June 11, 2021 |
2021 |
WIN1C03928 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Baliwag - Candaba - Sta. Ana Rd, K0075+650 - K0076+141
|
June 11, 2021 |
2021 |
WIN1C03923 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bataan 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Secondary Roads
Tabacan Poblacion Rd, K0102 +(-127) - K0102+047, K0102+349 - K0102+593
|
June 11, 2021 |
2021 |
WIN1C03934 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bataan 1st District Engineering Office |
Convergence and Special Support - Special Road - Motor Vehicle Users Charge (MVUC) as per R. A. 11239
Preventive Maintenance (Asphalt Overlay) along Jct. Layac - Balanga - Mariveles port Rd (S01272LZ), K0107+980 - K0108+750, K0111+000 - K0113+143, Orani and Samal, Bataan |
June 11, 2021 |
2021 |
WIN1C03922 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Jose Abad Santos Ave (JASA), K0108+587.50 - K0108+827.30, K0112+000.00 - K0112+848.80 |
June 10, 2021 |
FY 2021 |
WIN1F06058 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS NO.: 310202100707000
Project ID : P00505154LZ
001: Ensure Safe and Reliable National Road Systems
Network Development - Road Widening - Secondary Roads
FROM:
Puerto Princesa North Road
K0082+(-672) - K0084+835
Physical Target: CW1 - Road Widening: 6.996 Lane Km
Allocation : Php 104.940 Million
TO:
Puerto Princesa North Road
K0213+740 - K0216+283
Physical Target: CW1 - Road Widening: 5.058 Lane Km
Allocation : Php 104.940 Million |
June 10, 2021 |
FY 2021 GAA |
WIN1F06065 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310202100709000
Project ID : P00505157LZ
001: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM:
Puerto Princesa South Road
K0101+000 - K0101+908,
K0101+1001 - K0104+334
Physical Target: CW1 - Road Widening: 6.514 Lane Km
Allocation : Php 105.00 Million
TO:
Puerto Princesa South Road
K0101+000 - K0101+908,
K0101+1001 - K0102+332,
K0102+726 - K0104+776
Physical Target : CW1 - Road Widening - 6.610 Lane Km
Allocation : Php 105.00 Million |
June 10, 2021 |
FY 2021 GAA |
WIN1F06179 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310202100708000
Project ID : P00505158LZ
001: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM:
Puerto Princesa South Road
K0022+595 - K0022+974,
K0023+049 - K0023+650,
K0025+024 - K0027+156,
K0029+962 - K0030+681,
K0030+772 - K0031+045
Physical Target : CW1 - Road Widening: 8.466 Lane Km
Allocation : Php 103.00 Million
TO:
Puerto Princesa South Road
K0022+595 - K0022+974,
K0023+049 - K0023+650,
K0025+024 - K0027+156
Physical Target : CW1 - Road Widening: 6.336 Lane Km
Allocation : Php 103.00 Million |
June 10, 2021 |
FY 2021 GAA |
WIN1F06073 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310202100706000
Project ID : P00505159LZ
001: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM:
Puerto Princesa North Road
K0034+000 - K0035+000,
K0037+1004 - K0038+000,
K0039+000 - K0040+000
Physical Target : CW1 - Road Widening : 4.006 Lane Km
Allocation : Php 102.485 Million
TO:
Puerto Princesa North Road
K0034+000 - K0035+000,
K0037+1004 - K0038+000,
K0039+000 - K0041+161
Physical Target : CW1 - Road Widening : 6.330 Lane Km
Allocation : Php 102.485 Million |
June 10, 2021 |
FY 2021 GAA |
WIN1F06066 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310202100701000
Project ID : P00505160LZ
001: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Secondary Roads
FROM:
Irawan - Tagburos Road
K0012 + (-667) - K0012 + (-291),
K0012+1003 - K0015+1007
Physical Target : CW1 - Road Widening : 6.808 Lane Km
Allocation : Php 101.875 Million
TO:
Irawan - Tagburos Road
K0012 + (-667) - K0012+ (-291),
K0012 + 1003 - K00160+176
Physical Target : CW1 - Road Widening ; 7.162 Lane Km
Allocation : Php 101.875 Million |
June 10, 2021 |
FY 2021 GAA |
WIN1F06151 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310102100586000
Project ID : P00505408LZ
001: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
FROM:
Calapan South Road
K0071+000 - K0072+850
Physical Target : CW1 - Preventive maintenance of Road :
Asphalt Overlay : 6.976 Lane Km
Allocation : Php 25.00 Million
TO :
Calapan South Road
K0071 + 000 - K0071 + 867
Physical Target : CW1 - Preventive Maintenance :
Asphalt Overlay : 1.734 Lane Km
Allocation : Php 25.00 Million
|
June 10, 2021 |
2021 |
WIN1C03892 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road, K0064+879 - K0065+357
|
June 10, 2021 |
FY 2021 GAA |
WIN1F06152 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No.: 310109100555000
Project ID : P00505813LZ
001: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of
National Roads with Slips, Slope Collapse,
and Landslide - Tertiary Roads
FROM:
F.B. Reyes ( Busuanga - Coron ) Road
K0012 + 810 - K0015 + 550,
K0020 + 763.98 - K0022 + 673.98
Physical Target : CW1 - Construction of Road Slope Protection :
5,750.00 square meter
Allocation : Php 115.00 Million
TO:
F.B. Reyes ( Busuanga - Coron ) Road
K0011 + 121 - K0011 + 220.00,
K0011 + 260 - K0011 + 393.00
Physical Target : CW1 - Construction of Road Slope protection:
5,094.00 square meter
Allocation : Php 115.00 Million |
June 10, 2021 |
2021 |
WIN1C03901 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
NCR / Bulacan Bdry. - Bigte - Ipo Dam Road, K0037+102 - K0037+383.55 |
June 10, 2021 |
2021 |
WIN1C03895 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Muzon - Tungkong Manga Road, K0042+000 - K0042+644.65 |
June 8, 2021 |
2021 |
WIN1C03869 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road, K0142+891 - K0143+160 |
June 8, 2021 |
2021 |
WIN1C03830 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Camiling - Agno River Floodway Phase 1, Sta. 0+000 - Sta. 0+280.86, Camiling, Tarlac |
June 8, 2021 |
2021 |
WIN1C03829 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Asset Preservation - Preventive Maintenance - Primary Roads
Manila North Road, K0138+533.90 - K0138+812.60 |
June 8, 2021 |
2021 |
WIN1C03864 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Asset Preservation - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads
Manila North Road,K0156+350 - K0157+081
|
June 8, 2021 |
2021 |
WIN1C03841 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Gapan - Fort Magsaysay Rd - K0099+510.00 - K0099+828.32 |
June 8, 2021 |
2021 |
WIN1F06210 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Tacloban City District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
AS PER GAA/ORIGINAL:
Apitong - Paterno Road – K0908+(-015) – K0908 +000, K0908 + (-017) – K0908 + (-015), K0908 + (-350) – K0908 +(-017), K0908 + (-915) – K0908 + (-896), K0908 + (-922) – K0908 + (-915), K0908 + 000 – K0908 + 058
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: Asphalt P 9.604980 M
Overlay: 1.710 Lane Km
EAO P 0.196020 M
Total P 9.801 M
AS MODIFIED:
Apitong - Paterno Road – (S00017LT) K0908+(-339) – K0908 +058
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: Asphalt P 9.604980 M
Overlay: 1.588 Lane Km
EAO P 0.196020 M
Total P 9.801 M
|
June 8, 2021 |
2021 |
win1c03858 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Secondary Roads
Nueva Ecija - Aurora Rd, K0145+(-666) - K0145+000, K0145+000 - K0145+887.00
|
June 8, 2021 |
2021 |
WIN1F06208 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Tacloban City District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Tertiary Roads
AS PER GAA/ORIGINAL:
Sn Jose-Manlurip-MacArthur Park Rd - K0912 + (-266) - K0912 + 117
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 8.604400 M
Asphalt Overlay : 1.532 Lane Km
EAO P 0.175600 M
Total P 8.780 M
AS MODIFIED:
Preventive Maintenance - Sn Jose-Manlurip-Macarthur Park Rd- K0912 +(-336) – K0912 + (-004) (S00252LT) Chainage 0 – Chainage 59
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 8.604400 M
Asphalt Overlay : 1.387 Lane Km
EAO P 0.175600 M
Total P 8.780 M
|
June 8, 2021 |
2021 |
WIN1C03806 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Construction of Peñaranda River Flood Control, Sta. 4+148.77 to Sta. 4+419.17, Brgy. Malapit, San Isidro, Nueva Ecija |
June 8, 2021 |
2021 |
WIN1C03822 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Rehabilitation of Pampanga River Control, Sta. 0+000 - Sta. 0+540.80, Brgy. Calaba, San Isidro, Nueva Ecija |
June 8, 2021 |
2021 |
WIN1F06216 |
GAA FY 2021 |
February 1, 2021 |
Region VIII |
Leyte 4th District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development – Road Widening – Primary Road
AS PER GAA/ORIGINAL:
Road Widening – Palo-Carigara-Ormoc Rd – K0988+060.11 – K0989+073
Physical Target: Allocation:
CW1-Road Widening :1.00 Lane K m P 17.186260 M
EAO P 0.350740 M
Total P 17.537 M
AS MODIFIED:
Road Widening – Palo-Carigara-Ormoc Road – K0988+060 – K988+560
Physical Target: Allocation:
CW1-Road Widening : 1.00 Lane K m P 17.186260 M
EAO P 0.350740 M
Total P 17.537 M
|
June 8, 2021 |
2021 |
WIN1F06217 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Biliran District Engineering Office |
Local Program
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
AS PER GAA/ORIGINAL:
Construction of Access Road Leading to Pondol Falls, Naval, Biliran
Physical Target: Allocation:
CW1-Construction of Concrete Road P 20.580 M
: 1.814 Lane Km
EAO P 0.420 M
Total P 21.00 M
AS MODIFIED:
Construction of Access Road Leading to Pondol Falls, Almeria, Biliran
Physical Target: Allocation:
CW1-Construction of Concrete Road P 20.580 M
: 0.896 Lane Km
EAO P 0.420 M
Total P 21.00 M
|
June 7, 2021 |
FY 2021 GAA |
WIN1G02902 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way - K1764+184 - K1765+957
Physical Target:
CW1: 3.510 Lane Km (Road Widening)
Allocation:
TOTAL: P 85,000,000.00
CW1: P 82,025,000.00 (Road Widening)
EAO: P 2,975,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pres. Diosdado P. Macapagal Natl Hi-way - K1735+883 - K1736+069,
K1736+140 - K1736+314, K1764+191 - K1765+1005
Physical Target:
CW1: 3.996 Lane Km (Road Widening)
ROW: 33,000.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 85,000,000.00
CW1: P 71,410,000.00 (Road Widening)
ROW: P 10,615,000.00 (ROW Acquisition)
EAO: P 2,975,000.00 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02907 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Babak-Samal-Kaputian Rd - K1507+860 - K1509+062
Physical Target:
CW1: 2.272 Lane Km (Road Widening)
Allocation:
TOTAL: P 32,631,000.00
CW1: P 31,488,915.00 (Road Widening)
EAO: P 1,142,085.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Babak-Samal-Kaputian Rd - K1507+860 - K1509+062
Physical Target:
CW1: 1.500 Lane Km (Road Widening)
ROW: 11,250.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 32,631,000.00
CW1: P 25,505,915.00 (Road Widening)
ROW: P 5,983,000.00 (ROW Acquisition)
EAO: P 1,142,085.00 |
June 7, 2021 |
2021 |
310104100285000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads - Manila North Rd - K0603+724 - K0604+307 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02906 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Preventive Maintenance (Asphalt Overlay) - Davao City Div Rd, K1514+819 - K1515+911
Physical Target:
CW1: 16.781 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 201,060,000.00
CW1: P 194,022,900.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 7,037,100.00
TO: Convergence and Special Support Program - Special Road Fund - Motor Vehicle Users Charge (MVUC) as per R.A. 11239
Preventive Maintenance (Asphalt Overlay) - Davao City Div Rd, K1498+-165 - K1506+931
Physical Target:
CW1: 12.954 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 201,060,000.00
CW1: P 194,022,900.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 7,037,100.00 |
June 7, 2021 |
2021 |
320101106584000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Flood - Flood Management - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Reconstruction of Canayun - Sirit - Dana-ili Flood Control Along Abulug River, Abulug, Cagayan Sta. 12+860 - Sta. 12+980(L/S) |
June 7, 2021 |
FY 2021 GAA |
WIN1G02904 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Tubo-tubo Road connecting Monkayo Public Transport Terminal and SACARBEMCO Rubber Sheet Processing, SEMPCO Organic Fertilizer in support of Rubber, Palm Oil and Cardava Industries, Brgy. Tubo-tubo, Monkayo, Compostela Valley
Physical Target:
CW1: 2.470 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Concrete Road)
EAO: P 600,000.00
TO: Convergence and Special Support Program - Construction/Improvement of Access Roads leading to Trades, Industries and Economic Zones
Tubo-tubo Road connecting Monkayo Public Transport Terminal and SACARBEMCO Rubber Sheet Processing, SEMPCO Organic Fertilizer in support of Rubber, Palm Oil and Cardava Industries, Brgy. Tubo-tubo, Monkayo, Compostela Valley
Physical Target:
CW1: 1.770 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 29,400,000.00 (Construction of Concrete Road)
EAO: P 600,000.00 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02901 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Concreting Road, King-King, Pantukan, Davao de Oro
Physical Target:
CW1: 1.266 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Concreting Road, King-King, Pantukan, Davao de Oro
Physical Target:
CW1: 2.090 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00 |
June 7, 2021 |
2021 |
310201100741000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Manila North Rd - K0622+024 - K0622+295, K0623+215 - K0624+355 |
June 7, 2021 |
2021 |
310201100646000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Manila North Rd - K0660+620 - K0662+069 |
June 7, 2021 |
2021 |
310201100740000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Bangag - Magapit Rd - K0687+1019 - K0688+200, K0689+970 - K0689+992, K0690+057 - K0690+130, K0691+180 - K0691+934 |
June 7, 2021 |
2021 |
WIN1C03896 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Amungan - Palauig - Banlog Rd, K0217+760 - K0218+753 |
June 7, 2021 |
2021 |
310201100645000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Manila North Rd - K0654+322 - K0655+042, K0655+066 - K0655+388, K0655+411 - K0655+579 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02905 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Babak-Samal-Kaputian Rd - K1503+781 - K1505+000
Physical Target:
CW1: 2.364 Lane Km (Road Widening)
Allocation:
TOTAL: P 32,369,000.00
CW1: P 31,236,085.00 (Road Widening)
EAO: P 1,132,915.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Babak-Samal-Kaputian Rd - K1503+750 - K1504+524
Physical Target:
CW1: 1.500 Lane Km (Road Widening)
ROW: 11,250.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 32,369,000.00
CW1: P 25,253,085.00 (Road Widening)
ROW: P 5,983,000.00 (ROW Acquisition)
EAO: P 1,132,915.00 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02908 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of concreting road, Dona Josefa, Sta. Emelia Road (Phase 2), Laak, Davao de Oro
Physical Target:
CW1: 1.000 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00
TO: Local Program - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of concreting road, Dona Josefa, Sta. Emelia Road (Phase 2), Laak, Davao de Oro
Physical Target:
CW1: 1.300 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 15,000,000.00
CW1: P 14,700,000.00 (Construction of Concrete Road)
EAO: P 300,000.00 |
June 7, 2021 |
FY 2021 GAA |
WIN1G02909 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: Local Program - Water Management Facilities - Water Supply - Local Infrastructure Program
Concreting of Water System Level II/Spring Development, Sitio Malamig and Sitio Gaspang, Barangay Alegre, Bansalan, Davao del Sur
Physical Target:
CW1: 1 number of water supply system (Construction of Water Supply Systems)
Allocation:
TOTAL: P 4,000,000.00
CW1: P 3,960,000.00 (Construction of Water Supply Systems)
EAO: P 40,000.00
TO: Local Program - Water Management Facilities - Water Supply - Local Infrastructure Program
Construction of Water System Level II/Spring Development, Sitio Malamig and Sitio Gaspang, Barangay Alegre, Bansalan, Davao del Sur
Physical Target:
CW1: 1 number of water supply system (Construction of Water Supply Systems)
Allocation:
TOTAL: P 4,000,000.00
CW1: P 3,960,000.00 (Construction of Water Supply Systems)
EAO: P 40,000.00 |
June 7, 2021 |
2021 |
310107100201000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads - Manila North Rd - K0590+(-030) - K0590+(-010), K0590+100 - K0590+200, K0590+235 - K0590+265, K0590+750 - K0590+800, K0592+260 - K0592+284, K0592+950 - K0592+1000 |
June 7, 2021 |
2021 |
WIN1E02275 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Regional Office XIII |
UACS NO. 300119200432000
PROJECT ID: P00551501MN
Local Program - Local Roads and Bridges - Local Bridges - Local Infrastructure Program
FROM:
Construction of Las Nieves Bridge and Road Approaches in Cabadbaran City, Phase II, Agusan del Norte
Type of Work / Physical Target: Construction of
Bridge / 238.065 sq.m.
Unit Cost: P83,170.56/sq.m.
Allocation: P19,800,000
EAO: P200,000
TOTAL: P20,000,000
TO:
Construction of Las Nieves Bridge and Road Approaches in Las Nieves, Phase II, Agusan del Norte
Type of Work / Physical Target: Construction of
Steel Bridge / 5,234.6 sq.m.
Unit Cost: P3,782.52/sq.m.
Allocation: P19,800,000
EAO: P200,000
TOTAL: P20,000,000 |
June 7, 2021 |
2021 |
320102104064000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
OO2: Protect Lives and Properties Against Major Flood - Flood Management - Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Reconstruction of Canayun - Sirit - Dana-ili Flood Control Along Abulug River, Abulug, Cagayan Sta. 12+700 - Sta. 12+860, Sta. 13+220 - Sta. 13+300(L/S) |
June 7, 2021 |
2021 |
300116203974000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Cagayan 2nd District Engineering Office |
Local Program: Local - Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Concreting of Colony Road, Libertad, Abulug, Cagayan |
June 2, 2021 |
2021 |
310212100169000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Quirino District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads - Jct. Victoria - Maddela - Alicia -Kasibu Bdry Rd (Jct. Victoria - Kasibu Bdry) - K0414+381 - K0414+886, K0416+105 - K0417+000 |
June 2, 2021 |
FY2021 |
WIN1E02221 |
310204101152000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Vitali - Sibulao - Bypass Road Project (Alternate Road of N1), Package 1, Zamboanga City
Type of Work: Road Widening
Physical Target: 5.280 Lane Km.
Unit Cost: P 16,156,036.45/Lane Km.
ROW Acquisition: 5,153.7584 Square meters
EAO: P 3,150,000.00
Total Allocation: P 90,000,000.00 |
June 2, 2021 |
FY2021 |
WIN1E02220 |
310204101149000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Zamboanga City-Labuan-Limpapa Road (Sinunuc-Malagutay-San Roque Section), Zamboanga City
Type of Work: Construction of Concrete Road
Physical Target: 5.72 Lane Km.
Unit Cost: P 17,229,147.66/Lane Km.
EAO: P 3,449,275.36
Total Allocation: P 102,000,000.00 |
June 2, 2021 |
FY2021 |
WIN1E02222 |
310201100688000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City - Zamboanga City Rd - K1867+700.00 - K1870+300.00
Type of Work: Road Widening
Physical Target: 5.20 Lane Km.
Unit Cost: P 18,794,705.18/Lane Km.
EAO: P 3,420,636.34
Total Allocation: P 102,000,000.00 |
June 2, 2021 |
FY2021 |
WIN1E02228 |
310201100686000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City - Zamboanga City Rd - K1703+000 - K1705+200
Type of Work: Road Widening
Physical Target: 4.400 Lane Km.
Unit Cost: P 21,498,134.07/Lane Km.
ROW Acquisition: 13,658.62483 Square meters
EAO: P 3,310,712.65
Total Allocation: P 102,000,000.00 |
June 2, 2021 |
FY2021 |
WIN1E02241 |
310201100687000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City - Zamboanga City Rd - K1705+200.00 - K1705+880.00, K1706+120.00 - K1708+660.00
Type of Work: Road Widening
Physical Target: 6.440 Lane Km.
Unit Cost: P 14,857,733.50/Lane Km.
ROW Acquisition: 9,890.877 Square meters
EAO: P 3,348,933.13
Total Allocation: P 102,000,000.00 |
June 2, 2021 |
FY2021 |
WIN1E02243 |
310201100691000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Sindangan - Liloy Rd - K1939+125.00 - K1941+712.98, K1941+937.26 - K1942+480.00
Type of Work: Road Widening
Physical Target: 6.261 Lane Km.
Unit Cost: P 16,568,026.25/Lane Km.
ROW Acquisition: 8,789.844 Square meters
EAO: P 3,630,634.43
Total Allocation: P 110,000,000.00 |
June 1, 2021 |
2021 |
WIN1C03873 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Primary Roads
Jose Abad Santos Ave (JASA), K0098+569.05 - K0098+912.87 |
June 1, 2021 |
2021 |
WIN1C03872 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Secondary Roads
Jct. Tablang - Gabaldon Rd, K0146+000 - K0146+940.15 |
June 1, 2021 |
FY 2021 GAA |
WIN1E02268 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Digos-Makar Rd - K1564+(-030) - K1564+000, K1564+(-067) - K1564+(-030),
K1564+(-098) - K1564+(-067), K1564+(-140) - K1564+(-098),
K1564+(-153) - K1564+(-140), K1564+(-180) - K1564+(-153),
K1564+(-255) - K1564+(-180), K1564+(-271) - K1564+(-255),
K1564+(-495) - K1564+(-271), K1564+000 - K1564+004
Physical Target:
CW1: 1.936 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 24,774,000.00
CW1: P 24,278,520.00 (Reconstruction to Concrete Pavement)
EAO: P 495,480.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Digos-Makar Rd - K1564+(-030) - K1564+004, K1564+(-067) - K1564+(-030),
K1564+(-103.6) - K1564+(-067), K1564+(-153) - K1564+(-148.6),
K1564+(-180) - K1564+(-153), K1564+(-255) - K1564+(-180),
K1564+(-271) - K1564+(-255), K1564+(-484.5) - K1564+(-271),
K1564+004 - K1564+111
Physical Target:
CW1: 1.882 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 24,774,000.00
CW1: P 24,278,520.00 (Reconstruction to Concrete Pavement)
EAO: P 495,480.00 |
June 1, 2021 |
2021 |
WIN1C03880 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bataan 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Roads - Tertiary Roads
Calaguiman - Vicinal Rd, K0129+219.50 - K0129+785 |
June 1, 2021 |
2021 |
WIN1C03887 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
NCR/Bulacan Bdry - Bigte - Ipo Dam Rd, K0034+000 - K0034+302, K0035+000 - K0035+165
|
June 1, 2021 |
2021 |
WIN1C03875 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Meycauayan - Camalig - Bahay Pari Road, K0025+574 - K0025+766.50
|
June 1, 2021 |
2021 |
WIN1C03883 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Network Development - Road Widening - Tertiary Roads
Sn Marcelino - Sn Antonio - Sn Narciso Rd, K0163+469 - K0164+367
|
June 1, 2021 |
2021 |
WIN1E02218 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Regional Office XIII |
UACS No. 310107100235000
P00502029MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1264 + 900 - K1266 + 000
Type of Work / Physical Target: CW1 - Construction of Road Slope Protection Structure: 10,423.35 sq.m
Unit Cost: P9,720.963 / lane km
Allocation: P101,325,000
EAO: P3,675,000
TOTAL: P105,000,000
TO:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1262 + 590 - K1262 + 770, K1262 + 910 - K1263 + 010, K1264 + 580.60 - K1264 + 860.85
Type of Work / Physical Target: CW1 - Construction of Road Slope Protection Structure: 9,587.98 sq.m
Unit Cost: P10,567.919 / lane km
Allocation: P101,325,000
EAO: P3,675,000
TOTAL: P105,000,000 |
June 1, 2021 |
2021 |
WIN1E02245 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Regional Office XIII |
UACS No. 300116203603000
P00550740MN
Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road, Km 44 +000 - Km 60+000, Binicalan, San Luis, Agusan del Sur
Type of Work / Physical Target: CW1 - Construction of
Concrete Road: 9.815 lane km
Unit Cost: P10,323,484.46 / lane km
Allocation: P101,325,000
EAO: P3,675,000
TOTAL: P105,000,000
TO:
Construction of Road, Sta. 31+800 - Sta. 35+120, Binicalan, San Luis, Agusan del Sur
Type of Work / Physical Target: CW1 - Construction of
Gravel Road: 6.64 lane km
Unit Cost: P15,259,789.16 / lane km
Allocation: P101,325,000
EAO: P3,675,000
TOTAL: P105,000,000 |
June 1, 2021 |
2021 |
WIN1E02260 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. 300117210455000
P00551464MN
Local Program - Local Roads and Bridges - Local Roads and Bridges - Local Roads - Local Infrastructure Program
FROM:
Concreting of Barangay Road, Barangay Suyoc to Barangay Bugas-Bugas, Placer, Surigao del
Norte
Type of Work / Physical Target: CW1 - Construction of
Concrete Road: 0 lane km
Unit Cost: P0 / lane km
Allocation: P9,900,000.00
EAO: P100,000.00
TOTAL: P10,000,000.00
TO:
Concreting of Barangay Road, Barangay Suyoc to Barangay Bugas-Bugas, Placer, Surigao del
Norte
Type of Work / Physical Target: CW1 - Construction of
Concrete Road: 0.9518 lane km
Unit Cost: P10,401,344.82 / lane km
Allocation: P9,900,000.00
EAO: P100,000.00
TOTAL: P10,000,000.00 |
June 1, 2021 |
2021 |
WIN1E02263 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. 300117210454000
P00551463MN
Local Program - Local Roads and Bridges - Local Roads and Bridges - Local Roads - Local Infrastructure Program
FROM:
Concreting of road, Barangay Cayawan, Malimono, Surigao Del Norte
Type of Work / Physical Target: CW1 - Construction of
Concrete Road: 0.28 lane km
Unit Cost: P10,607,142.86 / lane km
Allocation: P2,970,000.00
EAO: P30,000.00
TOTAL: P3,000,000.00
TO:
Concreting of road, Barangay Cayawan, Malimono, Surigao Del Norte
Type of Work / Physical Target: CW1 - Construction of
Concrete Road: 0.369 lane km
Unit Cost: P8,048,780.49 / lane km
Allocation: P2,970,000.00
EAO: P30,000.00
TOTAL: P3,000,000.00
|
May 31, 2021 |
2021 |
WIN1C03788 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Coronel River Flood Control, Sta. 0+000 - Sta. 0+637.00, Gabaldon, Nueva Ecija |
May 31, 2021 |
2021 |
WIN1C03783 |
FY 2021 GAA |
December 28, 2021 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Gapan - Fort Magsaysay Rd, K0110+278.88 - K0112+026.25 |
May 31, 2021 |
2021 |
WIN1C03795 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Primary Roads
Jose Abad Santos Ave (JASA), K0097+180 - K0097+540.20, K0097+961.20 - K0097+1180, K0098+066.70 - K0098+569.05 |
May 31, 2021 |
2021 |
WIN1C03832 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Sta. Rosa - Fort Magsaysay Rd, K0112+400 - K0112+857.68, K0115+005.10 - K0117+072.30, K0122+580 - K0123+186 |
May 31, 2021 |
2021 |
WIN1C03846 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Coronel River Flood Control, Sta. 0+000 - Sta. 0+555.000, Gabaldon, Nueva Ecija |
May 31, 2021 |
2021 |
WIN1C03840 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Secondary Roads
Nueva Ecija - Aurora Rd, K0130+504 - K0130+844 |
May 31, 2021 |
2021 |
WIN1C03845 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Cabanatuan City - Carmen Rd , K0127+208 - K0127+794 |
May 31, 2021 |
2021 |
WIN1C03849 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Primary Roads
Sta. Rosa - Tarlac Rd, K0109+000 - K0109+726.00, K0110+1260.00 - K0111+117.15 |
May 31, 2021 |
2021 |
WIN1C03836 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Network Development - Off-Carriageway Improvement - Tertiary Roads
Gapan - Fort Magsaysay Rd - K0113+000.00 - K0113+78.03 |
May 31, 2021 |
2021 |
WIN1C03842 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Network Development - Road Widening - Primary Roads
Jose Abad Santos Ave (JASA), K0107+000 - K0107+591.15, K0108+284.80 - K0108+482.80, K0108+501.40 - K0108+587.50
|
May 31, 2021 |
2021 |
WIN1C03818 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Primary Roads
Jose Abad Santos Ave (JASA), K0115+000 - K0115+596.65 |
May 31, 2021 |
2021 |
WIN1C03844 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Nueva Ecija 2nd District Engineering Office |
Flood Management - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers
Rehabilitation of Pampanga River Control, Sta. 0+000 to Sta. 0+452.40, Brgy. Callos, Peñaranda, Nueva Ecija |
May 31, 2021 |
2021 |
WIN1C03789 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection along olongapo - Bugallon Road, Salaza Section, Palauig, Zambales |
May 31, 2021 |
2021 |
310204101013000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads - Alicia - Angadanan - San Guillermo - Cauayan City - Naguilian Alternate Route, Package 3, Isabela |
May 31, 2021 |
FY2021 |
WIN1E02265 |
310205100608000 |
April 13, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/New Roads
Zamboanga del Sur Coastal Road (Vincenzo Sagun - Margosatubig Section), Zamboanga del Sur
Type of Work: Construction of Concrete Road
Physical Target: 2.70 Lane Km.
Unit Cost: P 36,500,268.39/Lane Km.
EAO: P 3,449,275.36
Total Allocation: P 102,000,000.00 |
May 31, 2021 |
2021 |
310205100535000 |
GAA FY 2021 |
January 25, 2021 |
Region II |
Regional Office II |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/New Roads - Aritao - Quirino Road, Package 1, Quirino |
May 29, 2021 |
FY 2021 GAA |
WIN1E02257 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Tagum-Panabo Circum Rd - K1486+066 - K1487+000
Physical Target:
CW1: 1.808 Lane Km (Road Widening)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 28,950,000.00 (Road Widening)
EAO: P 1,050,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Tagum-Panabo Circum Rd - K1484+349 - K1485+214
Physical Target:
CW1: 1.740 Lane Km (Road Widening)
ROW: 13,050.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 30,000,000.00
CW1: P 24,704,000.00 (Road Widening)
ROW: P 2,246,000.00 (ROW Acquisition)
EAO: P 1,050,000.00 |
May 29, 2021 |
FY 2021 GAA |
WIN1E02258 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) - K1564+801 - K1565+000,
K1566+000 - K1566+713, K1566+824 - K1567+616
Physical Target:
CW1: 3.546 Lane Km (Road Widening)
Allocation:
TOTAL: P 75,014,000.00
CW1: P 72,388,510.00 (Road Widening)
EAO: P 2,625,490.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) - K1566+000 - K1566+740
Physical Target:
CW1: 1.480 Lane Km (Road Widening)
ROW: 26,605.1196 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 75,014,000.00
CW1: P 36,194,255.00 (Road Widening)
ROW: P 36,194,255.00 (ROW Acquisition)
EAO: P 2,625,490.00 |
May 29, 2021 |
FY 2021 GAA |
WIN1E02271 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) - K1571+310 - K1572+000
Physical Target:
CW1: 1.446 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 35,505,000.00
CW1: P 34,794,900.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 710,100.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Davao-Cotabato Rd (Jct Digos-Cotabato Sect) - K1571+310 - K1572+000
Physical Target:
CW1: 2.892 Lane Km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 35,505,000.00
CW1: P 34,794,900.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 710,100.00 |
May 29, 2021 |
FY 2021 GAA |
WIN1E02226 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Digos-Makar Rd - K1584+702 - K1585+000,
K1588+547 - K1589+000, K1591+083 - K1591+160
Physical Target:
CW1: 2.773 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 29,453,000.00
CW1: P 28,863,940.00 (Reconstruction to Concrete Pavement)
EAO: P 589,480.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Digos-Makar Rd - K1584+702 - K1585+000,
K1588+471 - K1589+000, K1591+083 - K1591+160
Physical Target:
CW1: 2.492 Lane Km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 29,453,000.00
CW1: P 28,863,940.00 (Reconstruction to Concrete Pavement)
EAO: P 589,480.00 |
May 29, 2021 |
FY 2021 GAA |
WIN1E02252 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Bansalan-Mt Apo Natl Park Rd - K1593+400 - K1594+061
Physical Target:
CW1: 5,400.00 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 27,000,000.00
CW1: P 26,460,000.00 (Construction of Road Slope Protection Structure)
EAO: P 540,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Bansalan-Mt Apo Natl Park Rd - K1593+400 - K1594+256
Physical Target:
CW1: 7,656.420 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 27,000,000.00
CW1: P 26,460,000.00 (Construction of Road Slope Protection Structure)
EAO: P 540,000.00 |
May 28, 2021 |
2021 |
WIN1C03807 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bataan 1st District Engineering Office |
Asset Preservation - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Secondary Roads
Gov. J.J. Linao Road, K0-170+000 - K0170+352, K0170+366 - K0170+540 |
May 28, 2021 |
2021 |
WIN1C03791 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation - Preventive Maintenance - Tertiary Roads
Sta. Maria - Norzagaray Road, K0033+843 - K0034+141, K0034+496 - K0034+511.90 |
May 28, 2021 |
2021 |
WIN1F06188 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Northern Samar 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Catarman - Calbayog Rd - K0746+140- K0746+265
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure: 2,500 square meters
EAO P 1.00 M
Total P 50.00 M
AS MODIFIED:
Catarman - Calbayog Rd - K0753+879- K0753+949, K0758+458- K0758+510, K0766+000- K0766+114
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 49.00 M
Structure: 2,405 square meters
EAO P 1.00 M
Total P 50.00 M
|
May 28, 2021 |
2021 |
WIN1C03851 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Aurora District Engineering Office |
Asset Preservation - Preventive Maintenance - Secondary Roads
Baler - Casiguran Rd, K0238+000 - K0238+767 |
May 28, 2021 |
2021 |
WIN1C03820 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Tertiary Roads
Amungan - Palauig - Banlog Rd, K0212+500 - K0212+940, K0213+443 - K0213+709.20 |
May 28, 2021 |
2021 |
WIN1C03812 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Slope Protection at Lipay River Control (Upstream) North Approach, Sta. 0+000 - Sta. 0+505, Santa Cruz, Zambales |
May 28, 2021 |
2021 |
WIN1C03870 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Zambales 1st District Engineering Office |
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Slope Protection along Sta. Cruz - Mangatarem Road, Guisguis Section, Sta. Cruz, Zambales |
May 28, 2021 |
FY 2021 GAA |
WIN1E02262 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Regional Office XI |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1507+010 - K1509+302
Physical Target:
CW1: 4.870 Lane Km (Road Widening)
Allocation:
TOTAL: P 120,000,000.00
CW1: P 115,800,000.00 (Road Widening)
EAO: P 4,200,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Fatima-Malabog Rd - K1507+010 - K1508+498
Physical Target:
CW1: 2.614 Lane Km (Road Widening)
CW2: 2,127.95 sq. m. (Construction of Road Slope Protection Structure)
ROW: 19,605.00 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 120,000,000.00
CW1: P 57,097,349.00 (Road Widening)
CW2: P 46,254,151.00 (Construction of Road Slope Protection Structure)
ROW: P 12,448,500.00 (ROW Acquisition)
EAO: P 4,200,000.00 |
May 27, 2021 |
2021 |
WIN1F06180 |
GAA FY 2021 |
January 4, 2021 |
Region VIII |
Leyte 5th District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement - Primary Roads
AS PER GAA/ORIGINAL:
Ormoc-Baybay-Southern Leyte Bdry Rd - K1056+179 - K1056+419
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: Shoulder P 3.528 M
Paving/Construction: 720 square meters
EAO P 0.072 M
Total P 3.60 M
AS MODIFIED:
Ormoc-Baybay-Southern Leyte Bdry Rd - K1038+(-732) - K1038+(-332)
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: Shoulder P 3.528 M
Paving/Construction: 1,200 square meters
EAO P 0.072 M
Total P 3.60 M |
May 27, 2021 |
2021 |
WIN1C03773 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Network Development - Road Widening - Tertiary Roads
Bocaue - Sn Jose Rd - K0039+100 - K0040+000, K0040+637 - K0041+617 |
May 27, 2021 |
2021 |
WIN1F06200 |
GAA FY 2021 |
January 16, 2021 |
Region VIII |
Southern Leyte District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Off-Carriageway Improvement - Secondary Roads
AS PER GAA/ORIGINAL:
Bdry Southern Leyte-Maasin-Macrohon-Sogod-Jct Daang Maharlika - K1206 + 000 - K1206 + 160, K1206 + 175 - K1207 + 123
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: Shoulder P 14.5677 M
Paving / Construction: 7,400.25 square meters
EAO P 0.2973 M
Total P 14.865 M
AS MODIFIED:
Bdry Southern Leyte-Maasin-Macrohon-Sogod-Jct Daang Maharlika - K1206 + 000 - K1206 + 160, K1206 + 175 - K1206 + 330, K1206 + 357 - K1206 + 647
Physical Target: Allocation:
CW1-Off-Carriageway Improvement: Shoulder P 14.5677 M
Paving / Construction: 3,630 square meters
EAO P 0.2973 M
Total P 14.865 M
|
May 27, 2021 |
2021 |
WIN1C03810 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Asset Preservation - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Nueva Ecija - Aurora Rd - K0193+270 - K0193+350 |
May 27, 2021 |
2021 |
WIN1F06190 |
GAA FY 2021 |
January 16, 2021 |
Region VIII |
Southern Leyte District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Bridge - Widening of Permanent Bridges
AS PER GAA/ORIGINAL:
Bogasong Br. 1 (B00601LT) along Daang Maharlika (LT)
Physical Target: Allocation:
CW1-Widening of Bridge : 118.4 square meters P 15.68 M
EAO P 0.32 M
Total P 16.00 M
AS MODIFIED:
Bogasong Br. 2 (B00602LT) along Daang Maharlika (LT)
Physical Target: Allocation:
CW1-Widening of Bridge : 114.48 square meters P 15.68 M
EAO P 0.32 M
Total P 16.00 M
|
May 27, 2021 |
2021 |
WIN1C03811 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Network Development - Road Widening - Tertiary Roads
Sta Maria - Norzagaray Rd - K0032+(-151) - K0032+383, K0034+768 - K0035+500, K0037+600 - K0038+903, K0039+060 - K0039+171, K0039+180 - K0039+329, K0039+341 - K0039+365, K0039+420 - K0036+703, K0039+720.9 - K0039+756 |
May 27, 2021 |
2021 |
WIN1F06197 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Tacloban City District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
AS PER GAA/ORIGINAL:
Picas-San Jose DZR Airport Rd - K0911 + 835 – K0912 + 127
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 6.844320 M
Asphalt Overlay: 1.172 Lane Km
EAO P 0.139680 M
Total P 6.984 M
AS MODIFIED:
Picas-San Jose DZR Airport Rd - K0911 + 690 – K0911 + 970
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 6.844320 M
Asphalt Overlay: 1.12 Lane Km
EAO P 0.139680 M
Total P 6.984 M
|
May 27, 2021 |
2021 |
WIN1C03769 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Network Development - Off-Carriageway Improvement - Tertiary Roads
Bagac - Mariveles Rd - K0162+221 - K0168+659, K0169+400 - K0169+890, K0170+101 - K0170+690, K0170+810 - K0170+910, K0171+050 - K0171+070, K0171+110 - K0171+390, K0171+930 - K0172+730, K0173+010 - K0173+250, K0173+730 - K0174+339, K0174+374 - K0174+970, K0175+050 - K0176+428, K0176+700 - K0176+820, K0177+300 - K0179+468 |