- The Southeast Metro Manila Expressway (C6) Project is a a toll road project with approximately 32.664 km that is intended to run from Skyway/FTI in Taguig City to Batasan Complex in Quezon City. The project is divided into six sections namely:
SEGMENT | SECTION | LENGTH (km.) |
Segment 1 | Section 1: Skyway/FTI - C5/Diego Silang · Section 1A: Skyway to FTI · Section 1B: FTI to C5/Diego Silang | 2.387 |
Section 2: C5/Diego Silang - C6/Taguig | 3.202 | |
Section 3: C6/Taguig - Ortigas Ave. Ext. | 11.783 | |
Segment 2 | Section 4: Ortigas Ave. Ext. - Marcos Highway | 5.337 |
Section 5: Marcos Highway - Tumana Bridge | 6.9 | |
Section 6: Tumana Bridge - Batasan Complex | 3.055 |
The general features of the Project are shown below:
Project Road Type : Combination of elevated and At-grade
Carriageway lanes : 2 x 3 lanes
Design speed expressway : 80 kph
Rampway design speed : 40 kph
Number of ramps : 28
The project aims to:
- Connect the South Luzon Expressway (SLEX) Skyway via FTI towards Batasan Complex in Quezon City
At the end of construction, the project is expected to:
- Provide an alternate route from Parañaque to Quezon City passing thru the developing areas of Taguig, Taytay, Antipolo and San Mateo to decongest EDSA, C5 and other major arteries of Metro Manila and Rizal.
Citra Intercity Tollways Inc. (CITI)
• PhP 45.00 Billion
- PTE to Ayala Land Inc. (ALI) Property and DOTr area already issued.
- Ongoing securing of Permits/Clearances and Right-of-Way (ROW) Acquisition.
- Ongoing securing of project endorsement from LGU on Section 4.
- Ongoing coordination with LGU and Assessor's Offices
- Completed the tagging and census of affected structures on Section 1.
- Groundbreaking held last January 8, 2018
- Section 2 (C5/Diego Silang - C6/Taguig) - DED for the realignment is ongoing
- ROWA Team secured the project endorsement on Section 1, 2, 3, 5 and 6
- Ongoing

Approval of Supplemental Toll Operations Agreement (STOA) by the Office of the President | 11 August 2014 |
ECC for Sections 1,2 & 3 issued | 20 February 2012 |
ECC for Sections 3, 4 & 5 issued | 05 March 2014 |
Issuance of Notice to Proceed | 27 June 2016 |
Implementation Schedule | June 2016 – August 2020 (52 months) |
Section 1 |
(April 2018 - April 2021) 36 months |
1A – Skyway to FTI | |
1B – FTI to C5/Diego Silang | |
Section 2 (C5/Diego Silang - C6/Taguig -- Subject for Realignment) | 24 months |
Section 3 | 36 months |
Section 4 | 36 months |
Section 5 | 36 months |
Section 6 | 36 months |