + 000 - K0431 + 100;
Type of Work: Road Safety: Pavement markings;
Physical Target: 15.951 Lane Km;
Allocation: Php 100,000,000.000"
"To:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0427 + 023 - K0430 + 967;
Type of Work:
CW1: Road Safety: Guardrails
CW2: Road Safety: Roadway Lighting;
Physical Target:
CW1: 656 meters
CW2: 165 units ;
Allocation: Php 100,000,000.000"
|
March 2, 2024 |
2023 |
WIN3E03222 |
SR2023-03-006985 |
March 15, 2023 |
Cordillera Administrative Region |
Abra District Engineering Office |
"From:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0431 + 100 - K0432 + 000;
Type of Work: Road Safety: Pavement markings;
Physical Target: 15.951 Lane Km;
Allocation: Php 100,000,000.000"
"To:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0431 + 104 - K0432 + 050;
Type of Work:
CW1: Preventive Maintenance of Road: Concrete Reblocking
CW2: Road Safety: Guardrails
CW3: Road Safety: Roadway Lighting;
Physical Target:
CW1: 1372.5 Lane Km
CW2: 734 meters
CW3: 60 units ;
Allocation: Php 100,000,000.000"
|
March 2, 2024 |
2023 |
WIN3E03219 |
SR2023-03-006986 |
March 15, 2023 |
Cordillera Administrative Region |
Abra District Engineering Office |
"From:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0432 + 000 - K0433 + 650;
Type of Work: Road Safety: Pavement markings;
Physical Target: 15.951 Lane Km;
Allocation: Php 100,000,000.000"
"To:
Installation of Road Safety Devices Along Abra-Ilocos Norte Rd - K0432 + 058 - K0433 + 460;
Type of Work:
CW1: Preventive Maintenance of Road: Concrete Reblocking
CW2: Road Safety: Guardrails
CW3: Road Safety: Roadway Lighting;
Physical Target:
CW1: 1417.5 Lane Km
CW2: 734 meters
CW3: 60 units ;
Allocation: Php 100,000,000.000"
|
March 2, 2024 |
2023 |
WIN3E03221 |
SR2023-03-006990 |
March 15, 2023 |
Cordillera Administrative Region |
Abra District Engineering Office |
"From:
Installation of Road Safety Devices Along Abra-Kalinga Rd - K0432 + 600 - K0450 + 000;
Type of Work: Road Safety: Pavement markings;
Physical Target: 15.951 Lane Km;
Allocation: Php 100,000,000.000"
"To:
Installation of Road Safety Devices Along Abra-Kalinga Rd - K0441 + 001.80 - K0449 + 943;
Type of Work:
CW1: Road Safety: Guardrails
CW2: Road Safety: Roadway Lighting;
Physical Target:
CW1: 734 meters
CW2: 134 units ;
Allocation: Php 100,000,000.000"
|
February 28, 2024 |
FY 2023 |
WIN3E02985 |
300214100453000 |
May 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100453000
Project ID: P00733756MN
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solar LED Street Light along National Road and Bridge with the following Section (Buenavista - Bolong By-pass Road) Sta. 1885+000 - Sta. 1895+000
CW1- Road Safety: Street Lighting: 1,365 No. of Units
Unit Cost: ₱ 98,974.36/ No. of Units
EAO: ₱ 4,900,000.00
Allocation: ₱ 140,000,000.00
|
February 28, 2024 |
FY 2023 |
WIN3E028993 |
300214100454000 |
May 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100454000
Project ID: P00733757MN
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solarization along National Road and Bridge with the following Section (Cabaluay-Mampang Zamboanga City Diversion Road) Sta. 10+245.27 to Sta. 13+732.95
CW1- Road Safety: Street Lighting: 464 No. of Units
Unit Cost: ₱ 103,987.07
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
February 28, 2024 |
FY 2023 |
WIN3E02986 |
300214100456000 |
May 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100456000
Project ID: P00733759MN
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solarization along National Road and Bridge with the following Section (Cabaluay-Mampang Zamboanga City Diversion Road) Sta. 13+732.95 to Sta. 17+220.64
CW1- Road Safety: Street Lighting: 464 No. of Units
Unit Cost: 103,987.07/ No. of Units
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00
|
February 28, 2024 |
FY 2023 |
WIN3E03051 |
300219101755000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 300219101755000
Project ID: P00733978MN
Convergence and Special Support Program (CSSP)– Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Flood Control Structure along Layawan River, De Venta Perla Bridge (Upstream) Sergio Osmeña, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 217.0 ln.m
Unit Cost: ₱ 316,849.07/ln.m
EAO: ₱ 2,493,750.00
Allocation: ₱ 71,250,000.00 |
February 28, 2024 |
FY 2023 |
WIN3E03035 |
300215102731000 |
May 8, 2023 |
Region IX |
Regional Office IX |
UACS No. 300215102731000
Project ID: P00733799MN
Convergence and Special Support Program (CSSP)– Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities
Construction of Bunguiao-Tolosa-Lapakan Bypass Road, Zamboanga City
CW1- Construction of Gravel Road: 6.08 Lane km
Unit Cost: ₱ 23,807,565.79 Lane km
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
February 28, 2024 |
2023 |
|
300215102734000 |
May 8, 2023 |
Region IX |
Regional Office IX |
UACS NO. 300215102734000
Project ID: P00733802MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Muti - Buenavista Bypass Road Package 1, Zamboanga City
CW1: Construction of Concrete Road: 18.68 Lane Km
Unit Cost: ₱ 7,748,929.34/Lane Km
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00
|
February 28, 2024 |
2023 |
WIN3E02968 |
300215102733000 |
May 8, 2023 |
Region IX |
Regional Office IX |
UACS NO. 300215102733000
Project ID: P00733801MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Mangusu - Muti Coastal Road Package 1, Zamboanga City
CW1: Construction of Concrete Road: 8.08 Lane Km
Unit Cost: ₱ 17,914,603.96/ Lane Km
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00
|
February 28, 2024 |
2023 |
WIN3E03060 |
300215102732000 |
May 8, 2024 |
Region IX |
Regional Office IX |
UACS NO. 300215102732000
Project ID: P00733800MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Bunguiao - Quiniput Road, Zamboanga City
CW1: Construction of Concrete Road: 6.59 Lane Km
Unit Cost: ₱ 21,965,098.63/ Lane Km
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00
|
February 28, 2024 |
2023 |
WIN3E03000 |
300219101756000 |
May 17, 2023 |
Region IX |
Regional Office IX |
UACS NO. 300219101756000
Project ID: P00733979MN
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Flood Control Structure (Revetment/Bank Protection) along Salug Daku River, Salug Daku Bridge, Sergio Osmeña, Zamboanga del Norte
CW1: Construction of Flood Mitigation Structure: 560.0 ln.m
Unit Cost: ₱ 172,321.42/ ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱ 100,000,000.00
|
February 27, 2024 |
FY 2023 |
|
310104100492000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100492000
Project ID: P00706252MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1758 + 650 - K1759 + 231, K1759 + 261 - K1760 + 075, K1760 + 153 - K1760 + 776, K1764 + 330 - K1764 + 849, K1767 + 000 - K1768 + 000, K1769 + 000.00 – K1770 + 000.00, K1771 + 576.00 – K1771 + 759.00
CW1- Reconstruction to Concrete Pavement 9.44 lane-km
Unit Cost: ₱10,733,580.51 /lane-km
EAO: ₱ 3,675,000.00
Allocation: ₱ 105,000,000.00
|
February 27, 2024 |
FY 2023 |
|
310305101843000 |
April 25, 2023 |
Region IX |
Regional Office IX |
UACS No. 310305101843000
Project ID: P00706632MN
OO1: Ensure Safe and Reliable National Road System – Bridge - Widening of Permanent Bridges
Talinga Br. (B00458MN) along Dipolog-Sindangan-Liloy Rd (Phase I)
CW1- Widening of Bridge: 2,312.50 Square Meters
Unit Cost: ₱ 62,594.59/Square Meters
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
February 27, 2024 |
FY 2023 |
|
310306100249000 |
May 31, 2023 |
Region IX |
Regional Office IX |
UACS No. 310306100249000
Project ID: P00706633MN
OO1: Ensure Safe and Reliable National Road System – Bridge - Construction of New Bridges
Liba Br. along Sindangan-Bayog-Lakewood Road (Phase II)
CW1- Construction of Bridge: 867.186 Square Meters
Unit Cost: ₱ 114,695.31 /Square Meters
CW2- Construction of Road Slope Protection Structure: 1,510.62 Square Meters
Unit Cost: ₱ 29,979.63 /Square Meters
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00
|
February 27, 2024 |
FY 2023 |
WIN3E03169 |
310204102140000 |
July 31, 2023 |
Region IX |
Regional Office IX |
UACS No. 310204102140000
Project ID: P00706812MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of Bypass and Diversion Roads
Buenavista - Bolong By-Pass Road, Package 8, Zamboanga City
CW1- Construction of Gravel Road: 1.09 Lane Km
Unit Cost: ₱ 134,083,512.14/Lane Km
ROW Acquisition 4,666.667 sq.m.
Unit Cost: ₱ 1,500.00/sq.m.
EAO: ₱ 5,300,814.50
Excess: ₱ 548,157.27
Allocation: ₱ 159,000,000.00
|
February 27, 2024 |
2023 |
WIN3F07367 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0788 + 000 - K0792 + 000
Physical Target: Allocation:
CW1-Rehabilitation of Paved Road P 107.333090 M
: 11.861 Lane Km
EAO P 3.892910M
Total P 111.226 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0789+000 - K0789+083, K0789+310 - K0789+467, K0789+817 - K0789+841, K0789+916 - K0790+184, K0790+401- K0790+475, K0790+535 - K0790+556, K0790+614 - K0790+820, K0791+74 - K0791+192, K0791+390 - K0791+451, K0791+629 - K0791+649, K0792+286 - K0792+312, K0792+821 - K0792+857, K0792+943 - K0792+985, K0831+277 - K0831+409, K0831+481 - K0831+503, K0831+610 - K0831+954, K0834+107 - K0834+170, K0834+299 - K0834+450, K0834+571 - K0834+775, K0834+838 – K0834+862, K0835+42 – K0835+057, K0835+216 – K0835+254, K0835+508 – K0835+552, K0835+844 – K0835+883, K0835+960 – K0836+018, K0836+123 – K0836+274, K0836+313 – K0836+372, K0836+467 – K0836+470, K0836+557 – K0836+950, K0837+083 - K0837+098, K0837+191 - K0837+410, K0837+500 - K0837+580, K0837+642 - K0837+686, K0837+893 - K0838+000, K0848+000 - K0848+874, K0848+968 - K0849+474
Physical Target: Allocation:
CW1-Rehabilitation of Paved Road P 107.333090 M
: 9.776 Lane Km
EAO P 3.892910M
Total P 111.226 M
|
February 27, 2024 |
FY 2023 |
|
310204102142000 |
March 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 310204102142000
Project ID: P00706814MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of Bypass and Diversion Roads
Buenavista - Bolong By-Pass Road, Package 10, Zamboanga City
CW1- Construction of Concrete Road/ 6.72 Lane-km
Unit Cost: ₱ 20,913,690.48 /Lane-km
ROW Acquisition 57,000.00 sq.m.
Unit Cost: ₱ 175.44/sq.m.
EAO: ₱ 5,460,000.00
Allocation: ₱ 156,000,000.00 |
February 27, 2024 |
FY 2023 |
|
310204102143000 |
March 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 310204102143000
Project ID: P00706815MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of Bypass and Diversion Roads
Buenavista - Bolong By-Pass Road, Package 11, Zamboanga City
CW1- Construction of Concrete Road: 7.02 lane-km
Unit Cost: ₱ 19,195,156.70 /Lane-km
ROW Acquisition 50,020.00 sq.m
Unit Cost: ₱ 199.92/sq.m.
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00
|
February 27, 2024 |
2023 |
WIN3F07740 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
AS PER GAA/ORIGINAL:
Wright - Taft - Borongan Road (S00123SM) K0828+(-581) - K0859 + 931
Physical Target: Allocation:
CW1-Road Widening: 65.114 Lane Km P 193.00 M
EAO P 7.00 M
Total P 200.00 M
AS MODIFIED:
Wright - Taft - Borongan Road (S00123SM) K0828+(-409) - K0830 + 861
Physical Target: Allocation:
CW1-Road Widening: 7.1 Lane Km P 193.00 M
EAO P 7.00 M
Total P 200.00 M
|
February 27, 2024 |
2023 |
WIN3F07741 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
AS PER GAA/ORIGINAL:
Basey - Marabut - Pinamitinan Rd. (S00124SM) k0909 + (-1024) - k0951 + 169
Physical Target: Allocation:
CW1-Road Widening: 88.890 Lane Km P 241.250 M
EAO P 8.750 M
Total P 250.00 M
AS MODIFIED:
Basey - Marabut - Pinamitinan Rd. (S00124SM) –K0914+000-K0915+000,K0936+000-K0937+000,K0939+000-K0940+000,K0940+000-K0941+000,K0946+000-K0947+000,K0947+000-K0948+000,K0948+000-K0948+875
Physical Target: Allocation:
CW1-Road Widening: 9.652 Lane Km P 241.250 M
EAO P 8.750 M
Total P 250.00 M
|
February 27, 2024 |
2023 |
WIN3F07477 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Calbiga Flood Control along Calbiga River, Calbiga Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure: 819.530 Lineal meters
EAO P 4.025 M
Total P 115.00 M
AS MODIFIED:
Construction of Calbiga Flood Control along Calbiga River, Calbiga Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure: 383 Lineal meters
EAO P 4.025 M
Total P 115.00 M
|
February 27, 2024 |
FY 2023 |
|
310104100494000 |
April 25, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100494000
Project ID: P00706835MN
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Dipolog-Sindangan-Liloy Rd - K1880 + 375 - K1881 + 375, K1881 + 540.00 – K1883 + 000.00
CW1- Reconstruction to Concrete Pavement: 4.920 Lane Km
Unit Cost: ₱ 9,806,910.57/Lane Km
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
February 27, 2024 |
2023 |
WIN3F07557 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure, Golden Bridge San Juanico-Basey-Sohoton Road, Basey, Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure:819.530 Lineal meters
EAO P 4.025 M
Total P 115.00 M
AS MODIFIED:
Construction of Flood Control Structure, Golden Bridge San Juanico-Basey-Sohoton Road, Basey, Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure:220 Lineal meters
EAO P 4.025 M
Total P 115.00 M
|
February 27, 2024 |
FY 2023 |
|
310104100496000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100496000
Project ID: P00706837MN
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Pagadian City-Zamboanga City Rd - K1880 + 000 - K1881 + 000, K1883 + 000 - K1883 + 322
CW1- Reconstruction to Concrete Pavement: 2.64 Lane-km
Unit Cost: ₱ 12,334,454.55 /Lane-km
EAO: ₱ 1,181,040.00
Allocation: ₱ 33,744,000.00 |
February 27, 2024 |
2023 |
WIN3F07492 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure, Silaga River, along Daang Maharlika, Silaga Bridge, Barangay Tulay, Sta. Rita, Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure: 819.530 Lineal meters
EAO P 4.025 M
Total P 115.00 M
AS MODIFIED:
Construction of Flood Control Structure, Silaga River, along Daang Maharlika, Silaga Bridge, Barangay Tulay, Sta. Rita, Samar
Physical Target: Allocation:
CW1-Construction of Flood Mitigation P 110.975 M
Structure: 250 Lineal meters
EAO P 4.025 M
Total P 115.00 M
|
February 27, 2024 |
2023 |
WIN3F07718 |
GAA FY 2023 |
January 2, 2023 |
Region VIII |
Samar 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Catbalogan Drainage System (Antiao Creek and Outfalls), Catbalogan City, Samar
Physical Target: Allocation:
CW1-Construction of Drainage P 101.325 M
Structure: 7,953.979 Lineal meters
EAO P 3.675 M
Total P 105.00 M
AS MODIFIED:
Construction of Catbalogan Drainage System (Antiao Creek and Outfalls), Catbalogan City, Samar
Physical Target: Allocation:
CW1-Construction of Drainage P 101.325 M
Structure: 1,531.71 Lineal meters
EAO P 3.675 M
Total P 105.00 M
|
February 27, 2024 |
FY 2023 |
WIN3E02896 |
310204102116000 |
April 25, 2023 |
Region IX |
Regional Office IX |
UACS No. 310204102116000
Project ID: P00707613MN
OO1: Ensure Safe and Reliable National Road System – Network Development - Construction of Bypass and Diversion Roads
By-Pass and Diversion Roads - Cawit to Baluno (Sta. 0+000 to Sta. 0+311.23, Sta. 0+326.41 – Sta. 1+340.00), Zamboanga
CW1- Construction of Concrete Road: 2.65 Lane-km
Unit Cost: ₱ 36,415,094.34/lane-km
EAO: ₱ 3,500,000.00
Allocation: ₱100,000,000.00
|
February 27, 2024 |
FY 2023 |
|
310104100495000 |
April 25, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100495000
Project ID: P00707780MN
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Pagadian City-Zamboanga City Rd – K1889 + 075.00 – K1889 + 275.00, K1898 + 101.70 – K1901 + 319.020, K1908 + 169.30 – K1908 + 566.30, K1910 + 892.00 – K1912 + 435.90, K1913 + 471.00 – K1913 + 779.00
CW1- Reconstruction to Concrete Pavement: 4.702 lane-km
Unit Cost: ₱ 10,245,993.19 /lane-km
EAO: ₱ 1,747,340.00
Allocation: ₱ 49,924,000.00
|
February 27, 2024 |
FY 2023 |
|
310104100497000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100497000
Project ID: P00707781MN
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Pagadian City-Zamboanga City Rd - K1883 + 322 - K1885 + 000, K1886 + 000 - K1887 + 277, K1888 + 570 - K1889 + 017
CW1- Reconstruction to Concrete Pavement: 6.80 lane-km
Unit Cost: ₱ 12,076,265.44 /lane-km
EAO: ₱ 2,978,395.00
Allocation: ₱ 85,097,000.00
|
February 27, 2024 |
FY 2023 |
|
310104100498000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 310104100498000
Project ID: P00707782MN
OO1: Ensure Safe and Reliable National Road System –
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads
Pagadian City-Zamboanga City Rd – K1895 + 898.70 – K1896 + 175.60, K1902 + 605.60 – K1906 + 044.90, K1909 + 384.20 – K1909 + 947.30, K1913 + 138.00 – K1913 + 471.00
CW1- Rehabilitation of Paved Road: 4.162 lane-km
Unit Cost: ₱ 10,128,326.53 /lane-km
EAO: ₱ 1,528,905.00
Allocation: ₱ 43,683,000.00
|
February 27, 2024 |
FY 2023 |
WIN3E02705 |
320101110237000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101110237000
Project ID: P00721221MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Bogayo River, Kumalarang Br. 1 Section(B00549MN) (Downstream - Rightside) along Pagadian City - Zamboanga City Road(S01453MN), Barangay Bogayo, Kumalarang, Zamboanga del Sur
CW1- Construction of Flood Mitigation Structure; 481.00 ineal Meters
Unit Cost: ₱ 220,686.07/Lineal Meters
EAO: ₱ 3,850,000.00
Allocation: ₱110,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02829 |
320101109326000 |
March 31, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109326000
Project ID: P00721229MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Upper Tungawan Flood Control Structure along Tungawan River (Phase V) Tungawan, Zamboanga Sibugay
CW1- Construction of Flood Mitigation Structure: 613.00 lineal Meters
Unit Cost: ₱ 173,164.763/Lineal Meters
EAO: ₱ 3,850,000.00
Allocation: ₱110,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02867 |
320102105920000 |
April 17, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105920000
Project ID: P00721402MN
OO2: Protect Lives and Properties Against Major Floods -
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control at Sibuguey River along Imelda - Bayog - Kumalarang - Lapuyan- Margosatubig Road, Barangay Paradise, Diplahan, Zamboanga Sibugay Package 2
CW1- Construction of Flood Mitigation Structure: 84.60 Lineal Meters
Unit Cost: ₱ 570,330.97 /Lineal Meters
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02866 |
320102105921000 |
April 17, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105921000
Project ID: P00721403MN
OO2: Protect Lives and Properties Against Major Floods -
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control at Sibuguey River along Imelda - Bayog - Kumalarang - Lapuyan- Margosatubig Road, Barangay Paradise, Diplahan, Zamboanga Sibugay Package 3
CW1- Construction of Flood Mitigation Structure: 81.80 Lineal Meters
Unit Cost: ₱ 589,853.30 /Lineal Meters
EAO: ₱ 1,750,000.00
Allocation: ₱ 50,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03050 |
320102105555000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105555000
Project ID: P00721404MN
OO2: Protect Lives and Properties Against Major Floods – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (revetment Wall) along Sibuguey River, Barangay Santa Barbara, Imelda, Zamboanga Sibugay
CW1- Construction of Revetment: 331.0 ln.m
Unit Cost: ₱ 291,540.78/ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱100,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03013 |
320101109312000 |
March 31, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109312000
Project ID: P00721521MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure Tumaga River ( Tetuan-Tugbungan Section ), Package
1, Zamboanga City
CW1- Construction of Flood Mitigation Structure: 433.0 lineal Meters
Unit Cost: ₱ 185,590.92/Lineal Meters
CW2- Construction of Flood Mitigation Structure: 433.0 lineal Meters
Unit Cost: ₱ 148,704.69/Lineal Meters
EAO: ₱ 5,250,000.00
Allocation: ₱150,000,000.00 |
February 27, 2024 |
FY 2023 |
|
320101109313000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109313000
Project ID: P00721522MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure, Ilaya Bridge, Abutment B, Downstream Section, Dapitan City, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 361.00 ln.m
Unit Cost: ₱ 267,313.02/ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱100,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02956 |
320101109314000 |
April 24, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109314000
Project ID: P00721523MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Conctrol Structure along Kabasalan River (Downstream), Barangay Banker, Kabasalan, Zamboanga Sibugay
CW1- Construction of Flood Mitigation Structure: 463.0ln.m
Unit Cost: ₱ 147,410.94/ln.m
CW2- Construction of Flood Mitigation Structure: 463.0ln.m
Unit Cost: ₱ 102,697.05/ln.m
EAO: ₱ 4,200,000.00
Allocation: ₱120,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03014 |
320101109315000 |
April 24, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109315000
Project ID: P00721524MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Kabasalan River (Upstream), Barangay Banker, Kabasalan, Zamboanga Sibugay
CW1- Construction of Flood Mitigation Structure: 533.00 ln.m
Unit Cost: ₱ 114,761.32/ln.m
CW2- Construction of Flood Mitigation Structure: 533.00 ln.m
Unit Cost: ₱ 102,499.46/ln.m
EAO: ₱ 4,200,000.00
Allocation: ₱120,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02839 |
320101109327000 |
April 3, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109327000
Project ID: P00721527MN
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Bacalan Br. Section (B00497MN), Lanao-Pagadian-Zamboanga City Rd (S01113MN), Ipil, Zamboanga Sibugay
CW1- Construction of Flood Mitigation Structure: 336.85 ln.m
Unit Cost: ₱ 300,801.54/ln.m
EAO: ₱ 3,675,000.00
Allocation: ₱105,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02766 |
320101109334000 |
March 9, 2023 |
Region IX |
Regional Office IX |
UACS No. 320101109334000
Project ID: P00721528MN
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Tictapul River, Barangay Tictapul, ZamboangaCity
CW1- Construction of Flood Mitigation Structure: 346.0 ln. m
Unit Cost: ₱ 376,517.34/ln. m.
EAO: ₱ 4,725,000.00
Allocation: ₱ 135,000,000.00
|
February 27, 2024 |
FY 2023 |
WIN3E03048 |
320102105557000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105557000
Project ID: P00721631MN
OO2: Protect Lives and Properties Against Major Floods – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure along Dipolog River, (Conacon-Guinles Section), Polanco, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 192.37 ln.m
Unit Cost: ₱ 351,146.22/ln.m
EAO: ₱ 2,450,000.00
Allocation: ₱ 70,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03078 |
320102105558000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105558000
Project ID: P00721632MN
OO2: Protect Lives and Properties Against Major Floods – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (Revetment) along Dapitan River, Ilaya-Oyan bridge (Bitoon Section) along Dipolog-Oroquieta Road, Dapitan City, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 372.0 ln.m
Unit Cost: ₱ 259,408.60/ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱ 100,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03004 |
320102105559000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105559000
Project ID: P00721633MN
OO2: Protect Lives and Properties Against Major Floods – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (Revetment) along Dapitan River, Barcelona-Leop Section, Dapitan City, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 418.0 ln.m
Unit Cost: ₱ 230,861.24/ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱ 100,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03052 |
320102105560000 |
May 15, 2023 |
Region IX |
Regional Office IX |
UACS No. 320102105560000
Project ID: P00721634MN
OO2: Protect Lives and Properties Against Major Floods – Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (Revetment/Bank Protection) along Dipolog River, (Sianib Section), Polanco, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure: 313.0 ln.m
Unit Cost: ₱ 308,306.71/ln.m
EAO: ₱ 3,500,000.00
Allocation: ₱ 100,000,000.00 |
February 27, 2024 |
FY 2023 |
|
300203102202000 |
April 25, 2023 |
Region IX |
Regional Office IX |
UACS No. 300203102202000
Project ID: P00731848MN
CSSP: Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Declared Tourism Destinations (Tourism Road Infrastructure Program - TRIP)
Brgy. Lukbuton to Brgy. Panigayan leading to White Beach, Malamawi Island, Isabela City, Basilan
CW1- Construction of Concrete Road: 1.46 Lane-km
Unit Cost: ₱ 19,089,154.11/lane-km
EAO: ₱ 1,010,835.00
Allocation: ₱ 28,881,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02984 |
300214100448000 |
May 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100448000
Project ID: P00733751MN
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solar LED Street Light along National Road and Bridge with the following Section (Cabaluay-Mampang Zamboanga City Diversion Road) Sta. 00+245.27 - Sta. 10+245.27
CW1- Road Safety: Street Lighting: 1,359 No. of Units
Unit Cost: ₱ 99,411.33/ No. of Units
EAO: ₱ 4,900,000.00
Allocation: ₱ 140,000,000.00
|
February 27, 2024 |
FY 2023 |
WIN3E03031 |
300214100449000 |
June 14, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100449000
Project ID: P00733752MN
Convergence and Special Support Program (CSSP) - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Road Safety Devices, Pagadian City-Zamboanga City Rd (Licomo-Putik Road) - K1889 + 000 - K1927 + 000, Zamboanga City
CW1- Road Safety: Street Lighting: 950.00 No. of Units
Unit Cost: ₱ 97,969.73 /No. of Units
CW2- Road Safety: Road Signs: 560.0 Number of Signs
Unit Cost: ₱ 12,048.17 /Number of Signs
CW3- Road Safety: Pavement Markings: 111.818 Lane Km
Unit Cost: ₱ 160,125.66/Lane Km
CW4 Road Safety: Guardrails: 7,563.0 Meters
Unit Cost: ₱ 3,573.56/Meters
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03095 |
300214100451000 |
July 18, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100451000
Project ID: P00733754MN
Convergence and Special Support Program (CSSP) - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solar Studs Lights along Pagadian City-Zamboanga City Rd (Licomo-Putik Road) - K1889 + 000 - K1927 + 000, Zamboanga City
CW1- Road Safety: Solar Studs: 12,547.00 No. of Studs
Unit Cost: ₱ 11,536.62 /No. of Studs
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E03114 |
300214100450000 |
July 18, 2023 |
Region IX |
Regional Office IX |
|
February 27, 2024 |
FY 2023 |
WIN3E03114 |
300214100450000 |
July 18, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100450000
Project ID: P00733753MN
Convergence and Special Support Program (CSSP) - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solar Studs Lights along Pagadian City-Zamboanga City Rd (Licomo-Putik Road) - K1851 + 000 - K1889 + 000, Zamboanga City
CW1- Road Safety: Solar Studs: 12,547.00 No. of Studs
Unit Cost: ₱ 11,536.62/No. of Studs
EAO: ₱ 5,250,000.00
Allocation: ₱ 150,000,000.00 |
February 27, 2024 |
FY 2023 |
WIN3E02983 |
300214100452000 |
May 16, 2023 |
Region IX |
Regional Office IX |
UACS No. 300214100452000
Project ID: P00733755MN
Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Installation of Solar LED Street Light along National Road and Bridge with the following Section (Buenavista - Bolong By-pass Road) Sta. 1895+000 - Sta. 1904+499
CW1- Road Safety: Street Lighting: 1,170 No. of Units
Unit Cost: ₱ 98,974.36/ No. of Units
EAO: ₱ 4,200,000.00
Allocation: ₱ 120,000,000.00 |
February 27, 2024 |
2023 |
WIN3E02978 |
GAA 2023 |
January 24, 2023 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From:
Baguio-Bontoc Rd - K0284+000 - K0284+128, K0284+164 - K0284+452, K0284+492 - K0285+565;
Type of Work: Off-Carriageway Improvement: Paving of Shoulders;
Physical Target: 6000.67 Square Meters;
Allocation: Php 30,000,000.000
To:
Baguio-Bontoc Rd - K0296+000 - K0297+500;
Type of Work:
CW1: Off-Carriageway Improvement: Paving of Shoulders
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 2305.50 Square meters
CW2: 2058 Square meters ;
Allocation: Php 30,000,000.000
|
February 27, 2024 |
2023 |
|
GAA 2023 |
January 24, 2023 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Baguio-Bontoc Rd - K0304+000 - K0305+491;
Type of Work: Off-Carriageway Improvement: Paving of Shoulders;
Physical Target: 6008.73 Square Meters;
Allocation: Php 30,000,000.000"
"To:
Baguio-Bontoc Rd - K0298+000 - K0299+600;
Type of Work:
CW1: Off-Carriageway Improvement: Paving of Shoulders
CW2: Construction of Drainage Structures along Road
CW3: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 2,360.50 Square meters
CW2: 1,267 lineal meters
CW3: 1,920.50 Square meters ;
Allocation: Php 30,000,000.000"
|