METRO MANILA EXPRESSWAY PROJECT (C6)

Project Description: 
    • The Southeast Metro Manila Expressway (C6) Project is a a toll road project with approximately 34.024 kilometers that is intended to run from Skyway/FTI in Taguig City to Batasan Complex in Quezon City. The project is divided into six sections namely:

             SEGMENT 1

1. SECTION 1         : Skyway/FTI – C5/Diego Silang            (L = 4.049 kms.)

    Section 1A          : Skyway to FTI

    Section 1B          : FTI to C5/Diego Silang

2. SECTION 2          : C5/Diego Silang – C6/Taguig              (L = 2.125 kms.)

3. SECTION 3          : C6/Taguig – Ortigas Ave. Ext              (L = 12.000 kms.)

SEGMENT 2

4. SECTION 4          : Ortigas Ave. Ext. – Marcos Highway    (L = 5.000 kms.)

5. SECTION 5          : Marcos Highway – Tumana Bridge       (L= 8.336 kms.)

6. SECTION 6          : Tumana Bridge to Batasan Complex     (L = 2.514 kms) 

                                                                            Total Length = 34.024 kms.

General features of the project:

Project Road Type                          : Combination of elevated and at grade

Project Road length                        : 34.024 kms.

Number of carriageway lanes          : 6 lanes (2 x 3 lanes)

Design speed expressway               : 80 kph (60 kph)

Rampway                                        : 40 kph

Number of ramps                            : 28

Project Objectives: 

·         To connect the South Luzon Expressway (SLEX) Skyway via FTI towards Batasan Complex in Quezon City.

·         To decongest EDSA, C5 and other major arteries of Metro Manila and Rizal by providing an alternate route from Parañaque to Quezon City by passing thru the developing areas of Taguig, Taytay, Antipolo, and San Mateo.

Project Concessionaire: 

Citra Intercity Tollways Inc. (CITI)

Operator:

Metro O&M Corporation 

Grantor:

Toll Regulatory Board (TRB)

Project Cost: 

• PhP 31.32 B

Project Status: 
  • PTE to ALI Property and PNR ROW already issued.
  • Right-of-Way Acquisition and securing of permits/clearances ongoing.
  • Securing of project endorsement from LGU ongoing.
  • Ongoing finalization of relocation plans of MWSI and MWC affected families in coordination with CITI.
  • Ongoing

       

Project Alignment: 
Project Timeline: 

Approval of Supplemental Toll Operations Agreement (STOA) by the Office of the President

11 August 2014

ECC for Sections 1,2 & 3 issued

20 February 2012

ECC for Sections 3, 4 & 5 issued

05 March 2014

Issuance of Notice to Proceed

27 June 2016

Implementation Schedule

June 2016 – August 2020 (52 months)

Section 1

 

   1A – Skyway to FTI

24 months

   1B – FTI to C5/Diego Silang

24 months

Section 2

24 months

Section 3

36 months

Section 4

36 months

Section 5

36 months

Section 6

36 months