Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
May 24, 2024 2024 300214100663000 FY 2024 GAA January 3, 2024 Region II Regional Office II
FROM:

Special Road Fund - Motor Vehicle Users Charge (MVUC) As Per R.A. 11239, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0344 + 349 - K0344 + 623, K0348 + 424 - K0348 + 456, K0356 + 831 - K0356 + 994, K0346 + 771 – K0347 + 000, K0347 + 993 – K0348 + 424


TO:

Special Road Fund - Motor Vehicle Users Charge (MVUC) As Per R.A. 11239, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (LZ) - K0344 + (-037.40) – K0345 + 000, K0346 + 278.40 – K0346 + 748, K0356 + 000 – K0356 + 674.50, K0356 + 831 – K0357 + 004.10
May 24, 2024 2024 300214100666000 FY 2024 GAA January 3, 2024 Region II Regional Office II
FROM:

Special Road Fund – Motor Vehicle User's Charge (MVUC) as
per R.A.11239 Rehabilitation/Reconstruction/
Upgrading of Damaged Paved Roads - Daang Maharlika (LZ) – K0423 + 144 – K0423 + 262

TO:

Special Road Fund – Motor Vehicle User's Charge (MVUC) as per
R.A.11239 Rehabilitation/Reconstruction/ Upgrading of
Damaged Paved Roads - Daang Maharlika (LZ) – K0402 + 1144 – K0402 + 1998.70, K0405 + 163 – K0405 + 861, K0413 +
954.60 – K0414 + 990.90, K0423 + 144 – K0423 +
239.30, K0435 + 076 – K0435 + 605, K0436 + 890 –
K0437 + 096.80, K0437 + 390.70 – K0437 +
553.30, K0439 + 579.40 – K0439+700, K0457 +
246.60 – K0457 + 508.50, K0457 + 535.30 – K0457
+ 616.40, K0458 + 167.20 – K0458+ 389, K0459
+ 628 – K0459 + 777.50



May 24, 2024 2024 310204102806000 FY 2024 GAA January 1, 2024 Region II Regional Office II
Network Development – Construction of Bypass and Diversion Roads
Ramon – Cordon – Diadi Bypass Road, Cordon, Isabela
May 24, 2024 2024 310104100640000 FY 2024 GAA January 3, 2024 Region II Regional Office II
FROM:

Asset Preservation Program – Rehabilitation/ Reconstruction / Upgrading of Damaged Paved Roads – Primary Roads - Daang Maharlika (LZ) – K0383 + 003 – K0383 + 668, K0383 + 740 – K0383 + 1629

TO:
Asset Preservation Program – Rehabilitation/ Reconstruction / Upgrading of Damaged Paved Roads – Primary Roads - Daang Maharlika (LZ) – K0383 + 003 – K0383 + 565.4, K0383 + 836.5 – K0383 + 1602.80
May 24, 2024 FY 2024 P00800367MN GAA 2024 January 1, 2024 Region XII Cotabato 2nd District Engineering Office
Contract ID: 24MC0022
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Tertiary Roads
Amount: ₱12,000,000.00
From: Magpet-Nowa-Doroluman-Greenfield Rd –
K1644 + 500 - K1644 + 514
TOW: Construction of Drainage Structure along Road
Physical Target: 14.00 Lineal Meters

To: Magpet-Nowa-Doroluman-Greenfield Rd –
K1643 + 843 - K1643 + 857, K1644 + 500 - K1644 + 514
TOW: Construction of Drainage Structure along Road
Physical Target: 28.00 Lineal Meters
May 24, 2024 FY 2024 P00800496MN GAA 2024 January 1, 2024 Region XII Cotabato 2nd District Engineering Office
Contract ID: 24MC0017
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Amount: ₱50,000,000.00
TOW: Construction of Road Slope Protection Structure
Physical Target: 2,259.38 Square Meters

From: Paco – Roxas - Arakan Valley - Jct Davao - Bukidnon Rd – K1667+450 - K1667+465

To: Paco – Roxas - Arakan Valley - Jct Davao - Bukidnon Rd – K1667+557 - K1667+607
May 24, 2024 FY 2024 P00800494MN SR2024-01-000914 January 26, 2024 Region XII Cotabato 2nd District Engineering Office
Contract ID: 24MC0011
OO1: Ensure Safe and Reliable National Road System – Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Amount: ₱75,000,000.00
From: Paco – Roxas - Arakan Valley - Jct Davao - Bukidnon Rd – K1666+800 - K1666+850
TOW: Construction of Road Slope Protection Structure
Physical Target: 3,499.77 Square Meters

To: Paco – Roxas – Arakan Valley - Jct Davao - Bukidnon Rd – K1666+620 - K1666+766
TOW: Construction of Road Slope Protection Structure
Physical Target: 3,500.00 Square Meters
May 23, 2024 FY 2024 GAA P00803801MN FY 2024 GAA RA 11975 January 15, 2024 Region XI Davao del Norte 2nd District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Babak-Samal-Kaputian Rd - K1515 + 000 - K1518 + 000
Physical Target:
CW1: 5.084 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Babak-Samal-Kaputian Rd - K1515 + 000 - K1518 + 935
Physical Target:
CW1: 7.674 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00
May 23, 2024 FY 2024 GAA P00821196MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao de Oro 2nd District Engineering Office
MODIFICATION:

FROM: OO2: Protect Lives and Properties Against Major Floods - Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Flood Mitigation Structure along Manat River leading to Agusan River, Barangay New Visayas, Montevista, Davao de Oro
Physical Target:
CW1: 631.400 lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Flood Mitigation Structure)
EAO: P 5,250,000.00

TO: OO2: Protect Lives and Properties Against Major Floods - Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Flood Mitigation Structure along Manat River leading to Agusan River, Barangay New Visayas, Montevista, Davao de Oro
Physical Target:
CW1: 865.480 lineal meters (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Flood Mitigation Structure)
EAO: P 5,250,000.00
May 23, 2024 FY 2024 GAA P00832694MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
Callawa Proper-Purok 5, 14, and 15 Road connecting Cassava Processing Area in support of Cassava, Banana and Cacao Industries of Brgy, Callawa, Buhangin District, Davao City, Davao del Sur
Physical Target:
CW1: 1.547 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 34,300,000.00 (Construction of Concrete Road)
EAO: P 700,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
Callawa Proper-Purok 5, 14, and 15 Road connecting Cassava Processing Area in support of Cassava, Banana and Cacao Industries of Brgy, Callawa, Buhangin District, Davao City, Davao del Sur
Physical Target:
CW1: 1,382.74 square meters (Construction of Road Slope Protection Structure)
CW2: 0.392 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 35,000,000.00
CW1: P 25,480,000.00 (Construction of Road Slope Protection Structure)
CW1: P 8,820,000.00 (Construction of Concrete Road)
EAO: P 700,000.00
May 23, 2024 FY 2024 GAA WIN4E03355 FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao Oriental 2nd District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Dahican-Lawigan Rd - K1721 + 418 - K1723 + 820
Physical Target:
CW1: 4.804 lane km (Road Widening)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Road Widening)
EAO: P 800,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Dahican-Lawigan Rd - K1721 + 372 - K1723 + 190
Physical Target:
CW1: 3.636 lane km (Road Widening)
Allocation:
TOTAL: P 40,000,000.00
CW1: P 39,200,000.00 (Road Widening)
EAO: P 800,000.00
May 23, 2024 2024 SR2024-02-008174 February 1, 2024 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0715 + 000 - K0715 + 282, K0723 + 000 - K0723 + 586, K0724 + 579 - K0724 + 650

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement: P 28.900785 M
: 2.442 Lane Km

EAO P 1.048215 M

Total P 29.949 M

AS MODIFIED:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0715 + 000 - K0715 + 282, K0723 + 000 - K0723 + 586, K0724 + 579 - K0724 + 650

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement: P 28.900785 M
: 2.178 Lane Km

EAO P 1.048215 M

Total P 29.949 M
May 22, 2024 2024 WIN4F07948 FY 2024 GAA November 20, 2023 Region III Pampanga 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Secondary Roads

Lubao Bypass Rd - Chainage 5251.36 - Chainage 5879
May 22, 2024 2024 WIN4XY00179 FY 2024 GAA December 20, 2023 Region III Pampanga 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Jose Abad Santos Ave (JASA) - K0090+000 - K0090+299.50
May 22, 2024 2024 WIN4XY00195 SR2024-01-004962 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads -Tertiary Roads

AS PER GAA/ORIGINAL:

Calbayog Diversion Rd - K0737 + 000 - K0738 + 514

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 49.698465 M
Road: 3,028.00 Lineal meters

EAO P 1.802535 M

Total P 51.501 M

AS MODIFIED:

Calbayog Diversion Rd - K0737 + 572 – K0737 + 852, K0737 + 928 – K0738 + 291, K0738 + 295 – K0738 + 323, K0738 + 328 – K0738 + 545, K0738 + 627 – K0738 + 908

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 29.07136213 M
Road: 1,276 Lineal meters

CW2-RoadWidening: 1.322 Lane Km P 20.12710287M

ROW-ROW Acquisition: 241.00 Square meters P 0.500 M

EAO P 1.802535 M

Total P 51.501 M
May 22, 2024 2024 GAA 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Calbayog Diversion Rd - K0727 + 640 - K0727 + 892

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 24.500 M
Asphalt Overlay: 1.008 Lane Km

EAO P 0.500 M

Total P 25.00 M

AS MODIFIED:

Calbayog Diversion Rd - K0727 + 000 - K0727 + 348.15

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 16.96391874 M
Asphalt Overlay: 0.701 Lane Km

CW2-Preventive Maintenance of Road: P 7.53608126 M
Concrete Reblocking : 0.701 Lane Km


EAO P 0.500 M

Total P 25.00 M
May 22, 2024 2024 GAA 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
Convergence and Special Support Program

Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) – Access Roads and/or Bridges from the National Road/s Leading to Major/ Strategic Public Buildings/ Facilities

AS PER GAA/ORIGINAL:

Construction of Road, Barangay San Agustin – Barangay Hinugacan Road, Gandara, Samar

Physical Target: Allocation:

CW1-Construction of Gravel Road P 24.750 M
: 0.65 Lane Km

EAO P 0.250 M

Total P 25.00 M

AS MODIFIED:

Construction of Road, Barangay San Agustin – Barangay Hinugacan Road (Phase 1), Gandara, Samar

Physical Target: Allocation:

CW1-Construction of Concrete Road P 16.89877010 M
: 1.10 Lane Km

CW2-Construction of Drainage Structure P 7.85122990 M
along Road: 1,000.00 Lineal meters

EAO P 0.250 M

Total P 25.00 M
May 22, 2024 FY 2024 P00800166MN GAA 2024 January 1, 2024 Region XII Cotabato 3rd District Engineering Office
Amount: ₱ 49,488,000.00
UACS No. 310202101781000
From: Bukidnon-Cotabato Rd - K1624 + 633 -K1626 + 048
Road Widening : 2.828 Lane Km

To: Bukidnon-Cotabato Rd - K1624 +471 – K1625 + 646
Road Widening : 2.360 Lane Km
May 22, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Agusan del Sur 2nd District Engineering Office
UACS No. : 310105101268000
Project ID: P00801229MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Secondary Roads


FROM:

NRJ Cuevas-Sampaguita Rd - K1387 + 167 - K1388 + 300

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 2.340 Lane Km

Allocation:
TOTAL: P 31,361,000
CW1: P 30,733,780
EAO: P 627,220

Unit Cost:
CW1: P 13,134,094.02/Lane Km

TO:

NRJ Cuevas-Sampaguita Rd - K1387 + 280 - K1388 + 300

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 2.114 Lane Km

Allocation:
TOTAL: P 31,361,000
CW1: P 30,733,780
EAO: P 627,220

Unit Cost:
CW1: P 14,538,211.92/Lane Km

May 22, 2024 2024 WIN4E03333 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Agusan del Sur 2nd District Engineering Office
UACS No. : 300221106983000
Project ID: P00837272MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities


FROM:

Concreting of Purok 10 Agpangon to Purok 11 Barangay Poblacion, La Paz, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 2.641 Lane Km

Allocation:
TOTAL: P 30,000,000
CW1: P 29,700,000
EAO: P 300,000,000

Unit Cost:
CW1: P 11,245,740.25/Lane Km

TO:

Concreting of Purok 10 Agpangon to Purok 11 Barangay Poblacion, La Paz, Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 1.880 Lane Km

Allocation:
TOTAL: P 30,000,000
CW1: P 29,700,000
EAO: P 300,000,000

Unit Cost:
CW1: P 15,797,872.34/Lane Km

May 21, 2024 2024 WIN4F07970 FY 2024 GAA December 20, 2023 Region III Regional Office III
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Manila North Rd - K0026+023 - K0026+573, K0028+210 - K0028+582, K0029+500 - K0029+914, K0034+057 - K0034+160, K0034+273 - K0035+749
May 21, 2024 2024 GAA FY 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Calbayog Diversion Rd - K0733 + 030 - K0733 +286

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 25.186 M
Asphalt Overlay: 1.024 Lane Km

EAO P .514 M

Total P 25.7 M

AS MODIFIED:

Calbayog Diversion Rd - K0733 + 306 - K0736 +665.65

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 17.434 M
Asphalt Overlay: 0.721 Lane Km

CW2- Preventive Maintenance of Road: P 7.752 M
Concrete Re-blocking: 0.721 Lane Km

EAO P .514 M

Total P 25.7 M
May 21, 2024 2024 WIN4XY00180 FY 2024 GAA December 20, 2023 Region III Pampanga 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Secondary Roads

Angeles-Porac-Floridablanca-Dinalupihan Rd - K0110+700 - K0111+000, K0112+000 - K0112+218.85
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0652 + 388 - K0652 + 442;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
648.150 Square meters;
Allocation:
Php 11,200,000"

"To:
Apayao-Ilocos Norte Rd - K0652 + 360 - K0652 + 410;
Type of Work:
CW1: Construction of Slope Protection Structure
CW2: Reconstruction to Concrete Pavement;
Physical Target:
CW1: 740.69 Square meters
CW2: 0.10 Lane Km;
Allocation:
Php 11,200,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0659 + 100 - K0659 + 115;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
310.2 Square meters;
Allocation:
Php 6,450,000"

"To:
Apayao-Ilocos Norte Rd - K0659 + 050 - K0659 + 250;
Type of Work:
CW1: Construction of Slope Protection Structure
CW2: Construction of Drainage Structure along Road;
Physical Target:
CW1: 398.76 Square meters
CW2: 212 Lineal meters;
Allocation:
Php 6,450,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0646 + 620 - K0646 + 640;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
334.4 Square meters;
Allocation:
Php 6,500,000"

"To:
Apayao-Ilocos Norte Rd - K0652 + 280 - K0652 + 360;
Type of Work:
Construction of Slope Protection Structure;
Physical Target:
406.60 Square meters;
Allocation:
Php 6,500,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0647 + 050 - K0647 + 065;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
315.8 Square meters;
Allocation:
Php 6,330,000"

"To:
Apayao-Ilocos Norte Rd - K0647 + 050 - K0647 + 065;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
429.30 Square meters;
Allocation:
Php 6,330,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0655 + 230 - K0655 + 250;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
323 Square meters;
Allocation:
Php 6,340,000"

"To:
Apayao-Ilocos Norte Rd - K0658 + 820 - K0659 + 050;
Type of Work:
CW1: Construction of Slope Protection Structure
CW2: Construction of Drainage Structure along Road;
Physical Target:
CW1: 180 Square meters
CW2: 303.3 Lineal meters;
Allocation:
Php 6,340,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Cong. Andres Acop Cosalan Rd - K0348 + 950 - K0350 + 250, K0353 + 900 - K0354 + 150, K0360 + 350 - K0360 + 500, K0361 + 250 - K0361 + 300, K0362 + 350 - K0362 + 500;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
1878 Lineal meters;
Allocation:
Php 16,262,000"

"To:
Cong. Andres Acop Cosalan Rd - K0348 + 950 - K0350 + 250, K0353 + 900 - K0354 + 150, K0360 + 250 - K0360 + 500, K0361 + 470 - K0361 + 250, K0362 + 350 - K0362 + 500;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
1905 Lineal meters;
Allocation:
Php 16,262,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Cong. Andres Acop Cosalan Rd - K0348 + 510 - K0348 + 535, K0348 + 973 - K0349 + 000;
Type of Work:
CW1: Construction of Road Slope Protection Structure
CW2: Rehabilitation / Major Repair of Road Slope Protection Structure;
Physical Target:
CW1: 336.06 Square meters
CW2: 150 Square meters;
Allocation:
Php 5,350,000"

"To:
Cong. Andres Acop Cosalan Rd - K0348 + 510 - K0348 + 535, K0364+030 - K0364+065;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
439 Square meters;
Allocation:
Php 5,350,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Abatan-Mankayan-Cervantes Rd - K0346 + 620 - K0346 + 722, K0347 + 375 - K0347 + 400;
Type of Work:
CW1: Construction of Road Slope Protection Structure
CW2: Rehabilitation / Major Repair of Road Slope Protection Structure;
Physical Target:
CW1: 408.18 Square meters
CW2: 100 Square meters;
Allocation:
Php 5,590,000"

"To:
Abatan-Mankayan-Cervantes Rd - K0341+940 - K0341+965, K0346 + 620 - K0346 + 722;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
502 Square meters;
Allocation:
Php 5,590,000"
May 20, 2024 2024 WIN4E03314 SR2024-01-003941 January 29, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Flood Mitigation Structure along Agno River, Paneg-an Section, Sta. 4+000 - Sta. 4+702 (B.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1404 Lineal meters;
Allocation:
Php 65,000,000"

"To:
Construction of Flood Mitigation Structure along Agno River, Paneg-an Section, Sta. 3+228 - Sta. 4+402 (BS), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1120 Lineal meters;
Allocation:
Php 65,000,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Ifugao 1st District Engineering Office
"From:
Construction of Flood Control Structure along Ibulao River, Sta. 325+450 - Sta. 325+685 and Sta. 325+080 - Sta. 325+250, Hapid, Lamut, Ifugao;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
405 Lineal meters;
Allocation:
Php 30,000,000"

"To:
Construction of Flood Control Structure along Ibulao River, Sta. 325+444 - Sta. 325+685 and Sta. 332+180 - Sta. 332+350, Hapid, Lamut, Ifugao;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
411 Lineal meters;
Allocation:
Php 30,000,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Ifugao 1st District Engineering Office
"From:
Kiangan-Tinoc-Buguias Rd - (S00634LZ) Chainage 41830 - Chainage 41860, Chainage 43251 - Chainage 43306, Chainage 44835 - Chainage 44887, Chainage 44849 - Chainage 44876, Chainage 45368 - Chainage 45428, Chainage 45438 - Chainage 45478, Chainage 45886 - Chainage 46086, Chainage 47070 - Chainage 47100;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
3052.06 Square meters;
Allocation:
Php 34,000,000"

"To:
Kiangan-Tinoc-Buguias Road, Chainage 27705 - Chainage 27768, Chainage 38876 - Chainage 38921, , Chainage 41830 - Chainage 41860 , Chainage 43251 - Chainage 43306, Chainage 44835 - Chainage 44887, Chainage 45368 - Chainage 45428, Chainage 45438 - Chainage 45478, Chainage 47070 - Chainage 47100;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
2586.05 Square meters;
Allocation:
Php 34,000,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Ifugao 2nd District Engineering Office
"From:
Nueva Vizcaya-Ifugao-Mt Province Rd - K0338 + 296, K0338 + 852, K0340 + 1208, K0340 + 511, K0342 + 338;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
120 Lineal meters;
Allocation:
Php 18,033,000"

"To:
Nueva Vizcaya-Ifugao-Mt Province Rd - K0338 + 296, K0338 + 852, K0340 + 1208, K0340 + 511, K0342 + 338;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
293.00 Lineal meters;
Allocation:
Php 18,033,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Ifugao 2nd District Engineering Office
"From:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0355 + 793 - K0356 + 126, K0365 + 533, K0367 + 498, K0367 + 560, K0367 + 644, K0367 + 874, K0369 + 321, K0370 + 746;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
236 Lineal meters;
Allocation:
Php 26,200,000"

"To:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0355 + 793 - K0356 + 126, K0365 + 533, K0367 + 498, K0367 + 560, K0367 + 644, K0367 + 874, K0369 + 321, K0370 + 746;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
348.55 Lineal meters;
Allocation:
Php 26,200,000"
May 20, 2024 2024 SR2024-01-004333 January 29, 2024 Cordillera Administrative Region Ifugao 2nd District Engineering Office
"From:
Nueva Vizcaya-Ifugao-Mt Province Rd - K0335 + 621, K0336 + 909, K0336 + 979, K0337 + 439, K0337 + 985, K0338 + 167, K0338 + 316, K0338 + 683, K0338 + 760, K0339 + 049, K0339 + 071, K0339 + 383, K0340 + 065, K0340 + 219, K0340 + 347, K0340 + 459, K0340 + 810, K0340 + 861, K0340 + 960, K0340 + 960, K0340 + 1054, K0340 + 1229, K0340 + 1229 - K0341 + 000, K0341 + 008 - K0341 + 396, K0341 + 188, K0341 + 396, K0341 + 525, K0341 + 764, K0342 + 190, K0342 + 316, K0342 + 584, K0342 + 771, K0342 + 771 - K0343 + 062, K0343 + 062, K0343 + 510, K0343 + 706, K0343 + 942, K0344 + 205, K0344 + 431, K0345 + 622, K0358 + 480, K0361 + 410;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
1784 Lineal meters;
Allocation:
Php 62,404,000"

"To:
Nueva Vizcaya-Ifugao-Mt Province Rd - K0335 + 621, K0336 + 909, K0336 + 979, K0337 + 439, K0337 + 985, K0338 + 167, K0338 + 316, K0338 + 683, K0338 + 760, K0339 + 049, K0339 + 071, K0339 + 383, K0340 + 065, K0340 + 219, K0340 + 347, K0340 + 459, K0340 + 810, K0340 + 861, K0340 + 960, K0340 + 1054, K0340 + 1229, K0340 + 1229 - K0341 + 000, K0341 + 008 - K0341 + 396, K0341 + 188, K0341 + 396, K0341 + 525, K0341 + 764, K0342 + 190, K0342 + 316, K0342 + 584, K0342 + 771, K0342 + 771 - K0343 + 062, K0343 + 062, K0343 + 510, K0343 + 706, K0343 + 942, K0344 + 205, K0344 + 431, K0345 + 622, K0358 + 480, K0361 + 410;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
1,847.27 Lineal meters;
Allocation:
Php 62,404,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Mountain Province 2nd District Engineering Office
"From:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0390 + 931 - K0391 + 517, K0463 + 462 - K0463 + 669;
Type of Work:
Reconstruction to Concrete Pavement;
Physical Target:
1.562 Lane Km;
Allocation:
Php 15,699,000"

"To:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0463 + 667 - K0463 + 1152;
Type of Work:
CW1: Reconstruction of Concrete Pavement
CW2: Construction of Road Slope Protection Structures;
Physical Target:
CW1: 0.970 Lane Km
CW2: 898 Square meters;
Allocation:
Php 15,699,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Mountain Province 2nd District Engineering Office
"From:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0390 + 931 - K0391 + 517, K0463 + 462 - K0463 + 669;
Type of Work:
Reconstruction to Concrete Pavement;
Physical Target:
1.562 Lane Km;
Allocation:
Php 15,699,000"

"To:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0463 + 667 - K0463 + 1152;
Type of Work:
CW1: Reconstruction of Concrete Pavement
CW2: Construction of Road Slope Protection Structures;
Physical Target:
CW1: 0.970 Lane Km
CW2: 898 Square meters;
Allocation:
Php 15,699,000"
May 20, 2024 2024 SR2024-01-005167 January 30, 2024 Cordillera Administrative Region Lower Kalinga District Engineering Office
"From:
Nambaran-Isabela Rd;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
9.000 Lane Km;
Allocation:
Php 200,000,000"

"To:
Nambaran-Isabela Rd - K0509+(-903) - K0520+865;
Type of Work:
CW1: Preventive Maintenance of Road: Asphalt Overlay
CW2: Road Widening;
Physical Target:
CW1: 27.953 Lane Km
CW2: 7.798 Lane Km;
Allocation:
Php 200,000,000"
May 20, 2024 2024 GAA 2024 January 31, 2024 Region VIII Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

AS PER GAA/ORIGINAL:

Calbayog-Catarman Rd-K0790 + 735.5 - K0790 + 898

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 39.200 M
Structure: 2,538.250 Square meters

EAO P 0.800 M

Total P 40.00 M

AS MODIFIED:

Calbayog-Catarman Rd-K0786 + (-090) - K0786 + (-010), K0786 + 025 - K0786 + 085

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 39.200 M
Structure: 2,676.80 Square meters

EAO P 0.800 M

Total P 40.00 M
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Kabugao-Pudtol-Luna-Cagayan Bdry Rd - K0650 + 076 - K0650 + 129, K0659 + 540.5 - K0659 + 551, K0664 + 640 - K0664 + 643;
Type of Work:
CW1: Construction of Road Slope Protection Structure
CW2: Construction of Drainage Structure along Road;
Physical Target:
CW1: 613.5 Square meters
CW2: 43 Lineal meters;
Allocation:
Php 12,300,000"

"To:
Kabugao-Pudtol-Luna-Cagayan Bdry Rd - K0650 + 076 - K0650 + 129, K0659 + 509 - K0659 + 563.5, K0664 + 640 - K0664 + 643;
Type of Work:
CW1: Construction of Road Slope Protection Structure
CW2: Construction of Drainage Structure along Road;
Physical Target:
CW1: 906.252 Square meters
CW2: 44.5 Lineal meter;
Allocation:
Php 12,300,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao-Ilocos Norte Rd - K0647 + 200 - K0647 + 286 ;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
2064 Square meters;
Allocation:
Php 35,000,000"

"To:
Apayao-Ilocos Norte Rd - K0647 + 120 - K0647 + 320 ;
Type of Work:
CW1: Construction of Road Slope Protection Structure;
Physical Target:
2,341.58;
Allocation:
Php 35,000,000"
May 20, 2024 2024 WIN4E03327 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Apayao (Calanasan)-Ilocos Norte Rd - K0619 + 670 - K0619 + 763;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
1922.5 Square meters;
Allocation:
Php 30,760,000"

"To:
Apayao (Calanasan)-Ilocos Norte Rd - K0619 + 650 - K0619 + 800;
Type of Work:
CW1: Construction of Slope Protection Structure
CW2: Reconstruction to Concrete Pavement;
Physical Target:
CW1: 1895.96 Square meters
CW2: 0.118 Lane Km;
Allocation:
Php 30,760,000"
May 20, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Apayao 2nd District Engineering Office
"From:
Construction (Completion) of Malasakit Center, Far North Luzon Gen. Hospital and Training Center, San Isidro, Luna, Apayao;
Type of Work:
Construction of Other Building;
Physical Target:
1 Number of Building;
Allocation:
Php 10,000,000"

"To:
Construction (Completion) of Malasakit Center, Far North Luzon Gen. Hospital and Training Center, Quirino, Luna, Apayao;
Type of Work:
Construction of Other Building;
Physical Target:
1;
Allocation:
Php 10,000,000"
May 17, 2024 FY 2024 WIN4E03334 310201101309000 March 25, 2024 Region IX Regional Office IX
UACS No. 310201101309000
Project ID: P00800214MN

OO1: Ensure Safe and Reliable National Road System – Network Development – Road Widening – Primary Roads

Pagadian City-Zamboanga City Rd - K1684+620 - K1684+674, K1684+697.15 - K1684+750.19, K1690+514.4 - K1690+554.76, K1690+586 - K1690+642.45, K1691+661.92 - K1691+713.5, K1694+770 - K1694+827, K1694+866 - K1694+924.31, K1706+021.76 - K1706 + 167.73, K1715 + 560 - K1715+590, K1715+640 - K1716+191.29, K1716+232 - K1716+362.63

CW1- Road Widening/2.457 Lane-km
Unit Cost: ₱ 25,613,160.44/lane-km CW2- Construction of Road Slope Protection Structure/9,676.69 sq.m. Unit Cost: ₱ 1,316.45/sq.m.
ROW Acquisition - 9,600.00 sq.m.
Unit Cost: ₱ 500.00/ sq.m.
EAO: ₱2,918,615.00
Allocation: ₱83,389,000.00
May 17, 2024 FY 2024 GAA P00837224MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao del Norte District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road - Jct. Tagum City Diversion Road, Prk. Bautista to Prk. Abaca, Mankilam, Tagum City, Davao del Norte
Physical Target:
CW1: 1.760 lane km (Construction of Concrete Road)
CW2: 1,589.340 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 26,744,018.00 (Construction of Concrete Road)
CW2: P 22,755,982.00 (Construction of Drainage Structure along Road)
EAO: P 500,000.00

TO: Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road - Jct. Tagum City Diversion Road, Prk. Bautista to Prk. Abaca, Mankilam, Tagum City, Davao del Norte
Physical Target:
CW1: 1.688 lane km (Construction of Concrete Road)
CW2: 1,518.150 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 26,292,290.00 (Construction of Concrete Road)
CW2: P 22,207,710.00 (Construction of Drainage Structure along Road)
EAO: P 500,000.00
May 17, 2024 FY 2024 300215103998000 April 4, 2024 Region IX Regional Office IX
UACS No. 300215103998000
Project ID: P00834832MN


Convergence and Special Support Program (CSSP)– Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/Facilities

Construction of Road - Salug - Godod - Kabasalan Road, Zamboanga Sibugay


CW1- Construction of Concrete Road: 8.633 Lane km
Unit Cost: ₱ 18,443,762.31 Lane km
EAO: ₱ 5,775,000.00
Allocation: ₱ 165,000,000.00
May 17, 2024 FY 2024 GAA P00834907MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao del Norte 2nd District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road and Drainage, Carmen, Davao del Norte
Physical Target:
CW1: 1.444 lane km (Construction of Concrete Road)
CW2: 466.000 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 19,575,759.00 (Construction of Concrete Road)
CW2: P 9,374,241.00 (Construction of Drainage Structure along Road)
EAO: P 1,050,000.00

TO: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road and Drainage, Carmen, Davao del Norte
Physical Target:
CW1: 1.670 lane km (Construction of Concrete Road)
CW2: 1,143.000 lineal meters (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 14,240,618.00 (Construction of Concrete Road)
CW2: P 14,709,382.00 (Construction of Drainage Structure along Road)
EAO: P 1,050,000.00
May 16, 2024 2024 FY 2024 GAA December 20, 2023 Region III Nueva Ecija 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Tertiary Roads

Gapan-Fort Magsaysay Rd - K0104+000 - K0106+258.43
May 16, 2024 2024 WIN4F07955 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00800222LZ
UACS : 310201101268000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0486 + 250 - K0488 + 393.75

Physical Target :
CW1 - Road Widening - 5.808 Lane Km
CW2 - Construction of Drainage Structure along Road - 4221.16 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 3095 Square meters
Row - Row Acquisition - 290.6 Square meters


TO
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0486 + 297.75 - K0488 + 393.75

Physical Target :
CW1 - Road Widening - 4.20 Lane Km
CW2 - Construction of Drainage Structure along Road - 5185.80 Lineal meters
CW3 - Construction of Road Slope Protection Structure - 3876 Square meters
Row - Row Acquisition - 10500 Square meters
May 16, 2024 2024 GAA 2024 January 19, 2024 Region V Regional Office V
Project ID : P00802125LZ
UACS : 310101101264000

FROM :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads - Daang Maharlika (LZ) K0448 + 622 - K0450 + 595, K0454 + 207 - K0455 + 013, K0436 + (-888) - K0438 + 000

Physical Target :
Preventive Maintenance of Road - Asphalt Overlay - 22.7 Lane Km


TO :
ORGANIZATIONAL OUTCOME 1 - Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads - Daang Maharlika (LZ) K0448 + 622 - K0450 + 595, K0454 + 207 - K0455 + 013, K0436 + (-888) - K0437 + 258

Physical Target :
CW1 - Preventive Maintenance of Road - Asphalt Overlay - 19.72 Lane Km
May 15, 2024 FY 2024 GAA P00800096MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1517 + 820 - K1517 + 889,
K1517 + 917 - K1517 + 1003, K1518 + 138 - K1518 + 502
Physical Target:
CW1: 1.038 lane km (Road Widening)
Allocation:
TOTAL: P 33,230,000.00
CW1: P 32,565,400.00 (Road Widening)
EAO: P 664,600.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1517 + 820 - K1517 + 889,
K1517 + 917 - K1517 + 1003, K1518 + 138 - K1518 + 502
Physical Target:
CW1: 0.963 lane km (Road Widening)
CW2: 662.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 33,230,000.00
CW1: P 14,798,000.00 (Road Widening)
CW2: P 17,767,400.00 (Construction of Road Slope Protection Structure)
EAO: P 664,600.00
May 15, 2024 FY 2024 GAA P00800100MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Digos-Makar Rd - K1589 + 1172 - K1590 + 280, K1590 + 340 - K1590 + 391
Physical Target:
CW1: 0.772 lane km (Road Widening)
ROW: 3,860.00 square meters (ROW Acquisition)
Allocation:
TOTAL: P 26,300,000.00
CW1: P 16,887,500.00 (Road Widening)
ROW: P 8,492,000.00 (ROW Acquisition)
EAO: P 920,500.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Digos-Makar Rd - K1589 + 1172 - K1590 + 132, K1590 + 194 - K1590 + 282,
K1590 + 342 - K1590 + 393, K1590 + 432 - K1590 + 666
Physical Target:
CW1: 0.952 lane km (Road Widening)
ROW: 3,860.00 square meters (ROW Acquisition)
Allocation:
TOTAL: P 26,300,000.00
CW1: P 16,887,500.00 (Road Widening)
ROW: P 8,492,000.00 (ROW Acquisition)
EAO: P 920,500.00
May 15, 2024 FY 2024 GAA P00800091MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Daang Maharlika (MN) - K1444 + 988 - K1445 + 780
Physical Target:
CW1: 1.584 lane km (Road Widening)
CW2: 980.00 square meters (Construction of Road Slope Protection Structure)
ROW: 11,880.00 square meters (ROW Acquisition)
Allocation:
TOTAL: P 86,500,000.00
CW1: P 49,129,115.00 (Road Widening)
CW2: P 22,763,385.00 (Construction of Road Slope Protection Structure)
ROW: P 11,580,000.00 (ROW Acquisition)
EAO: P 3,027,500.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Daang Maharlika (MN) - K1444 + 988 - K1445 + 1058
Physical Target:
CW1: 1.9801 lane km (Road Widening)
CW2: 1,504.00 square meters (Construction of Road Slope Protection Structure)
ROW: 7,920.00 square meters (ROW Acquisition)
Allocation:
TOTAL: P 86,500,000.00
CW1: P 42,242,838.00 (Road Widening)
CW2: P 39,299,662.00 (Construction of Road Slope Protection Structure)
ROW: P 1,930,000.00 (ROW Acquisition)
EAO: P 3,027,500.00
May 15, 2024 FY 2024 GAA P00800454MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslides - Primary Roads
Daang Maharlika (MN) - K1438 + 865 - K1438 + 965
Physical Target:
CW1: 1,200.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,050,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslides - Primary Roads
Daang Maharlika (MN) - K1438 + 865 - K1438 + 965
Physical Target:
CW1: 1,260.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,050,000.00
May 15, 2024 FY 2024 GAA P00800216MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Daang Maharlika (MN) - K1486 + 781 - K1487 + 205,
K1487 + 650 - K1488 + 057, K1489 + 857 - K1489 + 870
Physical Target:
CW1: 0.954 lane km (Road Widening)
ROW: 4,674.80 square meters (ROW Acquisition)
Allocation:
TOTAL: P 76,128,000.00
CW1: P 36,731,760.00 (Road Widening)
ROW: P 36,731,760.00 (ROW Acquisition)
EAO: P 2,664,480.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Daang Maharlika (MN) - K1486 + 781 - K1487 + 205, K1487 + 574 - K1487 + 671,
K1487 + 711 - K1488 + 057, K1489 + 857 - K1489 + 870
Physical Target:
CW1: 0.920 lane km (Road Widening)
ROW: 4,892.851 square meters (ROW Acquisition)
Allocation:
TOTAL: P 76,128,000.00
CW1: P 36,731,760.00 (Road Widening)
ROW: P 36,731,760.00 (ROW Acquisition)
EAO: P 2,664,480.00
May 15, 2024 FY 2024 GAA P00800453MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslides - Primary Roads
Daang Maharlika (MN) - K1426 + 850 - K1426 + 955
Physical Target:
CW1: 1,260.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,050,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslides - Primary Roads
Daang Maharlika (MN) - K1426 + 850 - K1426 + 955
Physical Target:
CW1: 1,214.99 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Construction of Road Slope Protection Structure)
EAO: P 1,050,000.00
May 15, 2024 FY 2024 GAA P00802422MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao del Norte 2nd District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Tagum-Panabo Circum Rd - K1496 + 612 - K1498 + 500
Physical Target:
CW1: 3.856 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Tagum-Panabo Circum Rd - K1496 + 268 - K1496 + 448, K1496 + 532 - K1498 + 075
Physical Target:
CW1: 7.052 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00
May 15, 2024 FY 2024 GAA P00801020MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Davao City Div Rd - K1509 + 066 - K1511 + 113
Physical Target:
CW1: 7.876 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Davao City Div Rd - K1508 + 580 - K1508 + 760, K1509 + 066 - K1509 + 955
Physical Target:
CW1: 5.694 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00
May 15, 2024 2024 FY 2024 GAA November 20, 2023 Region III Aurora District Engineering Office
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads

Nueva Ecija - Aurora Rd - K0215+340 - K0215+920
May 15, 2024 2024 FY 2024 GAA December 20, 2023 Region III Nueva Ecija 2nd District Engineering Office
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Jose Abad Santos Ave (JASA) - K0097+(-881) - K0097+000, K0097+000 - K0097+180, K0098+000 - K0098+066, K0101+728.60 - K0101+1003, K0102+000 - K0102+186.30, K0102+272.50 - K0102+468.30, K0102+486.70 - K0102+965, K0103+000 - K0103+181.70, K0103+287.60 - K0103+324.80, K0103+368.70 - K013+1010, K0104+000 - K0104+099.20,K0104+147.30 - K0104+287, K0104+313.10 - K0104+488.30, K0104+551.50 - K0104+631.80, K0104+696.40 - K0105+016
May 15, 2024 FY 2024 GAA WIN4E03338 FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao Oriental 1st District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry-Davao Or Coastal Rd - K1650 + 081 - K1651 + 000
Physical Target:
CW1: 1.868 lane km (Road Widening)
Allocation:
TOTAL: P 14,944,000.00
CW1: P 14,645,120.00 (Road Widening)
EAO: P 298,880.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry-Davao Or Coastal Rd - K1650 + 081 - K1650 + 342
Physical Target:
CW1: 0.522 lane km (Road Widening)
CW2: 538.00 square meters (Construction of Road Slope Protection Structure)
ROW: 3,351.60 square meters (ROW Acquisition)
Allocation:
TOTAL: P 14,944,000.00
CW1: P 6,968,780.00 (Road Widening)
CW2: P 4,736,340.00 (Construction of Road Slope Protection Structure)
ROW: P 2,940,000.00 (ROW Acquisition)
EAO: P 298,880.00
May 15, 2024 FY 2024 GAA WIN4E03339 FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao Oriental 1st District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/Facilities to support Social Services
Construction of Multipurpose Building (Boston District Elementary School), Central, Caraga, Davao Oriental
Physical Target:
CW1: 1.00 number of buildings (Construction of Multi-Purpose Building)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,950,000.00 (Construction of Multi-Purpose Building)
EAO: P 50,000.00

TO: Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/Facilities to support Social Services
Construction of Multipurpose Building (Boston District Elementary School), Central, Boston, Davao Oriental
Physical Target:
CW1: 1.00 number of buildings (Construction of Multi-Purpose Building)
Allocation:
TOTAL: P 5,000,000.00
CW1: P 4,950,000.00 (Construction of Multi-Purpose Building)
EAO: P 50,000.00
May 14, 2024 FY 2024 GAA P00800188MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry-Davao Or Coastal Rd - K1559 + 404 - K1562 + 000
Physical Target:
CW1: 5.191 lane km (Road Widening)
ROW: 38,933.955 square meters (ROW Acquisition)
Allocation:
TOTAL: P 152,000,000.00
CW1: P 106,922,000.00 (Road Widening)
ROW: P 39,758,000.00 (ROW Acquisition)
EAO: P 5,320,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Surigao del Sur Bdry-Davao Or Coastal Rd - K1558 + 648 - K1562 + 000
Physical Target:
CW1: 6.702 lane km (Road Widening)
ROW: 50,265.000 square meters (ROW Acquisition)
Allocation:
TOTAL: P 152,000,000.00
CW1: P 137,030,000.00 (Road Widening)
ROW: P 9,650,000.00 (ROW Acquisition)
EAO: P 5,320,000.00
May 14, 2024 FY 2024 GAA P00832695MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
Sitio Tibungol-Purok 13 Road connecting to future Cacao & Coconut Processing Area in Support of Cacao, Banana & Coconut Industries of Barangay Pandaitan, Paquibato District, Davao City, Davao del Sur
Physical Target:
CW1: 0.951 lane km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 400,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)
Sitio Tibungol-Purok 13 Road connecting to future Cacao & Coconut Processing Area in Support of Cacao, Banana & Coconut Industries of Barangay Pandaitan, Paquibato District, Davao City, Davao del Sur
Physical Target:
CW1: 0.600 lane km (Construction of Concrete Road)
CW2: 240.00 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 10,486,000.00 (Construction of Concrete Road)
CW2: P 9,114,000.00 (Construction of Road Slope Protection Structure)
EAO: P 400,000.00
May 14, 2024 FY 2024 GAA P00800095MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1516 + 232 - K1516 + 250, K1516 + 331 - K1516 + 349,
K1516 + 481 - K1516 + 519, K1516 + 820 - K1516 + 905
Physical Target:
CW1: 0.318 lane km (Road Widening)
Allocation:
TOTAL: P 7,950,000.00
CW1: P 7,791,000.00 (Road Widening)
EAO: P 159,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1513 + 156 - K1513 + 356,
K1513 + 391 - K1513 + 480, K1516 + 820 - K1516 + 905
Physical Target:
CW1: 0.663 lane km (Road Widening)
Allocation:
TOTAL: P 7,950,000.00
CW1: P 7,791,000.00 (Road Widening)
EAO: P 159,000.00
May 14, 2024 2024 FY 2024 GAA December 20, 2023 Region III Nueva Ecija 1st District Engineering Office
Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Multi-Purpose Buildings / Facilities to Support Social Services

Construction/Rehabilitation of Multipurpose (Senior Citizens Building), Municipality of Aliaga, Nueva Ecija
May 14, 2024 2024 WIN4F07934 FY 2024 GAA December 20, 2023 Region III Bataan 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Secondary Roads

Roman Expressway- K0123+249 - K0123+320
May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100710000
Project ID: P00801255MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1356 + 790 - K1356 + 805, K1356 + 859 - K1357 + 636, K1357 + 759 - K1357 + 800, K1358 + 000 - K1358 + 500, K1359 + 000 - K1360 + 519, K1366 + 000 - K1367 + 000

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 7.704 Lane Km

Allocation:
TOTAL: P 231,120,000
CW1: P 223,030,800
EAO: P 8,089,200

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1356 + 790 - K1356 + 805, K1356 + 859 - K1357 + 636, K1357 + 759 - K1357 + 800, K1359 + 000 - K1360 + 519, K1366 + 000 - K1367 + 000

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 10.426 Lane Km

Allocation:
TOTAL: P 231,120,000
CW1: P 223,030,800
EAO: P 8,089,200

Unit Cost:
CW1: P 21,391,789.76/Lane Km

May 14, 2024 2024 FY 2024 GAA December 20, 2023 Region III Tarlac 2nd District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Rehabilitation of Existing Dike along Rio Chico River (Matayumtayum Section, Right Bank) U/S of Rio Chico Bridge, Phase 1, Sta. 14+395.50 to Sta. 14+837.48, La Paz, Tarlac
May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100708000
Project ID: P00801254MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1346 + 000 - K1347 + 760, K1347 + 962 - K1348 + 896, K1349 + 487 - K1350 + 000, K1355 + 276 - K1356 + 441

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 8.744 Lane Km

Allocation:
TOTAL: P 262,320,000
CW1: P 253,138,800
EAO: P 9,181,200

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1346 + 000 - K1347 + 760, K1347 + 962 - K1348 + 896, K1349 + 487 - K1350 + 000, K1355 + 276 - K1356 + 441

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 14.425 Lane Km

Allocation:
TOTAL: P 262,320,000
CW1: P 253,138,800
EAO: P 9,181,200

Unit Cost:
CW1: P 17,548,616.98/Lane Km

May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100706000
Project ID: P00801253MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1318 + 544 - K1319 + 581, K1321 + 532 - K1323 + 379, K1323 + 621 - K1324 + 191, K1333 + 300 - K1333 + 390, K1340 + 000 - K1340 + 228, K1341 + 742 - K1341 + 858, K1343 + 006 - K1343 + 559

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 8.882 Lane Km

Allocation:
TOTAL: P 266,460,000
CW1: P 257,133,900
EAO: P 9,326,100

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1318 + 544 - K1319 + 581, K1321 + 532 - K1323 + 180, K1323 + 200 - K1323 + 379, K1323 + 621 - K1324 + 191, K1333 + 300 - K1333 + 390, K1340 + 000 - K1340 + 228, K1343 + 006 - K1343 + 559

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 9.254 Lane Km

Allocation:
TOTAL: P 266,460,000
CW1: P 257,133,900
EAO: P 9,326,100

Unit Cost:
CW1: P 27,786,243.79/Lane Km

May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100708000
Project ID: P00801254MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1346 + 000 - K1347 + 760, K1347 + 962 - K1348 + 896, K1349 + 487 - K1350 + 000, K1355 + 276 - K1356 + 441

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 8.744 Lane Km

Allocation:
TOTAL: P 262,320,000
CW1: P 253,138,800
EAO: P 9,181,200

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1346 + 000 - K1347 + 760, K1347 + 962 - K1348 + 896, K1349 + 487 - K1350 + 000, K1355 + 276 - K1356 + 441

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 14.425 Lane Km

Allocation:
TOTAL: P 262,320,000
CW1: P 253,138,800
EAO: P 9,181,200

Unit Cost:
CW1: P 17,548,616.98/Lane Km

May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100706000
Project ID: P00801253MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1318 + 544 - K1319 + 581, K1321 + 532 - K1323 + 379, K1323 + 621 - K1324 + 191, K1333 + 300 - K1333 + 390, K1340 + 000 - K1340 + 228, K1341 + 742 - K1341 + 858, K1343 + 006 - K1343 + 559

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 8.882 Lane Km

Allocation:
TOTAL: P 266,460,000
CW1: P 257,133,900
EAO: P 9,326,100

Unit Cost:
CW1: P 28,950,000/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1318 + 544 - K1319 + 581, K1321 + 532 - K1323 + 180, K1323 + 200 - K1323 + 379, K1323 + 621 - K1324 + 191, K1333 + 300 - K1333 + 390, K1340 + 000 - K1340 + 228, K1343 + 006 - K1343 + 559

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 9.254 Lane Km

Allocation:
TOTAL: P 266,460,000
CW1: P 257,133,900
EAO: P 9,326,100

Unit Cost:
CW1: P 27,786,243.79/Lane Km

May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 300214100861000
Project ID: P00833091MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239

FROM:

Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (Agusan-Davao Sect) - K1241 + (-321) - K1243 + 000

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 4.644 Lane Km

Allocation:
TOTAL: P 169,541,000
CW1: P 163,607,065
EAO: P 5,933,935

Unit Cost:
CW1: P 35,229,772.83/Lane Km

TO:

Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads along Daang Maharlika (Agusan-Davao Sect) - K1241 + (-321) - K1241 + 510, K1242 + 025 - K1243 + 800

Type of Work:
CW1- Rehabilitation of Paved Road
CW2- Construction of Road Slope Protection Structure

Physical Target:
CW1- 5.216 Lane Km
CW2- 2,160 Square meters

Allocation:
TOTAL: P 169,541,000
CW1: P 96,539,565
CW2: P 67,067,500
EAO: P 5,933,935

Unit Cost:
CW1: P 35,229,772.83/ Lane Km
CW2: P 31,049.77/ Square meters

May 14, 2024 2024 FY 2024 GAA, R.A 11975 December 25, 2023 Region XIII Regional Office XIII
UACS No. : 310104100701000
Project ID: P00801247MN

ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads
- Primary Roads

FROM:

Daang Maharlika (Agusan-Davao Sect) - K1243 + 000 - K1246 + 000

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 6.014 Lane Km

Allocation:
TOTAL: P 150,199,000
CW1: P 144,942,035
EAO: P 5,256,965

Unit Cost:
CW1: P 24,100,770.70/Lane Km

TO:

Daang Maharlika (Agusan-Davao Sect) - K1243 + 800 - K1244 + 670, K1244 + 690 - K1246 + 000

Type of Work:
CW1- Rehabilitation of Paved Road

Physical Target:
CW1- 8.748 Lane Km

Allocation:
TOTAL: P 150,199,000
CW1: P 144,942,035
EAO: P 5,256,965

Unit Cost:
CW1: P 16,568,591.11/Lane Km

May 14, 2024 FY 2024 GAA P00832627MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations (Tourism Road Infrastructure Program - TRIP)
Jct. Acacia Road - Purok New Visayas leading to Safari Land Crocodile Park, Brgy. Acacia, Davao City
Physical Target:
CW1: 428.571 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Road Slope Protection Structure)
EAO: P 300,000.00

TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations (Tourism Road Infrastructure Program - TRIP)
Jct. Acacia Road - Purok New Visayas leading to Safari Land Crocodile Park, Brgy. Acacia, Davao City
Physical Target:
CW1: 490.000 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Road Slope Protection Structure)
EAO: P 300,000.00
May 14, 2024 2024 FY 2024 GAA December 20, 2023 Region III Tarlac 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Secondary Roads

Concepcion-Capas Rd - K0109+(-321) - K0109+(-045); K0109+459 - K0109+500; K0115+783- K0115+844
May 14, 2024 2024 FY 2024 GAA December 20, 2023 Region III Tarlac 2nd District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Rehabilitation of Existing Dike along Rio Chico River (Matayumtayum Section, Right Bank) U/S of Rio Chico Bridge, Phase 2, Sta. 14+837.48 to Sta. 15+278.69, La Paz, Tarlac
May 14, 2024 FY 2024 GAA P00855094MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program - Building and Other Structures - Multipurpose/Facilities - National Building Program
Completion of Multipurpose Building PRC 11 Dpwh Region 11, Davao City
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Construction of Multi-Purpose Building)
EAO: P 1,750,000.00

TO: Local Program - Building and Other Structures - Multipurpose/Facilities - National Building Program
Completion of Multipurpose Building PRC Region 11, Davao City
Physical Target:
CW1: 1 number of buildings (Construction of Multi-Purpose Building)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Construction of Multi-Purpose Building)
EAO: P 1,750,000.00
May 14, 2024 2024 FY 2024 GAA December 20, 2023 Region III Tarlac 2nd District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Rehabilitation of Existing Dike along Parua River (Castillo Section, Left Bank), Package J, Sta. 4+764.08 to Sta. 5+169.10, Concepcion, Tarlac
May 14, 2024 FY 2024 GAA P00800094MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1513 + 1014 - K1514 + 015, K1513 + 156 - K1513 + 356,
K1513 + 391 - K1513 + 582, K1514 + 316 - K1514 + 444, K1514 + 845 - K1514 + 904
Physical Target:
CW1: 1.272 lane km (Road Widening)
Allocation:
TOTAL: P 36,440,000.00
CW1: P 35,771,200.00 (Road Widening)
EAO: P 728,800.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1513 + 480 - K1513 + 582, K1513 + 961 - K1514 + 015,
K1514 + 316 - K1514 + 444, K1514 + 845 - K1514 + 904
Physical Target:
CW1: 0.502 lane km (Road Widening)
CW2: 1,170.07 square meters (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 36,440,000.00
CW1: P 12,877,200.00 (Road Widening)
CW2: P 22,834,000.00 (Construction of Road Slope Protection Structure)
EAO: P 728,800.00
May 13, 2024 2024 GAA 2024 January 1, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Flood Mitigation Structure along Agno River, Salingao Section, Sta. 0+162 - Sta. 0+402 (B.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
480 Lineal meters;
Allocation:
Php 20,000,000"

"To:
Construction of Flood Mitigation Structure along Agno River, Salingao Section, Sta. 0+022 - Sta. 0+306 (BS), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
421 Lineal meters;
Allocation:
Php 20,000,000"
May 13, 2024 2024 SR2024-01-003946 January 29, 2024 Cordillera Administrative Region Benguet 2nd District Engineering Office
"From:
Construction of Flood Mitigation Structure along Agno River, Tin-apan Section, Sta. 0+068 - Sta. 0+593 (B.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1050 Lineal meters;
Allocation:
Php 70,000,000"

"To:
Construction of Flood Mitigation Structure along Agno River, Tin-apan Section, Sta. 0+058 - Sta. 0+650 (B.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1110 Lineal meters;
Allocation:
Php 70,000,000"
May 13, 2024 2024 SR 2024-001-004212 January 29, 2024 Cordillera Administrative Region Ifugao 1st District Engineering Office
"From:
Kiangan-Tinoc-Buguias Rd - (S00634LZ) Chainage 34710 - Chainage 34862, Chainage 37193 - Chainage 37271, Chainage 39907 - Chainage 39961;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
1903 Square meters;
Allocation:
Php 49,070,000"

"To:
Kiangan-Tinoc-Buguias Rd - (S00634LZ) Chainage 24531 - Chainage 24578, Chainage 27854 - Chainage 27893, Chainage 34710 - Chainage 34862, Chainage 37193 - Chainage 37281, Chainage 39907 - Chainage 39961, Tinoc, Ifugao;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
2538.88 Square meters;
Allocation:
Php 49,070,000"
May 13, 2024 2024 SR2024-01-005364 January 30, 2024 Cordillera Administrative Region CAR - Regional Office
"From:
Construction of Masablang Flood Control Structure (Section 2M), Sta. 112+780 - Sta. 112+980 (Left Side) and Sta. 113+025 - Sta. 113+275 (Both Side);
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
820.50 Lineal meters;
Allocation:
Php 100,000,000"

"To:
Construction of Masablang Flood Control Structure (Section 2M), Sta. 112+780 - Sta. 113+312 (Both Side);
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1050 Lineal meters;
Allocation:
Php 100,000,000"
May 13, 2024 2024 FY 2024 GAA December 20, 2023 Region III Aurora District Engineering Office
Asset Preservation Program - Preventive Maintenance - Secondary Roads

Nueva Ecija - Aurora Rd - K0174+260 - K0174+482; K0179+047 - K0179+599
May 13, 2024 FY 20204 P00801061MN 310102101932000 January 2, 2024 Region XII South Cotabato 1st District Engineering Office
Asset Preservation Program- Preventive Maintenance - Secondary Roads
Contract ID: 24MB0061
From: Makar-Kiamba Rd - K1667 + 243 - K1667 + 254, K1667 + 254 - K1667 + 393
Preventive Maintenance of Road: Asphalt Overlay:
0.878 lane-km
To:Makar-Kiamba Rd - K1667 + 243 - K1667 + 254, K1667 + 254 - K1667 + 394
Preventive Maintenance of Road: Asphalt Overlay:
0.884 lane-km

May 13, 2024 FY 20204 P00800143MN 310102101932000 January 2, 2024 Region XII South Cotabato 1st District Engineering Office
Network Development Program - Road Widening - Secondary Roads
Contract ID: 24MB0063
Amount:₱ 11,266,000.00

From: Albert Morrow Blvd - K1650 + 878 - K1651 + 503
Road Widening: 1.20 lane-km

To: Albert Morrow Blvd - K1650 + 878 - K1651 + 501
Road Widening: 1.196 lane-km
May 13, 2024 FY 2024 GAA P00803776MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Daang Maharlika (MN) - K1422 + 514 - K1423 + 1085
Physical Target:
CW1: 5.386 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Daang Maharlika (MN) - K1423 + 139 - K1423 + 1085
Physical Target:
CW1: 5.676 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00
May 13, 2024 FY 2024 GAA P00800098MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) - K1448 + 585 - K1450 + 197
Physical Target:
CW1: 1.692 lane km (Road Widening)
ROW: 2,329.00 square meters (ROW Acquisition)
Allocation:
TOTAL: P 50,663,000.00
CW1: P 32,967,295.00 (Road Widening)
ROW: P 15,922,500.00 (ROW Acquisition)
EAO: P 1,773,205.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Daang Maharlika (MN) - K1448 + 666 - K1449 + 293, K1449 + 471 - K1449 + 882
Physical Target:
CW1: 1.431 lane km (Road Widening)
ROW: 4,383.68 square meters (ROW Acquisition)
Allocation:
TOTAL: P 50,663,000.00
CW1: P 32,967,295.00 (Road Widening)
ROW: P 15,922,500.00 (ROW Acquisition)
EAO: P 1,773,205.00
May 13, 2024 FY 2024 GAA P00801127MN FY 2024 GAA RA 11975 January 1, 2024 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Daang Maharlika (MN) - K1497 + 669 - K1498 + 065
Physical Target:
CW1: 2.391 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 44,048,000.00
CW1: P 42,506,320.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 1,541,680.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Daang Maharlika (MN) - K1497 + 653 - K1498 + 296
Physical Target:
CW1: 2.676 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 44,048,000.00
CW1: P 42,506,320.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 1,541,680.00
May 9, 2024 2024 FY 2024 GAA December 20, 2023 Region III Nueva Ecija 2nd District Engineering Office
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads

Nueva Ecija - Aurora Rd - K0142+745 - K0142+981; K0143+000 - K0143+200; K0147+435.50 - K0147+993; K0148+000 - K0148+045
May 9, 2024 FY 2024 300226115231000 April 4, 2024 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS: 300226115231000
Project ID: P00836345MN

Convergence and Special Support Program - Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

Construction of Multi-Purpose Building, Brgy. Fernandino, Roseller Lim, Zamboanga Sibugay


CW1 - Construction of Multi-Purpose Building: 1 Number of Building
Unit Cost: ₱ 9,900,000.00/ Number of Building
EAO: ₱ 100,000.00
Allocation: ₱ 10,000,000.00
May 9, 2024 2024 SR2024-01-008091 January 31, 2024 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (LT) - K0939 + 300 - K0939 + 770, K0947 + 000 - K0948 + 613, K0948 + 659 - K0949 + 288, K0965 + 204 - K0956 + 581, K0956 +606 - K0957 + 000, K0958 + 118 - K0958 + 804

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 215.041565 M
Asphalt Overlay: 16.074 Lane Km

EAO P 7.799435 M

Total P 22.841 M

AS MODIFIED:

Daang Maharlika (LT) - K0939 + 300 - K0939 + 770, K0947 + 000 - K0948 + 613, K0948 + 659 - K0949 + 288, K0956 + 204 - K0956 + 581, K0956 +606 - K0957 + 000, K0958 + 118 - K0958 + 804

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 215.041565 M
Asphalt Overlay: 16.074 Lane Km

EAO P 7.799435 M

Total P 22.841 M
May 9, 2024 2024 SR2024-02-008179 February 1, 2024 Region VIII Regional Office VIII
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads- Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0791 + 649 - K0791 + 649, K0796 + 558 - K0797 + 000, K0806 + 120 - K0807 + 000, K0822 + 000 - K0824 + 500, K0824 + 500 - K0825 + 000, K0826 + 000 - K0826 + 200

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement P 164.050 M
: 10.208 Lane Km

EAO P 5.950 M

Total P 170.00 M

AS MODIFIED:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0791 + 649 - K0792 + 200, K0796 + 558 - K0797 + 000, K0806 + 120 - K0807 + 000, K0822 + 000 - K0824 + 500, K0824 + 500 - K0825 + 000, K0826 + 000 - K0826 + 200

Physical Target: Allocation:

CW1-Reconstruction to Concrete Pavement P 164.050 M
: 10.208 Lane Km

EAO P 5.950 M

Total P 170.00 M
May 9, 2024 FY 2024 300219102957000 April 4, 2024 Region IX Zamboanga Sibugay 2nd District Engineering Office
UACS No. 300219102957000
Project ID: P00835860MN


Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities

Construction of Flood Control Structure at Barangay Nazareth, Kabasalan, Zamboanga Sibugay

CW1 - Construction of Flood Mitigation Structure: 150.00 Lineal meters
Unit Cost: ₱ 196,000.00/Lineal meters
EAO: ₱ 600,000.00
Allocation: ₱ 30,000,000.00
May 9, 2024 FY 2024 P00800142MN SR2024-01-005125 January 30, 2024 Region XII Regional Office XII
Network Development - Road Widening - Primary Roads
Contract ID: 24M00151
Amount: ₱ 5,000,000.00
Type of Work: Road Widening
Physical Target: 0.400 Lane Km
Project Name:
From: Makar-Marbel Rd - K1658 + 240 - K1658 + 440
To: Makar-Marbel Rd - K1658 + 014 - K1658 + 214
May 9, 2024 FY 2024 P00800142MN SR2024-01-005125 January 30, 2024 Region XII Regional Office XII
Network Development - Road Widening - Primary Roads
Contract ID: 24M00151
Amount: ₱ 5,000,000.00
Type of Work: Road Widening
Physical Target: 0.400 Lane Km
Project Name:
From: Makar-Marbel Rd - K1658 + 240 - K1658 + 440
To: Makar-Marbel Rd - K1658 + 014 - K1658 + 214