Project Status - Physical progress, bidders, and contract awards

 

                                                                                                         CORE PROJECTS

                                                                                                                (As of August 25, 2024)

 

No.

Road Name

NetLength (km)

[Road (km) & Bridge (m)]

Contractor

Contract Amount

Million PHP

Implementation

 Period

Progress

PR-06

Alicia-Malangas Road Province, Zamboanga Sibugay

24.03 km

[23.73 km (Road) & 302.52 m (8 Bridges)]

China Geo-Engineering Corporation/ESR Construction and Development Corporation (J/V)

1,422.91

Mar 28, 2019

- July 19, 2022

100.00%

PR-07

Tampilisan - Sandayong Road Province, Zamboanga del Norte

15.35 km

[15.24 km (Road) & 112.82 m (3 Bridges)]

MAC Builders/Fiat Construction Services (JV)

658.19

Mar 28, 2019 – Feb 28, 2023

100.00%

PR-09

Lutiman – Guicam – Olutanga Road Province, Zamboanga Sibugay

29.70 km

[29.70 km (Road) & 0.00 m]

Sino Road and Bridge Group Co., Ltd./M. Abubakar Construction and Engineering, Inc. (JV)

1,086.29

Mar 28, 2019 –

June 04, 2023

100.00%

Total

69.08 km

[68.67 km &

415.34 m]

 

3,167.39

 

100.00%

 

 

 

 

 

 

 

 

 

 

  

 

NON-CORE PROJECT

(As of August 25, 2024)

 

No.

Road Name

NetLength (km)

[Road (km) & Bridge (m)]

Contractor

Contract Amount

Million PHP

Implementation

Period

Progress

PR-01a

Gutalac-Baliguan Alternative Road, Zamboanga del Norte

7.38km [7.08km (Road) & 301.5m (7 Bridges)]

China Wuyi Co., Ltd.

1,064.38

July 21, 2022 – Nov 13, 2025

 

57.02%

PR-08

RT Lim-Siocon Road, Zamboanga Sibugay & del Norte

24.46km [24.03km (Road) & 430.11 m (6 Bridges)]

China Wuyi Co. Ltd.

2,395.82

Feb 26, 2021 – Sept 25, 2024

 

91.06%

 

PR-12

Curuan-Sibuco Road, Zamboanga City & del Norte

33.05km [32.98km (Road) & 71.8m (2 Bridges)]

M. Abubakar Construction and Engineering, Inc./ Sino Road and Bridge Group Co. Ltd. (J/V)

2,088.14

Mar 15, 2021 – Mar 09, 2025

 

 

90.39%

 

 

PR-13

Siay-Gapol Road, Zamboanga Sibugay

18.64km [18.32km (Road) & 311.8m (2 Bridges)]

Qingdao Municipal Construction Group Co., Ltd/ESR Construction and Development Corporation (J/V)

1,328.72

Jan 28, 2021 – Dec 15, 2024

 

 

75.44%

Total

 

83.53km

[82.41km & 1115.21m]

 

6,877.06

 

82.57%

 

 

        

 

 

 

 

 

 

 

 

 

 

                             

                                             

 

 

 

 

 

 

 

                                           

 

 

 

 

                                                   MAJOR BRIDGE PROJECTS

                                                              (As of August 25, 2024)

 

No.

Road Name

NetLength (m)

[Road (m) & Bridge (m)]

Contractor

Contract Amount

Million PHP

Implementation

 Period

Progress

 

PR-09a

Guicam Bridge, Zamboanga Sibugay

1.21km [0.67km (Road) & 540.80m (1 Bridges]

Tianyuan Construction Group Corporation/ Grace Construction Corporation (JV)

1,155.18

Jan 29, 2021 – Dec 30, 2024

 

 

80.64%

Br.1

Nalil-Sikkiat Bridge, Tawi-Tawi

0.541km

[160m & 380.80m]

China Wuyi Co., Ltd.

893.73

July 21, 2022 – July 20, 2025

72.83%

Br. 2

Tongsinah-Paniongan, Tawi-Tawi

0.569km

[188.46m & 380.80m]

China Wuyi Co., Ltd. / Vicente T. Lao Construction (Consortium)

1,167.75

August 14, 2024 – August 14, 2027

0.63%

Br.3

Malassa-Lupa Pula Bridge, Tawi-tawi

0.681km

[200m & 480.60m]

Vicente T. Lao Construction / China Wuyi Co., Ltd. (Consortium)

1,250.47

July 21, 2022 – Sept 18, 2025

 

39.23%

Total

 

3.001km

[1219.13m & 1783.00m]

 

4,467.12

 

46.41%