September 24, 2021 |
2021 |
WIN1C04510 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Rehabilitation of Slope Protection along Tarlac River Control Right Dike, San Nicolas Section, San Nicolas, Tarlac City, Tarlac |
September 24, 2021 |
2021 |
WIN1C04511 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Tarlac District Engineering Office |
Flood Management - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structures within Agno River Basin System along Camiling River Right Bank, Surgui 1st - Cacamilingan Sur Section (Package E), Camiling, Tarlac
|
September 23, 2021 |
2021 |
WIN1F06515 |
GAA FY 2021 |
January 4, 2021 |
Region VIII |
Leyte 5th District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Bato-Bontoc Rd - K1113+830 - K1114+225, K1116+700 - K1116+910, K1117+270 - K1117+640, K1117+880 - K1117+970
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 15.582 M
Structure: 3,600 Square Meters
EAO P 0.318 M
Total P 15.900 M
AS MODIFIED:
Bato-Bontoc Rd - K1113+830 - K1114+225, K1116+700 - K1116+800, K1117+270 - K1117+440
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 15.582 M
Structure: 1,826.60 Square Meters
EAO P 0.318 M
Total P 15.900 M
|
September 23, 2021 |
2021 |
WIN1F06717 |
GAA FY 2021 |
January 1, 2021 |
Region VIII |
Biliran District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Preventive Maintenance - Secondary Roads
AS PER GAA/ORIGINAL:
Biliran Circumferential Rd - K1052 + 867 - K1053 + 356
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 10.550 M
Asphalt Overlay : 0.984 Lane Km
EAO P 0.215 M
Total P 10.765 M
AS MODIFIED:
Biliran Circumferential Rd - K1052 + 867 - K1053 + 236
Physical Target: Allocation:
CW1-Preventive Maintenance of Road: P 10.550 M
Asphalt Overlay : 0.744 Lane Km
EAO P 0.215 M
Total P 10.765 M
|
September 22, 2021 |
2021 |
WIN1E02833 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Regional Office XIII |
UACS No. : 310110100203000
Project ID: P00501690MN
OO1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
FROM:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1240 + 307 - K1240 + 835
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 528 Lineal meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 191,903.41/Lineal meters
TO:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1240 + 306 - K1240 + 819, K1240 + 854 - K1241 + 210
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 932 Lineal meters
Allocation:
TOTAL: P 105,000,000
CW1: P 101,325,000
EAO: P 3,675,000
Unit Cost:
CW1: P 108,717.81/Lineal meters
|
September 22, 2021 |
2021 |
WIN1C04493 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Rehabilitation / Improvement (Upgrading and Widening to 4 lanes with Concrete Slope Protection) of San Matias - Sto. Rosario Pau Road, Sto. Tomas, Pampanga
|
September 20, 2021 |
2021 |
WIN1C04496 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Regional Office III |
Network Development Program - Construction of By-Pass and Diversion Roads
Lubao - Guagua - Minalin - Sto. Tomas Road (Sto. Tomas - Minalin Section) Package 5, Pampanga |
September 20, 2021 |
2021 |
WIN1C04516 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Pampanga 1st District Engineering Office |
Network Development - Road Widening - Tertiary Roads
Baliwag - Candaba - Sta. Ana Road, K0060+005 - K0061+054, K0064+800 - K0065+020, K0068+450 - K0068+819, K0071+615 - K0072+070 (Sta. Ana - Candaba Section) |
September 20, 2021 |
2021 |
WIN1C04513 |
FY 2021 GAA |
December 28, 2020 |
Region III |
Pampanga 1st District Engineering Office |
Network Development Program - Road Widening - Tertiary Roads
Baliwag - Candaba - Sta. Ana Road, K0073+445 - K0075+360 (Sta. Ana Section)
|
September 20, 2021 |
2021 |
WIN1E02841 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Sur 2nd District Engineering Office |
UACS No. : 300111200356000
Project ID: P00550594MN
Local Program - National Roads and Bridges - National Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Bislig City Coastal Protection along Surigao-Davao Coastal Rd, Surigao del Sur
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 5.474 Lane Km
Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,000
EAO: P 2,800,000
Unit Cost:
CW1: P 14,103,032.52/Lane Km
TO:
Construction of Bislig City Coastal Protection along Surigao-Davao Coastal Rd, Surigao del Sur
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Slope Protection Structure
Physical Target:
CW1- 0.480 Lane Km
CW2- 2,353.37 Square meters
Allocation:
TOTAL: P 80,000,000
CW1: P 43,722,708.75
CW2: P 32,787,739.18
EAO: P 2,775,552.07
Excess: P 714,000
Unit Cost:
CW1: P 91,088,976.56/Lane Km
CW2: P 13,932.25/Square meters
|
September 18, 2021 |
CY 2021 |
WIN1F06723 |
UACS No. 300103203173000 |
July 12, 2021 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 300103203173000
Project ID.: P00556800LZ
Local Program
Local – Buildings And Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of Multi-Purpose / Facilities – Construction / Repair / Rehabilitation / Improvement of
Various Infrastructure including Local Projects
Construction of Multi-Purpose Building (Phase 2), Barangay Paso de Blas, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building 1.00 No. of Bldg.
Unit Cost = P 9,800.00 / No. of Bldg.
Allocation (P’000) = P 9,800.00
EAO (P’000) = P 200.00
Total (P’000) = P 10,000.00
As Modified
Local Program
Local – Buildings And Other Structures – Multipurpose/Facilities – Local Infrastructure Program
Construction of Multi-Purpose / Facilities – Construction / Repair / Rehabilitation / Improvement of
Various Infrastructure including Local Projects
Construction of Multi-Purpose Building, Barangay Paso de Blas, Valenzuela City
Physical Target: CW1 = Construction of Multi-Purpose Building 1.00 No. of Bldg.
Unit Cost = P 9,800.00 / No. of Bldg.
Allocation (P’000) = P 9,800.00
EAO (P’000) = P 200.00
Total (P’000) = P 10,000.00
WIN1F06723
|
September 16, 2021 |
2021 |
WIN1C04515 |
GAA 2021 |
September 7, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Benguet-Nueva Vizcaya Rd - K0283 + 280 - K0283 + 380, K0284 + 000 - K0284 + 100;
Physical Target: CW1 : 9,751 Square meters;
Allocation= Php 222,000,000
To: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads - Benguet-Nueva Vizcaya Rd - K0283 + 280 - K0283 + 380, K0284 + 000 - K0284 + 100;
Physical Target: CW1 : 9,088 Square meters;
Allocation= Php 222,000,000
|
September 16, 2021 |
2021 |
WIN1C04518 |
GAA 2021 |
September 7, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Marcos Hi-way - K0272 + 800 - K0272 + 960;
Physical Target: CW1 : 0 Square meters;
Allocation= Php 125,000,000
To: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads - Marcos Hi-way - K0272 + 800 - K0272 + 909;
Physical Target: CW1 : 5,076 Square meters;
Allocation= Php 125,000,000
|
September 16, 2021 |
2021 |
WIN1C04519 |
GAA 2021 |
September 7, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Benguet-Nueva Vizcaya Rd - K0254 + 270 - K0254 + 360;
Physical Target: CW1 : 0 Square meters;
Allocation= Php 110,000,000
To: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads - Benguet-Nueva Vizcaya Rd - K0254 + 270 - K0254 + 380;
Physical Target: CW1 : 4,382.2 Square meters;
Allocation= Php 110,000,000
|
September 16, 2021 |
2021 |
WIN1C04514 |
GAA 2021 |
September 7, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Cong. Andres Acop Cosalan Rd - K0334 + 140 - K0334 + 400;
Physical Target: CW1 : 5838.1 Square meters;
Allocation= Php 148,000,000
To: Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads - Cong. Andres Acop Cosalan Rd - K0333 + 1188 - K0333 + 1448;
Physical Target: CW1 : 5838.1 Square meters;
Allocation= Php 148,000,000
|
September 16, 2021 |
2021 |
WIN1C04508 |
GAA 2021 |
September 2, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Mausoc - Labaan Flood Control Structure, Sta. 0+000 - Sta. 0+500, San Quintin, Abra;
Physical Target: CW1: 500 Lineal meters;
Allocation= Php 50,000,000
To: Construction of Mausoc - Labaan Flood Control Structure, Sta. 0+000 - Sta. 0+500, San Quintin, Abra;
Physical Target: CW1: 420 Lineal meters;
Allocation= Php 50,000,000
|
September 16, 2021 |
2021 |
WIN1C04517 |
GAA 2021 |
September 14, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Gomonot Flood Control, Barangay Patiao, Peñarrubia, Abra;
Physical Target: CW1: 612 Lineal meters;
Allocation= Php 50,000,000
To: Construction of Gomonot Flood Control, Barangay Patiao, Peñarrubia, Abra;
Physical Target: CW1: 522 Lineal meters;
Allocation= Php 50,000,000
|
September 16, 2021 |
FY 2021 |
WIN1C04308 |
FY 2021 GAA RA 11518 |
March 27, 2021 |
Region V |
Masbate 2nd District Engineering Office |
UACS No.: 310202100834000
Project ID: P00505300LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Jct Crossing-Mandaon Rd – K0052 + 500 – K0053 + 007
Physical Target: CW1- Road Widening – 1.0 Lane km.
Allocation: Php 10,000,000.00
AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Jct Crossing-Mandaon Rd – K0052 + 500 – K0052 + 624
Physical Target: CW1- Road Widening – 0.248 Lane km.
Allocation: Php 10,000,000.00
|
September 16, 2021 |
FY 2021 |
WIN1C04079 |
FY 2021 GAA RA 11518 |
March 27, 2021 |
Region V |
Masbate 2nd District Engineering Office |
UACS No.: 310202100835000
Project ID: P00505301LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Jct Tawad - Balud Rd – K0028 + 944 – K029 + 270
Physical Target: CW1- Road Widening – 0.64 Lane km.
Allocation: Php 10,000,000.00
AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Jct Tawad - Balud Rd – K0028 + 944 – K029 + 064
Physical Target: CW1- Road Widening – 0.228 Lane km.
Allocation: Php 10,000,000.00
|
September 16, 2021 |
FY 2021 |
WIN1C04014 |
FY 2021 GAA RA 11518 |
March 27, 2021 |
Region V |
Masbate 2nd District Engineering Office |
UACS No.: 310202100837000
Project ID: P00505302LZ
AS PER GAA:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Masbate -Milagros Rd – K0005 + 719 – K0006 + 365
Physical Target: CW1- Road Widening – 1.304 Lane km.
Allocation: Php 10,000,000.00
AS MODIFIED:
OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Secondary Roads – Masbate -Milagros Rd – K0005 + 719 – K0005 + 840
Physical Target: CW1- Road Widening – 0.242 Lane km.
Allocation: Php 10,000,000.00
|
September 15, 2021 |
FY 2021 GAA |
WIN1E02842 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Revetment Along Manat River (Up- stream and Down Stream) leading to Agusan River at Purok 7 Tapia, Montevista, Davao De Oro (Sta. 11+500 - Sta. 12+600 LS)
Physical Target:
CW1: 374.99 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 67,550,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,450,000.00
TO: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Revetment Along Manat River (Up- stream and Down Stream) leading to Agusan River at Purok 7 Tapia, Montevista, Davao De Oro (Sta. 7+820.139 - Sta. 7+894.829 LS, Sta. 8+040.000 - Sta. 8+289.480 LS)
Physical Target:
CW1: 374.99 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 70,000,000.00
CW1: P 67,550,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,450,000.00 |
September 13, 2021 |
FY 2021 GAA |
WIN1F06584 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310107100213000
Project ID : P00516153LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National
Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM :
Itabiak - San Vicente Road, Palawan
K0169 + 413 - K0169 + 538
Physical Target - CW1 - Construction of Road Slope Protection :
7,800.00 Square Meter
Allocation - Php 78.00 Million
TO :
Itabiak - San Vicente Road, Palawan
K0169 + 403 - K0169 + 592
Physical Target - CW1 - Construction of Road Slope Protection :
3,522.00 Square Meter
Allocation - Php 78.00 Million |
September 13, 2021 |
FY 2021 GAA |
WIN1F06585 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310107100214000
Project ID : P00516154LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of National
Roads with Slips, Slope Collapse, and Landslide - Primary Roads
FROM :
Itabiak - San Vicente Road, Palawan
K0170 + 173 - K0170 + 233
Physical Target - CW1 - Construction of Road Slope Protection :
5,096.00 Square Meter
Allocation - Php 50.96 Million
TO :
Itabiak - San Vicente Road, Palawan
K0170 + 158.50 - K0170 + 260
Physical Target - CW1 - Construction of Road Slope Protection :
2,106.00 Square Meter
Allocation - Php 50.96 Million |
September 13, 2021 |
FY 2021 GAA |
WIn1F06583 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300117209166000
Project ID : P00564719LZ
LOCAL PROGRAM
Local Roads and Bridges - Local Roads -
Local Infrastructure Program
FROM :
Construction of Road Slope Protection along
Calapan Couth Road,
Brgy. Hagan, Bongabong, Oriental Mindoro
K0119 + 106 - K0119 + 283.50,
Bongabong, Oriental Mindoro
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 0 Square Meter
Allocation - Php 50.00 Million
TO :
Construction of Road Slope Protection along
Calapan South Road,
Brgy. Hagan,
K0119 + 130 - K0119 + 190,
Bongabong, Oriental Mindoro
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,196.06 Square Meter
Allocation - Php 50.00 Million
|
September 13, 2021 |
FY 2021 GAA |
WIN1F06560 |
FY 2021 GAA DPWH Infra Projects |
December 28, 2020 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300117209167000
Project ID : P00564720LZ
LOCAL PROGRAM
Local Roads and Bridges - Local Roads -
Local infrastructure Program
FROM :
Construction of Slope Protection along
Calapan South Road
K0127 + 803 - K0127 + 974050
Bongabong, Oriental Mindoro
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 0 Square Meter
Allocation - Php 50.00 Million
TO :
Construction of Slope Protection along
Calapan South Road
K0118 + 353 - K0118 + 460
Bongabong, Oriental Mindoro
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,285.18 Square Meter
Allocation - Php 50.00 Million |
September 9, 2021 |
2021 |
WIN1E02832 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Dinagat Islands District Engineering Office |
UACS No. : 310108100752000
Project ID: P00509858MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
FROM:
Dinagat-Loreto Rd - K0072 + 530 - K0072 + 720
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 50,000,000
CW1: P 49,000,000
EAO: P 1,000,000
Unit Cost:
CW1: P 0 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Dinagat-Loreto Rd - K0072 + 530 - K0072 + 720
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1,810.00 Square meter
Allocation:
TOTAL: P 50,000,000
CW1: P 49,000,000
EAO: P 1,000,000
Unit Cost:
CW1: P 27,071.82 / Square meter |
September 9, 2021 |
2021 |
WIN1E02801 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200281000
Project ID: P00550443MN
Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 19+090 - Sta. 19+233, San Francisco, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 70,000,000
CW1: P 67,550,000
EAO: P 2,450,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 19+100 - Sta. 19+213.92, San Francisco, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 2,827.13 Square meter
Allocation:
TOTAL: P 70,000,000
CW1: P 67,550,000
EAO: P 2,450,000
Unit Cost:
CW1: P 23,893.49 / Square meter |
September 8, 2021 |
FY 2021 GAA |
WIN1E02812 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1511+524 - K1511+604 (L/S)
Physical Target:
CW1: 0.000 Sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1511+633 - K1511+687 (L/S)
Physical Target:
CW1: 1,947.00 Sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02813 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Drainage Protection Works -Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Matina Pangi Bridge-I Upstream, Matina Pangi Section, Left Bank, Davao City Physical Target:
CW1: 400.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 88,400,000.00
CW1: P 85,306,000.00 (Construction of Revetment)
EAO: P 3,094,000.00
TO: Local - Flood Control and Drainage - Flood Control Structures / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Matina Pangi Bridge-I Upstream, Matina Pangi Section, Left Bank, Davao City Physical Target:
CW1: 285.00 lm (Construction of Revetment)
Allocation:
TOTAL: P 88,400,000.00
CW1: P 85,306,000.00 (Construction of Revetment)
EAO: P 3,094,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02807 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1512+428 - K1512+474
Physical Target:
CW1: 0.000 Sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 40,316,000.00
CW1: P 39,509,680.00 (Construction of Road Slope Protection Structure)
EAO: P 806,320.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1512+428 - K1512+450
Physical Target:
CW1: 789.00 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 40,316,000.00
CW1: P 39,509,680.00 (Construction of Road Slope Protection Structure)
EAO: P 806,320.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02811 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Rehabilitation of Drainage Structure at Sasa Creek, Davao City
Physical Target:
CW1: 300.000 lm (Rehabilitation/Major Repair of Drainage Structure)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Rehabilitation/Major Repair of Drainage Structure)
EAO: P 2,100,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Rehabilitation of Drainage Structure at Sasa Creek, Davao City
Physical Target:
CW1: 210.00 lm (Rehabilitation/Major Repair of Drainage Structure)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Rehabilitation/Major Repair of Drainage Structure)
EAO: P 2,100,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02805 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Drainage Structure, Eagle Street, Phase 2, Barangay Bucana, Davao City
Physical Target:
CW1: 500.000 lm (Construction of Drainage Structure)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Drainage Structure)
EAO: P 200,000.00
TO: Local - Flood Control and Drainage - Flood Control Structures / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Drainage Structure, Eagle Street, Phase 2, Barangay Bucana, Davao City
Physical Target:
CW1: 327.00 lm (Construction of Drainage Structure)
Allocation:
TOTAL: P 10,000,000.00
CW1: P 9,800,000.00 (Construction of Drainage Structure)
EAO: P 200,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02810 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/Upgrading/Rehabilitation of Drainage along National Roads - Secondary Roads
Davao City Div Rd - K1501+860
Physical Target:
CW1: 1,555.000 lm (Construction of Drainage Structure along Road)
Allocation:
TOTAL: P 105,000,000.00
CW1: P 101,325,000.00 (Construction of Drainage Structure along Road)
EAO: P 3,675,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1501+860
Physical Target:
CW1: 188.00 lm (Construction of Drainage Structure along Road)
ROW: 1,000.000 sq. m. (ROW Acquisition)
Allocation:
TOTAL: P 105,000,000.00
CW1: P 77,200,000.00 (Construction of Drainage Structure along Road)
ROW: P 24,125,000.00 (ROW Acquisition)
EAO: P 3,675,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02806 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Outfall Section, Sta. 0+241 to Sta. 0+671, Left Bank, Davao City
Physical Target:
CW1: 452.000 lm (Construction of Revetment)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Revetment)
EAO: P 3,500,000.00
TO: Local Program - Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Construction of Revetment along Matina River, Outfall Section, Sta. 0+115 to Sta. 0+465, Left Bank, Davao City Physical Target:
CW1: 328.00 lm (Construction of Revetment)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Revetment)
EAO: P 3,500,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02836 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao de Oro 1st District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Revetment Along Manat River (Up- stream and Down Stream) leading to Agusan River at Bankeruhan Sur to Bankeruhan Norte, Montevista, Davao de Oro (Sta. 12+700 - Sta. 13+900 LS)
Physical Target:
CW1: 481.250 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Construction of Flood Mitigation Structure)
EAO: P 3,150,000.00
TO: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Revetment Along Manat River (Up- stream and Down Stream) leading to Agusan River at Bankeruhan Sur to Bankeruhan Norte, Montevista, Davao de Oro (Sta. 11 + 561.000 - Sta. 11 + 612.660 LS, Sta. 11 + 612. 660 - Sta. 12 + 042.250 LS)
Physical Target:
CW1: 481.250 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 90,000,000.00
CW1: P 86,850,000.00 (Construction of Flood Mitigation Structure)
EAO: P 3,150,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02838 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basin and Principal Rivers
Construction of Revetment along Talomo River, Davao City
Physical Target:
CW1: 530.00 lm (Construction of Revetment)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Revetment)
EAO: P 2,100,000.00
TO: OO2: Protect Lives and Properties Against Major Floods - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basin and Principal Rivers
Construction of Revetment along Talomo River, Davao City
Physical Target:
CW1: 188.00 lm (Construction of Revetment)
Allocation:
TOTAL: P 60,000,000.00
CW1: P 57,900,000.00 (Construction of Revetment)
EAO: P 2,100,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02834 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basin and Principal Rivers
Construction of Esplanade at Davao River, Right Bank, Bolton Bridge Downstream Section, Davao City
Physical Target:
CW1: 309.00 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 74,400,000.00
CW1: P 71,796,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,604,000.00
TO: OO2: Protect Lives and Properties Against Major Floods - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basin and Principal Rivers
Construction of Esplanade at Davao River, Right Bank, Bolton Bridge Downstream Section, Davao City
Physical Target:
CW1: 3559.00 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 74,400,000.00
CW1: P 71,796,000.00 (Construction of Flood Mitigation Structure)
EAO: P 2,604,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02837 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Rehabilitation / Major Repair of Flood Control Structure along Davao River, Bolton Bridge Upstream, Left Bank, Davao City (Sta. 1+570 - Sta. 1+843)
Physical Target:
CW1: 872.012 lm (Rehabilitation/Major Repair of Flood Control Structure)
Allocation:
TOTAL: P 80,000,000.00
CW1: P 77,200,000.00 (Rehabilitation/Major Repair of Flood Control Structure)
EAO: P 2,800,000.00
TO: OO2: Protect Lives and Properties Against Major Floods - Construction/Maintenance of Flood Mitigations Structures and Drainage Systems
Rehabilitation / Major Repair of Flood Control Structure along Davao River, Bolton Bridge Upstream, Left Bank, Davao City (Sta. 1+614 - Sta. 2+173)
Physical Target:
CW1: 572.000 lm (Rehabilitation/Major Repair of Flood Control Structure)
Allocation:
TOTAL: P 80,000,000.00
CW1: P 77,200,000.00 (Rehabilitation/Major Repair of Flood Control Structure)
EAO: P 2,800,000.00 |
September 8, 2021 |
FY 2021 GAA |
WIN1E02835 |
FY 2021 GAA RA 11518 |
January 1, 2021 |
Region XI |
Davao City District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1511+604 - K1511+684 (L/S)
Physical Target:
CW1: 0.000 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Davao City Div Rd - K1511+687 - K1511+741
Physical Target:
CW1: 1,905.00 sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Road Slope Protection Structure)
EAO: P 3,500,000.00 |
September 8, 2021 |
2021 |
WIN1E02827 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200278000
Project ID: P00550440MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta 6+259 - Sta. 6+395, Tagana-an, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 98,000,000
CW1: P 94,570,000
EAO: P 3,430,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta 6+259 - Sta. 6+395, Tagana-an, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,960.48 Square meter
Allocation:
TOTAL: P 98,000,000
CW1: P 94,570,000
EAO: P 3,430,000
Unit Cost:
CW1: P 23,878.42 / Square meter |
September 8, 2021 |
2021 |
WIN1E02831 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200279000
Project ID: P00550441MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta. 6+840 - Sta. 7+070, Tagana-an, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta. 6+840 - Sta. 6+995, Tagana-an, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,039.87 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.25 / Square meter |
September 8, 2021 |
2021 |
WIN1E02822 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200280000
Project ID: P00550442MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta. 7+090 - Sta. 7+190, Placer, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 90,000,000
CW1: P 86,850,000
EAO: P 3,150,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Capalayan-Placer Road Sta. 7+090 - Sta. 7+190, Placer, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,636.78 Square meter
Allocation:
TOTAL: P 90,000,000
CW1: P 86,850,000
EAO: P 3,150,000
Unit Cost:
CW1: P 23,881.02 / Square meter |
September 8, 2021 |
2021 |
WIN1E02821 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200282000
Project ID: P00550444MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 28+922 - Sta. 29+022, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 19+547.54 - Sta. 19+590, Sta. 28+930 - Sta. 29+020, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,432.89 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 23,893.86 / Square meter |
September 8, 2021 |
2021 |
WIN1E02830 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200283000
Project ID: P00550445MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 35+485 - Sta. 35+855, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 35+570 - Sta. 35+781.28, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,039.58 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,888.62 / Square meter
|
September 8, 2021 |
2021 |
WIN1E02828 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200284000
Project ID: P00550446MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 39+467 - Sta. 39+735, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 98,000,000
CW1: P 94,570,000
EAO: P 3,430,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 39+550 - Sta. 39+696.49, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,958.60 Square meter
Allocation:
TOTAL: P 98,000,000
CW1: P 94,570,000
EAO: P 3,430,000
Unit Cost:
CW1: P 23,889.76 / Square meter |
September 8, 2021 |
2021 |
WIN1E02818 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200285000
Project ID: P00550447MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 39+773 - Sta. 39+953, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 95,000,000
CW1: P 91,675,000
EAO: P 3,325,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 39+780 - Sta. 39+904.38, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,838.46 Square meter
Allocation:
TOTAL: P 95,000,000
CW1: P 91,675,000
EAO: P 3,325,000
Unit Cost:
CW1: P 23,883.28 / Square meter |
September 8, 2021 |
2021 |
WIN1E02819 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200286000
Project ID: P00550448MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 40+368 - Sta. 40+505, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 95,000,000
CW1: P 91,675,000
EAO: P 3,325,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 40+368 - Sta. 40+502.82, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,837.87 Square meter
Allocation:
TOTAL: P 95,000,000
CW1: P 91,675,000
EAO: P 3,325,000
Unit Cost:
CW1: P 23,886.95 / Square meter |
September 8, 2021 |
2021 |
WIN1E02816 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200288000
Project ID: P00550450MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 36+430 - Sta. 36+748, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 36+430 - Sta. 36+685.8, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.11 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.49 / Square meter |
September 8, 2021 |
2021 |
WIN1E02826 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200289000
Project ID: P00550451MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 42+200 - Sta. 42+320, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 42+200 - Sta. 42+320, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.11 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.55 / Square meter |
September 8, 2021 |
2021 |
WIN1E02815 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200292000
Project ID: P00550454MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 44+820 - Sta. 44+970, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 29+072 - Sta. 29+222.68, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.14 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.31 / Square meter |
September 8, 2021 |
2021 |
WIN1E02814 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310109100732000
Project ID: P00502023MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1133 + 360 - K1133 + 428
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 2,250.00 Square meter
Allocation:
TOTAL: P 45,000,000
CW1: P 44,100,000
EAO: P 900,000
Unit Cost:
CW1: P 19,600 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1133 + 360 - K1133 + 406.38
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1,814.32 Square meter
Allocation:
TOTAL: P 45,000,000
CW1: P 44,100,000
EAO: P 900,000
Unit Cost:
CW1: P 24,306.63 / Square meter |
September 8, 2021 |
2021 |
WIN1E02825 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310108100757000
Project ID: P00502025MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
FROM:
Surigao-Davao Coastal Rd - K1189 + 750 - K1189 + 900
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 2,571.429 Square meter
Allocation:
TOTAL: P 40,000,000
CW1: P 39,200,000
EAO: P 800,000
Unit Cost:
CW1: P 15,244.44 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Surigao-Davao Coastal Rd - K1189 + 750 - K1189 + 819.51
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1,601.53 Square meter
Allocation:
TOTAL: P 40,000,000
CW1: P 39,200,000
EAO: P 800,000
Unit Cost:
CW1: P 24,476.59 / Square meter |
September 8, 2021 |
2021 |
WIN1E02817 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310109100578000
Project ID: P00509859MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1134 + 705 - K1134 + 770
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 75,000,000
CW1: P 72,375,000
EAO: P 2,625,000
Unit Cost:
CW1: P 0 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Quezon-Mapawa-Capalayan-Espina-Navarro Rd - K1133 + 345.58 - K1133 + 360, K1134 + 705 - K1134 + 770
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,029.26 Square meter
Allocation:
TOTAL: P 75,000,000
CW1: P 72,375,000
EAO: P 2,625,000
Unit Cost:
CW1: P 23,891.97 / Square meter |
September 8, 2021 |
2021 |
WIN1E02829 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310109100579000
Project ID: P00509860MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Surigao-Davao Coastal Rd - K1149 + 000 - K1149 + 248
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 0 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Surigao-Davao Coastal Rd - K1149 + 067 - K1149 + 146.83
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,430.19 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 23,912.67 / Square meter |
September 8, 2021 |
2021 |
WIN1E02820 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310109100580000
Project ID: P00509861MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Surigao-Davao Coastal Rd - K1149 + 818 - K1149 + 930
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,000
EAO: P 2,800,000
Unit Cost:
CW1: P 0 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Surigao-Davao Coastal Rd - K1149 + 150 - K1149 + 203.17
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,223.68 Square meter
Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,000
EAO: P 2,800,000
Unit Cost:
CW1: P 23,947.79 / Square meter |
September 8, 2021 |
2021 |
WIN1E02824 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 310109100581000
Project ID: P00509862MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
FROM:
Surigao-Davao Coastal Rd - K1174 + 705 - K1174 + 850
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 0 / Square meter
TO:
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Surigao-Davao Coastal Rd - K1174 + 705 - K1174 + 821.89
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 3,430 Square meter
Allocation:
TOTAL: P 85,000,000
CW1: P 82,025,000
EAO: P 2,975,000
Unit Cost:
CW1: P 23,913.99 / Square meter |
September 8, 2021 |
2021 |
WIN1E02823 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Dinagat Islands District Engineering Office |
UACS No. : 300111200350000
Project ID: P00550589MN
Local Program - National Roads and Bridges - National Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Rehabilitation / Reconstruction of National Roads with Slips Slope Collapse and Landslide Dinagat - Loreto Road, Dinagat Islands
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - National Roads and Bridges - National Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Rehabilitation / Reconstruction of National Roads with Slips Slope Collapse and Landslide Dinagat - Loreto Road, Dinagat Islands
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 12,418.71 Square meter
Allocation:
TOTAL: P 250,000,000
CW1: P 241,250,000
EAO: P 8,750,000
Unit Cost:
CW1: P 19,426.33 / Square meter |
September 6, 2021 |
FY2021 |
WIN1E02641 |
300204100716000 |
April 12, 2021 |
Region IX |
Regional Office IX |
CSSP: Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Access Road at Sitio Anuling, Pamucutan to Sta. Rita in support of High Value Crops (Abaca, Cacao, Rubber and Coffee), Upper La Paz, Zamboanga City, Package III
CW1: Construction of Concrete Road
Physical Target (Road): 0.86 Lane Km.
Unit Cost (Road): Php 90,895,516.15/lane km.
CW2: Construction of Slope Protection Structure
Physical Target (Slope Protection: 2,085.50 Sq. M.
Unit Cost (Slope Protection): Php 16,127.87/sq.m.
EAO: Php 3,913,169.08
Total Allocation: Php 115,718,000.00 |
September 6, 2021 |
FY2021 |
WIN1E02311 |
300204100717000 |
April 20, 2021 |
Region IX |
Regional Office IX |
Convergence and Special Support Program - Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones
Barangay San Juan-Dampalan-San Isidro Road connecting National Road and Marapong in support of Rubber, Coconut and Abaca Industries, Sergio Osmeña, Zamboanga del Norte, Package II
CW1: Construction of Concrete Bridge
Physical Target: 1,156.248 Sq. M.
Unit Cost: Php 84,947.498/sq. m.
EAO: Php 3,570,000.00
Excess: Php 209,625.40
Total Allocation: Php 102,000,000.00 |
September 6, 2021 |
FY2021 |
WIN1E02665 |
300111200357000 |
May 31, 2021 |
Region IX |
Regional Office IX |
Local Program - National Roads and Bridges - National Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Jct. Blancia-Molave-Josefina Road, K1673+000 - K1676+057.57
CW1: Road Widening
Physical Target: 6.115 Lane Km.
Unit Cost: Php 14,790,238.35/lane km.
ROW Acquisition: 20,000.00 Sq. M. (Php 6,000,000.00)
EAO: Php 3,500,000.00
Excess: Php 57,692.49
Total Allocation: Php 100,000,000.00 |
September 6, 2021 |
FY2021 |
WIN1E02688 |
300116203724000 |
June 17, 2021 |
Region IX |
Regional Office IX |
Local Program - Local Roads and Bridges - Local Roads - Construction/ Repair/ Rehabilitation/ Improvement of Various Infrastructure including Local Projects
Labangan-Midsalip Road, Sta. 17+540 - Sta. 20+200, (Package 2), Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 5.320 Lane Km.
Unit Cost: Php 17,770,169.33/Lane Km.
ROW Acquisition: 6,542.330467 Sq. M. (Php 1,962,699.14)
EAO: Php 3,500,000.00
Total Allocation: Php 100,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02600 |
310204101151000 |
April 13, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Conctruction of Bypass and Diversion Roads
Sominot - Mahayag Road, Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 2.020 Lane Km.
Unit Cost: Php 48,679,016.20/lane km.
EAO: Php 3,441,606.45
Excess: Php 226,780.83
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02385 |
310204101142000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Balucot - Lower Usugan - Tungawan Bypass Road, Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 2.80 Lane Km.
Unit Cost: Php 35,153,571.43/lane km.
EAO: Php 3,570,000.00
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02315 |
310205100732000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/New Roads
Sindangan - Bayog - Lakewood Road, Package 1, Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 3.706 Lane Km.
Unit Cost: Php 21,909,667.14/lane km.
EAO: Php 2,947,000.00
Excess: Php 55,773.59
Total Allocation: Php 84,200,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02402 |
310205100734000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/New Roads
Sindangan - Bayog - Lakewood Road, Package 2, Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 3.60 Lane Km.
Unit Cost: Php 22,560,441.24/lane km.
EAO: Php 2,947,000.00
Excess: Php 35,411.54
Total Allocation: Php 84,200,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02444 |
310205100735000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/New Roads
Sindangan - Bayog - Lakewood Road, Package 3, Zamboanga del Sur
CW1: Construction of Concrete Road
Physical Target: 2.20 Lane Km.
Unit Cost: Php 36,900,876.44/lane km.
EAO: Php 2,947,000.00
Excess: Php 71,071.83
Total Allocation: Php 84,200,000.00 |
September 3, 2021 |
FY2021 |
WIN1G02990 |
310204101145000 |
May 31, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Ipil Circumferential Road, Zamboanga Sibugay, Phase III
CW1: Construction of Concrete Road
Physical Target: 1.62 Lane Km.
Unit Cost: Php 44,687,590.48/lane km.
ROW Acquisition: 88,333.0 Sq. M. (Php 25,572,500.00)
EAO: Php 3,570,000.00
Excess: Php 463,603.42
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02561 |
310204101143000 |
May 31, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Buenavista - Bolong By-pass Road, Package 3, Zamboanga City
CW1: Construction of Concrete Road
Physical Target: 1.50 Lane Km.
Unit Cost: Php 62,286,666.67/lane km.
ROW Acquisition: 16,666.67 Sq. M. (Php 5,000,000.00)
EAO: Php 3,570,000.00
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02416 |
310204101148000 |
April 20, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Lapakan - Lamisahan - Victoria By-pass Road, Zamboanga City
CW1: Construction of Concrete Road
Physical Target: 5.74 Lane Km.
Unit Cost: Php 17,148,083.62/lane km
EAO: Php 3,570,000.00
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1G02982 |
310306100188000 |
May 24, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Bridges - Construction of New Bridges
Liba Br. along Sindangan - Bayog - Lakewood Rd
CW1: Construction of Concrete Road
Physical Target: 867.186 Sq. M.
Unit Cost: Php 155,590.535/sq.m.
EAO: Php 4,900,000.00
Excess: Php 174,066.03
Total Allocation: Php 140,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02394 |
310305101245000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
Limpapa Parallel Br. along Zamboannga City-Labuan-Limpapa Road
CW1: Construction of Parallel Bridge
Physical Target: 867.186 Sq. M.
Unit Cost: Php 166,919.2076/sq. m.
EAO: Php 5,250,000.00
Total Allocation: Php 150,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02474 |
320101106238000 |
April 13, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Baybay River, along Sindangan-Liloy Road, K1964+000, Brgy, Baybay, Liloy, Zamboanga del Norte
CW1: Construction of Flood Mitigation Structure
Physical Target: 510.0 Ln. M.
Unit Cost: Php 98,878.10/ln.m.
ROW Acquisition: 2,273.983 Sq. M. (Php 682,194.87)
EAO: Php 1,764,974.09
Total Allocation: Php 52,875,000.00 |
September 3, 2021 |
2021 |
WIN1C04455 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Rehabilitation/Improvement of Villaviciosa Road Phase 2, Villaviciosa, Abra;
Type of Work: Rehabilitation of Concrete Road;
Physical Target: CW1: 12 Lane Km;
Allocation= Php 50,000,000
To: Rehabilitation/Improvement of Villaviciosa Road Phase 2, Villaviciosa, Abra;
Type of Work: CW1: Rehabilitation of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 7 Lane Km
CW2: 870 Square meters;
Allocation= Php 50,000,000
|
September 3, 2021 |
2021 |
WIN1C04479 |
GAA 2021 |
August 16, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Patiao Flood Control, Sta. 67+300 - 67+800, Peñarrubia, Abra;
Physical Target: CW1: 354 Lineal meters;
Allocation= Php 30,000,000
To: Construction of Patiao Flood Control, Sta. 67+300 - 67+800, Peñarrubia, Abra;
Physical Target: CW1: 292 Lineal meters;
Allocation= Php 30,000,000
|
September 3, 2021 |
2021 |
WIN1C04476 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Sinalang Flood Control, Peñarrubia, Abra;
Physical Target: CW1: 611.20 Lineal meters;
Allocation= Php 100,000,000
To: Construction of Sinalang Flood Control, Peñarrubia, Abra;
Physical Target: CW1: 663.20 Lineal meters;
Allocation= Php 100,000,000
|
September 3, 2021 |
2021 |
WIN1C04480 |
GAA 2021 |
August 16, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Pawa Flood Control, Lagangilang, Abra;
Physical Target: CW1: 445.594 Lineal meters;
Allocation= Php 50,000,000
To: Construction of Pawa Flood Control, Lagangilang, Abra;
Physical Target: CW1: 534 Lineal meters;
Allocation= Php 50,000,000
|
September 3, 2021 |
2021 |
WIN1C04478 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Demet Flood Control, La Paz, Abra;
Physical Target: CW1: 891.189 Lineal meters;
Allocation= Php 100,000,000
To: Construction of Demet Flood Control, La Paz, Abra;
Physical Target: CW1: 768.80 Lineal meters;
Allocation= Php 100,000,000
|
September 3, 2021 |
2021 |
WIN1C04481 |
GAA 2021 |
August 16, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Botnong Flood Control, Tineg, Abra;
Physical Target: CW1: 522 Lineal meters;
Allocation= Php 50,000,000
To: Construction of Botnong Flood Control, Tineg, Abra;
Physical Target: CW1: 440 Lineal meters;
Allocation= Php 50,000,000
|
September 3, 2021 |
2021 |
WIN1C04450 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Badas-Lam-ag Flood Control, San Juan, Abra;
Physical Target: CW1: 891.189 Lineal meters;
Allocation= Php 100,000,000
To: Construction of Badas-Lam-ag Flood Control, San Juan, Abra;
Physical Target: CW1: 432.80 Lineal meters;
Allocation= Php 100,000,000
|
September 3, 2021 |
2021 |
WIN1C04458 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Abra-Ilocos Norte Rd - K0434 + 650 - K0434 + 750;
Physical Target: CW1: 10,000 Square meters;
Allocation= Php 100,000,000
To: Abra-Ilocos Norte Rd - K0434 + 300 - K0434 + 450;
Physical Target: CW1: 4,063.5 Square meters;
Allocation= Php 100,000,000
|
September 3, 2021 |
2021 |
WIN1C04446 |
GAA 2021 |
August 11, 2021 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Abra-Ilocos Norte Rd - K0431 + 850 - K0431 + 920;
Physical Target: CW1: 10,000 Square meters;
Allocation= Php 100,000,000
To: Abra-Ilocos Norte Rd - K0432 + 080 - K0432 + 480;
Physical Target: CW1: 4,064 Square meters;
Allocation= Php 100,000,000
|
September 3, 2021 |
2021 |
WIN1C04485 |
GAA 2021 |
August 16, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Construction of Carumsing Bridge, Carumsing, Dangtalan, Pasil, Kalinga;
Physical Target: CW1 : 0 Square meters;
Allocation= Php 102,000,000
To: Construction of Carumsing Bridge, Carumsing, Dangtalan, Pasil, Kalinga;
Physical Target: CW1 : 1,159.11 Square meters;
Allocation= Php 102,000,000
|
September 3, 2021 |
2021 |
WIN1C04495 |
GAA 2021 |
August 19, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Gov. Bado Dangwa National Rd - K0348 + 760 - K0349 + 068;
Physical Target: CW1 : 0 Square meters;
Allocation= Php 110,000,000
To: Gov. Bado Dangwa National Rd - K0348 + 760 - K0348 + 908;
Physical Target: CW1 : 4898.40 Square meters;
Allocation= Php 110,000,000
|
September 3, 2021 |
2021 |
WIN1C04459 |
GAA 2021 |
August 10, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0275 + 350 - K0275 + 456, K0275 + 509 - K0275 + 635, K0275 + 690 - K0275 + 848;
Physical Target: CW1 : 0 Square meters;
Allocation= Php 290,000,000
To: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0275 + 510 - K0275 + 635, K0275 + 690 - K0275 + 810;
Physical Target: CW1 : 11,945 Square meters;
Allocation= Php 290,000,000
|
September 3, 2021 |
2021 |
WIN1C04447 |
GAA 2021 |
August 10, 2021 |
Cordillera Administrative Region |
CAR - Regional Office |
From: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0362 + 560 - K0362 + 720, K0372 + 210 - K0372 + 310;
Physical Target: CW1 : 5,200 Square meters;
Allocation= Php 102,762,000
To: Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0362 + 560 - K0362 + 675, K0372 + 210 - K0372 + 310;
Physical Target: CW1 : 4,874.23 Square meters;
Allocation= Php 102,762,000
|
September 3, 2021 |
FY2021 |
WIN1E02650 |
320101106239000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Kumalarang, Zamboanga del Sur
CW1: Construction of Flood Mitigation Structure
Physical Target: 550.50 Ln. M.
Unit Cost: Php 184,285.6955/ln. m.
EAO: Php 3,550,724.64
Total Allocation: Php 105,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02705 |
320101106242000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structures with Esplanade at Limpapa River, Zamboanga City-Labuan-Limpapa Road (Limpapa Br. Section)
CW1: Construction of Flood Mitigation Structure
Physical Target: 259.79 Ln. M.
Unit Cost: Php 371,909.4557/ln.m.
EAO: Php 3,381,642.51
Total Allocation: Php 100,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1G02954 |
320101106243000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Labason Flood Control at Antonino, Labason, Zamboanga del Norte (Upstream) Package 1
CW1: Construction of Flood Mitigation Structures
Physical Target: 557.0 Ln. M.
Unit Cost: Php 181,398.69/ln. m.
ROW Acquisition: 953.1065 Sq. M. (Php 285,931.96)
EAO: Php 3,675,000.00
Total Allocation: Php 105,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1G02958 |
320101106244000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Labason Flood Control at Antonino, Labason, Zamboanga del Norte (Upstream) Package 2
CW1: Construction of Flood Mitigation Structure
Physical Target: 440.0 Ln. M.
Unit Cost: 225,854.55/ln.m.
ROW Acquisition: 830.0003 Sq. M. (Php 249,000.09)
EAO: Php 3,675,000.00
Excess: Php 1,700,000.00
Total Allocation: Php 105,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1E02327 |
320101106246000 |
April 13, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Revetment, Kumalarang River, Isabela City
CW1: Construction of Flood Mitigation Structure
Physical Target: 888.40 Ln. M.
Unit Cost: Php 162,716.5296/ln.m.
ROW Acquisition: 1,277.09 Sq. M. (Php 383,127.29)
EAO: Php 5,059,507.77
Total Allocation: 150,000,000.00 |
September 3, 2021 |
2021 |
WIN1E02803 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200287000
Project ID: P00550449MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 40+576 - Sta. 40+830, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 40+596 - Sta. 40+712.56, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.15 Square meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.25 / Square meter |
September 3, 2021 |
FY2021 |
WIN1E02475 |
320101106247000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO2: Protect Lives and Properties - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Upper Tungawan Flood Control Structure along Tungawan River (Phase III), Tungawan, Zamboanga Sibugay
CW1: Construction of Flood Mitigation Structure
Physical Target: 641.0 Ln. M.
Unit Cost: Php 165,319.75/ln.m.
ROW Acquisition: 600.1378 Sq. M. (Php 180,041.34)
EAO: Php 3,850,000.00
Total Allocation: Php 110,000,000.00 |
September 3, 2021 |
2021 |
WIN1E02797 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200290000
Project ID: P00550452MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 44+107 - Sta. 44+300, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 44+170 - Sta. 44+262.92, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.16 Square meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.19 / Square meter |
September 3, 2021 |
2021 |
WIN1E02798 |
FY 2021 GAA RA 11518 |
January 25, 2021 |
Region XIII |
Surigao del Norte 2nd District Engineering Office |
UACS No. : 300108200291000
Project ID: P00550453MN
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
FROM:
Construction of Road Slope Protection Structure along Surigao-Agusan West Coastal Road Sta. 44+360 - Sta. 44+590, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 0 Square meter
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 0 / Square meter
TO:
Local Program - Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects
Construction of Road Slope Protection Structure along Surigao - Agusan West Coastal Road Sta. 44+360 - Sta. 44+468.5, Malimono, Surigao del Norte
Type of Work:
CW1- Construction of Road Slope Protection Structure
Physical Target:
CW1- 4,040.15 Square meters
Allocation:
TOTAL: P 100,000,000
CW1: P 96,500,000
EAO: P 3,500,000
Unit Cost:
CW1: P 23,885.25 / Square meter |
September 3, 2021 |
FY2021 |
WIN1E02530 |
300211100199000 |
April 12, 2021 |
Region IX |
Regional Office IX |
CSSP: Convergence and Special Support Program - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
Repair/Maintenance National Roads and Bridges, Painting/Repainting of Centerline and Edge Line along: Dipolog-Orquieta Rd (K1795+(-437)-K1829+543 Intermittent Section);
Dipolog-Punta-Dansullan Sergio Osmena Road (K1857+(-1123)-K1893+775 Intermittent Section); Rizal-Dakak-Dapitan Coastal Loop Road (K1798+(-893)-K1868+881 Intermittent Section); Dipolog-Polanco-Pinan Jct Oroq Road (K1810+(-471)-K1828+800 Intermittent Section); Pinan-Mutia Rd (K1817+000-K1830+000); Jct. Polo-Dapitan Park Road (K1825+(-305) - K1829+000 Intermittent Section); Dipolog-Polanco-Macleodes Rd. (K1828+(-220)-K1848+952 Intermittent Section); Jct. Polo-Pulauan Port Road (K1827+(-320)-K1828+438 Intermittent Section)
CW1: Road Safety: Pavement Markings
Physical Target: 408.316 Lane Km.
Unit Cost: Php 108,775.0916/lane km.
EAO: Php 1,554,511.36
Excess: Php 30,878.32
Total Allocation: Php 46,000,000.00
|
September 3, 2021 |
FY2021 |
WIN1E02278 |
310201100683000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1777+980.00 - K1778+580.00, K1778+660.00 - K1782+580.00
CW1: Road Widening
Physical Target: 9.040 Lane Km.
Unit Cost: Php 10,481,823.98/lane km.
ROW Acquisition: 13,092.874 Sq. M. (Php 3,927,862.10)
EAO: Php 3,316,449.10
Total Allocation: Php 102,000,000.00 |
September 3, 2021 |
FY2021 |
WIN1G02899 |
310201100684000 |
April 12, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Liloy-Ipil Road - K1981+373 - K1984+460, K1984+497.65 - K1984+800.00
CW1: Road Widening
Physical Target: 6.779 Lane Km.
Unit Cost: Php 15,288,220.27/lane km.
ROW Acquisition: 9,112.651 Sq. M. (Php 2,733,795.20)
EAO: Php 3,627,359.58
Total Allocation: Php 110,000,000.00 |
September 2, 2021 |
FY2021 |
WIN1G02961 |
310202100720000 |
April 20, 2021 |
Region IX |
Regional Office IX |
OO1:Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Basilan Circumferential Rd - K0006+635.45 - K0007+585.50, K0008+544.96 - K0009+380.00, K0009+640.00 - K0011+049.95
CW1: Road Widening
Physical Target: 6.39 Lane Km.
Unit Cost: Php 17,793,077.81/lane km.
ROW Acquisition: 39,174.1093 Sq. M. (Php 11,752,232.79)
EAO: Php 4,550,000.00
Total Allocation: Php 130,000,000.00 |
September 2, 2021 |
FY2021 |
WIN1E02379 |
310212100171000 |
April 19, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads
Zamboanga del Sur Coastal Road - (S01167MN) Chainage 16134 - Chainage 16791, (S01167MN) Chainage 18571 - Chainage 20180, (S01168MN) Chainage 10160 - Chainage 11160
CW1: Paving of Unpaved Roads
Physical Target: 6.532 Lane Km.
Unit Cost: Php 15,087,373.64/lane km.
EAO: Php 3,449,275.37
Total Allocation: Php 102,000,000.00 |
September 2, 2021 |
FY2021 |
WIN1E02450 |
310108100567000 |
April 13, 2021 |
Region IX |
Regional Office IX |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse and Landslide - Secondary Roads
Zamboanga City - Labuan - Limpapa Road - K1976+300 - K1977+063.04
CW1:Construction of Slope Protection Structure
Physical Target: 8,059.39 Lane Km.
Unit Cost: Php 17,957.90061/Square Meter
EAO: Php 5,065,540.36
Total Allocation: Php 150,000,000.00 |