May 2, 2018 |
FY 2018 |
WIN8C02613 |
UACS No. 320101102157000 |
April 24, 2018 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 320101102157000
Project ID: P00221457MN
OO2: Protect Lives and Properties
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Flood Control Structure along Ponot Diut River (downstream) both sides, Jose Dalman, Zamboanga del Norte
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 459 l.m
Unit Cost: P 85,000/l.m
EAO: P 800,000.00
Allocation: P 40,000,000.00 |
May 2, 2018 |
FY 2018 |
WIN8C02611 |
UACS No. 320101102156000 |
April 24, 2018 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 320101102156000
Project ID: P00220346MN
OO2: Protect Lives and Properties
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure along Dohinob River, Roxas, Zamboanga del Norte
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 545 l.m
Unit Cost: P 89,900/l.m
EAO: P 1,000,000.00
Allocation: P 50,000,000.00 |
May 2, 2018 |
FY 2018 |
WIN8C02629 |
UACS No. 300204100197000 |
April 24, 2018 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 300204100197000
Project ID: P00230010MN
Convergence and Special Support Program
Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Jct. Dipolog- Sindangan - Liloy Road connecting to Bago-Siari Section in Support of Rice, Rubber, Coconut, & Abaca Industries, Sindangan, Zamboanga del Norte
Physical Target:
CW-1- Construction of Concrete Road: 4.148 Lane km
Unit Cost: P 11,812,921.89/Lane km
EAO: P 1,000,000.00
Allocation: P 50,000,000.00 |
May 2, 2018 |
FY 2018 |
WIN8C02616 |
UACS No. 300118200016000 |
April 24, 2018 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 300118200016000
Project ID: P00240240MN
Local Roads and Bridges - Local Bridges - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure Including Local Projects
Replacement of Barra Bridge 1 along Barra- Minaog Road leading to Dipolog City Airport, Dipolog City, Zamboanga del Norte
Physical Target:
CW-1- Replacement of Bridge: 518.549 Sq.m.
Unit Cost: P 97,700.00/Sq.m.
EAO: P 1,838,375.00
Excess: P 12,475,000.00
Allocation: P 65,000,000.00 |
May 2, 2018 |
2018 |
WIN8C02606 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
OO2- Organizational Outcome 2 / Protect Lives and Properties Against Major Floods / Construction/ Maintenance of Flood Mitigation Structures and Drainage System
FROM:
Construction of Hamogaway Flood Control Structure including River Training (Downstream) along Daang Maharlika (Agusan - Davao Section), K0000+000 - K0000+268, Bayugan, Agusan del Sur
Scope of Work: Construction of Flood Mitigation Structure
Physical Target: 268.00 lm
Amount : Php 10,000,000.00
TO:
Construction of Hamogaway Flood Control Structure including River Training (Downstream) along Daang Maharlika (Agusan - Davao Section), Sta.0+000 – Sta.0+134, Bayugan, Agusan del Sur
Scope of Work: Construction of Flood Mitigation Structure
Physical Target: 134.00 lm
Amount : Php 10,000,000.00
|
May 2, 2018 |
2018 |
WIN8C02607 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
OO1- Ensure Safe and Reliable National Road System
Network Development
Construction of By-pass and Diversion Roads
FROM:
Talacogon Bypass Road, incl. ROW, Agusan del Sur
Scope of Work: Construction of Concrete Road
ROW Acquisition
Physical Target: 0.951 lane km
120,000.00 square meters
Amount : Php 26,536,000.00
TO:
Scope of Work: Construction of Concrete Road
ROW Acquisition
Physical Target: 0.612 lane km
18,360.00 square meters
Amount : Php 26,536,000.00
|
May 1, 2018 |
FY 2018 |
WIN8C02646 |
UACS No. 310204100311000 |
April 25, 2018 |
Region IX |
Regional Office IX |
UACS No. 310204100311000
Project ID: P00200309MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
Zamboanga City Diversion Road (Cabaluay - Zambowood - Mampang Section), Package 1, Zamboanga City
Physical Target:
CW-1- Construction of Concrete Road: 3.52 lane km
Unit Cost: P 38,380,681.82
EAO: P 4,900,000.00
Allocation: P 140,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02647 |
UACS No. 310204100312000 |
April 25, 2018 |
Region IX |
Regional Office IX |
UACS No. 310204100312000
Project ID: P00200310MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Construction of By-Pass and Diversion Roads
Zamboanga City Diversion Road (Cabaluay - Zambowood - Mampang Section), Package 2, incl. ROW, Zamboanga City
Physical Target:
CW-1- Construction of Concrete Road: 6.75 lane km
Unit Cost: P 19,467,346.22/lane km
Physical Target:
CW-2- ROW: 165,109.71 sq.m
Unit Cost: P 300/sq.m
EAO: P 6,562,500.00
Allocation: P 187,500,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02476 |
UACS No. 320101102175000 |
April 2, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 320101102175000
Project ID: P00220995MN
OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Flood Control Structure along Bucayan River, Dumingag, Zamboanga del Sur
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 185 l.m
Unit Cost: P 132,432.43/l.m
EAO: P 500,000.00
Allocation: P 25,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02477 |
UACS No. 320101102171000 |
April 2, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 320101102171000
Project ID: P00220992MN
OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Dipolo Flood Control, Sagrada Familia, Tambulig, Zamboanga del Sur
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 490.63 l.m
Unit Cost: P 59,922.96/l.m
EAO: P 600,000.00
Allocation: P 30,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02473 |
UACS No. 320101102180000 |
April 2, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 320101102180000
Project ID: P00220722MN
OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Guitran Flood Control, Brgy. Caridad, Dumingag, Zamboanga del Sur
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 193.00 l.m
Unit Cost: P 101,554.40/l.m
EAO: P 400,000.00
Allocation: P 20,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02474 |
UACS No. 320101102179000 |
April 2, 2018 |
Region IX |
Zamboanga del Sur 1st District Engineering Office |
UACS No. 320101102179000
Project ID: P00220719MN
OO2: Protect Lives and Properties Against Major Floods
Flood Management Program
Construction/Maintenance of Flood Mitigation Structures and Drainage System
Construction of Guinabot Flood Control, Poblacion, Midsalip, Zamboanga del Sur
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 168 l.m
Unit Cost: P 116,666.67/l.m
EAO: P 400,000.00
Allocation: P 20,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02648 |
UACS No. 310103100029000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310103100029000
Project ID: P00201575MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
Asphalt Overlay along Junction Imelda - Alicia Road,
K1758+119.80 - K1759+582.50
Physical Target:
CW-1- Preventive Maintenance of Road: Asphalt Overlay: 2.1074 Lane km
Unit Cost: P 16,141,335.29/Lane km
EAO: P 1,233,750.00
Allocation: P 35,250,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02645 |
UACS No. 310107100049000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310107100049000
Project ID: P00201578MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Lanao - Pagadian - Zamboanga City Rd
K1742+900 - K1742+940
K1743+450 - K1743+480
K1743+550 - K1743+710
K1743+820 - K1744+087
K1752+200 - K1752+270
K1753+030 - K1753+095
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 8,893.39 Sq. m
Unit Cost: P 7,162.62/ sq. m.
EAO: P 1,300,000.00
Allocation: P 65,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02501 |
UACS No. 320102100511000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 320102100511000
Project ID: P00220494MN
OO2: Protect Lives and Properties
Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control Structure (Revetment Wall) along Sibuguey River, Brgy. Conception, Alicia, Zamboanga Sibugay
Sta. 00+-002 - Sta. 00+297
Physical Target:
CW-1- Construction of Revetment: 299 l.m
Unit Cost: P 88,494.98/l.m
EAO: P 540,000.00
Allocation: P 27,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02634 |
UACS No. 310212100070000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310212100070000
Project ID: P00200874MN
OO1: Ensure Safe and Reliable National Road System
Network Development - Paving of Unpaved Roads - Tertiary Roads
Imelda - Bayog - Kumalarang - Lapuyan - Margosatubig Rd.
K1756+311 - K1756+667.30
K1771+590 - K1771+720
K1772+917 - K1773+969
Physical Target:
CW-1- Paving of Unpaved Roads: 3.0766 Lane km
Unit Cost: P 13,755,866.90/Lane km
EAO: P 863,700.00
Allocation: P 43,185,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02644 |
UACS No. 310107100050000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310107100050000
Project ID: P00201579MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Lanao - Pagadian - Zamboanga City Road
K1724+(-483) - K1724+(-385)
K1724+120 - K1724+260
K1724+520 - K1724+535
K1725+244 - K1725+320
K1725+737 - K1725+800
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 8,941 Sq. m
Unit Cost: P 5,480.37/Sq.m.
EAO: P 1,000,000.00
Allocation: P 50,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02642 |
UACS No. 310104100070000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310104100070000
Project ID: P00200088MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Lanao - Pagadian - Zamboanga City Rd.
K1743+510 - K1743+906
Physical Target:
CW-1- Reconstruction from Paved to Concrete: 0.792 Lane km
Unit Cost: P 16,035,126.26/ Lane km
EAO: P 259,180.00
Allocation: P 12,959,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02631 |
UACS No. 310109100124000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310109100124000
Project ID: P00200261MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Imelda - Bayog - Kumalarang - Lapuyan - Margosatubig Rd.
K1751+211 - K1751+224
K1751+460 - K1751+490
K1752+544 - K1752+728
K1752+973 - K1753+338
K1753+835 - K1754+173
K1754+306 - K1754+440
K1754+750 - K1754+780
K1754+962 - K1755+019
K1754+928 - K1755+000
K1755+050 - K1755+182
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 7,240.75 Sq. m
Unit Cost: P 5,007.77/Sq.m.
EAO: P 740,000.00
Allocation: P 37,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02632 |
UACS No. 310103100028000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310103100028000
Project ID: P00201574MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
Asphalt Overlay along Junction Imelda - Alicia Road
K1757+574.68 - K1758+119.80
Physical Target:
CW-1- Preventive Maintenance of Road: Asphalt Overlay: 1.720 lane km
Unit Cost: P 17,532,703.49/lane km
EAO: P 1,093,750.00
Allocation: P 31,250,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02633 |
UACS No. 310109100123000 |
April 25, 2018 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 310109100123000
Project ID: P00200260MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Diplahan Jct. Malangas Port Rd.
K1747+280 - K1747+540
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 2,938 Sq. m
Unit Cost: P 3,335.60/sq.m
EAO: P 200,000.00
Allocation: P 10,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02554 |
UACS No. 320101102142000 |
April 10, 2018 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 320101102142000
Project ID: P00220444MN
OO2: Protect Lives and Properties Against Major Floods
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control at Cawit River, Cawit, Zamboanga City
Physical Target:
CW-1- Construction of Flood Mitigation Structure: 544.15 ln.m.
Unit Cost: P 35,734.59/ln.m.
Physical Target:
ROW: 140 sq. m.
Unit Cost: P 1,107.3/sq.m
EAO: P 400,000.00
Allocation: P 20,000,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02549 |
UACS No. 310102100188000 |
April 10, 2018 |
Region IX |
Isabela City District Engineering Office |
UACS No. 310102100188000
Project ID: P00201335MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Road
Basilan Circumferential Road
K0004+860 - K0005+553
K0007+585.50 - K0008+867
Physical Target:
CW-1- Preventive Maintenance of Road: Asphalt Overlay: 3.949 lane km
Unit Cost: P 12,395.30010/lane km
EAO: P 998,960.00
Allocation: P 49,948,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02490 |
UACS No. 310102100191000 |
April 10, 2018 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310102100191000
Project ID: P00200036MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation Program
Preventive Maintenance - Secondary Roads
Jct. Polo - Dapitan Park National Road
K1829+008 - K1829+527
Physical Target:
CW-1- Preventive Maintenance of Road: Asphalt Overlay: 1.038 lane km
Unit Cost: P 7,148,901.73/lane km
EAO: P 151,440.00
Allocation: P 7,572,000.00 |
May 1, 2018 |
FY 2018 |
WIN8C02542 |
UACS No. 310107100046000 |
April 10, 2018 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310107100046000
Project ID: P00200190MN
OO1: Ensure Safe and Reliable National Road System
Asset Preservation Program
Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Primary Roads
Dipolog-Punta-Dansullan- Sergio Osmeña-Zamboanga del Norte/Sur Bdry Rd
K1873+210 - K1873+280
K1879+390 - K1879+462
Physical Target:
CW-1- Construction of Road Slope Protection Structure: 790.49 sq.m
Unit Cost: P 7,043.73/sq.m
Physical Target:
ROW: 77 sq.m
Unit Cost: P 1,506.49/sq.m
EAO: P 116,000.00
Allocation: P 5,800,000.00 |
April 30, 2018 |
FY - 2018 |
WIN8F05396 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
002 - Protect lives and Properties Against Major Floods
Construction/Maintenance of Flood Mitigation Structure and Drainage Systems
FROM:
Construction of Flood Control and Mitigation Structure at
Tagbarungis - Inagawan Section, Puerto Princesa South Road, Palawan
CW1: 20 lineal Meters ( Construction of Flood Mitigation
Structure )
Allocation: 5,000,000 Php
TO:
Construction of Flood Control and Mitigation Structure at
Tagbarungis - Inagawan Section, Puerto Princesa South Road, Palawan
CW1: 92014 lineal meters ( Construction of Flood Mitigation
Structure )
Allocation: 5,000,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05395 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
001 - Ensure safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides
- Tertiary Roads
FROM:
Puerto Princesa South Diversion Rd
Chainage 1060 - Chainage 1170
CW1: 550 square meters ( Construction of Road Slope
Protection Structure )
Allocation: 10,000,000 Php
TO:
Puerto Princesa South Diversion Rd
Chainage 1060 - Chainage 1170
CW1: 1,615 square meters ( Construction of Road Slope
Protection Structure )
Allocation: 10,000,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05342 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
Local Program
Local Infrastructure Program - Buildings and Other Structures - School Buildings
FROM:
Construction of 2 CL at Marcelo Bantog Elementary School
Brgy. San Juan, Aborlan, Palawan
CW1: 2 Classrooms ( Construction of Classrooms )
Allocation: 2,000,000 Php
TO:
Construction of 2 Classroom Building, Marcelo Bantog
National High School, Brgy. San Juan, Aborlan, Palawan
CW1: 2 Classrooms ( Construction of Classrooms )
Allocation: 2,000,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05351 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
Local Program
Local Infrastructure Program - National Roads and Bridges
- Local roads
FROM:
Concreting of T. Paredes Interior Road along Abad Santos Extn., Brgy. Bagong Sikat, Puerto princesa City, Palawan
CW1: 0.352 lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php
TO:
Concreting of T. Paredes Interior Road along Abad Santos
Extn., Brgy. Bagong Sikat, Puerto Princesa City, Palawan
CW1: 0.316 lane km ( Construction of Concrete Road )
Allocation: 2,000,000 Php |
April 30, 2018 |
FY 2018 |
WIN8G02152 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Regional Office III |
Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) incl. ROW - K0047 + 508 - K0047 + 973, K0047 + 989 - K0048 + 770, K0048 + 786 - K0050 + 437, K0050 + 453 - K0050 + 652, K0050 + 662 - K0052 + 592
|
April 30, 2018 |
FY 2018 |
WIN8G02155 |
SR2018-01-000834 |
January 26, 2018 |
Region III |
Regional Office III |
Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ)
K0085 + (-360) - K0085 + 000, K0087 + 225 - K0089 + 098, K0090 + 564 - K0092 + 000
|
April 30, 2018 |
FY 2018 |
WIN8G02154 |
SR2018-01-000225 |
January 25, 2018 |
Region III |
Regional Office III |
OO-1: Ensure Safe and Reliable National Road System
Asset Preservation Program
Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Rd
K0038 + 306 – K0039 + 151, K0041 + 840 - K0042 + 900, K0043 + 118 – K0044 + 500, K0050 + 741 - K0050 + 1320
|
April 30, 2018 |
FY 2018 |
WIN8G02153 |
SR2018-01-002056 |
January 30, 2018 |
Region III |
Regional Office III |
Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction / Rehabilitation of Eroded Pampanga River Bank (San Jose, San Simon and Sucad, Apalit Section), Pampanga
|
April 30, 2018 |
FY 2018 |
WIN8G02152 |
SR2018-01-000928 |
January 26, 2018 |
Region III |
Regional Office III |
Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) incl. ROW
K0047 + 508 - K0047 + 973, K0047 + 989 - K0048 + 770, K0048 + 786 - K0050 + 437, K0050 + 453 - K0050 + 652, K0050 + 662 - K0052 + 592
Allotment: P152.026M
|
April 30, 2018 |
FY - 2018 |
WIN8F05316 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 2 km. Malinao to Purok Mirasol road,
Barangay Malinao, Torrijos, Marinduque
CW1: 1.759 lane km ( Construction of Concrete Road )
Allocationn: 10,000,000 Php
TO:
Concreting of 2 lane km. Malinao to Purok Mirasol road,
Barangay Malinao, Torrijos, Marinduque
CW1: 2.000 lane km ( Construction of Concre Road )
Allocation: 10,000,000 Php
|
April 30, 2018 |
FY - 2018 |
WIN8F05317 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 2 km. Bolo to Pulang Lupa road,
Barangay Bolo, Torrijos, Marinduque
CW1: 1.759 Lane km ( Construction of Concrete Road )
Allocation: 10,000,000 Php
TO:
Concreting of 2 lane km. Bolo to Pulang Lupa road,
Barangay Bolo, Torrijos, Marinduque
CW1: 2.000 Lane km ( Construction of Concrete Road )
Allocation: 10,000,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05314 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
FROM:
Concreting of 1.1 km. Makawayan to Purok Star. Ana road
Barangay Makawayan, Torrijos, Marinduque
CW1: 0.967 Lane km ( Construction of Concrete Road )
Allocation: 5,500,000 Php
TO:
Concreting of 1.1 lane km. Makawyan to Sta. Ana road
Barangay Makawayan, Torrijos, Marinduque
CW1: 1.100 Lane km ( Construction of Concrete Road )
Allocation: 5,500,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05326 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local projects
FROM:
Concreting of 3 km. Bayakbakin to payanas road,
Barangay Payanas, Torrijos, Marinduque
CW1: 2.639 Lane km ( Construction of Concrete Road )
Allocation: 15,000,000 Php
TO:
Concreting of 3 lane km. Bayakbakin to Payanas road,
Barangay Payanas, Torrijos, Marinduque
CW1: 3.000 Lane km ( Construction of Concrete Road )
Allocation: 15,000,000 Php |
April 30, 2018 |
FY - 2018 |
WIN8F05304 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Marinduque District Engineering Office |
Local Program
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects
Concreting of 300 m. Bayanan to Mabuhay road,
Barangay Matuyatuya, Torrijos, Marinduque
CW1: 0.264 Lane km ( Construction of Concrete Road )
Allocation: 1,500,000 Php
TO:
Concreting of 0.300 lane km. Bayanan to Mabuhay road,
Barangay Matuyatuya, Torrijos, Marinduque
CW1: 0.300 Lane km. (Construction of Concrete Road )
Allocation: 1,500,000 Php |
April 28, 2018 |
2018 |
310109100053000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide: Tertiary Roads
Peñablanca-Callao Cave Rd - K0476 + 560 - K0476 + 650, K0477 + 470 - K0477 + 600, K0479 + 560 - K0479 + 670 |
April 28, 2018 |
2018 |
310201100202000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
Santiago-Tuguegarao Rd (Jct Kalinga-Tuguegarao Sect) - K0442 + 226 - K0442 + 409, K0442 + 880 - K0445 + 500 |
April 28, 2018 |
2018 |
310104100037000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Santiago-Tuguegarao Rd (Jct Kalinga-Tuguegarao Sect) - K0437 + (-031) - K0437 + 100, K0437 + 900 - K0438 + 100, K0438 + 700 - K0439 + 000, K0441 + 200 - K0442 + 000, K0442 + 000 - K0442 + 168, K0442 + 252 - K0443 + 047, K0443 + 305 - K0443 + 565, K0444 + 000 - K0445 + 000, K0445 + 000 - K0446 + 150, K0447 + 000 - K0448 + 296 |
April 28, 2018 |
2018 |
310103100007000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Cagayan Apayao Rd - K0492 + 255 - K0493 + 669, K0493 + 685 - K0493 + 965, K0498 + 777 - K0502 + 601, K0502 + 601 - K0503 + 500 |
April 28, 2018 |
2018 |
310201100028000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening: Primary Roads
Cagayan Valley Rd - K0499 + 260 - K0501 + 300, K0503 + 164 - K0503 + 248 |
April 28, 2018 |
2018 |
310209100036000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Off-Carriageway Improvement - Tertiary Roads
Cagayan Apayao Rd - K0489 + 625 - K0489 + 655, K0489 + 686 - K0491 + 480, K0489 + 686 - K0491 + 300, K0491 + 360 - K0491 + 480 |
April 28, 2018 |
2018 |
310201100030000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
Cagayan Valley Rd - K0506 + 277 - K0507 + 342.8, K0507 + 522 - K0509 + 786 |
April 28, 2018 |
2018 |
310207100008000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Off-Carriageway Improvement - Primary Roads
Kalinga-Cagayan Rd (Calanan-Enrile Section) - K0438 + 010 - K0441 + 576, K0441 + 600 - K0443 + 765 |
April 28, 2018 |
2018 |
310101100062000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Kalinga - Cagayan Rd (Calanan-Enrile Section) - K0438 + 010 - K0440 + 000, K0440 + 415 - K0441 + 498, K0441 + 668 - K0442 + 813 |
April 28, 2018 |
2018 |
310209100037000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Off-Carriageway Improvement - Tertiary Roads
Cagayan Apayao Rd (Tuao-Rizal Sect) - K0525 + 180 - K0525 + 278, K0525 + 360 - K0525 + 478, K0525 + 220 - K0525 + 478, K0525 + 506 - K0526 + 042 |
April 28, 2018 |
2018 |
310201100225000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
Santiago-Tuguegarao Rd - K0435 + 144 - K0436 + 226 |
April 28, 2018 |
2018 |
320102100262000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
OO2: Protect Lives and Properties: Flood Management - Construction/ Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Cagayan River Flood Control Project (Phase I), Sta. 0+000 – Sta. 0+170.40, Dabburab, Cauayan City, Isabela |
April 28, 2018 |
2018 |
300117200653000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
Local Program: Local – National Roads and Bridges – Local Roads – Local Infrastructure Program
Concreting of local roads, San Mateo, Isabela |
April 28, 2018 |
2018 |
320101101011000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
OO2: Protect Live and Properties Against Major Floods - Flood Management Program - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Magat River Flood Control Projects, Sta. 0+000 - Sta. 0+172.40, Lalog, Luna, Isabela |
April 28, 2018 |
2018 |
320101101009000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
OO2: Protect Live and Properties Against Major Floods - Flood Management Program - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Magat River Flood Control Project (Bridge Protection Works) San Roque, San Mateo, Isabela |
April 28, 2018 |
2018 |
320102100264000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Cagayan River Flood Control Project (Phase I),Sta. 0+000 – Sta. 0+174, Amobocan, Cauayan City, Isabela |
April 28, 2018 |
2018 |
320101101012000 |
GAA FY 2018 |
January 1, 2018 |
Region II |
Isabela 3rd District Engineering Office |
OO2: Protect Live and Properties Against Major Floods - Flood Management Program - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Magat River Flood Control Projects, Sta. 0+000 - Sta. 0+172.40, Pulay, Luna, Isabela |
April 27, 2018 |
FY- 2018 |
WIN8F05306 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Mindoro Oriental District Engineering Office |
Local Program
Local - Flood Control and Drainage - Flood Control Structures/
Facilities - Construction/Repair/Rehabilitation/Improvement
of various Infrastructure including Local Projects
FROM:
Construction of Flood Control/Drainage System,
Bucayao Gabion Armouring BBRIS,
Calapan, Oriental Mindoro
CW1: 134.40 l.m. (Construction of Flood Mitigation Structure)
Allocation: 25,000,000 Php
TO:
Construction of Flood Control/Drainage System,
Bucayao Gabion Armouring BBRIS,
Calapan, Oriental Mindoro
CW1: 114.00 l.m. (Construction of Flood Mitigation Structure)
Allocation: 25,000,000 Php |
April 27, 2018 |
FY - 2018 |
WIN8F05250 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Mindoro Oriental District Engineering Office |
Local Program
Local - Water Management Facilities - Water Supply -
Construction/Repair/Rehabilitation/Improvement of Various
Infrastructure including Local Projects
FROM:
Construction of Water Supply System Level III, Barangays
San Antonio, Loyal, Sampaguita, San Cristobal, Antonio, Pakyas, Victoria, Oriental Mindodo
CW1: 1 ( Number of Water Systems )
Allocation: 30,000,000 Php
TO:
Construction of Water Supply System Level III,
Barangays San Antonio, Loyal, Sampaguita, San Cristobal,
Antonio, Pakyas, Victoria, Oriental Mindodo
CW1: 6 ( Number of Water Systems )
Allocation: 30,000,000 Php |
April 27, 2018 |
FY - 2018 |
WIN8F05401 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Southern Mindoro Engineering District Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance -
Secondary Roads
FROM:
Calapan South Rd
K0164+650 - K0164+850,
K0168+150 - K0168+500,
K0174+000 - K0174+100,
K0174+785 - K0174+894,
K0175+000 - K0175+041
CW1: 1.6000 lane km ( Preventive Maintenance of Road:
Concrete Reblocking )
Allocation: 7,124,000 Php
TO:
Calapan South Road
K0164+650 - K0164+681.80,
K0164+745.30 - K0164+804.20,
K0164+822.30 - K0164+500,
K0174+068.70 - K0174+100,
K0174+785 - K0174+894,
K0175+000 - K0175+041
CW1: 0.8621 lane km ( Preventive Maintenance of Road:
Concrete Reblocking )
Allocation: 7,124,000 Php
K |
April 27, 2018 |
FY - 2018 |
WIN8F05363 |
FY - 2018 DPWH GAA Infra Program |
December 19, 2017 |
Region IV-B |
Southern Mindoro Engineering District Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
FROM:
Calapan South Rd
K0188+000 - K0188+345,
K0189+000 - K0189+122
CW1: 0.934 lane km ( Preventive Maintenance of Road :
Concrete Reblocking )
Allocation: 4,158,000 Php
TO:
Calapan South Road
K0188+060 - K0188+258,
K0189+112.80 - K0189+122
CW1: 0.4144 lane km ( Preventive Maintenance of Road:
Concrete Reblocking )
Allocation: 4,158,000 Php
|
April 27, 2018 |
FY - 2018 |
WIN8F05284 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
002 -Protect Lives and Properties Against Major Floods
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Control and Mitigation Structure Along Bgy. Sta. Monica, Puerto Princesa South Road
CW1: 20 lineal meters ( Construction of Flood Mitigation
Structure )
Allocation; 5,000,000 Php
TO:
Construction of Flood Control and Mitigation Structure along Bgy. Sta. Monica, Puerto Princesa South Road
CW1: 491 lineal meters ( Construction of Flood Mitigation
Structure )
Allocation: 5,000,000 Php |
April 27, 2018 |
FY 2018 |
WIN8G02117 |
FY 2018 GAA |
January 4, 2018 |
Region III |
Pampanga 3rd District Engineering Office |
Flood Management Program – Construction / Maintenance of Flood Mitigation Structures and Drainage Systems – Slope Protection works along Quitangil Creek, Brgy. Bundagul and Paralayunan, Mabalacat City, Pampanga |
April 27, 2018 |
FY - 2018 |
WIN8F05288 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
Local Program
Buildings and Other Structures - Multipurpose/Facilities
Local Infrastructure Program
FROM:
Construction of Multi-Purpose Building
(Philippine Councilor's League) at PEO Compound,
Brgy. Bancao-Bancao, Puerto Princesa City, Palawan
CW1: 1 Building ( Construction of Multi-Purpose Building )
Allocation: 1,000,000 Php
TO:
Construction of Multi-Purpose Building
(Philocal Infrastructure Programpine Councilor's League)
at PEO Compound. Brgy. Bancao-Bancao,
Puerto Princesa City
CW1; 1 Building ( Construction of Multi-Purpose Building )
Allocation: 1,000,000 Php
|
April 27, 2018 |
FY - 2018 |
WIN8F05297 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
Convergence and Special Support Program
Convergence and Special Support Program -
Construction/Improvement of Access Roads leading to Trades, industries and Economic Zones
FROM:
Sitio Communal Multi-Purpose Cooperative Road
connecting Barangay Road of Iraan in support of Oil Palm Industry, Iraan, Aborlan, Palawan
CW1: 5.60 lane km ( Construction of Concrete Road )
Allocation: 70,000,000 Php
TO:
Road Concreting - Sitio Communal Multi-Purpose Cooperativd Road connecting Barangay Road of Irran
in support of Oil Palm Industry, Iraan, Aborlan, Palawan
CW1: 7.472 lane km
Allocation: 70,000,000
|
April 27, 2018 |
FY - 2018 |
WIN8F05282 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 3rd District Engineering Office |
002 - Protect Lives and Properties Against Major Floods
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Flood Control and Drainage System along Puerto Princesa North Road
( Jct. PPNR - Honda Bay Road to Inabuyan Bridge ),
Palawan
CW1: 10 lineal meters ( Construction of Flood Mitigation
Structure )
Allocation: 10,000,000 Php
TO:
Construction of Flood Control And Drainage System along Puerto Princesa North Road
( Jct. PPNR - Honda Bay Road to Inabuyan Bridge ),
Palawan
CW1: 984.1 lineal meters ( Construction of Flood Mitigation
Structure )
Allocation: 10,000,000 Php |
April 27, 2018 |
2018 |
WIN8F05451 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Siquijor District Engineering Office |
ORGANIZATIONAL OUTCOME 1: Ensure Safe and Reliable National Road System, Bridge- Construction of New Permanent Bridges, Sinunogan Br. along Luyang-Poo-Lazi Rd |
April 27, 2018 |
2018 |
WIN8F05447 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1: Ensure Safe and RelIable National Road System, Asset Preservation Program--Rehabilitation/Reconstruction of Roads with slips, slope Collapse and Landslide-Cebu-Toledo Wharf Rd (Jct Naga-Uling)- K0024+240 - K0024+380, K0026+497.5 - K0026+900, K0026+900 - K0027+000, K0028+500 - K0028+550 |
April 27, 2018 |
2018 |
WIN8F05448 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1:Ensure Safe and Reliable National Road System, Asset Preservation Program -Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads- -Secondary Roads, Cebu North Hagnaya Wharf Rd- K0046 + 172 - K0046 +918, K0047 + 668 - K0047 + 777, K0067 + 000- K0068 + 000, K0072 + 110 - K0072 + 650, K0074 + 550 - K0075 + 000, K0075 + 830 -K0075 + 925 |
April 27, 2018 |
2018 |
WIN8F05450 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Local Programs - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/
Improvement of Various Infrastructure including Local Projects - Widening of Punta Engaño road, including ROW Acquisition , Lapu-lapu City, Cebu |
April 27, 2018 |
2018 |
WIN8F05450 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Local Programs - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/
Improvement of Various Infrastructure including Local Projects - Widening of Punta Engaño road, including ROW Acquisition , Lapu-lapu City, Cebu |
April 27, 2018 |
2018 |
WIN8C02637 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1: Ensure Safe and Reliable National Roads system, Network Development Program, Construction of Missing Links/New roads Bayawan-Kabankalan Road , incl ROW, Package A, Negros Oriental |
April 27, 2018 |
2018 |
WIN8C02636 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1: Ensure Safe and Reliable National Roads system, Network Development Program, Construction of Missing Links/New roads Bayawan-Kabankalan Road , incl ROW, Package B, Negros Oriental |
April 27, 2018 |
2018 |
WIN8C02638 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizatioinal Outcome 1: Ensure Safe and Reliable National Road System, Asset Preservation-Rehabilitation/Reconstruction of Roads, with Slips, Slope Collapse and Landslide-Tertiary Roads, Sibonga-Dumanjug Rd K0055+554 - K0057+580, K0057+937 - K0058+592, K0059+546 - K0059+706.50, K0059+706.50 - K0059+946, K0060+749 - K0061+720, K0062+846 - K0063+406, K0063+406 - K0063+832, K0063+870 - K0065+000 |
April 27, 2018 |
2018 |
WIN8F05449 |
R.A. 10964 |
December 19, 2017 |
Region VII |
Regional Office VII |
Organizational Outcome 1:Ensure Safe and Reliable National Road System, Network Development Program -Road Widening - Secondary Roads - Cebu North Hagnaya Wharf Rd - K0034+648-K0035+000, K0052+000-K0055+648 |
April 27, 2018 |
2018 |
WIN8C02603 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Regional Office XIII |
OO 1 : Ensure Safe and Reliable National Road System
Network Development – Construction of Missing Links/New Roads
FROM:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 8, Agusan del Sur
Project Component ID: P00200567MN
Scope of Work: Construction of Concrete Road
Physical Target: 19.234 lane km
Allocation: Php 300,000,000 (Total)
Php 289,500,000 (Road)
Php 10,500,000 (EAO)
TO:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 8, Agusan del Sur
Project Component ID: P00200567MN
Scope of Work: Construction of Gravel Road
Physical Target: 9.18 lane km
Allocation: Php 300,000,000 (Total)
Php 289,500,000 (Road)
Php 10,500,000 (EAO) |
April 27, 2018 |
2018 |
WIN8C02604 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Regional Office XIII |
OO 1 : Ensure Safe and Reliable National Road System
Network Development – Construction of Missing Links/New Roads
FROM:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 13, Agusan del Sur
Project Component ID: P00200563MN
Scope of Work: Construction of Gravel Road
Physical Target: 7.272 lane km
Allocation: Php 200,000,000 (Total)
Php 193,000,000 (Road)
Php 7,000,000 (EAO)
TO:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 13, Agusan del Sur
Project Component ID: P00200563MN
Scope of Work: Construction of Gravel Road
Physical Target: 4.40 lane km
Allocation: Php 200,000,000 (Total)
Php 193,000,000 (Road)
Php 7,000,000 (EAO)
|
April 27, 2018 |
2018 |
WIN8C03018 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Regional Office XIII |
OO1 : Ensure Safe and Reliable National Road System
Network Development - Construction of Missing Links/New Roads
FROM:
Cabadbaran – Puting Bato – Lanuza Road, Surigao del Sur
Project Component ID: P00200561MN
Scope of Work: Construction of Gravel Road
Physical Target: 12.10 lane km
Allocation: Php 270,000,000 (Total)
Php 260,550,000 (Road)
Php 9,450,000 (EAO)
TO:
Cabadbaran – Puting Bato – Lanuza Road, Surigao del Sur
Project Component ID: P00200561MN
Scope of Work: Construction of Gravel Road
Physical Target: 7.00 lane km
Allocation: Php 270,000,000 (Total)
Php 260,550,000 (Road)
Php 9,450,000 (EAO)
|
April 27, 2018 |
2018 |
WIN8C02568 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Regional Office XIII |
OO1 : Ensure Safe and Reliable National Road System
Network Development – Construction of Missing Links/New Roads
FROM:
Butuan City – Pianing – Tandag Road (Tandag Section), Surigao del Sur
Project Component ID: P00200558MN
Scope of Work: Construction of Gravel Road
Physical Target: 8.00 lane km
Allocation: Php 180,000,000 (Total)
Php 173,700,000 (Road)
Php 6,300,000 (EAO)
TO:
Butuan City – Pianing – Tandag Road (Tandag Section), Surigao del Sur
Project Component ID: P00200558MN
Scope of Work: Construction of Gravel Road
Physical Target: 3.64 lane km
Allocation: Php 180,000,000 (Total)
Php 173,700,000 (Road)
Php 6,300,000 (EAO) |
April 27, 2018 |
2018 |
WIN8C02630 |
FY 2018 GAA RA 10964 |
December 19, 2017 |
Region XIII |
Regional Office XIII |
OO1 : Ensure Safe and Reliable National Road System
Network Development – Construction of Missing Links/New Roads
FROM:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 14, Agusan del Sur
Project Component ID: P00200564MN
Scope of Work: Construction of Gravel Road
Physical Target: 7.272 lane km
Allocation: Php 200,000,000 (Total)
Php 193,000,000 (Road)
Php 7,000,000 (EAO)
TO:
Completion of the East-West lateral road connecting Agusan Del Sur/Agusan del Norte to Bukidnon Sampaguita - Makilos (Agusan del Sur/Bukidnon Boundary), Package 14, Agusan del Sur
Project Component ID: P00200564MN
Scope of Work: Construction of Gravel Road
Physical Target: 4.32 lane km
Allocation: Php 200,000,000 (Total)
Php 193,000,000 (Road)
Php 7,000,000 (EAO)
|
April 26, 2018 |
FY - 2018 |
WIN8F05276 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Support Program
Convergence and Special Support Program -
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
FROM:
Access Road from Coron Town Proper to Borac Roro Port,
Coron, Palawan
CW1: 4.78 lane km ( Construction of Concrete Road )
Allocation; 75,000,000 Php
TO:
Access Road from Coron Town Proper to Borac Roro Port,
Coron, Palawan
CW1: 4.154 lane km ( Construction of Concrete Road )
Allocation: 75,000,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05248 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Special Support Program
Convergence and Special Support Program -
Construction/Improvement of Access Roads leading to Declared Tourism Destinations
FROM:
New Agutaya - Alimanguan Tourism Road leading to
San Vicente Long Beach, San Vicente, Palawan
CW1: 1.18 lane km ( Construction of Concrete Road )
Allocation: 13,000,000 Php
TO:
New Agutaya - Alimanguan Tourism Road leading to
San Vicente Long Beach, San Vicente, Palawan
CW1: 0.816 lane km ( Construction of Concrete Road )
Allocation: 13,000,000 Php
|
April 26, 2018 |
FY - 2018 |
WIN8F05270 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse and Landslide -
Secondary Roads
FROM:
Puerto Princesa North Rd
K0082+523 - K0082+596,
K0188+257 - K0188+434,
K0225+026 - K0225+085,
K0266+067 - K0266+165,
K0266+190 - K0266+350
CW1: 11,151 sq.m. ( Construction of Road Slope Protection Structure )
Allocation; 97,503,000 Php
TO:
Puerto Princesa North Rd
K0266+067 - K0266+140,
K0266+240 - K0266+290,
K0225+026 - K0225+086
CW1: 5,375 sq.m. ( Construction of Road Slope
Protection Structure )
Allocation: 97,503,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05223 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Preventive maintenance - Tertiary Roads
FROM:
Looc ( Cogon Tulay ) - Odiongan Rd
K0119+000 - K0120+300
CW1: 2.516 lane km ( Preventive Maintenance of Road )
Allocation: 11,203,000 Php
TO:
Looc ( Cogon Tulay ) - Odiongan Rd
K0110+225.70 - K0113+599.70,
K0113+728.4 0- K0115+941.20,
K0116+007.90 - K0117+032.60,
K0117+109.80 - K0117+832.10,
K0117+854.70 - K0120+54+.60
CW1: 2.544 lane km ( Preventive Maintenance of Road )
Allocation: 11,203,000 hp |
April 26, 2018 |
FY - 2018 |
WIN8F05323 |
FY - 2018 GAA DPWG Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslides
- Secondary Roads
FROM:
Sibuyan Circumferential Rd
K0033+896 - K0034+108
CW1: 5,411 square meters ( Construction of Road Slope Protection Structure )
Allocation: 89,270,000 Php
TO:
Sibuyan Circumferential Rd
K0039+420 - K0039+570
CW1: 3,822.30 square meters ( Construction of Road Slope Protection Structure )
Allocation: 89,270,000 Php
|
April 26, 2018 |
FY - 2018 |
WIN8F05247 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
FROM:
Dapawan - Torrel Rd
K0001+(-828) - K0001+000,
K0001+971 - K0003+085
CW1: 3.886 lane km ( Rehabilitation of Paved Road )
Allocation: 60,134,000 Php
TO:
Dapawan - Torrel Rd
K0001+( -825 ) - L0001+074,
K0001+971 - K0002+781,
K0002+781 - K0003+085
CW1: 4.026 lane km ( Rehabilitation of paved Road )
Allocation: 60,134,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05310 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement -
Secondary Roads
FROM:
Sibuyan Circumferential Rd
K0000+632 - K0002+850,
K0003+104 - K0006+119,
K0073+1003 - K0075+720
CW1: 20,736 square meters ( Off-Carriageway Improvement )
Allocation: 67,728,000 Php
TO:
Sibuyan Circumferential Rd
K0000+632 - K0002+935,
K0003+104 - K0006+114.25,
K0073+1003 - K0075+677.85
CW1: 20,795.49 square meters ( Off-Carriageway Improvement )
Allocation: 67,728,000 php
|
April 26, 2018 |
FY - 2018 |
WIN8F05295 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable national Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide -
- Secondary Roads
FROM:
Romblon - Cogon - Sablayan Rd
K00019+300 - K0019+400,
K0015+730 - K0015+780,
K0015+980 - K0016+020,
K0019+000 - K0019+699
CW1: 5,156 square meters ( Construction of Road Slope Protection Structure )
Allocation: 56,500,000 Php
TO:
Romblon - Cogon - Sablayan Rd
K0014+469.40 - K0014+525.30,
K0014+531.20 - K0014+611.50,
K0014+615 - K0014+720,
K0014+734 - K0014+860,
K0015+714 - K0016+020,
K0016+160 - K0016+244.70,
K0016+246.53 - K0016+480,
K0016+498.50 - K0016+600,
K0016+602.18 - K0016+649.17,
K0016+651.35 - K0016+805.40,
K0017+890.20 - K0017+906.80,
K0017+908.63 - K0017+940,
K0017+940.50 - K0017+975.50,
K0017+977.33 - K0018+056.40,
K0018+058.23 - K0018+232.70,
K0018+234.83 - K0018+320,
K0018+321.83 - K0018+455.80,
K0018+457.03 - K0018+622.90,
K0018+624.73 - K0018+820,
K0019+400 - K0019+760
CW1: 7,410.62 square meters
Allocation: 56,500,000 Php
|
April 26, 2018 |
FY - 2018 |
WIN8F05309 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road SYstem
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged paved Roads - Secondary Roads
FROM:
Sibuyan Circumferential Rd
K0075+937 - K0076+138
CW1: 0.358 lane km ( rehabilitation of Paved road )
Allocation: 5,551,000 Php
TO:
Sibuyan Circumferential Rd
K0075+937 - K0076+252
CW1: 0.586 lane km ( Rehabilitation of Paved Road )
Allocation: 5,551,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05273 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide -
Secondary Roads
FROM;
Tablas Circumferential Road
K0069+000 - K0069+600
CW1: 3,600 square meters ( Construction of Road Slope Protection Structure )
Allocation: 25,000,000 Php
TO:
Tablas Circumferential Rd
K0069+090 - K0069+160,
K0069+190 - K0069+340,
K0069+345 - K0069+538,
K0069+543 - K0069+625,
K0069+635 - K0069+840
CW1: 5,113.15 square meters ( Construction of Road Slope Protection Structure )
Allocation: 25,000,000 Php
|
April 26, 2018 |
FY - 2018 |
WIN8F05312 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and landslide -
Tertiary Roads
FROM:
Looc ( Cogon Tulay ) - Odiongan Rd
K0111+917.37 - K0112+128.40,
K00115+010 - k0115+190
CW1: 3,882 square meters ( Construction of Road Slope Protection Structure )
Allocation: 48,600,000 Php
TO:
Looc ( Cogon Tulay ) - Odiongan Rd
K0111+744 - K0112+000,
K0115+002 - K0115+320
CW1: 3,238.80 square meters ( Construction of Road Slope Protection Structure )
Allocation: 48,600,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05319 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Off- Carriageway Improvement
- Secondary Roads
FROM:
Romblon - Cogon - Sablayan Rd
K0007+280 - K0008+708,
K0011+000 - K0013+724,
K0013+915 - K0014+430,
K0015+792 - K0016+009,
K0017+054 - K0017+356,
K0017+659 - K0017+861
CW1: 16,164 square meters ( Off-Carriageway
Improvement )
Allocation: 51,000,000 Php
TO:
Romblon - Cogon - Sablayan Rd
K0007+280 - K0008+699.40,
K0011+000 - K0013+710.40,
K0013+871.30 - K0014+430,
K0015+714.50 - K0016+020,
K0017+035 - K0017+372,
K0017+646.40 - K0017+880
CW1: 15,290.84 square meters ( Off-Carriageway
Improvement )
Allocation: 51,000,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05281 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National ROad System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
FROM:
Odiongan - East - West Rd
K0003+ (- 176) - K0003+724,
K0004+633 - K0005+000
CW1: 2.560 lane km ( Rehabilitation oof Paved Road )
Allocation: 39,692,000 Php
TO:
Odiongan - East - West Rd
K0003+ (-176) - K0003+724,
K0004+602 - K0005+000
CW1: 2.62 lane km ( Rehabilitation of Paved Road )
Allocation: 39,692,000
|
April 26, 2018 |
FY - 2018 |
WIN8F05278 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National roads with Slips, Slope Collapse, and Landslide
- Secondary Roads
FROM:
Tablas Circumferential Rd
K0026+580 - K0027+220,
K0027+480 - K0027+930,
K0040+600 - K0040+680
CW1: 7,450 square meters ( Construction of Road Slope Protection Structure )
Allocation: 99,081.000 Php
TO:
Tablas Circumferential Rd
K0026+580 - K0026+722,
K0026+760.75 - K0027+010,
K0040+600 - K0040+720
CW1: 4,346.40 square meters ( Construction of Road Slope Protection Structure )
Allocation: 99,081,000 Php |
April 26, 2018 |
FY - 2018 |
WIN8F05277 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Romblon District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads- Tertiary Roads
FROM:
Looc ( Cogon Tulay ) - Odiongan Rd
K0103+ (-303) - K0103+000,
K0104+409 - K0104+912
CW1: 10612 lane km ( Rehabilitation of Pved Road )
Allocation: 24,994,000 Php
TO:
Looc ( Cogon Tulay ) - Odiongan Road
K0103+(-303) - K0103+008.78,
K0104+409 - K0104+838.68
CW1: 1.483 lane km ( rehabilitation of Paved Road )
Allocation: 24,994,000 Php |
April 25, 2018 |
FY - 2018 |
WIN8F05230 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 2nd District Engineering Office |
Local Program
Local Infrastructure Program - Buildings and Other Structures - Multipurpose/Facilities
FROM:
Construction of Senior Citizens Federation Building,
Brgy. Poblacion. Sofronio Espanola, Palawan
CW1: 1 Building ( Construction of Multi-Purpose Building )
Allocation: 1,000,000 Php
TO:
Construction of Sr. Citizen Federation Building,
Brgy. Pulot Center, Sofronio Espanola, Palawan
CW1: 1 Building ( Construction of Multi-Purpose Building )
Allocation: 1,000,000 Php
|
April 25, 2018 |
FY - 2018 |
WIN8F05234 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 2nd District Engineering Office |
Local Program
Local Infrastructure Program - Buildings and Other Structures
- School Buildings
FROM:
Construction of one (1) Classroom Building in Pob. 2 Elementary School, Poblacion 2, Balabac, Palawan
CW1: 1 classroom ( Construction of 1-storey Classrooms)
Allocation: 1,100,000 Php
TO:
Construction of one (1) Classroom Building Balabac Central School, Balabac, Palawan
CW1: 1 classroom ( Construction of 1-storey Classrooms )
Allocation: 1,100,000 Php
|
April 25, 2018 |
FY - 2018 |
WIN8F05210 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 2nd District Engineering Office |
Local Program
Local Infrastructure Program - Buildings and Other Structures
- Schgool Buildings
FROM:
Construction of one (1) Classroom Building in Pob. 4 Elementary School, Poblacion 4, Balabac, Palawan
CW1: 1 Classroom ( Construction of 1-storey Classrooms )
Allocation; 1,100,000 Php
TO:
Construction of one (1) Classroom Building Balabac Central School, Balabac, Palawan
CW1: 1 Classroom ( Construction of 1-storey Classrooms )
Allocation; 1,100,000 Php |
April 25, 2018 |
FY - 2018 |
WIN8F05294 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence and Special Support Program
Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Declared Tourism Destinations
FROM:
Guadalupe - San Nicolas - Borac - Roro Port, Coron
CW1: 4.0 lane km ( Construction of Concrete Road )
Allocation: 60,000,000 Php
TO:
Guadalupe - San Nicolas - Borac Roro Port, Coron
CW1: 3.45 lane km ( Construction of Concrete Road )
Allocation: 60,000,000 Php |
April 25, 2018 |
FY- 2018 |
WIN8F5292 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
001 - Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement
- Secondary Roads
FROM;
Puerto Pincesa North Rd.
K0193+000 - K0194+000,
K0206+000 - K0207+000,
K0209+915 - K0211+000
CW1: 8,139 sq.m. ( Off-Carriageway Improvement
Shoulder Paving/Construction )
Allocation: 70,967,000 Php
TO:
Puerto Princesa North Rd
K0192+681 - K0194+000,
K0206+000 - K0207+000,
K0211+ (-667) - K211+000
CW1: 18,234 sq.m. ( Off-Carriageway Imrovement
Shoulde Paving/Construction )
Allocation; 70,967,000 Php |
April 25, 2018 |
FY - 2018 |
WIN8F05296 |
FY - 2018 GAA DPWH Infra Program |
December 19, 2017 |
Region IV-B |
Palawan 1st District Engineering Office |
Convergence Special Support Program
Convergence and Special Support - Construction/Improvement of Access Roads leading to Declare Tourism Destination
FROM:
San Jose - Port Barton Road leading to various resorts in Port Barton, San Vicente, Palawan
CW1: 2.722 lane km ( Construction of Concrete Road )
Allocation: 55,000,000 Php
TO:
San Jose - Port Barton leading to various resorts in Port Barton, San Vicente, Palawan
CW1: 2.128 lane km ( Construction of Concrete Road )
Allocation; 55,000,000 Php
- |