Civil Works - Awarded Contracts





A) Date Entered in Civil Works Registry B) Contract ID C) Contract Name D) Implementing Office 1) Awarded Contractor 2) Awarded Amount 3) Extent Of Participation % 4) Notice to Proceed Date
A) April 16, 2024
B) 24OF0164
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. CULIAT (PHASE 2), QUEZON CITY
D) Quezon City 1st District Engineering Office
1) JYBL CORPORATION (FORMERLY: JYBL CONSTRUCTION AND TR
2) 39,186,832.04
3) 100
4) 4/30/2024
A) April 16, 2024
B) 24OB0288
C) CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE I)
D) Metro Manila 1st District Engineering Office
1) RVR3 CONSTRUCTION SUPPLY AND SERVICES
2) 88,779,589.60
3) 100
4) 6/4/2024
A) April 16, 2024
B) 24OB0294
C) REHABILITATION OF ROAD AT BARANGAY MAHARLIKA, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS
2) 8,974,601.67
3) 100
4) 6/4/2024
A) April 16, 2024
B) 24OB0292
C) REHABILITATION OF ROAD AT BARANGAY CENTRAL BICUTAN, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) B. VALENCERINA TRADING AND CONSTRUCTION
2) 8,974,575.22
3) 100
4) 6/6/2024
A) April 16, 2024
B) 24OA0084
C) CONSTRUCTION OF PANGHULO BARANGAY HALL, PANGHULO, MALABON CITY
D) Malabon-Navotas District Engineering Office
1) J. SIMEON CONSTRUCTION
2) 9,699,120.46
3) 100
4) 5/7/2024
A) April 16, 2024
B) 24OA0089
C) MAINTENANCE, REPAIR AND REHABILITATION OF INFRASTRUCTURE FACILITIES AND OTHER RELATED ACTIVITIES - P
D) Malabon-Navotas District Engineering Office
1) P7 BUILDERS INC.
2) 979,249.47
3) 100
4) -/-/-
A) April 16, 2024
B) 24OF0162
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. TANDANG SORA (PHASE 2), QUEZON CITY
D) Quezon City 1st District Engineering Office
1) R.D. TALENS CONSTRUCTION AND TRADING
2) 63,651,461.84
3) 51
4) 4/25/2024
A) April 16, 2024
B) 24OF0168
C) CONSTRUCTION OF 4-STOREY 8-CLASSROOM SCHOOL BUILDING IN JUDGE JUAN LUNA HIGH SCHOOL, BARANGAY BUNGAD
D) Quezon City 1st District Engineering Office
1) FRAMECON BUILDERS
2) 39,517,388.50
3) 100
4) -/-/-
A) April 16, 2024
B) 24OF0163
C) REHABILITATION / RECONSTRUCTION / UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - CONGRESSIONAL A
D) Quezon City 1st District Engineering Office
1) IM CONSTRUCTION CORPORATION
2) 68,113,819.83
3) 100
4) 4/29/2024
A) April 16, 2024
B) 24OD0256
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BRGY. 179, CLAOOCAN CITY
D) Metro Manila 3rd District Engineering Office
1) IM CONSTRUCTION CORPORATION
2) 9,748,405.38
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OF0170
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING, NINOY AQUINO PARKS AND WILDLIFE, BARANGAY VASRA, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) KING EIGHT BUILDERS AND SUPPLY
2) 68,606,669.95
3) 100
4) -/-/-
A) April 16, 2024
B) 24OD0255
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING, (3S PINALAGAD BUILDING, FIRE, HEALTH AND DAYCARE) MALINTA, V
D) Metro Manila 3rd District Engineering Office
1) DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERL
2) 77,689,630.93
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OF0162
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. TANDANG SORA (PHASE 2), QUEZON CITY
D) Quezon City 1st District Engineering Office
1) REND ENTERPRISES AND GENERAL CONTRACTOR
2) 63,651,461.84
3) 49
4) 4/25/2024
A) April 16, 2024
B) 24OD0252
C) REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS MAC ARTHUR H-WAY -
D) Metro Manila 3rd District Engineering Office
1) DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERL
2) 23,920,034.70
3) 100
4) 6/10/2024
A) April 16, 2024
B) 24OF0169
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING AT STO. NI�O, BRGY. HOLY SPIRIT, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) JYBL CORPORATION (FORMERLY: JYBL CONSTRUCTION AND TR
2) 49,044,850.91
3) 100
4) 4/29/2024
A) April 16, 2024
B) 23O00094
C) REHABILITATION OF FORMER PACE BUILDING INTO 8888 OFFICE BUILDING, J.P. LAUREL STREET, SAN MIGUEL, MA
D) National Capital Region
1) BILREY CONSTRUCTION
2) 67,761,750.74
3) 100
4) 8/9/2024
A) April 16, 2024
B) 24OB0326
C) CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG (PHASE 7)
D) Metro Manila 1st District Engineering Office
1) FRANZCOR TRADING AND CONSTRUCTION
2) 45,569,750.07
3) 100
4) 5/3/2024
A) April 16, 2024
B) 24OB0283
C) CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CONGA CREEK (PHASE 2), TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) FRANZCOR TRADING AND CONSTRUCTION
2) 68,744,472.06
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OA0085
C) CONSTRUCTION (COMPLETION) OF FLOODGATES NO. 5 AND NO. 6 ALONG NAVOTAS COASTAL DIKE, NAVOTAS CITY
D) Malabon-Navotas District Engineering Office
1) HALREY CONSTRUCTION INC.
2) 93,563,775.05
3) 100
4) 5/7/2024
A) April 16, 2024
B) 24OB0214
C) CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 2)
D) Metro Manila 1st District Engineering Office
1) DAHL CONSTRUCTION CORP. (FORMERLY: DAHL CONSTRUCTI
2) 125,754,544.80
3) 100
4) 5/29/2024
A) April 16, 2024
B) 24OF0160
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 4) MEDICAL CENTER, AT BRGY. TANDANG SORA, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) R.D. TALENS CONSTRUCTION AND TRADING
2) 147,225,578.60
3) 51
4) -/-/-
A) April 16, 2024
B) 24OB0296
C) REHABILITATION OF ROAD AT BARANGAY SOUTH DAANG HARI, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) ZYRE TRADING AND CONSTRUCTION
2) 17,949,163.46
3) 100
4) 6/6/2024
A) April 16, 2024
B) 24OB0297
C) REHABILITATION OF ROAD AT BARANGAY SOUTH SIGNAL, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) ZYRE TRADING AND CONSTRUCTION
2) 17,929,428.30
3) 100
4) 6/6/2024
A) April 16, 2024
B) 24OA0087
C) RAINWATER COLLECTORS IN PUBLIC FACILITIES
D) Malabon-Navotas District Engineering Office
1) TWO DIMENSION CONSTRUCTION
2) 2,851,148.00
3) 100
4) 5/7/2024
A) April 16, 2024
B) 24OA0088
C) REHABILITATION OF MULTI-PURPOSE BUILDING (DPWH) MALABON-NAVOTAS DISTRICT ENGINEERING OFFICE, NAVOTAS
D) Malabon-Navotas District Engineering Office
1) P7 BUILDERS INC.
2) 5,289,298.30
3) 100
4) -/-/-
A) April 16, 2024
B) 24OB0215
C) CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 3)
D) Metro Manila 1st District Engineering Office
1) J. SIMEON CONSTRUCTION
2) 90,685,600.66
3) 100
4) 5/29/2024
A) April 16, 2024
B) 24OD0253
C) PREVENTIVE MAINTENANCE - PRIMARY ROADS MACARTHUR H-WAY - K0011 + (-297) - K0011 + 014, K0011 + (-447
D) Metro Manila 3rd District Engineering Office
1) PASCAL CONSTRUCTION
2) 16,124,107.26
3) 100
4) 6/10/2024
A) April 16, 2024
B) 24OD0254
C) INSTALLATION/ APPLICATION OF SIGNAGE, PAVEMENT MARKINGS, AND IMPROVE SIGHT DISTANCE-CLEAR OBSTRUCTIO
D) Metro Manila 3rd District Engineering Office
1) DIADEMA CONSTRUCTION AND ENTERPRISES INC. (FORMERL
2) 3,653,586.14
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OF0160
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 4) MEDICAL CENTER, AT BRGY. TANDANG SORA, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) REND ENTERPRISES AND GENERAL CONTRACTOR
2) 147,225,578.60
3) 49
4) -/-/-
A) April 16, 2024
B) 24OF0159
C) ROAD REHABILITATION AND IMPROVEMENT AT TANDANG SORA AVENUE, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) C AND F CONSTRUCTION AND DEVELOPMENT CORPORATION
2) 57,263,075.21
3) 100
4) 4/29/2024
A) April 16, 2024
B) 23O00044
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (BASEBALL STADIUM), BRGY. USUSAN, TAGUIG CITY (PHASE 2)
D) National Capital Region
1) NEWBIG FOUR J CONSTRUCTION INC., (FORMERLY FOUR J
2) 141,563,077.96
3) 100
4) -/-/-
A) April 16, 2024
B) 24OB0376
C) COMPLETION OF MULTI-PURPOSE BUILDING (MSME), BRGY. PINAGSAMA, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) HONY TRADING AND CONSTRUCTION
2) 49,929,787.69
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OA0086
C) CONSTRUCTION OF FOUR (4) STOREY, EIGHT (8) CLASSROOM SCHOOL BUILDING, NINOY AQUINO ELEMENTARY SCHOOL
D) Malabon-Navotas District Engineering Office
1) C.B. TAMPENGCO CONSTRUCTION AND SUPPLY
2) 42,883,584.47
3) 100
4) 5/7/2024
A) April 16, 2024
B) 24OB0282
C) CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CONGA CREEK (PHASE 1), TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) FRANZCOR TRADING AND CONSTRUCTION
2) 68,698,564.66
3) 100
4) 5/3/2024
A) April 16, 2024
B) 24OB0295
C) REHABILITATION OF ROAD AT BARANGAY NORTH SIGNAL, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) B. VALENCERINA TRADING AND CONSTRUCTION
2) 13,459,896.30
3) 100
4) 6/4/2024
A) April 16, 2024
B) 24OB0486
C) CONSTRUCTION (COMPLETION) OF DPWH HEALTH CENTER, BRGY. CENTRAL BICUTAN, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) HONY TRADING AND CONSTRUCTION
2) 57,023,516.85
3) 100
4) 5/6/2024
A) April 16, 2024
B) 24OB0216
C) CONSTRUCTION OF SLOPE PROTECTION ALONG PINAGSAMA RIVER, TAGUIG CITY (PHASE 4)
D) Metro Manila 1st District Engineering Office
1) J. SIMEON CONSTRUCTION
2) 90,709,571.71
3) 100
4) 5/11/2024
A) April 16, 2024
B) 24OB0293
C) REHABILITATION OF ROAD AT BARANGAY KATUPARAN, TAGUIG CITY
D) Metro Manila 1st District Engineering Office
1) B. VALENCERINA TRADING AND CONSTRUCTION
2) 8,974,800.19
3) 100
4) 6/6/2024
A) April 15, 2024
B) 24OF0155
C) PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - NORTH AVE - K0011 + 471 - K0012 + 705, K0012 + (-7
D) Quezon City 1st District Engineering Office
1) C AND F CONSTRUCTION AND DEVELOPMENT CORPORATION
2) 23,998,961.88
3) 100
4) 4/29/2024
A) April 15, 2024
B) 24OD0245
C) CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AT ALMAR, BRGY. 177, CALOOCAN CITY
D) Metro Manila 3rd District Engineering Office
1) FRAMECON BUILDERS
2) 9,760,952.92
3) 100
4) 5/6/2024
A) April 15, 2024
B) 24OI0092
C) REHABILITATION OF MULTI - PURPOSE BUILDING, SANTOS VILLAGE 3, BRGY. ZAPOTE, LAS PINAS CITY
D) Las Pi�as-Muntinlupa District Engineering Office
1) AYANA CONSTRUCTION AND TRADING
2) 3,841,197.63
3) 100
4) 5/17/2024
A) April 15, 2024
B) 24OF0154
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2) AT BARANGAY CULIAT, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) ROSAND BUILDERS CORPORATION (FORMERLY: ROSAND BUIL
2) 4,898,980.12
3) 100
4) 4/29/2024
A) April 15, 2024
B) 24OF0152
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY HOLY SPIRIT, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) R. ROSE CONSTRUCTION SERVICES
2) 9,810,850.40
3) 100
4) 5/6/2024
A) April 15, 2024
B) 24OF0153
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2) AT BARANGAY NEW ERA, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) C.E.M. CONSTRUCTION, INC.
2) 9,856,090.60
3) 100
4) 4/29/2024
A) April 15, 2024
B) 24OD0246
C) INSTALLATION/ APPLICATION OF SIGNAGE-WARNING, ADVISORY AND REGULATORY SIGNS AND PAVEMENT MARKINGS AL
D) Metro Manila 3rd District Engineering Office
1) TWO DIMENSION CONSTRUCTION
2) 3,697,386.90
3) 100
4) 5/6/2024
A) April 15, 2024
B) 24OF0151
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING (PHASE 2), BARANGAY PAYATAS, QUEZON CITY
D) Quezon City 1st District Engineering Office
1) R. ROSE CONSTRUCTION SERVICES
2) 9,828,841.11
3) 100
4) 5/6/2024
A) April 15, 2024
B) 24OF0150
C) CONSTRUCTION OF 2 - STOREY SCHOOL BUILDING IN KALIGAYAHAN ELEMENTARY SCHOOL, BARANGAY KALIGAYAHAN, Q
D) Quezon City 1st District Engineering Office
1) FRAMECON BUILDERS
2) 9,868,853.60
3) 100
4) -/-/-
A) April 15, 2024
B) 24OI0093
C) REHABILITATION OF DRAINAGE SYSTEM, BERNABE, BRGY. PULANGLUPA 1, LAS PINAS CITY
D) Las Pi�as-Muntinlupa District Engineering Office
1) ZERO ONE CONSTRUCTION AND TRADING INC.
2) 5,642,215.48
3) 100
4) -/-/-
A) April 15, 2024
B) 24OD0243
C) CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CAPITOL PARK HOMES I, BRGY. 179, CALOOCAN CITY
D) Metro Manila 3rd District Engineering Office
1) JAGONBUILD CONSTRUCTION CORP. (FOR. JAGON BUILDERS
2) 9,720,899.06
3) 100
4) 5/6/2024
A) April 15, 2024
B) 24OF0148
C) SUPPLY, DELIVERY AND INSTALLATION OF NEW ELECTRIC INCLUDING DISMANTLING OF OLD EXISTING ELEVATOR AT
D) Quezon City 1st District Engineering Office
1) JUSTBILT BUILDERS
2) 9,176,066.28
3) 100
4) -/-/-