Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
April 7, 2022 FY 2022 WINC03514 UACS No. 300219100446000 February 24, 2022 National Capital Region Metro Manila 3rd District Engineering Office
As per GAA/Original
UACS No. 300219100446000
Project ID.: P00637045LZ
Convergence and Special Support Program
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) – Flood Mitigation Structures Protecting
Public Infrastructure/Facilities
Construction of Flood Control Wall along Bisi-Mabolo, Brgy. Mabolo, Valenzuela City
Physical Target: CW1 – Construction of Flood Mitigation Structure = 212.00 lane km
Unit Cost = P 69,339.62/lane km
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000

As Modified
Convergence and Special Support Program
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) – Flood Mitigation Structures Protecting
Public Infrastructure/Facilities
Construction of Flood Control Wall along Bisig-Mabolo, Brgy. Mabolo, Valenzuela City
Physical Target: CW1 – Construction of Flood Mitigation Structure = 212.00 lane km
Unit Cost = P 69,339.62/lane km
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000
WINC03514
April 7, 2022 FY 2022 WIN2C03504 UACS No. 310106100691000 February 10, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310106100691000
Project ID.: P00603570LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction / Upgrading of Damaged Paved Roads – Tertiary Roads
Aurora Avenue – (S02355LZ) Chainage 832 – Chainage 895
Physical Target: CW1 – Reconstruction of Concrete Pavement=0.252 lane km
Unit Cost = P 38,888,889/lane km
Allocation = P 9,800,000
EAO = P 200,000
Total = P 10,000,000

As Modified
OO1: Ensure Safe and Reliable National Road, System
Asset Preservation – Rehabilitation/ Reconstruction / Upgrading of Damaged Paved Roads – Tertiary Roads
Aurora Avenue – (S02355LZ) Chainage 000.0 – Chainage 76.0, Chainage 832.0 – Chainage 895.0
Physical Target: CW1 – Reconstruction of Concrete Pavement=0.834 lane km
Unit Cost = P 11,750,560/lane km
Allocation = P 9,800,000
EAO = P 200,000
Total = P 10,000,000
WIN2C03504
April 7, 2022 FY 2022 WIN2C03513 UACS No. 300221100150000 February 8, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 300221100150000
Project ID.: P00631920LZ
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Rehabilitation of Road, Zone 1-7, Barangay 100-190, Manila City
Physical Target: CW1 – Rehabilitation of Concrete Road=2.359 lane km
Unit Cost = P 14,688,427/lane km
Allocation = P 34,650,000
EAO = P 350,000
Total = P 35,000,000

As Modified
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Rehabilitation of Road, Zone 1-7, Barangay 1-90, Manila City
Physical Target: CW1 – Rehabilitation of Concrete Road=2.359 lane km
Unit Cost = P 14,688,427/lane km
Allocation = P 34,650,000
EAO = P 350,000
Total = P 35,000,000
WIN2C03513
April 6, 2022 2022 WIN2F05892 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Asset Preservation Program - Preventive Maintenance - Tertiary Roads

Concepcion - La Paz Rd - K0134+000 - K0134+345, K0135+366 - K0135+889

April 6, 2022 2022 WIN2F05893 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures / Facilities

Rehabilitation of Dike along Parua River, Sta. 6+675 to Sta. 7+119 (Brgy. San Francisco Section Left Bank), Concepcion, Tarlac
April 5, 2022 FY 2022 WIN2C03472 UACS No. 300226100254000 February 8, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 300226100254000
Project ID.: P00633123LZ
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Multi-Purpose Building, Zone 1-7, Barangay 100-190, Manila City
Physical Target: CW1 = Rehabilitation/ Major Repair Multi-Purpose Building 1.0 bldg.
Unit Cost = P 39,600,000/ bldg
Allocation = P 39,600,000
EAO = P 400,000
Total = P 40,000,000

As Modified
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Multi-Purpose Building, Zone 1-7, Barangay 1-90, Manila City
Physical Target: CW1 = Rehabilitation/ Major Repair Multi-Purpose Building 6.0 bldg.
Unit Cost = P 6,600,000/ bldg
Allocation = P 39,600,000
EAO = P 400,000
Total = P 40,000,000
WIN2C03472
April 5, 2022 FY 2022 WIN2C03472 UACS No. 300226100254000 February 8, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 300226100254000
Project ID.: P00633123LZ
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Multi-Purpose Building, Zone 1-7, Barangay 100-190, Manila City
Physical Target: CW1 = Rehabilitation/ Major Repair Multi-Purpose Building 1.0 bldg.
Unit Cost = P 39,600,000/ bldg
Allocation = P 39,600,000
EAO = P 400,000
Total = P 40,000,000

As Modified
Convergence and Special Support Program
Convergence and Special Support – Basic Infrastructure Program (BIP) – Access Roads and/or
Bridges from National Road/s leading to Major/Strategic Public Buildings/ Facilities
Construction of Multi-Purpose Building, Zone 1-7, Barangay 1-90, Manila City
Physical Target: CW1 = Rehabilitation/ Major Repair Multi-Purpose Building 6.0 bldg.
Unit Cost = P 6,600,000/ bldg
Allocation = P 39,600,000
EAO = P 400,000
Total = P 40,000,000
WIN2C03472
April 5, 2022 2022 310201100862000 GAA FY 2022 January 3, 2022 Region II Regional Office II
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads - Daang Maharlika (LZ) - K0373+(-387.25) - K0374+170
April 5, 2022 2022 3002191000043000 GAA FY 2022 January 3, 2022 Region II Regional Office II
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities - Construction of Catotoran Norte Flood Structure, Sta. 0+000 - Sta. 0+130, Sta. 0+000 - Sta. 0+057, Sta. 0+000 - Sta. 0+200, Camalaniugan, Cagayan
April 5, 2022 2022 310101100545000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads - Manila North Rd - K0615+000 - K0617+198
April 5, 2022 2022 310101100546000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads - Manila North Rd - K0625+000 - K0628+061
April 5, 2022 2022 310101100547000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads - Manila North Rd - K640+1007 - K0644+019
April 5, 2022 2022 310101100621000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads - Manila North Rd - K0647+000 - K0648+565
April 5, 2022 2022 310101100622000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads - Manila North Rd - K0664+020 - K0664+455
April 5, 2022 2022 310102100904000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads - Calog-Pudtol Rd - K0666+065 - K0667+387
April 5, 2022 2022 310104100387000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads - Manila North Rd - K0679+272 - K0679+762
April 5, 2022 2022 310107100370000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads - Manila North Rd - K0600+560 - K0600+830
April 5, 2022 2022 310209100331000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development - Off-Carriageway Improvement - Tertiary Roads - Jct Logac-Lasam-Gagabutan Rd - K0717+027 - K0720+028
April 5, 2022 FY 2021 WIN2C03450 UACS No. 320101106435000 January 31, 2022 National Capital Region Metro Manila 3rd District Engineering Office
As per GAA/Original
UACS No. 320101106435000
Project ID.: P00525801LZ
OO2: Protect Lives and Properties Against Major Flood
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Improvement of Flood Control River Wall along Polo River, Tagalag, Valenzuela City
Physical Target: CW1 - Rehabilitation/ Major of Flood Control Structure – 0.000 Lineal Meters
Unit Cost = -
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000

As Modified
OO2: Protect Lives and Properties Against Major Flood
Flood Management – Construction/Maintenance of Flood Mitigation Structures and Drainage Systems
Improvement of Flood Control River Wall along Polo River, Tagalag, Valenzuela City
Physical Target: CW1 - Rehabilitation/ Major of Flood Control Structure – 70.000 Lineal Meters
Unit Cost = P 210,000.00/Lineal Meter
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000
WIN2C03450
April 5, 2022 2022 310212100216000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads - Jct Logac-Lasam-Gagabutan Rd - (S00656LZ) Chainage 13758 - Chainage 14860, Chainage 14949 - Chainage 15159
April 5, 2022 FY 2022 WIN2C03495 UACS No. 300215100901000 March 9, 2022 National Capital Region South Manila District Engineering Office
As per GAA/Original
UACS No. 300215100901000
Project ID.: P00630332LZ
Convergence and Special Support Program
Sustainable Infrastructure Projects alleviating Gaps (SIPAG) – Access Roads and/or Bridges from
the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road including Drainage Improvement of Zone 931, Pandacan, Manila
Physical Target: CW1 – Construction of Concrete Road – 2.810 lane km
Unit Cost = P 10,462,634/lane km
Allocation = P 29,400,000
EAO = P 600,000
Total = P 30,000,000

As Modified
Convergence and Special Support Program
Sustainable Infrastructure Projects alleviating Gaps (SIPAG) – Access Roads and/or Bridges from
the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road including Drainage Improvement of Zone 91, Pandacan, Manila
Physical Target: CW1 – Construction of Concrete Road – 2.810 lane km
Unit Cost = P 10,462,634/lane km
Allocation = P 29,400,000
EAO = P 600,000
Total = P 30,000,000
WIN2C03495
April 5, 2022 2022 310201100965000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Manila North Rd - K0662+069 - K0663+000
April 5, 2022 2022 310201100966000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads - Manila North Rd - K0650+927 - K0651+000, K0655+579 - K0655+728, K0655+751 - K0656+938, K0656+961 - K0657+000
April 5, 2022 2022 320102104913000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Pata Flood Control Structure along Pata River (Sta. 0+000 - Sta. 0+120), Pata, Claveria, Cagayan
April 5, 2022 2022 320102104910000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Langgangan Flood Control along Langgangan River, Sta. 0+000 - Sta. 0+418 (Section 1), Sta. 0+000 - Sta. 0+025 (Section 2), Sta. 0+000 - Sta. 0+132 (Section 3), Sta. Praxedes, Cagayan
April 5, 2022 2022 320102104522000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Canayun-Sirit-Dana-Ili Flood Control Along Abulug River (Sta. 13+300 - Sta. 13+580) Left Side, Abulug, Cagayan
April 5, 2022 2022 320102104909000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Dugo Flood Control along Abulug River (Sta. 10+310 - Sta. 10+600 R/S), Abulug, Cagayan
April 5, 2022 2022 320102104910000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Simayung Flood Control along Abulug River, Sta. 7+241 - Sta. 7+416 Section 1, Sta. 7+416 - Sta. 7+466 Section 2, Abulug, Cagayan
April 5, 2022 2022 320102104912000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation along Major River Basins and Principal Rivers - Construction of Masi Flood Control Structure along Pamplona River (Sta. 0+000 - Sta. 0+250), Pamplona, Cagayan
April 5, 2022 2022 310212100217000 GAA FY 2022 January 3, 2022 Region II Cagayan 2nd District Engineering Office
OO1: Ensure Safe and Reliable National Road System - Network Development Program - Paving of Unpaved Roads - Tertiary Roads - (S00656LZ) Chainage 500 - Chainage 1865
April 2, 2022 2022 WIN2F05909 SR2022-02-000068 February 3, 2022 Cordillera Administrative Region CAR - Regional Office
From: Cong. Andres Acop Cosalan Rd - K0301 + (-905) - K0304 + 024, K0313 + 175 - K0317 + 533, K0319 + 000 - K0322 + 600, K0324 + 000 - K0327 + 000, K0328 + 700 - K0330 + 500, K0331 + 751 - K0333 + 1495, K0336 + 000 - K0342 + 222;
Physical Target: 50.530 Lane Km;
Allocation: Php 300,000,000

To: Cong. Andres Acop Cosalan Rd - K0301 + (-905) - K0304 + 024, K0313 + 175 - K0317 + 533, K0319 + 000 - K0322 + 600, K0324 + 000 - K0327 + 000, K0328 + 700 - K0330 + 500, K0331 + 751 - K0333 + 381;
Physical Target: 35.902 Lane Km;
Allocation: Php 300,000,000

April 2, 2022 2022 WIN2F05909 SR2022-02-000068 February 3, 2022 Cordillera Administrative Region CAR - Regional Office
From: Cong. Andres Acop Cosalan Rd - K0301 + (-905) - K0304 + 024, K0313 + 175 - K0317 + 533, K0319 + 000 - K0322 + 600, K0324 + 000 - K0327 + 000, K0328 + 700 - K0330 + 500, K0331 + 751 - K0333 + 1495, K0336 + 000 - K0342 + 222;
Physical Target: 50.530 Lane Km;
Allocation: Php 300,000,000

To: Cong. Andres Acop Cosalan Rd - K0301 + (-905) - K0304 + 024, K0313 + 175 - K0317 + 533, K0319 + 000 - K0322 + 600, K0324 + 000 - K0327 + 000, K0328 + 700 - K0330 + 500, K0331 + 751 - K0333 + 381;
Physical Target: 35.902 Lane Km;
Allocation: Php 300,000,000

April 2, 2022 2022 WIN2F05904 SR2022-03-007586 March 23, 2022 Cordillera Administrative Region CAR - Regional Office
From: Benguet-Nueva Vizcaya Rd - K0302 + 320 - K0302 + 415;
Physical Target: 6,666.670 Square meters;
Allocation: Php 120,000,000


To: Benguet-Nueva Vizcaya Rd - K0293+ 245 - K0293 + 308;
Physical Target: 4,774.000 Square meters;
Allocation: Php 120,000,000
April 2, 2022 2022 WIN2F05902 SR2022-02-001190 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0271 + 286 - K0271 + 413;
Physical Target: 8333.330 Square meters;
Allocation: Php 150,000,000

To: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0271 + 216 - K0271 + 466;
Physical Target: 6,434.000 Square meters;
Allocation: Php 150,000,000

April 2, 2022 2022 WIN2F05898 SR2022-02-001197 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0271 + 889 - K0272 + 050, K0272 + 393 - K0272 + 458;
Physical Target: 8333.340 Square meters;
Allocation: Php 150,000,000

To: Itogon-Dalupirip-Sn Manuel Bdry Rd - K0271 + 875 - K0272 + 045, K0272 + 400 - K0272 + 455;
Physical Target: 6,341.000 Square meters;
Allocation: Php 150,000,000

April 2, 2022 2022 WIN2F05905 SR2022-02-001865 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Preventive Maintenance (Asphalt Overlay) along Baguio-Bontoc Rd - K0254 + (-586) - K0260 + 000;
Physical Target: 9.800 Lane Km;
Allocation: Php 130,000,000

To: Preventive Maintenance (Asphalt Overlay) along Baguio-Bontoc Rd - K0253 + (-586) - K0262 + 000;
Physical Target: 19.232 Lane Km;
Allocation: Php 130,000,000

April 2, 2022 2022 WIN2F05941 SR2022-02-001889 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Preventive Maintenance (Asphalt Overlay) along Baguio-Itogon Rd - K0254 + (-651) - K0258 + 595, K0261 + 000 - K0268 + 055;
Physical Target: 15.831 Lane Km;
Allocation: Php 210,000,000

To: Preventive Maintenance (Asphalt Overlay) along Baguio-Itogon Rd - K0254 + (-651) - K0258 + 595, K0261 + 000 - K0264+768;
Physical Target: 17.948 Lane Km;
Allocation: Php 210,000,000

April 2, 2022 2022 WIN2F05934 SR2022-02-001142 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Gov. Bado Dangwa National Rd - K0338 + 150 - K0338 + 300;
Physical Target: 8333.330 Square meters;
Allocation: Php 150,000,000

To: Gov. Bado Dangwa National Rd - K0338 + 038 - K0338 + 151, K0338 + 220 - K0338 + 250;
Physical Target: 6166.000 Square meters;
Allocation: Php 150,000,000

April 2, 2022 2022 WIN2F05913 SR2022-02-001927 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Preventive Maintenance along Baguio-Bontoc Rd - K0281 + 195 - K0288 + 827;
Type of Work: Preventive Maintenance of Road: Concrete Reblocking;
Physical Target: 11.308 Lane Km;
Allocation: Php 150,000,000.000

To: Preventive Maintenance along Baguio-Bontoc Rd - K0273 + 500 - K0281 + 438;
Type of Work: Preventive
Maintenance of Road: Asphalt Overlay;
Physical Target: 15.940 Lane Km;
Allocation: Php 150,000,000.000

April 2, 2022 2022 WIN2F05914 SR2022-02-001930 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Preventive Maintenance along Baguio-Bontoc Rd - K0288 + 827 - K0299 + 730, K0299 + 750 - K0300 + 636;
Physical Target: 16.584 Lane Km;
Allocation: Php 220,000,000

To: Preventive Maintenance along Baguio-Bontoc Rd - K0294 + 969 - K0299 + 760, K0299 + 820 - K0307 + 205;
Physical Target: 24.096 Lane Km;
Allocation: Php 220,000,000

April 2, 2022 2022 WIN2F05915 SR2022-02-001933 February 4, 2022 Cordillera Administrative Region CAR - Regional Office
From: Preventive Maintenance along Gov. Bado Dangwa National Rd - K0346 + 000 - K0351 + 256, K0328 + (-085) - K0335 + 000;
Physical Target: 16.584 Lane Km;
Allocation: Php 220,000,000

To: Preventive Maintenance along Gov. Bado Dangwa National Rd - (S00377LZ) K0328 + (-085) - K0329 + 420, (S00376LZ) K0320 + 100 - K0331 + 000;
Physical Target: 24.852 Lane Km;
Allocation: Php 220,000,000

March 30, 2022 2022 WIN2F05881 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Convergence and Special Support Program - Basic Infrastructure Program - Flood Mitigation Structures protecting Public Infrastructures/Facilities

Rehabilitation of Existing Dike along Binabakod River, Paludpud Section, D/S of Check Gate, La Paz, Tarlac
March 30, 2022 2022 WIN2F05880 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers

Rehabilitation of Dike along O'Donnell River (Brgy. Maruglu Section, Sta. 2+603 to Sta. 3+137 Right Bank), Capas, Tarlac
March 30, 2022 2022 WIN2F05835 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Convergence and Special Support Program - Flood Mitigation Structures protecting Public Infrastructures/Facilities

Rehabilitation of Existing Dike along O'Donnell River (Sta. Lucia Section, Right Bank), Sta. 10+820.00 to Sta. 11+102.80, Capas, Tarlac
March 30, 2022 2022 WIN2F05873 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Asset Preservation Program - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Tertiary Roads

Concepcion - La Paz Rd - K0120+915 - K0121+108, K0121+108 - K0121+570, K0122+710 - K0123+013, K0132+117 - K0132+363
March 30, 2022 2022 WIN2F05879 FY 2022 GAA December 30, 2021 Region III Tarlac 2nd District Engineering Office
Network Development Program - Off-Carriageway Improvement - Primary Roads

Tarlac - Sta. Rosa Rd - K0133+954 - K0134+340
March 30, 2022 2022 WIN2F05942 FY 2022 GAA December 30, 2021 Region III Regional Office III
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads

Madella - Dinadiawan Rd - K0418+690 - K0418+750
March 29, 2022 FY 2022 WIN2C03467 UACS No. 310106100696000 February 11, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310106100696000
Project ID.: P00603572LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads
North Antipolo St – K0007+000 – K0007+044, K0008+931 – K0007+000
Physical Target: CW1 = Rehabilitation of Paved Road 0.226 lane km
Unit Cost = P 21,681,416/lane km
Allocation = P 4,900,000
EAO = P 100,000
Total = P 5,000,000

As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads
North Antipolo St – K0009+(-267.80) – K0009+(129.30)
Physical Target: CW1 = Rehabilitation of Paved Road 0.277 lane km
Unit Cost = P 17,689,531/lane km
Allocation = P 4,900,000
EAO = P 100,000
Total = P 5,000,000
WIN2C03467
March 29, 2022 FY 2022 WIN2C03469 UACS No. 310102100868000 February 10, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 310102100868000
Project ID.: P00603562LZ
OO1: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
J Rizal Ave – K0003+(-168.80)– K0003+000, K0003+(-170) – K0003+(-168.80), K0003+(195.10) – K0003+(-170), K0003+000 – K0003+529
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay = 1.448 lane km
Unit Cost = P 6,767,956/lane km
Allocation = P 9,800,000
EAO = P 200,000
Total = P 10,000,000

As Modified
OO1: Ensure and Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
J Rizal Ave –K0003+(-529) – K0003+(-195.1)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay = 1.448 lane km
Unit Cost = P 5,871,779/lane km
Allocation = P 9,800,000
EAO = P 200,000
Total = P 10,000,000
WIN2C03469
March 29, 2022 FY 2022 WIN2C03477 UACS No. 3101022100872000 February 10, 2022 National Capital Region North Manila District Engineering Office
As per GAA/Original
UACS No. 3101022100872000
Project ID.: P00603560LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Legarda St. – K0003+(-523)-K0003+(-320), K0003+(-603)-K0003+(-523), K0003+(-683)-
K0003+(-603), K0003+(-693)-K0003+(-683), K0003+(=752.70)-K0003+(-693)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 0.865 lane km
Unit Cost = P 16,994,219 / lane km.
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000

As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Secondary Roads
Legarda St. – K0003+(-655.3)-K0003+(-210.6)
Physical Target: CW1 = Preventive Maintenance of Road: Asphalt Overlay 0.889 lane km
Unit Cost = P 16,535,433 / lane km.
Allocation = P 14,700,000
EAO = P 300,000
Total = P 15,000,000
WIN2C03477
March 29, 2022 2022 WIN2F05870 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation - Construction / Upgrading / Rehabilitation of Drainage along National Roads - Primary Roads

Romulo H-way - K0160+390 - K0161+158
March 29, 2022 2022 WIN2F05821 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Manila North Rd - K0155+876 - K0156+210, K0159+721 - K0160+565
March 29, 2022 2022 WIN2F05830 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Manila North Rd - K0156+210 - K0156+350, K0157+081 - K0158+800
March 29, 2022 2022 WIN2F05837 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Tarlac - Sta. Rosa Rd - K0136+ (-404) - K0136+487, K0136+511 - K0137+093, K0137+384 - K0137+549

March 29, 2022 2022 WIN2F05832 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Romulo H-way - K0141+024 - K0141+361
March 29, 2022 2022 WIN2F05834 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Rehabilitation of Flood Control Structure along Tarlac River Control (Right Dike), Tagumbao - Dicolor Section (Package B), Sta. 0+000 - Sta. 0+313, Gerona, Tarlac
March 29, 2022 2022 WIN2F05822 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

Construction of Flood Control Structure along Camiling River (Left Bank), Libueg - Bacabac Section (Package D), Sta. 0+249 - Sta. 0+525, Camiling, Tarlac
March 29, 2022 2022 WIN2F05833 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

Construction of Flood Control Structure along Camiling River (Right Bank), Bilad Section (Package B), Sta. 0+000 - Sta. 0+194, Bilad, Camiling, Tarlac
March 29, 2022 2022 WIN2F05824 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities along Major River Basins and Principal Rivers

Construction of Flood Control Structure along Camiling River (Right Bank), Tambugan - Sawat Section (Package A), Sta. 0+567 - Sta. 0+863, Camiling, Tarlac
March 29, 2022 2022 WIN2F05823 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Romulo H-way - K0140+361 - K0141+024, K0141+361 - K0141+810
March 29, 2022 2022 WIN2F05827 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Manila North Rd - K0131+605 - K0132+073
March 29, 2022 2022 WIN2F05831 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Manila North Rd - K0131+081 - K0131+605
March 29, 2022 2022 WIN2F05825 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program - Preventive Maintenance - Primary Roads

Romulo H-way - K0132+599 - K0134+410
March 29, 2022 2022 WIN2F05826 FY 2022 GAA December 30, 2021 Region III Tarlac District Engineering Office
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads - Primary Roads

Manila North Rd - K0133+674 - K0134+173
March 24, 2022 2022 WIN2E01980 FY 2022 GAA RA 11639 January 20, 2022 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 300214100095000
Project ID: P00633706MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239

FROM:

Preventive Maintenance along Daang Maharlika (Surigao-Agusan Sect) - K1125 + 050 - K1680 + 546.25

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 3.910 Lane Km

Allocation:
TOTAL: P 60,000,000
CW1: P 57,900,000
EAO: P 2,100,000

Unit Cost:
CW1: P 14,808,184.14/ Lane Km

TO:

Preventive Maintenance along Daang Maharlika (Surigao-Agusan Sect) - K1125 + 000.00 - K1126+954.10

Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay

Physical Target:
CW1- 3.910 Lane Km

Allocation:
TOTAL: P 60,000,000
CW1: P 57,900,000
EAO: P 2,100,000

Unit Cost:
CW1: P 14,808,184.14/ Lane Km
March 24, 2022 2022 WIN2F05829 FY 2022 GAA December 30, 2021 Region III Bataan 1st District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Construction / Rehabilitation of Flood Control Project along Colo River, Sta. (-) 0+739.50 - Sta. (-) 1+111.41, Palihan Section Phase 2AGP, Hermosa, Bataan
March 24, 2022 2022 WIN2F05839 FY 2022 GAA December 30, 2021 Region III Bataan 1st District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Construction/Rehabilitation of Flood Control Project along Colo River, Sta. 0+441.43 - Sta. (-)0+596.40, Palihan Section Phase 1AGP, Hermosa, Bataan

March 24, 2022 2022 WIN2F05838 FY 2022 GAA December 30, 2021 Region III Bataan 1st District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Construction/Rehabilitation of Flood Control Project along Colo River, Sta. 0+495.50 - Sta. 0+846.62, Layac Section Phase 2AGP, Dinalupihan, Bataan
March 24, 2022 2022 WIN2F05828 FY 2022 GAA December 30, 2021 Region III Bataan 1st District Engineering Office
Flood Management Program - Construction / Maintenance of Flood Mitigation Structures and Drainage Systems

Construction/Rehabilitation of Flood Control Project along Colo River, Sta. (-)0+159 - Sta. 0+495.50. Layac Section Phase 1AGP, Dinalupihan, Bataan
March 22, 2022 FY 2021 GAA WIN1G02575 DPWH Infra Program FY 2021 December 28, 2020 Region IV-B Regional Office IV-B
UACS No.: 300202100197000
Project ID : P00534413LZ

Convergence and Special Support Program

Construction/Improvement of Access Roads leading to Seaports

FROM :

Concreting of Access Road leading to San Vicente Port Barton Docking Area MIMAROPA/Palawan/San Vicente/Port Barton, Palawan
Physical Target : CW1 - Construction of Concrete Road :
3.2 Lane Km
Allocation : Php 40.00 Million

TO :

Concreting of Access Road leading to San Vicente Port Barton Docking Area MIMAROPA/Palawan/San Vicente/Port Barton,
Palawan
Physical Target : CW1 - Construction of Concrete Road :
1.52978 Lane Km
CW2 - Road Safety : Pavement Markings :
1,923.0 Lineal Meters
Allocation : Php 40.00 Million
March 21, 2022 FY 2021 GAA WIN2G02604 DPWH FY 2021 GAA December 28, 2020 Region IV-B Regional Office IV-B
UACS No. : 300116204189000
Project ID : P00562450LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/repair/Rehabilitation /Improvement of
Various Infrastructure including Local Projects

FROM :

Construction of Road leadinng to San Vicente Port Barton, Palawan
Physical Target : CW1 - Construction of Concrete road : 0 Lane km
Allocation : Php 20.00 Million

TO:

Construction of Road leading to San Vicente Port Barton, Palawan
Physical Target : CW1 - Construction of Concrete Road :
1.30 Lane Km
Allocation : Php 20.00 Million
March 21, 2022 FY 2021 GAA WIN2G02603 DPWH Infra Program FY 2021 December 28, 2020 Region IV-B Regional Office IV-B
UACS No. : 300116204190000
Project ID : P00562451LZ

LOCAL PROGRAM

Local Roads and Bridges - Local Roads -
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM :

Construction/Improvement of Taradungan - Antonio Road,
Roxas, Palawan
Physical Target : CW1 - Construction of Concrete Road :
0 Lane Km
Allocation : Php 25.00 Million

TO :

Construction/Improvement of Taradungan - Antonio Road,
Roxas, Palawan
Physical Target : CW1 - Construction of Concrete Road :
1.90 Lane Km
Allocation : Php 25.00 Million
March 17, 2022 2022 WIN2E01979 FY 2022 GAA RA 11639 January 20, 2022 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 300215100616000
Project ID: P00630154MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:

Construction of Road, Sitio Puyawon, Barangay Mahanub - Sitio Buya, Barangay Camam-onan, Gigaquit, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 5.004 Lane Km

Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,00
EAO: P 2,800,00

Unit Cost:
CW1: P 15,427,657.87/ Lane Km

TO:

Construction of Road, Sitio Puyawon, Sitio Buya, Barangay Camam-onan, Gigaquit, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 5.004 Lane Km

Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,00
EAO: P 2,800,00

Unit Cost:
CW1: P 15,427,657.87/ Lane Km
March 17, 2022 2022 WIN2E01978 FY 2022 GAA RA 11639 January 20, 2022 Region XIII Surigao del Norte 2nd District Engineering Office
UACS No. : 300215100617000
Project ID: P00630663MN

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities

FROM:

Construction of Road in Barangay Ferlda - Sitio Puyawon, Barangay Mahanub, Gigaquit, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 4.020 Lane Km

Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,00
EAO: P 2,800,00

Unit Cost:
CW1: P 19,203,024.73/ Lane Km

TO:

Construction of Road in Barangay Ferlda - Sitio Puyawon, Barangay Camam-onan, Gigaquit, Surigao del Norte

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 4.020 Lane Km

Allocation:
TOTAL: P 80,000,000
CW1: P 77,200,00
EAO: P 2,800,00

Unit Cost:
CW1: P 19,203,024.73/ Lane Km
December 27, 2021 2021 WIN1F06705 SR2021-11-014754 November 18, 2021 Region VIII Leyte 4th District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

AS PER GAA/ORIGINAL:

Rehabilitation/Reconstruction of Road with Slips, Slope Collapse, and Lanslide – Kananga – Tunongan Hot Spring Rd – K0996+000 – K0996+450

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 72.375 M
Structure: 0.00 square meters
EAO P 2.625 M

Total P 75.00 M

AS MODIFIED:

Rehabilitation/Reconstruction of Road with Slips, Slope Collapse, and Lanslide – Kananga – Tunongan Hot Spring Rd – K0996+304 – K0996+430; K0996+474 – K0996+777

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 72.375 M
Structure: 3, 065 square meters
EAO P 2.625 M

Total P 75.00 M
December 27, 2021 2021 WIN1F06649 SR2021-11-014756 November 18, 2021 Region VIII Leyte 4th District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads

AS PER GAA/ORIGINAL:

Rehabilitation/Reconstruction of Road with Slips, Slope Collapse, and Landslide – Kananga – Tungonan Hot Spring Rd – K0997+400 – K0997+800

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 72.375 M
Structure: 0.00 square meters
EAO P 2.625 M

Total P 75.00 M

AS MODIFIED:

Rehabilitation/Reconstruction of Road with Slips, Slope Collapse, and Landslide – Kananga – Tungonan Hot Spring Rd – K0997+040 – K0997+370; K0998+140 – K0998+222

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 72.375 M
Structure: 2,880 square meters
EAO P 2.625 M

Total P 75.00 M
December 27, 2021 2021 WIN1F06204 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Tertiary Roads

AS PER GAA/ORIGINAL:

Leyte-Samar Rd (via Guintigui-an) – K0899+048 – K0899+434, K0899+466 – K0899+555

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.62222 M
Asphalt Overlay: 1.891 Lane Km

EAO P 0.21678 M

Total P 10.839 M

AS MODIFIED:

Leyte-Samar Rd (via Guintigui-an) – K0899+048 – K0899+418, K0899+482 – K0899+547

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 10.62222 M
Asphalt Overlay: 1.740 Lane Km

EAO P 0.21678 M

Total P 10.839 M
December 27, 2021 2021 WIN1F06205 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
Convergence and Special Support Program

Convergence and Special Support - Construction/ Improvement of Access Roads leading to Airports

AS PER GAA/ORIGINAL:

Access Road from San Jose Road to the New Passenger Terminal Building, Daniel Z. Romualdez Airport, San Jose,Tacloban City

Physical Target: Allocation:

CW1-Construction of Concrete P 28.09366 M
Road: 2.668 Lane Km

EAO P 0.57334 M

Total P 28.667 M

AS MODIFIED:

(Kalsada Tungo sa Paliparan, Rules at Daungan Program – Katuparan) Access Road from San Jose Road to the New Passenger Terminal Building, Daniel Z. Romualdez Airport, San Jose, Tacloban City

Physical Target: Allocation:

CW1-Construction of Concrete P 28.09366 M
Road: 2.352 Lane Km

EAO P 0.57334 M

Total P 28.667 M
December 27, 2021 2021 WIN1F06183 GAA FY 2021 January 1, 2021 Region VIII Northern Samar 1st District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0687 + 964 - K0688 + 000

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 18.669 M
Structure: 3,883.891 square meters
EAO P 0.381 M

Total P 19.050 M

AS MODIFIED:

Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0688 + 000 - K0688 + 033

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 18.669 M
Structure: 1,156.46 square meters
EAO P 0.381 M

Total P 19.050 M
December 20, 2021 2021 WIN1C03407 GAA 2021 October 29, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Rehabilitation of Bucay North Road with Road Opening, San Miguel-Bancagan Section, Bucay, Abra;
Type of Work: Rehabilitation of Concrete Road;
Physical Target: CW1: 10.396 Lane Km;
Allocation= Php 100,000,000

To: Rehabilitation of Bucay North Road with Road Opening, San Miguel-Bancagan Section, Bucay, Abra;
Type of Work: CW1: Rehabilitation of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 1.542 Lane Km
CW2: 13,878 Square meters;
Allocation= Php 100,000,000


December 20, 2021 2021 WIN1C03402 GAA 2021 October 29, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Pakiling-Banglolao Flood Control, Barangay Pakiling, Bucay, Abra;
Type of Work: Construction of Flood Mitigation Structure;
Physical Target: CW1: 293.20 Lineal meters;
Allocation= Php 50,000,000

To: Construction of Pakiling-Banglolao Flood Control, Barangay Pakiling, Bucay, Abra;
Type of Work: Construction of Flood Mitigation Structure;
Physical Target: CW1: 241.60 Lineal meters;
Allocation= Php 50,000,000

December 20, 2021 2021 WINC03404 GAA 2021 October 29, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Soot Flood Control, Barangay Mudeng, La Paz, Abra;
Type of Work: Construction of Flood Mitigation Structure;
Physical Target: CW1: 445.594 Lineal meters;
Allocation= Php 50,000,000

To: Construction of Soot Flood Control, Barangay Mudeng, La Paz, Abra;
Type of Work: Construction of Flood Mitigation Structure;
Physical Target: CW1: 219.20 Lineal meters;
Allocation= Php 50,000,000

December 15, 2021 FY 2021 WIN1E01932 300117210088000 November 9, 2021 Region IX Zamboanga del Norte 1st District Engineering Office
UACS No. 300117210088000
Project ID : P00551097MN

Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program

Rehabilitation/Improvement of Sindangan Rotonda, Sindangan, Zamboanga del Norte

CW1 - Rehabilitation of Concrete Road : 0.982 lane km
Unit Cost : P 10,481,280.52 /lane km

CW2 - Construction of Drainage Structure: 235.190 ln. m.
Unit Cost : P 8,854.04 /ln.m

EAO : P 125,000.00
Allocation : P 12,500,000.00
December 14, 2021 FY2021 WIN1B01184 300117210006000 April 23, 2021 Region IX Regional Office IX
Local - Local Roads and Bridges - Local Roads - Local Infrastructure Program - Concreting of Road at Sitio Ratag, Barangay Baligtang, Pandami, Sulu

CW1: Construction of Concrete Road
Physical Target: 0.880 Lane Km.
Unit Cost: Php 11,250,000.00/lane km.
EAO: Php 100,000.00
Total Allocation: Php 10,000,000.00
December 2, 2021 2021 WIN1F06105 SARO-BMB-A-21-0010265 October 25, 2021 Region VIII Leyte 1st District Engineering Office
Local Program

Local - Buildings And Other Structures - Multipurpose / Facilities - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

AS PER GAA/ORIGINAL:

Construction of Covered Court-Regional Rehabilitation Center for Youth (RRCY) Brgy. Pawing, Palo, Leyte

Physical Target: Allocation:

CW1-Construction of Multi Purpose Building: P 9.800 M
1.00 Number of Building
EAO P 0.200 M

Total P 10.00 M

AS MODIFIED:

Construction of Covered Court-Regional Rehabilitation Center for Youth (RRCY) Brgy. Sto. Niño, Tanauan, Leyte

Physical Target: Allocation:

CW1-Construction of Multi Purpose Building: P 9.800 M
1.00 Number of Building
EAO P 0.200 M

Total P 10.00 M
December 2, 2021 2021 WIN1F06286 SARO-BMB-A-21-0010166 October 22, 2021 Region VIII Leyte 4th District Engineering Office
Local Program

Local – Flood Control and Drainage – Drainage/Protection Works – Local Infrastructure Program

AS PER GAA/ORIGINAL:

Construction of Albuera Seawall, Albuera, Leyte

Physical Target: Allocation:

CW1-Construction of Flood Mitigation P 49.00 M
Structure: 412.092 Lineal Meters
EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Construction of Albuera Seawall, Albuera, Leyte

Physical Target: Allocation:

CW1-Construction of Flood Mitigation P 49.00 M
Structure: 400.00 Lineal Meters
EAO P 1.00 M

Total P 50.00 M
December 2, 2021 2021 WIN1F06276 SR2021-09-012555 September 14, 2021 Region VIII Leyte 5th District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Preventive Maintenance - Secondary Roads

AS PER GAA/ORIGINAL:

Asphalt Overlay along National Road: Ormoc-Baybay Southern Leyte Boundary Road K1116+000 - K1117+000, K1118+000 - K1119+000, K1120+000 - K1120+857, K1121+000 - K1122+000

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 38.60 M
Asphalt Overlay: 0.00 Lane Km
EAO P 1.40 M

Total P 40.00 M

AS MODIFIED:

Asphalt Overlay along National Road: Ormoc-Baybay Southern Leyte Boundary Road K1117+985 - K1119+000, K1120+000 - K1120+857, K1120+866 – K1121+672

Physical Target: Allocation:

CW1-Preventive Maintenance of Road: P 38.60 M
Asphalt Overlay: 5.412 Lane Km
EAO P 1.40 M

Total P 40.00 M
December 2, 2021 2021 WIN1F06671 SARO-BMB-A-21-0010157 October 22, 2021 Region VIII Northern Samar 2nd District Engineering Office
Local Program

Flood Control and Drainage - Drainage / Protection Works - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

AS PER GAA/ORIGINAL:

Construction/Upgrading/Rehabilitation of Drainage along National Roads (Arteche – Jipapad – Las Navas – Rawis) at Barangay Gibuangan and Barangay Sagudsuron, Catubig, Northern Samar

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 32.340 M
: 0.00 Lineal Meters
EAO P 0.660 M

Total P 33.00 M

AS MODIFIED:

Construction/Upgrading/Rehabilitation of Drainage along National Roads (Arteche – Jipapad – Las Navas – Rawis) at Barangay Gibuangan and Barangay Sagudsuron, Catubig, Northern Samar

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 12.22309 M
: 625.00 Lineal Meters

CW2-Road Widening: 2.504 Lane Km P 20.11691 M

EAO P 0.660 M

Total P 33.00 M
December 2, 2021 2021 WIN1F06233 SARO-BMB-A-21-0008585 September 22, 2021 Region VIII Samar 1st District Engineering Office
Local Program

Local - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

AS PER GAA/ORIGINAL:

Concreting of Brgy. Talahid – Brgy. Rica Road, Costa, Almagro, Samar

Physical Target: Allocation:

CW1-Construction of Concrete Road P 49.00 M
: 6.478 Lane Km
EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Concreting of Brgy. Talahid – Brgy. Costa Rica Road, Almagro, Samar

Physical Target: Allocation:

CW1-Construction of Concrete Road P 49.00 M
: 6.478 Lane Km
EAO P 1.00 M

Total P 50.00 M
December 2, 2021 2021 WIN1F06109 SARO-BMB-A-21-0007316 August 24, 2021 Region VIII Southern Leyte District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Primary Roads

AS PER GAA/ORIGINAL:

Daang Maharlika (LT) - K1100 + 087 - K1100+177

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 49.00 M
Structure: 0.00 Square Meters
EAO P 1.00 M

Total P 50.00 M

AS MODIFIED:

Daang Maharlika (LT) - K1006 + 801 - K1006+901

Physical Target: Allocation:

CW1-Construction of Road Slope Protection P 49.00 M
Structure: 3000 Square Meters
EAO P 1.00 M

Total P 50.00 M
December 2, 2021 2021 WIN1E01921 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Butuan City District Engineering Office
UACS No. : 310207100128000
Project ID: P00501573MN

OO1 : Ensure Safe and Reliable National Road System - Network Development Program - Off-Carriageway Improvement - Primary Roads

FROM:

Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1233 + (-088) - K1234 + 124, K1235 + 335 - K1236 + 262

Type of Work:
CW1- Off-Carriageway Improvement: Shoulder Paving/Construction

Physical Target:
CW1- 10,501.920 Square meters

Allocation:
TOTAL: P 90,200,000
CW1: P 87,043,000
EAO: P 3,157,000

Unit Cost:
CW1: P 8,288.29/Square meters

TO:

Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1233 + (-088) - K1233 + 244, K1243 + 060 - K1243 + 083, K1243 + 200 – K1243 + 746, K1243 + 1002 – K1244 +257

Type of Work:
CW1- Off-Carriageway Improvement: Shoulder Paving/Construction
CW2- Construction of Drainage Structure along Road

Physical Target:
CW1- 9,669.340 Square meters
CW2- 481.00 Lineal meters

Allocation:
TOTAL: P 90,200,000
CW1: P 49,167,337.59
CW2: P 37,875,662.41
EAO: P 3,157,000

Unit Cost:
CW1: P 5,084.87/Square meters
CW2: P 78,743.58/Lineal meters
December 2, 2021 2021 WIN1F06674 SARO-BMB-A-21-0010271 October 25, 2021 Region VIII Tacloban City District Engineering Office
Local Program

Local - National Roads and Bridges - National Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

AS PER GAA/ORIGINAL:

Gov. Benjamin "Kokoy" Romualdez Diversion Road (S00253LT) Chainage 0-205, (S00255LT) K0908+946-K0909+030, (S00254LT) Chainage 0-55, Picas San Jose DZR Airport Road (S00257LT) K0910+-926-K0910+-857, (S00258LT) Chainage 0-094, Tacloban City

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 4.900 M
along Road: 117 Lineal Meters
EAO P 0.100 M

Total P 5.00 M

AS MODIFIED:

Gov. Benjamin "Kokoy" Romualdez Diversion Road (S00255LT) K0908+950-K0909+026 Tacloban Baybay South Road (S00244LT) K0913+977-K0914+017

Physical Target: Allocation:

CW1-Construction of Drainage Structure P 4.950 M
along Road: 117 Lineal Meters
EAO P 0.050 M

Total P 5.00 M
December 2, 2021 2021 WIN1F06163 SARO-BMB-A-21-0010294 October 25, 2021 Region VIII Tacloban City District Engineering Office
Local Program

Local - National Roads and Bridges - National Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

AS PER GAA/ORIGINAL:

Gov. Benjamin “Kokoy” Romualdez Diversion Road (S00255LT) K0908+825-K0908+755, Tacloban City

Physical Target: Allocation:

CW1-Asphalt Overlay: 0.800 Lane Km P 4.900 M

EAO P 0.100 M

Total P 5.00 M

AS MODIFIED:

Gov. Benjamin “Kokoy” Romualdez Diversion Road (S00255LT) K0908+265-K0908+472, Tacloban City

Physical Target: Allocation:

CW1-Asphalt Overlay: 0.800 Lane Km P 4.950 M

EAO P 0.050 M

Total P 5.00 M
December 2, 2021 2021 WIN1F06678 GAA FY 2021 January 1, 2021 Region VIII Tacloban City District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Tertiary Roads

AS PER GAA/ORIGINAL:

Leyte-Samar Rd (via Guintigui-an) – K0904 +467 – K0904 +603

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 4.900 M
Road: 272 Lineal Meters
EAO P 0.100 M

Total P 5.00 M

AS MODIFIED:

Leyte-Samar Rd (via Guintigui-an) – K0904 + 459 – K0904 + 663, K0904 + 513 – K0904 + 536

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 4.900 M
Road: 227 Lineal Meters
EAO P 0.100 M

Total P 5.00 M
December 2, 2021 2021 WIN1F06321 GAA FY 2021 January 4, 2021 Region VIII Leyte 5th District Engineering Office
OO1: Ensure Safe and Reliable National Road System

Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads

AS PER GAA/ORIGINAL:

Ormoc-Baybay-Southern Leyte Bdry Rd - K1059 + 400 - K1059 + 610

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 1.6464 M
Road: 210.00 Lineal Meters
EAO P 0.0336 M

Total P 1.68 M

AS MODIFIED:

Ormoc-Baybay-Southern Leyte Bdry Rd - K1059 + 817 - K1060 + 019

Physical Target: Allocation:

CW1-Construction of Drainage Structure along P 1.6464 M
Road: 150.00 Lineal Meters
EAO P 0.0336 M

Total P 1.68 M
December 1, 2021 2021 WIN1C03417 GAA 2021 October 27, 2021 Cordillera Administrative Region Mountain Province 1st District Engineering Office
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Road - K0414 + 770 - K0414 +800, K0440 + 1020 - K0440 + 1080, K0441 + 810 - K0441 + 855, K0444 + 314 - K0444 + 344, K0446 + 036 - K0446 + 046, K0446 + 190 - K0446 + 220, K0446 + 240 - K0446 + 260;
Physical Target: CW1: 0 Square meters;
Allocation= Php 27,000,000

To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Road - K0414 + 770 - K0414 +800, K0440 + 1020 - K0440 + 1080, K0441 + 810 - K0441 + 855, K0444 + 314 - K0444 + 344, K0446 + 036 - K0446 + 046, K0446 + 190 - K0446 + 220, K0446 + 240 - K0446 + 260;
Physical Target: CW1: 1,451 Square meters;
Allocation= Php 27,000,000

December 1, 2021 2021 WIN1C03419 GAA 2021 October 29, 2021 Cordillera Administrative Region Abra District Engineering Office
From: Construction of Pagala Flood Control, Bucay, Abra;
Physical Target: CW1: 720 Lineal meters;
Allocation= Php 100,000,000

To: Construction of Pagala Flood Control, Bucay, Abra;
Physical Target: CW1: 536 Lineal meters;
Allocation= Php 100,000,000

November 23, 2021 FY 2021 GAA WIN1E01904 FY 2021 GAA RA 11518 January 1, 2021 Region XI Davao City District Engineering Office
MODIFICATION:

FROM: Local Program - Flood Control and Drainage - Drainage Protection Works -Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Seawall at NHA Bangkal Relocation, Davao City
Physical Target:
CW1: 913.372 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Flood Mitigation Structure)
EAO: P 3,500,000.00

TO: Local Program - Flood Control and Drainage - Drainage Protection Works -Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of Seawall at NHA Bangkal Relocation, Davao City
Physical Target:
CW1: 240.000 lm (Construction of Flood Mitigation Structure)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Construction of Flood Mitigation Structure)
EAO: P 3,500,000.00
November 23, 2021 2021 WIN1E01922 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. : 320101106328000
Project ID: P00522129MN

OO2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems

FROM:

Construction of Revetment along Agusan River Basin, Esperanza Section, Agusan del Sur

Type of Work:
CW1- Construction of Revetment

Physical Target:
CW1- 947.425 Lineal meters

Allocation:
TOTAL: P 120,000,000
CW1: P 115,800,000
EAO: P 4,200,000

Unit Cost:
CW1: P 122,226.03/Lineal meters

TO:

Construction of Revetment along Agusan River Basin, Esperanza Section, Agusan del Sur

Type of Work:
CW1- Construction of Revetment

Physical Target:
CW1- 258.2 Lineal meters

Allocation:
TOTAL: P 120,000,000
CW1: P 115,034,755
EAO: P 4,172,245
Excess: P 793,000

Unit Cost:
CW1: P 445,525.77/Lineal meters
November 18, 2021 2021 WIN1E01915 FY 2021 GAA RA 11518 January 25, 2021 Region XIII Regional Office XIII
UACS No. : 300116203535000
Project ID: P00550699MN

Local Program - Local Roads and Bridges - Local Roads - Construction / Repair / Rehabilitation / Improvement of Various Infrastructure including Local Projects

FROM:

Construction of Circumferential Road along Agusan Marsh Road, Bunawan Section (Phase 4), Agusan del Sur

Type of Work:
CW1- Construction of Concrete Road

Physical Target:
CW1- 12.151 Lane Km

Allocation:
TOTAL: P 130,000,000
CW1: P 125,450,000
EAO: P 4,550,000

Unit Cost:
CW1: P 10,324,253.15/Lane Km

TO:

Construction of Circumferential Road along Agusan Marsh Road, Bunawan Section (Phase 4), Agusan del Sur

Type of Work:
CW1- Construction of Gravel Road

Physical Target:
CW1- 1.84 Lane Km

Allocation:
TOTAL: P 130,000,000
CW1: P 125,297,576.51
EAO: P 4,544,471.69
Excess: P 157,951.80

Unit Cost:
CW1: P 68,096,508.97/Lane Km