METRO MANILA EXPRESSWAY PROJECT (C6)

Project Description: 
    • The Southeast Metro Manila Expressway (C6) Project is a a toll road project with approximately 32.664 kilometers that is intended to run from Skyway/FTI in Taguig City to Batasan Complex in Quezon City. The project is divided into six sections namely:       

 

SEGMENT

SECTION

LENGTH (km.)

Segment 1

Section 1: Skyway/FTI - C5/Diego Silang

·         Section 1A: Skyway to FTI

·         Section 1B: FTI to C5/Diego Silang

2.387

Section 2: C5/Diego Silang - C6/Taguig

3.202

Section 3: C6/Taguig - Ortigas Ave. Ext.

11.783

Segment 2

Section 4: Ortigas Ave. Ext. - Marcos Highway

5.337

Section 5: Marcos Highway - Tumana Bridge

6.9

Section 6: Tumana Bridge - Batasan Complex

3.055

The general features of the Project are shown below:

Project Road Type                          : Combination of elevated and At-grade

Carriageway lanes                          : 2 x 3 lanes

Design speed expressway               : 80 kph (60 kph)

Rampway                                        : 40 kph

Number of ramps                            : 28

Project Objectives: 

The project aims to:

  • Connect the South Luzon Expressway (SLEX) Skyway via FTI towards Batasan Complex in Quezon City

 

Project Benefits: 

At the end of construction, the project is expected to:

  • Provide an alternate route from Parañaque to Quezon City passing thru the developing areas of Taguig, Taytay, Antipolo and San Mateo to decongest EDSA, C5 and other major arteries of Metro Manila and Rizal.
Project Concessionaire: 

Citra Intercity Tollways Inc. (CITI)

 

Project Cost: 

• PhP 45.00 Billion

Project Status: 
  • PTE to ALI Property and PNR ROW already issued.
  • Ongoing securing of Permits/Clearances and Right-of-Way (ROW) Acquisition.
  • Ongoing securing of project endorsement from LGU on Section 3, 4, 5 and 6.
  • Ongoing coordination with LGU and Assessor's Offices.
  • Ongoing finalization of relocation plans of Maynilad Water Systems Incorporated (MWSI) and Manila Water Company (MWC) affected utilities in coordination with CITI.
  • Completed the tagging and census of affected structures on Section 1.
  • Groundbreaking held last January 8, 2018.
  • Section 2 (C5/Diego Silang - C6/Taguig) - Subject for Realignment
  • Ongoing
Project Alignment: 
Project Timeline: 

Approval of Supplemental Toll Operations Agreement (STOA) by the Office of the President

11 August 2014

ECC for Sections 1,2 & 3 issued

20 February 2012

ECC for Sections 3, 4 & 5 issued

05 March 2014

Issuance of Notice to Proceed

27 June 2016

Implementation Schedule

June 2016 – August 2020 (52 months)

Section 1

 

(April 2018 - April 2021)

36 months

   1A – Skyway to FTI

   1B – FTI to C5/Diego Silang

Section 2 (C5/Diego Silang - C6/Taguig -- Subject for Realignment)

24 months

Section 3

36 months

Section 4

36 months

Section 5

36 months

Section 6

36 months