Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
April 4, 2018 2018 WIN8G01833 WIN8G01833 March 15, 2018 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Construction of Concrete Road - Ballay-Tabio-Tonoman-Bulalacao-Tawangan-Lusod Road leading to Bulalacao Lakes and Mt. Tabeo, Kabayan, Benguet; Physical Target:3.342 Lane Km.; Allocation = Php 58,485,000

To: Construction of Concrete Road - Ballay-Tabio-Tonoman-Bulalacao-Tawangan-Lusod Road leading to Bulalacao Lakes and Mt. Tabeo, Kabayan, Benguet; Physical Target:2.780 Lane Km.; Allocation = Php58,485,000
April 4, 2018 FY 2018 WIN8C02212 UACS No. 310106100208000 March 21, 2018 Region IX Zamboanga del Norte 3rd District Engineering Office
UACS No. 310106100208000
Project ID: P00201347MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation Program - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Dipolog-Polanco-Piñan-Jct. Oroquieta Rd
K1828+919 - K1830+079
Physical Target:
CW-1- Reconstruction from Paved to Concrete: 2.320 lane km
Unit Cost: P 14,543,586.21/lane km
Physical Target:
ROW: 468.63 sq. m
Unit Cost: P 1,499.99/sq. m
EAO: P 702,940.00
Allocation: P 35,147,000.00
April 4, 2018 2018 WIN8G01875 WIN8G01875 March 14, 2018 Cordillera Administrative Region Benguet 1st District Engineering Office
From: Construction of Road Slope Protection Structure - Kennon Rd - K0233+576 - K0234+028; Physical Target:5,000.00 Square meters; Allocation = Php 50,000,000

To: Construction of Road Slope Protection Structure - Kennon Rd - K0233+904 - K0234+000; Physical Target:2,760.00 Square meters; Allocation = Php50,000,000
April 4, 2018 FY 2018 WIN8C02222 UACS No. 320101100198000 March 21, 2018 Region IX Zamboanga del Norte 3rd District Engineering Office
UACS No. 320101100198000
Project ID: P00221251MN
OO2: Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction/Extension of Flood Control Structure (Revetment) along Dipolog River, Dapdap Bridge, Labrador Section including RROW along Polanco-Macleodes National Road, Zamboanga del Norte
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 273.20 l.m.
Unit Cost: P 210,560.03/l.m.
Physical Target:
ROW: 200 sq.m
Unit Cost: P 1,500.00/sq. m
Physical Target:
Soil Exploration:1 Borehole
Unit Cost: P75,000/borehole
EAO: P 2,100,000.00
Allocation: P 60,000,000.00
April 4, 2018 FY 2018 WIN8C02237 UACS No. 320101102160000 March 21, 2018 Region IX Zamboanga del Norte 3rd District Engineering Office
UACS No. 320101102160000
Project ID: P00220565MN
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure, De Venta Perla, (Polanco Side) including RROW, Zamboanga del Norte
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 140.40 l.m.
Unit Cost: P 204,594.02/l.m.
Physical Target:
ROW: 400 sq.m
Unit Cost: P 1,500.00/sq.m
Physical Target:
Soil Exploration: 1 borehole
Unit Cost: P 75,000/borehole
EAO: P600,000.00
Allocation: P 30,000,000.00
April 3, 2018 2018 WIN8F05173 UACS No. 310102100045000 January 1, 2018 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 3101022100045000
Project ID: P00200061LZ
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Road
PPTA Road K0025+510 – K0027+-050, K0027+000 – K0028+545

As Modified
UACS No. 3101022100045000
Project ID: P00200061LZ
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Road
PPTA Road K0025+510 – K0026+110.40, K0027+(-050.70) – K0028+545
April 3, 2018 2018 WIN8F05172 UACS No. 310103100038000 January 1, 2018 National Capital Region Las Piñas - Muntinlupa District Engineering Office
As per GAA/Original
UACS No. 31010310003800
Project ID: P00200196LZ
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Road
Daang Maharlika (LZ) (S03288LZ) Chainage 30 – Chainage 225

As Modified
UACS No. 31010310003800
Project ID: P00200196LZ
Organizational Outcome 001: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Road
Daang Maharlika (LZ) (S03288LZ) Chainage 30 – Chainage 225.40
April 3, 2018 FY - 2018 WIN8C02118 FY - 2018 GAA DPWH Infra Program December 22, 2017 Region IV-B NCR - Regional Office
001: Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads -
Tertiary Roads

FROM:
Palawan Circum. Rd ( Panalingaan - Tagbita - Latud )
K0267+210 - K0272+519

CW1: 10.904 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php

TO:
Palawan Circum. Rd ( Panalingaan - Tagbita - Latud )
K0267+242 - K0271+180

CW1: 8.100 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php
April 3, 2018 FY - 2018 WIN8F05099 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Road -
Secondary Roads

FROM:
Palawan Circum. Rd.
K0232+764 - K0232+900,
K0233+090 - K0236+121,
K0236+388 - K0236+655,
K0211+625 - K0212+089,
K0212+257 - K0212+1026,
K0215+036 - K0215+230

CW1: 10.00 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php

TO:

Palawan Circum. Rd.
K0232+764 - K0232+900,
K0233+090 - K0236+098,
K0236+417 - K0236+694,
K0211+625 - K0212+089,
K0212+257 - K0212+312

CW1: 8.138 lane km ( Paving of unpaved Road )
Allocation: 150,000,000 Php
April 3, 2018 FY - 2018 WIN8F05076 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads -
Secondary Roads

FROM:
Palawan Circum. Rd.
K0236+665 - K0241+524

CW1: 10.00 lane km ( Paving of Unpaved Roads )
Allocation: 150,000,000 Php

TO:
Palawan Circum. Rd.
K0236+665 - K0241+283

CW1: 9.518 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000
April 3, 2018 FY - 2018 WIN8F05067 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads -
Secondary Roads

FROM:
Quezon - Punta Baja Rd
K0189+429 -K0192+309,
K0192+358 - K0193+049,
K0162+014 - K0162+471,
K0167+591 - K0168+282

CW1: 10.00 lane km (Paving of Unpaved Road )
Allocation: 150,000,000 Php

TO:
Quezon - Punta Baja Rd.
K0162+014 - K0162+433,
K0167+591 - K0168+233,
K0189+429 - K0192+309

CW1: 8.342 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php
April 3, 2018 FY - 2018 WIN8F05074 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Roads -
Secondary Roads

FROM:
Quezon - Punta Baja Rd.
K0198+344 - K0201+377,
K0202+506 - K0203+063,
K0170+892 - K0171+216

CW1: 8.358 lane km ( Paving of Unpaved Road )
Allocation: 125,364,000 Php

TO:
Quezon - Punta Baja Rd.
K0170+892 - K0171+216,
K0198+344 - K0200+627

CW1: 5.55 lane km ( Paving of Unpaved Road )
Allocation: 125,364,000 Php
April 3, 2018 GAA CY2018 WIN8F05180 UACS No. 320101100377000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100377000
Project ID: P00221400LZ-CW1
WIN8F05180
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Pinagkabalian River (Sta. 2+339 to Sta. 2+199), (Phase I), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 144 lm Unit Cost: P 340,277.78/lm
Allocation: P 49 M
EAO P 1 M
Total: P 50 M

As Modified
UACS No. 320101100377000
Project ID: P00221400LZ-CW1
WIN8F05180
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Pinagkabalian River (Sta. 2+340 to Sta. 2+226), (Phase I), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 114 lm, Unit Cost: P 423,394.74/lm
Allocation: P 48.267 M
EAO P 1 M
Excess P 0.733 M
Total: P 50 M
April 3, 2018 GAA CY2018 WIN8F05178 UACS No. 320101100231000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100231000
Project ID: P00221395LZ-CW1
WIN8F05178
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing of Riverwall along Santulan River (Sta. 2+454 to 2+929), from Women’s Hospital to Valenzuela, Boundary, Malabon City
Physical Target: CW1-Construction of Revetment: 475 lm
Unit Cost: P 152,368.42/lm
Allocation: P 72.375 M
EAO P 2.625 M
Total: P 75 M

As Modified
UACS No. 320101100377000
Project ID: P00221400LZ-CW1
WIN8F05180
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing of Riverwall along Santulan River (Sta. 2+454 to 2+901.5), from Women’s Hospital to Valenzuela, Boundary, Malabon City
Physical Target: CW1-Construction of Revetment: 447 lm
Unit Cost: P 164,243.85/lm
Allocation: P 73.417 M
EAO P 1.50 M
Excess 0.083 M
Total: P 75 M
April 3, 2018 GAA CY2018 WIN8F05179 UACS No. 320101100376000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100376000
Project ID: P00221399LZ-CW1
WIN8F05179
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Malabon-Tullahan River (Sta. 4+900 to Sta. 5+190), from Acacia Pumping Station to Philippine National Railway (PNR), Brgy. Tinajeros, Malabon City
Physical Target: CW1-Construction of Revetment: 290 lm
Unit Cost: P 168,965.52/lm
Allocation: P 49 M
EAO P 1 M
Total: P 50 M

As Modified
UACS No. 320101100376000
Project ID: P00221399LZ-CW1
WIN8F05179
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Malabon-Tullahan River (Sta. 4+885.6 to Sta. 5+175.6), from Acacia Pumping Station to Philippine National Railway (PNR), Brgy. Tinajeros, Malabon City
Physical Target: CW1-Construction of Revetment: 290 lm
Unit Cost: P 168,955.17/lm
Allocation: P 48.997 M
EAO P 1 M
Excess P 0.003 M
Total: P 50 M
April 3, 2018 GAA CY2018 WIN8F05176 UACS No. 320101100371000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100371000
Project ID: P00221394LZ
WIN8F05176
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing of Riverwall along Santulan River (Sta. 1+611 to Sta. 1+927), from Santulan Bridge (Upstream), Malabon City
Physical Target: CW1-Construction of Revetment: 311 lm
Unit Cost: P 157,556.27/lm
Allocation: P 49 M
EAO P 1 M
Total: P 50 M

As Modified
UACS No. 320101100371000
Project ID: P00221394LZ
WIN8F05176
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing of Riverwall along Santulan River (Sta. 1+611 to Sta. 1+903), from Santulan Bridge (Upstream), Malabon City
Physical Target: CW1-Construction of Revetment: 292 lm
Unit Cost: P 167,421.23/lm
Allocation: P 48.887 M
EAO P 1 M
Excess P 0.113 M
Total: P 50 M
April 3, 2018 GAA CY2018 WIN8F05183 UACS No. 320101100232000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100232000
Project ID: P00221397LZ
WIN8F05183
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Malabon-Tullahan River along Malabon-Tullahan River (Sta. 1+043 to Sta. 1+517), Brgy. Tañong, Malabon City
Physical Target: CW1-Construction of Revetment: 477 lm
Unit Cost: P 151,729.56/lm
Allocation: P 72.735 M
EAO P 2.625 M
Total: P 75 M

As Modified
UACS No. 320101100232000
Project ID: P00221397LZ
WIN8F05183
Organizational Outcome 2: Protect Lives and Properties
Construction/Sealing/Improvement of Riverwall along Malabon-Tullahan River along Malabon-Tullahan River (Sta. 1+043 to Sta. 1+527), Brgy. Tañong, Malabon City
Physical Target: CW1-Construction of Revetment: 484 lm
Unit Cost: P 151,431.82/lm
Allocation: P 73.293 M
EAO P 1.50 M
Excess P 0.207 M
Total: P 75 M
April 3, 2018 FY - 2018 WIN8F05081 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Paving of Unpaved Road -
Secondary Roads

FROM:
Quezon - Punta Baja Rd.
K0193+049 - K0196+320,
K0196+457 - K0196+976,
K0197+352 - K0198+344

CW1: 10.00 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php

TO:
Quezon - Punta Baja rd.
K0193+049 - K0196+320,
K0196+457 - K0196+976,
K0197+352 - K0197+580

CW1: 8.33 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php
April 3, 2018 FY - 2018 WIN8F05079 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Puerto Princesa North Rd
K0014+000 - K0015+433,
K0015+448.20 + K0022+000

CW1: 15.962 lane km ( Road Widening )
Allocation: 242,802,000 Php

TO:
Puerto Princesa North Rd
K0014+000 - K0015+373,
K0015+508 - K0020+433

CW1: 12.57 lane km ( Road Widening )
Allocation: 242,802,000
April 3, 2018 GAA CY2018 WIN8F05182 UACS No. 320101100146000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100146000
Project ID: P00222433LZ-CW1
WIN8F05182
Organizational Outcome 2: Protect Lives and Properties
Construction of Riverwall and Road Dike (Sta. 1+989 to Sta. 1+779), (Phase 2), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 210 lm
Unit Cost: P 344,642.86/lm
Allocation: P 72.375 M
EAO P 2.625 M
Total: P 75 M

As Modified
UACS No. 320101100146000
Project ID: P00222433LZ-CW1
WIN8F05182
Organizational Outcome 2: Protect Lives and Properties
Construction of Riverwall and Road Dike (Sta. 2+048 to Sta. 1+870), (Phase 2), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 210 lm
Unit Cost: P 410,662.92/lm
Allocation: P 73.098 M
EAO P 1.50 M
Excess 0.402 M
Total: P 75 M
April 3, 2018 FY - 2018 WIN8F05075 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
GAA 2018 Other Infrastructure ( CSSP )

Convergence and Special Support Program
- Construction/Improvement of Access Roads leading to
Declared Tourism Destinations

FROM:
NRJ leading to Tabon Cave, Palawan

CW1: 7.394 lane km ( Construction of Gravel Road )
Allocation: 110,903,000 Php

TO:
NRJ leading to Tabon Cave, Palawan

CW1: 3.735 lane km ( Construction of Gravel Road )
Allocation: 110,903,00 Php
April 3, 2018 FY - 2018 WIN8F05069 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Puerto Princesa North Rd.
K0022+000 - K0023+449,
K0023+496 - K0023+596,
K0023+651 - K0025+134,
K0025+150 - K0027+255,
K0027+274 - K0028+000

CW1: 11.744 lane km ( Road Widening )
Allocation: 200,000,000 Php

TO:
Puerto Princesa North Rd
K0021+320 - K0023+389,
K0023+711 - K0025+074,
K0025+210 - K0027+195,
K0027+334 - K0028+000

CW1: 12.184 lane km ( Road Widening )
Allocation: 200,000,000 Php
April 3, 2018 GAA CY2018 WIN8F05181 UACS No. 320101100145000 January 1, 2018 National Capital Region Malabon-Navotas District Engineering Office
As per GAA/Original
UACS No. 320101100145000
Project ID: P00222434LZ-CW1
WIN8F05181
Organizational Outcome 2: Protect Lives and Properties
Construction of Riverwall and Road Dike (Sta. 1+779 to Sta. 1+569), (Phase 3), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 210 lm
Unit Cost: P 344,642.86/lm
Allocation: P 72.375 M
EAO P 2.625 M
Total: P 75 M

As Modified
UACS No. 320101100145000
Project ID: P00222434LZ-CW1
WIN8F05181
Organizational Outcome 2: Protect Lives and Properties
Construction of Riverwall and Road Dike (Sta. 1+870 to Sta. 1+691.2), (Phase 3), Brgy. Dampalit, Malabon City
Physical Target: CW1-Construction of Revetment: 178.8 lm
Unit Cost: P 410,620.80/lm
Allocation: P 73.419 M
EAO P 1.50 M
Excess 0.081 M
Total: P 75 M
April 3, 2018 FY - 2018 WIN8F05100 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
GAA 2018 Other Infrastructure ( CSSP )

Convergence and Special Support Program
- Construction/Improvement of Access Road leading to
Declared Tourism destinations

FROM:
Bacungan - Simpucan - Bagumbayan - Napsan Road,
Puerto Princesa City, Palawan

CW1: 9.257 lane km ( Construction of Concrete Road )
Allocation: 200,000,000 Php

TO:
Bacungan - Simpucan - Bagumbayan - Napsan Road,
Puerto Princesa City, Palawan

CW1: 16.528 lane km ( Construction of Concrete Road )
Allocation: 200,000,000 Php
April 3, 2018 2018 310207100014000 GAA FY2018 January 1, 2018 Region II Isabela 2nd District Engineering Office
Network Development Program: Off-Carriageway Improvement-- Primary Roads: Santiago-Tuguegarao Rd - K0392 + 500 - K0392 + 560, K0392 + 670 - K0392 + 730, K0392 + 880 - K0392 + 950
April 3, 2018 2018 310209100039000 GAA FY2018 January 1, 2018 Region II Isabela 2nd District Engineering Office
Network Development Program: Off-Carriageway Improvement-Tertiary Roads-Ilagan-Delfin Albano-Mallig Rd - K0438 + 375 - K0440 + 638
April 3, 2018 2018 310102100076000 GAA FY2018 January 1, 2018 Region II Cagayan 1st District Engineering Office
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System: Asset Preservation Program: Preventive Maintenance-Secondary Roads-Aparri Airport Rd - K0583 + -714.20 - K0583 + 589
April 3, 2018 2018 310102100077000 GAA FY2018 January 1, 2018 Region II Cagayan 1st District Engineering Office
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System: Asset Preservation Program:Preventive Maintenance - Secondary Roads- Cagayan Valley Rd (Magapit-Jct Aparri Airport Sect) - K0570 + 745 - K0575 + 584.10
April 2, 2018 FY 2018 GAA WIN8C02220 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Nat'l Hi-way incl. ROW -
K1727+572 - K1729+770
Physical Target:
CW1: 4.124 Lane Km (Road Widening)
ROW: 19,792.20 sq.m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,262,675.00 (Road Widening)
ROW: P 487,325.00
EAO: P 5,250,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Nat'l Hi-way incl. ROW -
K1727+572 - K1729+270
Physical Target:
CW1: 3.17566 Lane Km (Road Widening)
ROW: 19,792.00 sq.m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,262,675.00 (Road Widening)
ROW: P 487,325.00
EAO: P 5,250,000.00
April 2, 2018 FY 2018 GAA WIN8C02223 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Nat'l Hi-way incl. ROW -
K1729+770 - K1732+220
Physical Target:
CW1: 4.960 Lane Km (Road Widening)
ROW: 23,808.00 sq.m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,183,545.00 (Road Widening)
ROW: P 566,455.00
EAO: P 5,250,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Nat'l Hi-way incl. ROW -
K1729+270 - K1731+360
Physical Target:
CW1: 4.2626 Lane Km (Road Widening)
ROW: 23,808.00 sq.m.
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,183,545.00 (Road Widening)
ROW: P 566,455.00
EAO: P 5,250,000.00
April 2, 2018 FY 2018 GAA WIN8C02219 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Jct Matti (along Davao-Cot. Road) - Jct Aurora (along Digos-Makar Road) Bypass Road, incl. ROW, Davao del Sur
Physical Target:
CW1: 3,186.40 sq.m. (Additional Lane Width)
CW2: 2.100 Lane Km (Construction of Concrete Road)
CW3: 1.336 Lane Km (Road Widening)
ROW: 57,921.478 sq.m.
Allocation:
TOTAL: P 114,583,000.00
CW1: P 25,331,250.00 (Additional Lane Width)
CW2: P 30,748,760.00 (Construction of Concrete Road)
CW3: P 30,290,385.00 (Road Widening)
ROW: P 24,202,200.00
EAO: P 4,010,405.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Jct Matti (along Davao-Cot. Road) - Jct Aurora (along Digos-Makar Road) Bypass Road, incl. ROW, Davao del Sur
Physical Target:
CW1: 1,803.290 sq.m. (Additional Lane Width)
CW2: 2.122 Lane Km (Construction of Concrete Road)
CW3: 3.363 Lane Km (Road Widening)
CW4: 0.675 Lane Km (Rehabilitation of Paved Road)
ROW: 57,921.478 sq.m.
Allocation:
TOTAL: P 114,583,000.00
CW1: P 12,685,346.50 (Additional Lane Width)
CW2: P 22,617,411.94 (Construction of Concrete Road)
CW3: P 44,160,481.15 (Road Widening)
CW4: P 6,907,155.41 (Rehabilitation of Paved Road)
ROW: P 24,202,200.00
EAO: P 4,010,405.00
April 2, 2018 FY - 2018 WIN8F05082 FY - 2018 ( GAA ) DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Network Development - Road Widening - Secondary Roads

FROM:
Mindoro West Coastal Road
K0322+600 - K0324+000,
K0229+833 - K0230+675,
K0229+(-871) - K0229+631,
K0229+757 - K0229+833

CW1: 7.792 lane km (Road Widening)
Allocation: 128,452,000 Php (Total)
123,956,180 Php (Road)
4,495,820 Php (EAO)
TO:
Mindoro West Coastal Road
K0229+(-871) - K0229+631,
K0229+757 - K0229+833,
K0229+833 - K0231+415,
K0322+600 - K0324+000

CW1: 9.248 lane km (Road Widening)
Allocation: 128,452,000 Php (Total)
123,956,180 (Road)
4,495,820 (EAO)
April 2, 2018 FY - 2018 WIN8F05102 FY - 2018 ( GAA ) DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Bridge - Widening of Permanent Bridges

FROM:
Caramay Bridge ( B00205PW) along Puerto Princesa North Road

CW1: 979.567 sq. meters (Widening of Bridge)
Allocation: 130,000,000 Php

TO:
Caramay Bridge (B00205PW) along Puerto Princesa North Road

CW1: 935.616 sq. meters (Widening of Bridge)
Allocation: 130,000,000 Php
April 2, 2018 FY 2018 GAA WIN8C02251 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation
Preventive Maintenance - Secondary Roads
Davao City Div Road -
K1499+132 - K1500+172, K1500+372 - K1502+786
Physical Target:
CW1: 20.376 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Asphalt Overaly)
EAO: P 7,000,000.00

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation
Preventive Maintenance - Secondary Roads
Davao City Div Road -
K1499+132 - K1500+172, K1500+372 - K1502+580
Physical Target:
CW1: 19.508 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Asphalt Overaly)
EAO: P 7,000,000.00
April 2, 2018 FY 2018 GAA WIN8C02250 FY 2018 GAA RA 10964 January 1, 2017 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation
Preventive Maintenance - Secondary Roads
Davao City Div Road -
K1502+786 - K1503+000, K1503+632 - K1504+588, K1504+599 - K1506+743
Physical Target:
CW1: 20.408 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Asphalt Overlay)
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation
Preventive Maintenance - Secondary Roads
Davao City Div Road -
K1502+580 - K1503+000, K1503+632 - K1504+588, K1504+599 - K1506+680
Physical Target
CW1: 20.087 Lane Km (Asphalt Overlay)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Asphalt Overlay)
EAO: P 7,000,000.00
April 2, 2018 FY - 2018 WIN8F05104 GAA FY - 2018 DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

FROM:
El Nido - Jct. New Ibahay Rd.
K0299+525 - K0299+675,
K0300+240 - K0300+260,
K0300+600 - K0300+733,
K0300+900 - K0301+097,
K0301+677 - K0301+827,
K0302+301 - K0302+721

CW1: 16,170 sq. meters ( Construction of Road Slope Protection Structure )
Allocation: 150,000,000 Php

TO:
El Nido - Jct. New Ibahay Rd
K0299+525 - K0299+675,
K0300+640 - K0300+709.2,
K0300+900 - K0301+074,
K0301+367 - K0301+477,
K0301+677 - K0301+827,
K0302+380 - K0302+720

CW1: 8,824.07 sq. meters ( Construction of Road Slope Protection Structure )
Allocation: 150,000,000 Php
April 2, 2018 FY - 2018 WIN8F05101 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and Reliable National Road System

Network Development - Construction of Missing Links/New Roads

FROM:
Palawan Circumferential Road (Latud - Canipaan Section)
Package A, Palawan

CW1: 33 lane km ( Construction of Gravel Road )
Allocation: 150,000,000 Php

TO:
Palawan Circumferential Road (Latud - Canipaan Section)
Package A, Palawan

CW1: 20.96 lane km ( Construction of Gravel Road )
Allocation: 150,000,000 Php
April 2, 2018 FY - 2018 WIN8F05065 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001: Ensure Safe and reliable National Road System

Network Development - Paving of Unpaved Roads -
Tertiary Road

FROM:
Palawan Circum. Rd ( Panalingaan - Tagbita - Latud )
K0258+983 - K0259+001,
K0259+043 - K0259+093,
K0263+216 - K0267+210

CW1: 8.53 lane km ( Paving of Unpaved Road)
Allocation: 150,000,000 Php

TO:
Palawan Circum. Rd ( Panalingaan - Tagbita - Latud )
K0258+983 - K0258+1001,
K0259+043 - K0259+093,
K0263+216 - K0267+242

CW1: 8.53 lane km ( Paving of Unpaved Road )
Allocation: 150,000,000 Php
April 2, 2018 2018 WIN8G01776 WIN8G01776 March 23, 2018 Cordillera Administrative Region CAR - Regional Office
From: Off-Carriageway Improvement - Primary Roads - Kennon Rd - K0216 + 270 - K0216 + 814, K0227 + 000 - K0227 + 068, K0227 + 079 - K0227 + 744, K0234 + 000 - K0235 + 000, K0233+576 - K0233+655; Physical Target: CW1 : 8,415 Square meters, CW2 : 3,035 Square meters; Allocation = Php122,011,000

To: Off-Carriageway Improvement - Primary Roads: Kennon Rd - K0216 + 270 - K0216 + 814, K0217 + 532 - K0217 + 650, K0227 + 000 - K0227 + 068, K0227 + 079 - K0227 + 744, K0234 + 000 - K0235 + 000, K0233+576 - K0233+677; Physical Target: CW1 : 8,531 Square meters, CW2 : 3,282.52 Square meters; Allocation = Php122,011,000
April 2, 2018 2018 WIN8G01775 WIN8G01775 March 23, 2018 Cordillera Administrative Region CAR - Regional Office
From: Construction of Missing Links/ New Roads - Taloy Norte Jct. - San Pascual Brgy. Hall Jct. (Section 7 of BLISTT Outer Ring Circumferential Road) incl. ROW, Bridge and Slope Protection, Tuba, Benguet; Physical Target:ROW : 7,500 Square meters, CW1 : 4.984 Lane Km, CW2 : 2.486 Lane Km, CW3 : 5,033 Square meters, CW4 : 443.60 Square meters; Allocation = Php150,000,000

To: Construction of Missing Links/ New Roads - Taloy Norte Jct. - San Pascual Brgy. Hall Jct. (Section 7 of BLISTT Outer Ring Circumferential Road) incl. ROW, Bridge and Slope Protection, Tuba, Benguet; Physical Target:ROW : 1,500 Square meters, CW1 : 1.7299 Lane Km, CW2 : 2.4731 Lane Km, CW3 : 4,968 Square meters, CW4 : 443.61 Square meters; Allocation = Php150,000,000
March 28, 2018 FY 2018 GAA WIN8C02247 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Nabunturan-Mawab Road, incl. ROW, Compostela Valley
Physical Target:
CW1: 15.612 Lane Km (Construction of Concrete Road)
ROW: 81,632.563 sq.m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 233,530,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 8,750,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Nabunturan-Mawab Road, incl. ROW, Compostela Valley
Physical Target:
CW1: 19.05346 Lane Km (Construction of Concrete Road)
ROW: 81,632.563 sq.m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 233,530,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 8,750,000.00
March 28, 2018 2018 WIN8C02262 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Secondary Roads

FROM:
Surigao – Davao Coastal Rd – K1209+731.5 – K1209+998.6
Project ID No. – P00200252MN
Physical Target – 8,013 Sq.m (Road Slope)
Allocation - Php 150M (Total)
- Php 144.75M (Road Slope)
- Php 5.25M (EAO)

TO:
Surigao – Davao Coastal Rd – K1209+640 – K1210+000
Project ID No. – P00200252MN
Physical Target – 8,013 Sq.m (Road Slope)
Allocation - Php 150M (Total)
- Php 144.75M (Road Slope)
- Php 5.25M (EAO)
March 28, 2018 2018 WIN8C02256 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Network Development - Road Widening – Primary Roads

FROM:
Daang Maharlika (Surigao – Agusan Sect) – K1131 + 500 – K1132+000, K1136+000 – K1136+127, K1136+176 – K1136+300, K1139+330 – K1141+778, K1145+850 – K1146+100, K1146+140 – K1146+390, K1146+450 – K1147+052, K1148+000 – K1148+700
Project ID No. – P00200690MN
Physical Target – 9.966 lane km (Roads)
Allocation - Php 167,355,000.00 (Total)
- Php 161,497,575.00 (Roads)
- Php 5,857,425.00 (EAO)

TO:
Daang Maharlika (Surigao – Agusan Section) (S00339MN)– K1131+500 -K1132+000, K1136+000 – K1136+127, K1136+176 – K1136+300, K1139+330 - K1139+447, K1139+447 – K1141+778, K1148+000 – K1148+700
Project ID No. – P00200690MN
Physical Target – 7.798 lane km (Roads)
Allocation - Php 167,355,000.00 (Total)
- Php 161,497,575.00 (Roads)
- Php 5,857,425.00 (EAO)
March 28, 2018 2018 WIN8C02252 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Network Development - Road Widening – Primary Roads

FROM:
Butuan City – Cagayan de Oro City – Iligan City Road (Agusan – Misamis Or Rd) – K1266+140 – K1268+852, K1268+876 – K1269+122, K1272+000 – K1272+753, K1272+767 – K1273+214
Project ID No. – P00200685MN
Physical Target – 8.312 lane km
Allocation - Php 168,219,000.00 (Total)
- Php 162,331,335.00 (Roads)
- Php 5,887,665.00 (EAO)

TO:
Butuan City – Cagayan de Oro City – Iligan City Road (Agusan – Misamis Or Rd) – K1264+540 – K1267+930
Project ID No. – P00200685MN
Physical Target – 6.760 lane km
Allocation - Php 168,219,000.00 (Total)
- Php 162,331,335.00 (Roads)
- Php 5,887,665.00 (EAO)
March 28, 2018 2018 WIN8C02254 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Network Development - Construction of Bypass and Diversion Roads

FROM:
Cantilan – Madrid Bypass Road (SDCR Alternate Route), incl. ROW, Surigao del Sur
Project ID No. – P00200450MN
Physical Target – 4.572 lane km (Roads)
- 30,000 Sq.M (ROW)
Allocation - Php 130,000,000.00 (Total)
- Php 105,350,000.00 (Concrete Road)
- Php 20,100,000.00 (ROW)
- Php 4,550,000.00 (EAO)

TO:
Cantilan – Madrid Bypass Road (SDCR Alternate Route), incl. ROW, Surigao del Sur
Project ID No. – P00200450MN
Physical Target – 3.126 lane km (Roads)
- 30,000 Sq.M (ROW)
Allocation - Php 130,000,000.00 (Total)
- Php 105,350,000.00 (Concrete Road)
- Php 20,100,000.00 (ROW)
- Php 4,550,000.00 (EAO)

March 28, 2018 2018 WIN8C02261 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Asset Preservation - Preventive Maintenance – Primary Roads

FROM:
Butuan City – Cagayan de Oro – Iligan (Agusan – Misamis Oriental), Butuan City
Project ID No. – P00201565MN
Physical Target – 10.20 Lane Km (Road)
Allocation - Php 150,000,000.00 (Total)
- Php 144,750,000.00 (Road)
- Php 5,250,000.00 (EAO)

TO:
Butuan City – Cagayan de Oro – Iligan (Agusan – Misamis Oriental), Butuan City
Project ID No. – P00201565MN
Physical Target – 8.239 Lane Km (Road)
Allocation - Php 150,000,000.00 (Total)
- Php 144,750,000.00 (Road)
- Php 5,250,000.00 (EAO)
March 28, 2018 2018 WIN8C02255 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Network Development - Road Widening –Secondary Roads

FROM:
Surigao – Davao Coastal Rd – K1428+660 – K1431+365, K1434+910 – K1437+057, K1442+672 - K1443+659, K1434+900 - K1437+057, K1457+096- K1457+654
Project ID No. – P00201585MN
Physical Target – 17.108 Lane Km (Road)
Allocation - Php 250,000,000.00 (Total)
- Php 241,250,000.00 (Road)
- Php 8,750,000.00 (EAO)

TO:
Surigao – Davao Coastal Rd – K1428+660 – K1431+365, K1434+910 – K1437+057, K1442+714 – K1443+044, K1443+073 – K1443+659, K1457+096 – K1457+654
Project ID No. – P00201585MN
Physical Target – 12.652 Lane Km (Road)
Allocation - Php 250,000,000.00 (Total)
- Php 241,250,000.00 (Road)
- Php 8,750,000.00 (EAO)
March 28, 2018 2018 WIN8C02253 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Regional Office XIII
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide – Tertiary Roads

FROM:
Jct Osmeña – Pilar Rd – K0019 +216 – K0019+514, K0019+565 – K0020+000
Project ID No. – P00200286MN
Physical Target – 9,690 Sq.m (Road Slope)
Allocation - Php 176,400,000.00 (Total)
- Php 170,226,000.00 (Road Slope)
- Php 6,174,000.00 (EAO)

TO:
Jct Osmeña – Pilar Rd – K0019 +216 – K0019+460, K0019+565 – K0019+615
Project ID No. – P00200286MN
Physical Target – 9,423 Sq.m (Road Slope)
Allocation - Php 176,400,000.00 (Total)
- Php 170,226,000.00 (Road Slope)
- Php 6,174,000.00 (EAO)
March 28, 2018 2018 WIN8C02257 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Sur 1st District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

FROM:
NJR Bah-Bah-Talacogon Rd - (S00460MN) K1294 + (-300) - K1294 + (-280), K1294 + (-300) - K1294 + (-240), K1294 + 058 - K1294 + 120, K1294 + 240 - K1294 + 254, K1294 + 280 - K1294 + 340, K1294 + 460 - K1294 + 500 , (S00469MN) K1311 + (-600) - K1311 + (-566.8)
Physical Target: 3,294.40 square meters (Road Slope)
Amount : Php 34,000,000.00 (Total)
:Php 32,810,000.00 (Road Slope)
:Php 1,190,000.00 (EAO)

TO:
NRJ Bahbah-Talacogon Road – K1294+460.00-K1294+500.00, K1294+601.50-K1294+623.10, K1294+674.70-K1294+697.50, K1294+909.80-K1294+932.20,
K1311+(-600.00)-K1311+(-570.00)
Physical Target: 2,052.00 square meters (Road Slope)
Amount : Php 34,000,000.00 (Total)
:Php 32,810,000.00 (Road Slope)
:Php 1,190,000.00 (EAO)
March 28, 2018 2018 WIN8C02257 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Sur 1st District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

FROM:
NJR Bah-Bah-Talacogon Rd - (S00460MN) K1294 + (-300) - K1294 + (-280), K1294 + (-300) - K1294 + (-240), K1294 + 058 - K1294 + 120, K1294 + 240 - K1294 + 254, K1294 + 280 - K1294 + 340, K1294 + 460 - K1294 + 500 , (S00469MN) K1311 + (-600) - K1311 + (-566.8)
Physical Target: 3,294.40 square meters (Road Slope)
Amount : Php 34,000,000.00 (Total)
:Php 32,810,000.00 (Road Slope)
:Php 1,190,000.00 (EAO)

TO:
NRJ Bahbah-Talacogon Road – K1294+460.00-K1294+500.00, K1294+601.50-K1294+623.10, K1294+674.70-K1294+697.50, K1294+909.80-K1294+932.20,
K1311+(-600.00)-K1311+(-570.00)
Physical Target: 2,052.00 square meters (Road Slope)
Amount : Php 34,000,000.00 (Total)
:Php 32,810,000.00 (Road Slope)
:Php 1,190,000.00 (EAO)
March 28, 2018 2018 WIN8C02259 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Sur 1st District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

FROM:
Butuan City-Talacogon-Loreto-Veruela-Sta Josefa Rd –
K1350+990-K1350+1030, K1351+050-K1351+113, K1351+090-K1351+100
Physical Target: 1,811.790 square meters (Road Slope)
Amount : Php 20,000,000.00 (Total)
: Php 19,600,000.00 (Road Slope)
: Php 400,000.00 (EAO)

TO:
Butuan City-Talacogon-Loreto-Veruela-Sta Josefa Rd –
K1350+990.00 - K1350+1030, K1351+050.00 - K1351+112.80, K1351+090.00 - K1351+112.80
Physical Target: 1,884.00 square meters (Road Slope)
Amount : Php 20,000,000.00 (Total)
: Php 19,600,000.00 (Road Slope)
: Php 400,000.00 (EAO)
March 28, 2018 FY 2018 GAA WIN8C02245 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Secondary Roads
Asuncion-San Isidro-Laak-Veruela Rd incl. ROW -
K1472+822 - K1477+000, K1477+320 - K1478+008
Physical Target:
CW1: 9.732 Lane Km (Road Widening)
ROW: 50,119.80 sq.m.
Allocation:
TOTAL: P 182,290,000.00
CW1: P 171,393,650.00 (Road Widening)
ROW: P 4,516,200.00
EAO: P 6,380,150.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Secondary Roads
Asuncion-San Isidro-Laak-Veruela Rd incl. ROW -
K1472+822 - K1477+000, K1477+320 - K1478+857
Physical Target:
CW1: 11.418 Lane Km (Road Widening)
ROW: 50,119.80 sq.m.
Allocation:
TOTAL: P 182,290,000.00
CW1: P 171,393,650.00 (Road Widening)
ROW: P 4,516,200.00
EAO: P 6,380,150.00
March 28, 2018 2018 WIN8C02260 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 1st District Engineering Office
Local Infrastructure Program - Buildings and Other Structures

FROM:
Construction of Barangay Hall, Brgy. Pananay-an, San Francisco, Surigao del Norte
Physical Target: - 1 Number of Bldg
Allocation: - Php 2,500,000.00 (Total)
- Php 2,475,000.00 (Building)
- Php 25,000.00 (EAO)

TO:
Construction of Barangay Hall, Brgy. Pananay-an, Placer, Surigao del Norte
Physical Target: - 1 Number of Bldg
Allocation: - Php 2,500,000.00 (Total)
- Php 2,475,000.00 (Building)
- Php 25,000.00 (EAO)
March 28, 2018 2018 WIN8C02258 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Norte 1st District Engineering Office
Protect Lives and Properties Against Major Floods - Flood Management Program

FROM:
Construction of Flood Control Structure along the River Banks of Lahi, Sico-sico and Camam-onan, Surigao del Norte
Physical Target: - 400 lineal meters (Flood Control)
Allocation - Php 50,000,000.00 (Total)
- Php 49,000,000.00 (Flood Control)
- Php 1,000,000.00 (EAO)

TO:
Construction of Flood Control Structure along the River Banks of Lahi, Sico-sico and Camam-onan, Surigao del Norte
Physical Target: - 484 lineal meters (Flood Control)
Allocation - Php 50,000,000.00 (Total)
- Php 49,000,000.00 (Flood Control)
- Php 1,000,000.00 (EAO)
March 28, 2018 FY 2018 GAA WIN8C02240 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Baganga Diversion Road, incl. ROW, Davao Oriental
Physical Target:
CW1: 4.960 Lane Km (Construction of Gravel Road)
ROW: 52,666.667 sq.m.
Allocation:
TOTAL: P 115,000,000.00
CW1: P 95,728,000.00 (Construction of Gravel Road)
ROW: P 15,247,000.00
EAO: P 4,025,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Baganga Diversion Road, incl. ROW, Davao Oriental
Physical Target:
CW1: 10.338 Lane Km (Construction of Gravel Road)
ROW: 52,666.667 sq.m.
Allocation:
TOTAL: P 115,000,000.00
CW1: P 95,728,000.00 (Construction of Gravel Road)
ROW: P 15,247,000.00
EAO: P 4,025,000.00
March 28, 2018 FY 2018 GAA WIN8C02241 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Montevista (Jct. Mayaon)-Laak Diversion Rd, incl. ROW, Compostela Valley
Physical Target:
CW1: 9.600 Lane Km (Construction of Concrete Road)
ROW: 81,632.563 sq.m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 185,280,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 7,000,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Bypass and Diversion Roads
Montevista (Jct. Mayaon)-Laak Diversion Rd, incl. ROW, Compostela Valley
Physical Target:
CW1: 10.51846 Lane Km (Construction of Concrete Road)
ROW: 81,632.563 sq.m.
Allocation:
TOTAL: P 250,000,000.00
CW1: P 185,280,000.00 (Construction of Concrete Road)
ROW: P 7,720,000.00
EAO: P 7,000,000.00
March 28, 2018 FY 2018 GAA WIN8C02246 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Davao-Cotabato Rd (Davao City-Jct. Digos Sect.) incl. ROW -
K1544+047 - K1548+320
Physical Target:
CW1: 8.598 Lane Km (Road Widening)
ROW: 36,973.078 sq.m.
Allocation:
TOTAL: P 188,214,000.00
CW1: P 170,097,655.00 (Road Widening)
ROW: P 11,528,855.00
EAO: P 6,587,490.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Davao-Cotabato Rd (Davao City-Jct. Digos Sect.) incl. ROW -
K1544+047 - K1548+320
Physical Target:
CW1: 8.544 Lane Km (Road Widening)
ROW: 36,973.078 sq.m.
Allocation:
TOTAL: P 188,214,000.00
CW1: P 170,097,655.00 (Road Widening)
ROW: P 11,528,855.00
EAO: P 6,587,490.00
March 28, 2018 FY 2018 GAA WIN8C02244 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Secondary Roads
Compostela-Cateel Rd (Davao Or Side) incl. ROW -
K1522+404 - K1556+873
Physical Target:
CW1: 8.676 Lane Km (Construction of Concrete Road)
ROW: 34,714.286 sq.m.
Allocation:
TOTAL: P 135,000,000.00
CW1: P 125,585,100.00 (Construction of Concrete Road)
ROW: P 4,689,900.00
EAO: P 4,725,000.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Secondary Roads
Compostela-Cateel Rd (Davao Or Side) incl. ROW -
K1522+404 - K1556+873
Physical Target:
CW1: 8.933 Lane Km (Const. of Concrete Road)
ROW: 34,714.286 sq.m.
Allocation:
TOTAL: P 135,000,000.00
CW1: P 125,585,100.00 (Construction of Concrete Road)
ROW: P 4,689,900.00
EAO: P 4,725,000.00
March 28, 2018 FY 2018 GAA WIN8C02243 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW -
K1447+040 - K1450+134
Physical Target:
CW1: 6.160 Lane Km (Road Widening)
ROW: 41,888.00 sq.m.
Allocation:
TOTAL: P 294,076,000.00
CW1: P 206,583,340.00 (Road Widening)
ROW: P 77,200,000.00
EAO: P 10,292,660.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Road Widening - Primary Roads
Daang Maharlika (MN) incl. ROW -
K1446+000 - K1450+134
Physical Target:
CW1: 8.260 Lane Km (Road Widening)
ROW: 41,888.00 sq.m.
Allocation:
TOTAL: P 294,076,000.00
CW1: P 206,583,340.00 (Road Widening)
ROW: P 77,200,000.00
EAO: P 10,292,660.00
March 28, 2018 FY 2018 GAA WIN8C02236 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Missing Links/New Roads
Davao-Bukidnon Highway (Calinan Poblacion Portion) to Dalagdag-Fatima National Road to Panabo, incl. ROW, Davao del Norte, Davao City
Physical Target:
CW1: 6.820 Lane Km (Construction of Concrete Road)
ROW: 34,099.50 sq.m.
Allocation:
TOTAL: P 136,898,00,.00
CW1: P 131,624,070.00 (Construction of Concrete Road)
ROW: P 482,500.00
EAO: P 4,791,430.00

TO: OO1: Ensure Safe and Reliable National Road System - Network Development Program
Construction of Missing Links/New Roads
Davao-Bukidnon Highway (Calinan Poblacion Portion) to Dalagdag-Fatima National Road to Panabo, incl. ROW, Davao del Norte, Davao City
Physical Target:
CW1: 10.895 Lane Km (Construction of Concrete Road)
ROW: 34,099.50 sq.m.
Allocation:
TOTAL: P 136,898,000.00
CW1: P 131,624,070.00 (Construction of Concrete Road)
ROW: P 482,500.00
EAO: P 4,791,430.00
March 28, 2018 FY 2018 GAA WIN8C02249 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
New Corella-Guadalupe-Del Monte Connecting New Corella Overland Transport Terminal In Support of Cacao, Coconut, Banana and Rubber Industry, New Corella, Davao del Norte
Physical Target:
CW1: 9.142 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
New Corella-Guadalupe-Del Monte Connecting New Corella Overland Transport Terminal In Support of Cacao, Coconut, Banana and Rubber Industry, New Corella, Davao del Norte
Physical Target:
CW1: 12.1206 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 200,000,000.00
CW1: P 193,000,000.00 (Construction of Concrete Road)
EAO: P 7,000,000.00
March 28, 2018 FY 2018 GAA WIN8C02248 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
NRJ Surigao Davao Coastal Road to Hijo Cadastral Connecting Tagum City Overland Terminal in Support of Business Processing Outsourcing, Coconut Farm and Renewable Energy Industries, Tagum City, Davao del Norte
Physical Target:
CW1: 6.400 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 140,000,000.00
CW1: P 135,100,000.00 (Construction of Concrete Road)
EAO: P 4,900,000.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
NRJ Surigao Davao Coastal Road to Hijo Cadastral Connecting Tagum City Overland Terminal in Support of Business Processing Outsourcing, Coconut Farm and Renewable Energy Industries, Tagum City, Davao del Norte
Physical Target:
CW1: 7.916 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 140,000,000.00
CW1: P 135,100,000.00 (Construction of Concrete Road)
EAO: P 4,900,000.00
March 28, 2018 FY 2018 GAA WIN8C02242 FY 2018 GAA RA 10964 January 2, 2018 Region XI Regional Office XI

MODIFICATION:

FROM: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Poblacion-Brgy. Dalawinon Connecting to Brgy. Kasuga in Support of Meat Processing, Magsaysay, Davao del Sur
Physical Target:
CW1: 7.140 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 121,370,000.00
CW1: P 117,122,050.00 (Construction of Concrete Road)
EAO: P 4,247,950.00

TO: Convergence and Special Support Program
Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Brgy. Poblacion-Brgy. Dalawinon Connecting to Brgy. Kasuga in Support of Meat Processing, Magsaysay, Davao del Sur
Physical Target:
CW1: 9.756 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 121,370,000.00
CW1: P 117,122,050.00 (Construction of Concrete Road)
EAO: P 4,247,950.00

March 27, 2018 2018 WIN8C02184 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) incl. ROW –
K1197+472-K1197+533,
K1199+322-K1200+700,
K1200+950-K1201+000,
K1201+050-K1202+000,
K1203+238-K1203+576
Physical Target: - 4.562 lane km.(Road)
- 16,232.40 square meter (ROW)
Allocation - Php 79.968M (Total)
- Php 72.53M (Road)
- Php 4.64M (ROW)
- Php 2.798 (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) incl. ROW –
K1199+422-K1200+700, K1201+370-K1202+000,
K1203+238-K1203+577
Physical Target: - 4.500 lane km.(Road)
- 52,425 square meter (ROW)
Allocation - Php 79.968M (Total)
- Php 67.17M (Road)
- Php 10.0M (ROW)
- Php 2.798 (EAO)
March 27, 2018 2018 WIN8C02183 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1194+092-K1196+733, K1196+751-K1197+472
Physical Target: - 6.796 lane km.(Road)
- 20,388 square meter (ROW)
Allocation - Php 100.0M(Total)
- Php 91.5M (Road)
- Php 5.0M (ROW)
- Php 3.50M (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1192+530 – K1193+573, K1194+120 – K1194+624
Physical Target: - 3.068 lane km.(Road)
- 32,365.40 square meter (ROW)
Allocation - Php 100.0M(Total)
- Php 76.50M (Road)
- Php 20.0M (ROW)
- Php 3.50M (EAO)
March 27, 2018 2018 WIN8C02187 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development – Road Widening - Tertiary Road

FROM:
Agusan-Malaybalay Rd. Incl. ROW – K1271+834 - K1272+535, K1272+775 – K1274+104
Physical Target: - 4.006 lane km.(Road)
- 28,042 square meter (ROW)
Allocation - Php 60.09M (Total)
- Php 53.49M (Road)
- Php 4.50M (ROW)
- Php 2.10M (EAO)

TO:
Agusan-Malaybalay Rd. Incl. ROW - K1271+984 - K1272+445.60, K1273+000 – K1274+031.96
Physical Target: - 2.933 lane km.(Road)
- 62.10 square meter (ROW)
Allocation - Php 60.09M (Total)
- Php 57.98M (Road)
- Php 0.01M (ROW)
- Php 2.10M (EAO)
March 27, 2018 2018 WIN8C02192 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Road

FROM:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or. Road) - K1266+222-K1266+543, K1272+914-K1273+000, K1273+000-K1273+287, K1273+411-K1274+000, K1275+157-K1275+446
Physical Target: - 2.867 Lane Km
Allocation - Php 32.835M (Total)
- Php 32.178M
- Php 0.657M (EAO)

TO:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or. Road) - K1266+222-K1266+562, K1272+914-K1274+000
Physical Target: - 2.862 Lane Km
Allocation - Php 32.835M (Total)
- Php 32.178M
- Php 0.657M (EAO)
March 27, 2018 2018 WIN8C02182 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Road

FROM:
Butuan-Cagayan de Oro-Iligan Road (Agusan-Misamis Or. Rd.) Incl. ROW-K1265+527-K1265+642, K1279+400-K1279+500
Physical Target: - 6,150 square meter (Slope Protection)
- 2,020 square meter (ROW)
Allocation - Php 39.0M (Total)
- Php 37.82M (Slope Protection)
- Php 0.40M (ROW)
- Php 0.78M (EAO)

TO:
Butuan-Cagayan de Oro-Iligan Road (Agusan-Misamis Or. Rd.) Incl. ROW-K1265+527 – K1265+652, K1279+440 – K1279+451.60
Physical Target: - 2,925.87 square meter (Slope)
- 50.51 square meter (ROW)
Allocation - Php 39.0M (Total)
- Php 38.21M (Slope Protection)
- Php 0.01M (ROW)
- Php 0.78M (EAO)
March 27, 2018 2018 WIN8C02191 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Road

FROM:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1179+600-K1180+000
Physical Target: - 1,880 square meter (Slope Protection)
- 4,090 square meter (ROW)
Allocation - Php 15.0M (Total)
- Php 13.0M (Slope Protection)
- Php 1.70M (ROW)
- Php 0.30M (EAO)

TO:
Daang Maharlika (Surigao-Agusan Sect.) Incl. ROW – K1179+600-K1179+651
Physical Target: - 1,161.27 square meter (Slope)
- 4,090 square meter (ROW)
Allocation - Php 15.0M (Total)
- Php 13.0M (Slope Protection)
- Php 1.70M (ROW)
- Php 0.30M (EAO)
March 27, 2018 2018 WIN8C02206 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Network Development - Paving of Unpaved Roads - Tertiary Roads

FROM:
Buenavista-Bunaguit Rd. incl. ROW - (S00396MN) K1271+145 – K1271+919, (S00475MN) K1273+463 – K1273+675, (S00390MN) CHAINAGE 000-CHAINAGE 120
Physical Target: - 2.212 lane km.(Road)
- 7,410.20 square meter (ROW)
Allocation - Php 33.0M (Total)
- Php 31.54M (Road)
- Php 0.80M (ROW)
- Php 0.66M (EAO)


TO:
Buenavista-Bunaguit Rd. incl. ROW - (S00396MN) K1271+178 – K1271+919, (S00475MN) K1273+463 – K1273+675, (S00390MN) CHAINAGE 0 - CHAINAGE 120
Physical Target: - 2.146 lane km.(Road)
- 92.59 square meter (ROW)
Allocation - Php 33.0M (Total)
- Php 32.33M (Road)
- Php 0.01M (ROW)
- Php 0.66M (EAO)
March 27, 2018 2018 WIN8C02186 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Agusan del Norte District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Banza to Magallanes Road leading to Centennial Tree and Beaches, Magallanes, Agusan del Norte
Physical Target: - 3.60 Lane Km. (Concrete Road)
Allocation - Php 81.0M (Total)
- Php 78.17M (Conc. Road)
- Php 2.83M (EAO)

TO:
Banza to Magallanes Road leading to Centennial Tree and Beaches, Magallanes, Agusan del Norte
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 81.0M (Total)
- Php 78.17M (Conc. Road)
- Php 2.83M (EAO)
March 27, 2018 2018 WIN8C02190 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Libuacan Cold Spring, Brgy. Carpenita, Tagbina, Surigao del Sur
Physical Target: - 1.181 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Conc. Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Libuacan Cold Spring, Brgy. Carpenito, Tagbina, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Conc. Road)
- Php 0.40M (EAO)
March 27, 2018 2018 WIN8C02185 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Caguyao Mangrove Site, Brgy. Caguyao, Bislig City, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Gravel Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Gravel Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Caguyao Mangrove Site, Brgy. Caguyao, Bislig City, Surigao del Sur
Physical Target: - 1.60 Lane Km. (Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Concrete Road)
- Php 0.40M (EAO)
March 27, 2018 2018 WIN8C02189 FY 2018 GAA RA 10964 December 19, 2017 Region XIII Surigao del Sur 2nd District Engineering Office
Construction/Improvement of Access Roads leading to Declared Tourism Destinations

FROM:
Access Road leading to Panaraga White Beach Resort, Brgy. Gamut, Barobo, Surigao del Sur
Physical Target: - 1.48 Lane Km. (Reconstruction from Paved to Concrete)
Allocation - Php 20.0M (Total)
- Php 19.60M (Road)
- Php 0.40M (EAO)

TO:
Access Road leading to Panaraga White Beach Resort, Brgy. Gamut, Barobo, Surigao del Sur
Physical Target: - 1.48 Lane Km. (Construction of Concrete Road)
Allocation - Php 20.0M (Total)
- Php 19.60M (Road)
- Php 0.40M (EAO)
August 25, 2017 DA CY 2017 S-06-17-0441 SR2017-03-006885 March 18, 2017 Region VII Cebu 3rd District Engineering Office
REALIGNMENT:

From: Concreting of Sitio Bangkal Brgy. Sibago - Sitio Laka Guimbawian FMR, Pinamungajan, Cebu

To: Concreting of Sitio Danawan, Sibago to Alpaco FMR, Pinamungajan, Cebu.
August 25, 2017 DA CY 2017 S-06-17-0441 SR2017-03-006886 March 18, 2017 Region VII Cebu 3rd District Engineering Office
REALIGNMENT:

From: Concreting of Sitio Tagaytay, Brgy. Binabag, Pinamungajan, Cebu.


To: Concreting of Sitio Pundol to Sitio Sangil FMR, Brgy. Binabag, Pinamungajan, Cebu.
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Activity Center/Covered Court, Pio V. Corpuz Municipality, Masbate
(Construction of Other Building)
Physical Target: 1 Bldg.
Unit Cost: P5,000/bldg.
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Two (2) Storey Multipurpose Building of Municipality of Pio V. Corpuz Municipality, Masbate
(Construction of Other Building)
Physical Target: 1 Bldg.
Unit Cost: P5,000/bldg.
Estimated Cost: PhP 5.0M
August 17, 2017 2017 WIN7E01073 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Building (Covered Court), Tunga, Esperanza, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Building (Covered Court), Putingbato, Esperanza, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 WIN7E01096 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Covered Court (MPB), Brgy. Naboctot, Placer, Masbate
(Construction of Multi- Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally Funded Project: Local Infrastructure Program,
Buildings and Other Structures, Multipurpose Facilities, Construction of Multi-Purpose Covered Court (MPB), Brgy. Calabad, Dimasalang, Masbate
(Construction of Multipurpose Building)
Physical Target: 1 Bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 WIN7E01037 FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
Locally-Funded Projects: Local Infrastructure Program,
Buildings and Other Structure - Multipurpose Facilities, Construction of Mufti-purpose Covered Court
Brgy. Sto. Niño, Cataingan, Masbate
(Construction of Multi-Purpose Building)
Physical Target: 1 bldg.
Unit Cost: P2,000/bldg.
Allocation: PhP 2.0M

As MODIFIED:
Locally-Funded Projects: Local Infrastructure Program,
Buildings and Other Structure - Multipurpose Facilities, Construction of Mufti-purpose Covered Court
Brgy. G. Aliño, Dimasalang, Masbate
(Construction of Multi-Purpose Building)
Physical Target: 1 bldg.
Unit Cost: P2,000/bldg.
Estimated Cost: PhP 2.0M
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Buenavista, Uson, Masbate
(Construction of Flood Mitigation Structure)
Physical Target: -
Unit Cost: P20,000/Lm.
Allocation: PhP 20.0M

As MODIFIED:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Magsaysay Uson, Masbate Sta.0+587 - Sta.1+037
(Construction of Flood Mitigation Structure)
Physical Target: 450 Lm.
Unit Cost: P20,000/Lm
Estimated Cost: PhP 20.0M
August 17, 2017 2017 No Reference Number FY 2017 GAA RA 10924 December 29, 2016 Region V Masbate 2nd District Engineering Office
As per GAA:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Buenavista, Uson, Masbate
(Construction of Flood Mitigation Structure)
Physical Target: -
Unit Cost: P20,000/Lm.
Allocation: PhP 20.0M

As MODIFIED:
MFO 2: Flood Management Services - Construction/
Maintenance of Flood Mitigation Structures and
Drainage Systems, Construction of Buenavista River Flood Control, Brgy. Magsaysay Uson, Masbate Sta.0+587 - Sta.1+037
(Construction of Flood Mitigation Structure)
Physical Target: 450 Lm.
Unit Cost: P20,000/Lm
Estimated Cost: PhP 20.0M
August 9, 2017 2017 165003014600182 FY 2017 GAA January 1, 2017 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation of National Roads - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary - Rehabilitation / Major Repair of Road Slope Protection Structure - Jct. Pinagpanaan - Rizal - Pantabangan Rd -
K0160+357.40 - K0160+371.80, K0160+379.10 - K0160+418.10, K0160+496.00 - K0160+523.30, K0160+529.20 - K0160+547.00, K0160+900.00 - K0160+951.50

(Rehabilitation / Major Repair of Slope Protection Structure)
August 9, 2017 2017 292003020402662 FY 2017 GAA January 1, 2017 Region III Zambales 1st District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Slope Protection / Flood Control at San Vicente River (Upstream), Sta. 0+240 - Sta. 0+377, Candelaria, Zambales

(Construction of Slope Protection Structure)
August 9, 2017 2017 103004010311211 FY 2017 GAA January 1, 2017 Region III Zambales 1st District Engineering Office
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Tourism Information Center Building, Pundaquit, San Antonio, Zambales
August 8, 2017 2017 WIN7F05060 FY 2017 GAA January 1, 2017 Region III Bataan 2nd District Engineering Office
Network Development - Improvement/Widening of National Roads - Tertiary - Balanga Poblacion Rd including RROW (S01336LZ) Chainage 0 - Chainage 500
(CW-1 Road Widening)
(ROW Acquisition)
August 2, 2017 2017 WIN7E01616 FY 2017 GAA RA 10924 December 29, 2016 Region V Camarines Norte District Engineering Office
As per GAA:
Locally-Funded Projects: Local Infrastructure Program: Roads and Bridges: Local Roads: Concreting / Construction of Iberica Road in Brgy. Iberica, Labo, Camarines Norte (Construction of Concrete Road)
Physical Target: 0.40 lane.km
Unit Cost: P5.0M/lane-km
Allocation: P2.0M

As MODIFIED:
Locally-Funded Projects: Local Infrastructure Program: Roads and Bridges: Local Roads: Concreting / Construction of Iberica Road in Brgy. Iberica, Labo, Camarines Norte (Construction of Concrete Road)
Physical Target: 0.742 lane.km
Unit Cost: P2,695.42M/lane-km
Estimated Cost: P2.0M

August 2, 2017 2017 WIN7E01576 FY 2017 GAA RA 10924 December 29, 2016 Region V Camarines Norte District Engineering Office
As per GAA:
Locally Funded Projects - Roads and Bridges - Local Roads : Construction of road, Barangay Il, Daet, Camarines Norte
(Construction of Concrete Road)
Physical Target: -
Unit Cost (P'000): -
Allocation Cost (P'000): P2,000

As MODIFIED:
Locally Funded Projects - Roads and Bridges - Local Roads : Construction of road, Barangay Il,
Daet, Camarines Norte
(Construction of Concrete Road)
Physical Target: 0.57
Unit Cost (P'000): P3,509/lane-km
Estimated Cost (P'000): P2,000
July 26, 2017 2017 WIN7E01032 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon District Engineering Office
As per GAA:
MFO 2 - Flood Management Services: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of Milagrosa River Control, Sorsogon City, Sorsogon
(Construction of Flood Mitigation Structure)
Physical Target: 780 Lm
Unit Cost: P44.87/Lm
Allocation: PhP35.0M

As MODIFIED:
MFO 2 - Flood Management Services: Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems, Construction of Milagrosa River Control, Castilla, Sorsogon
(Construction of Flood Mitigation Structure)
Physical Target: 780 Lm
Unit Cost: P44.87/Lm
Estimated Cost: PhP35.0M
July 26, 2017 2017 WIN7E01058 FY 2017 GAA RA 10924 December 29, 2016 Region V Sorsogon District Engineering Office
As per GAA:
MFO 1: National Road Network Services - Asset
Preservation of National Roads, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/Highway Development and Management - 4 (HDM-4) Tertiary, Reconstruction from Concrete to Concrete, Jct Donsol-Banuang Gurang Rd - (S04433LZ)
K0578+800 - K0579+732, K0580+604 - K0580+906, K0583+540 - K0584+423,
K0585+046 - K0585+333 (Rehabilitation of Concrete Road)
Physical Target: 4.6 Lm
Unit Cost: P10,434.78/Lm
Allocation: PhP 48.0M

As MODIFIED:
MFO 1: National Road Network Services - Asset
Preservation of National Roads, Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including drainage based on Pavement Management System/Highway Development and Management - 4 (HDM-4) Tertiary, Reconstruction from Concrete to Concrete, Jct Donsol-Banuang Gurang Rd - (S04433LZ) - K0578+800 - K0579+732, K0580+604 - K0580+906, K0583+540 - K0584+832 (Rehabilitation of Concrete Road)
Physical Target: 2,844 Lm
Unit Cost: P16,877.64/Lm
Estimated Cost: PhP 48.0M
July 25, 2017 CY 2017 WIN7F05033 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Palawan 3rd District Engineering Office
as MODIFIED:
Locally-Funded Projects
- Local Infrastructure Program
- Buildings and Other Structures
- Multipurpose/Facilities:
Construction of Multi-Purpose Building,
Barangay Bancao-Bancao, Puerto Princesa City
1 Bldg.
Php 3.00 Million
July 25, 2017 CY 2017 WIN7F05047 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Marinduque District Engineering Office
as MODIFIED:
Locally-Funded Projects
- Local Infrastructure Program
- Roads and Bridges :
National Roads:
- Road Opening of the Missing Gaps at
Dr. Damian Reyes Road ( Boac Side )
K0027+645 - K0028+056.5
L = 0.823 lane km
Php = 100.00 Million
( Road Opening )
July 25, 2017 CY 2017 UACS: 165003015700149 GAA CY 2017 RA 10924 December 29, 2016 Region IV-B Palawan 2nd District Engineering Office
as MODIFIED:
MF01 - National Road Network Services
- Road Upgrading ( Unpaved to Paved )
based on Gravel Road Strategies,
Traffic benchmark for Upgrading to
Paved Road Standards (HDM-4 Project Analysis)
- Secondary Road:
Road Upgrading
Gravel to Paved
Aramaywan - Berong - Pto. Princesa Road
L = 4.211 lane km
Php = 100.00 Million
July 25, 2017 2017 WIN7F04906 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - School Buildings - Construction of Two Classroom Building, Victory Village Elementary School, Victory Village, Legazpi City, Albay
Physical Target: 2 Classroom
Unit Cost: P1.875M/Classroom
Allocation: PhP 3.750M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - School Buildings - Construction of Three Classroom Building, Victory Village Elementary School, Victory Village, Legazpi City, Albay
(Construction of Classrooms)
Physical Target: 3 Classroom
Unit Cost: P1.250M/Classroom
Estimated Cost: PhP 3.750M
July 25, 2017 2017 WIN7F05003 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Peñafrancia, Daraga, Albay
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Villahermosa, Daraga, Albay
(Construction of Multi-Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Estimated Cost: PhP 5.0M
July 25, 2017 2017 WIN7F04957 FY 2017 GAA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, Brgy. Bonot, Legazpi City (Albay)
Physical Target:
Unit Cost:
Allocation: PhP 5.0M

As MODIFIED:
Locally Funded Projects, Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities - Construction of Multi-Purpose Building, School Division Office (SDO), Rawis, Legazpi City (Construction of Multi-Purpose Building)
Physical Target: 1 Bldg.
Unit Cost: P5.0M/Bldg.
Estimated Cost: PhP 5.0M
July 25, 2017 2017 WIN7F04930 FY 2017 GAA RA 10924 December 29, 2016 Region V Albay 2nd Engineering Office
As per GAA:
MFO-1 National Road Network Services, Network Development-Improvement/Widening of National Roads - Secondary - Road Widening - Daang Maharlika Jct - Legazpi - Sto Doming - Tabaco - Camarines Sur Bdry Rd including RROW - K0534+000 - K0534+300
Physical Target:
CW1 - Road Widening - 0.60 Lane Km
ROW - ROW Acquisition - 2,070 Sq.m.
Unit Cost:
CW1 - Road Widening - P12.458M/Lane Km
ROW - ROW Acquisition - P13.30T/Sq.m.
Allocation: PhP 35.0M

As MODIFIED:
MFO-1 National Road Network Services, Network Development-Improvement/Widening of National Roads - Secondary - Road Widening - Daang Maharlika Jct - Legazpi - Sto Doming - Tabaco - Camarines Sur Bdry Rd including RROW - K0534+000 - K0534+360
Physical Target:
CW1 - Road Widening - 0.720 Lane Km
ROW - ROW Acquisition - 1,444 Sq.m.
Unit Cost:
CW1 - Road Widening - P22.199M/Lane Km
ROW - ROW Acquisition - P13.17T/Sq.m.
Estimated Cost: PhP 35.0M
July 25, 2017 FY 2017 WIN7F04991 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 1: National Road Network Services- Network Development - Off- Carriageway Improvement including drainage- Tertiary Roads- Benguet-Nueva Vizcaya Rd - K0298 + 853 - K0304 + 000 ; Physical Target = 4,854 Sq.m.

To: MFO 1: National Road Network Services- Network Development - Off- Carriageway Improvement including drainage- Tertiary Roads- Benguet-Nueva Vizcaya Rd - K0298 + 853 - K0304 + 000 ; Physical Target = 8,000 Sq.m.
July 25, 2017 FY 2017 WIN7F04978 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 1: National Road Network Services- Construction and Maintenance of Bridges along National Roads - Replacement of Bridges (Temporary to Permanent)- Batuan Br. (B04275LZ) along Asin (Km 8)-Nangalisan-San Pascual, Tuba, Benguet-La Union Bdry Rd ; Physical Target = 286.20 Sq.m.

To: MFO 1: National Road Network Services- Construction and Maintenance of Bridges along National Roads - Replacement of Bridges (Temporary to Permanent)- Batuan Br. (B04275LZ) along Asin (Km 8)-Nangalisan-San Pascual, Tuba, Benguet-La Union Bdry Rd ; Physical Target =211.788 Sq.m.
July 25, 2017 FY 2017 WIN7F04992 FY 2017 APPROVED MODIFICATION June 19, 2017 Cordillera Administrative Region Benguet 1st District Engineering Office
From: MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Balili Flood Control, La Trinidad, Benguet ; Physical Target = 540 Lm

To: MFO 2: Flood Management Services- Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems- Construction of Balili Flood Control, La Trinidad, Benguet ; Physical Target = 250.40 Lm

Pages