May 3, 2022 |
2022 |
WIN2F06301 |
SR2022-03-007639 |
March 23, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Abra-Kalinga Rd - K0456 + 100 - K0456 + 200;
Physical Target: 5,555.560 Square meters;
Allocation: Php 100,000,000.000
To: Abra-Kalinga Rd - K0456 + 100 - K0456 + 200;
Physical Target: 3,404.880 Square meters;
Allocation: Php 100,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06287 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Abra District Engineering Office |
From: Construction of Sinalang Flood Control, Barangays Namarabar & Riang, Peñarrubia, Abra;
Physical Target: 442.321 Lineal meters;
Allocation: Php 50,000,000.000
To: Construction of Sinalang Flood Control, Barangays Namarabar & Riang, Peñarrubia, Abra;
Physical Target: 404.000 Lineal meters;
Allocation: Php 50,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06348 |
SR2022-03-007578 |
March 23, 2022 |
Cordillera Administrative Region |
Apayao 2nd District Engineering Office |
From: Sub-Program: Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads;
Project Description: along Claveria - Calanasan Road KO663+275 - KO663+376;
Physical Target: 3,888.890 Square meters;
Allocation: Php 70,000,000.000
To: Sub-Program: Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads;
Project Desciption: Claveria-Calanasan-Kabugao Road - K0663+275 - K0663+376;
Physical Target: 3,599.500 Square meters;
Allocation: Php 70,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06318 |
SR2022-03-007580 |
March 23, 2022 |
Cordillera Administrative Region |
Apayao 2nd District Engineering Office |
From: Sub-Program: Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads;
Project Description: along Claveria - Calanasan Road KO662+423 - KO662+667;
Physical Target: 3,333.330 Square meters;
Allocation: Php 60,000,000.000
To: Sub-Program: Asset Preservation Program - Rehabilitation/ Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads;
Project Desciption: Claveria-Calanasan-Kabugao Road - K0662+423 - K0662+667;
Physical Target: 3,212.500 Square meters;
Allocation: Php 60,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06233 |
SARO-BMB-A-22-0002929 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
From: Tawang-Ambiong Rd - K0260+(-193), K0260+018, K0260+250, K0260+497, K0260+518, K0260+918, K0261+042, K0261+409, K0261+958, K0262+710, K0262+900, K0263+090, K0264+250, K0264+620;
Physical Target: 2,800.000 Lineal Meters;
Allocation: Php 20,000,000.000
To: Tawang-Ambiong Rd - K0260+(-193), K0260+018, K0260+250, K0260+497, K0260+518, K0260+918, K0261+042, K0261+409, K0261+958, K0262+900, K0263+090, K0264+170 - K0264+280, K0264+552;
Physical Target: 1,631.000 Lineal Meters;
Allocation: Php 20,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06339 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Baguio - Bontoc Rd - K0336 + 400 - K0339+200;
Physical Target: 5.584 Lane Km;
Allocation: Php 35,000,000.000
To: Baguio - Bontoc Rd - K0336 + 400 - K0339+285;
Physical Target: 5.754 Lane Km;
Allocation: Php 35,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06236 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Gov. Bado Dangwa National Rd - K0338+600 - K0338+731;
Type of Work: CW1: Preventive Maintenance of Road: Asphalt Overlay
CW2: Construction of Road Slope Protection Structure;
Physical Target: CW1: 0.131 Lane Km
CW2: 242 Square meters;
Allocation: Php 6,000,000.000
To: Gov. Bado Dangwa National Rd - K0343+498 - K0344+000;
Type of Work: Preventive Maintenance of Road: Asphalt Overlay;
Physical Target: 1.048 Lane Km;
Allocation: Php 6,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06238 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Baguio-Bontoc Rd - K0297+144 - K0297+163, K0298+902 - K0298+908, K0298+924 - K0298+952;
Physical Target: 272.000 Square meters;
Allocation: Php 2,700,000.000
To: Baguio-Bontoc Rd - K0297+144 - K0297+200, K0298+924 - K0298+952;
Physical Target: 325 Square meters;
Allocation: Php 2,700,000.000
|
May 3, 2022 |
2022 |
WIN2F06340 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Baguio-Bontoc Rd - K0313+625 - K0313+649, K0315+605 - K0315+710, K0315+900 - K0315+927, K0320+780 - K0320+815, K0322+285 - K0322+300, K0328+900 - K0328+915;
Physical Target: 2,755.000 Square meters;
Allocation: Php 16,000,000.000
To: Baguio-Bontoc Rd - K0313+589 - K0313+649, K0315+661 - K0315+710, K0315+900 - K0315+933, K0320+780 - K0320+830, K0322+270 - K0322+305, K0328+900 - K0328+921;
Physical Target: 1456 Square meters;
Allocation: Php 16,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06292 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Gov. Bado Dangwa National Rd - K0279+659 - K0279+674, K0280+275 - K0280+310, K0292+141 - K0292+156, K0292+466 - K0292+511, K0293+074 - K0293+109, K0299+454 - K0299+489, K0300+824 - K0300+859, K0304+027 - K0304+067;
Physical Target: 1,630.000 Square meters;
Allocation: Php 19,000,000.000
To: Gov. Bado Dangwa National Rd - K0299+454 - K0299+489, K0304+027 - K0304+067;
Physical Target: 789 Square meters;
Allocation: Php 19,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06234 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Cong. Andres Acop Cosalan Rd - K0354+580 - K0354+581, K0355+400 - K0355+401,K0362+230 - K0362+233;
Physical Target: 660.000 Lineal meters;
Allocation: Php 8,000,000.000
To: Cong. Andres Acop Cosalan Rd - K0355+400 - K0355+401,K0362+230 - K0362+233;
Physical Target: 475 Lineal meters;
Allocation: Php 8,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06251 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Baguio-Bontoc Rd - K0309+800 - K0313+000;
Type of Work: Rehabilitation / Major Repair of Drainage Structure along Road;
Physical Target: 3,960.000 Lineal meters;
Allocation: Php 40,000,000.000
To: Baguio-Bontoc Rd - K0309+088 - K0309+500, K0309+800 - K0311+350, K0312+040 - K0312+855, K0313+015 - K0313+780, K0314+180 - K0315+030, K0315+146 - K0315+958, K0316+292 - K0316+661 , K0317+560 - K0317+609;
Type of Work: Construction of Drainage Structure along Road;
Physical Target: 2828 Lineal meters;
Allocation: Php 40,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06237 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Cong. Andres Acop Cosalan Rd - K0364+000 - K0365+865;
Physical Target: 1,900.000 Square meters;
Allocation: Php 15,000,000.000
To: Cong. Andres Acop Cosalan Rd - K0365+000 - K0365+679;
Physical Target: 1697.500 Square meters;
Allocation: Php 15,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06249 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Construction of Multi-Purpose Building at Toludan Elementary School, Barangay Cattubo, Atok, Benguet;
Physical Target: 1.000 Number of Building;
Allocation: Php 7,000,000.000
To: Construction of Multi-Purpose Building at Rufino Alawas Elementary School, Barangay Cattubo, Atok, Benguet;
Physical Target: 1.000 Number of Building;
Allocation: Php 7,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06256 |
SARO-BMB-A-22-0002930 |
March 21, 2022 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
From: Construction of Lam-Ayan - Dengao - Dekkan - Balintag Road, Baculongan Sur, Buguias, Benguet;
Physical Target: 0.989 Lane Km;
Allocation: Php 10,000,000.000
To: Construction of Lam-Ayan - Dengao - Dekkan - Balintag Road, Baculongan Norte, Buguias, Benguet;
Physical Target: 0.989 Lane Km;
Allocation: Php 10,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06232 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
From: Balbalan-Pinukpuk Rd - K0517 + 274 - K0517 + 308, K0522 + 830 - K0522 + 862 ;
Physical Target: 650.000 Square meters;
Allocation: Php 9,500,000.000
To: Balbalan-Pinukpuk Rd - K0522 + 830 - K0522 + 866 ;
Physical Target: 559.800 Square meters;
Allocation: Php 9,500,000.000
|
May 3, 2022 |
2022 |
WIN2F06266 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
From: Kalinga-Cagayan Rd (Calanan-Enrile Section) - K0496 + 591 - K0496 + 668,K0515 + 233 - K0515 + 280 ;
Physical Target: 449.000 Square meters;
Allocation: Php 5,500,000.000
To: Kalinga-Cagayan Rd (Calanan-Enrile Section) - K0496 + 591 - K0496 + 668, K0502 + 752 - K0502 + 763, K0513 + 172 - K0513 + 211;
Physical Target: 597.000 Square meters;
Allocation: Php 5,500,000.000
|
May 3, 2022 |
2022 |
WIN2F06297 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
From: Tabuk-Banawe via Tanudan-Barlig Rd - K0512 + 461 - K0512 + 472, K0514 + 169 - K0514 + 207, K0518 + 645 - K0518 + 695, K0536 + 808 - K0536 + 833, K0542 + 621 - K0542 + 658;
Physical Target: 1,385.000 Square meters;
Allocation: Php 16,500,000.000
To: Tabuk-Banawe via Tanudan-Barlig Rd - K0512 + 333 - K0512 + 408, K0527 + 254 - K0527 + 274, K0532 + 637 - K0532 + 687, K0532 + 795 - K0532 + 840;
Physical Target: 1,220.000 Square meters;
Allocation: Php 16,500,000.000
|
May 3, 2022 |
2022 |
WIN2F06243 |
SR2022-02-001457 DTD |
February 4, 2022 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
From: Construction of Mega Dike Project along Chico River (Left Bank), Tabuk City, Kalinga ;
Physical Target: 866.617 Lineal meters;
Allocation: Php 60,000,000.000
To: Construction of Mega Dike Project along Chico River Sta. 92 + 230 - Sta. 92 + 830 (Right Bank), Tabuk City, Kalinga ;
Physical Target: 600.000 Lineal meters;
Allocation: Php 60,000,000.000
|
May 3, 2022 |
2022 |
WIN2F06269 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Mountain Province 1st District Engineering Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0395 + 935 - K0396 + 574;
Physical Target: 1.324 Lane Km;
Allocation: Php 22,255,000.000
To: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0396 + 223 - K0396 + 800;
Physical Target: 1.154 Lane Km;
Allocation: Php 22,255,000.000
|
May 3, 2022 |
2022 |
WIN2F06242 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Mountain Province 1st District Engineering Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - (S04030LZ) Chainage 1830 - Chainage 2265;
Physical Target: 0.435 Lane Km;
Allocation: Php 9,570,000.000
To: Jct-Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - (S04030LZ) Chainage 1340 - Chainage 1640;
Physical Target: 0.600 Lane Km;
Allocation: Php 9,570,000.000
|
May 3, 2022 |
2022 |
WIN2F06260 |
GAA 2022 |
January 2, 2022 |
Cordillera Administrative Region |
Mountain Province 1st District Engineering Office |
From: Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - (S04030LZ) Chainage 3015 - Chainage 4015;
Physical Target: 1.000 Lane Km;
Allocation: Php 22,000,000.000
To: Jct-Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - (S04030LZ) Chainage 3415 - Chainage 4015;
Physical Target: 1.200 Lane Km;
Allocation: Php 22,000,000.000
|
April 29, 2022 |
FY 2022 |
WIN2E02244 |
310201100901000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100901000
Project ID: P00602313MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Dipolog-Sindangan-Liloy Rd - K1900 + 583 - K1902 + 820, K1902 + 990.00 - K1903 + 736.00
CW1- Road Widening
Physical Target: 5.966 Lane Km
Unit Cost: ₱ 16,568,172.54/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 24,347.61 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 3,850,000.00
Total Allocation: ₱ 110,000,000.00
|
April 29, 2022 |
FY 2022 |
WIN2E02250 |
310201100910000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100910000
Project ID: P00602314MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Sindangan-Liloy Rd - K1935 + 000 - K1935 + 240, K1935 + 500 - K1937 + 611.90, K1938 + 393.00 - K1938 + 895.65, K1942+500.00 - K1942+860.00
CW1- Road Widening
Physical Target: 6.429 Lane Km
Unit Cost: ₱ 15,411,171.91/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 7,372.786 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 3,673,740.00
Total Allocation: ₱ 104,964,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02246 |
310211100086000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310211100086000
Project ID: P00602318MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Secondary Roads
Liloy-Siocon Rd - K2034 + 005.00 - K2034 + 779.68, K2035 + 218.50 - K2037 + 020.00
CW1- Paving of Unpaved Roads
Physical Target: 5.152 Lane Km
Unit Cost: ₱ 19,054,013.63/Lane Km
EAO: ₱ 3,570,000.00
Excess: ₱ 263,721.76
Total Allocation: ₱ 102,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02182 |
310201100898000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100898000
Project ID: P00602320MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Dipolog-Punta-Dansullan-S Osmeña-Zamboanga del Norte/Sur Bdry Rd - K1879 + 000 - K1882 + 000
CW1- Road Widening
Physical Target: 6.000 Lane Km
Unit Cost: ₱ 13,866,245.97/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 60,425.08 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 3,675,000.00
Total Allocation: ₱ 105,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02202 |
310202101024000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310202101024000
Project ID: P00602322MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd - K1864 + 000 - K1866 + 800
CW1- Road Widening
Physical Target: 5.600 Lane Km
Unit Cost: ₱ 16,297,413.70/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 33,333.333 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 3,675,000.00
Excess: ₱ 59,483.26
Total Allocation: ₱ 105,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02176 |
310201100905000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100905000
Project ID: P00602324MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City-Zamboanga City Rd - K1710 + 100.00 - K1712 + 960.00
CW1- Road Widening
Physical Target: 5.72 Lane Km
Unit Cost: ₱ 15,450,405.45/Lane Km
ROW- Right-Of-Way Acquisition
Physical Target: 33,333.333 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 3,570,000.00
Excess: ₱ 53,680.84
Total Allocation: ₱ 102,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02213 |
310212100201000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310212100201000
Project ID: P00602331MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Paving of Unpaved Roads - Tertiary Roads
Zamboanga del Sur Coastal Rd - (S01186MN) Chainage 10653.00 - Chainage 13640.00
CW1- Paving of Unpaved Roads
Physical Target: 5.97 Lane Km
Unit Cost: ₱ 15,393,634.84/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.67 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,570,000.00
Excess: ₱ 1,530,000.00
Total Allocation: ₱ 102,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02218 |
310201100903000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100903000
Project ID: P00602333MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1789 + 738 - K1790 + 500.00, K1790 + 720.00 - K1791 + 864.00, K1793 + 100.00 - K1793 + 870.00, K1794 + 215.00 - K1795 + 240.00, K1795 + 500.00 - K1795 + 800.00
CW1- Road Widening
Physical Target: 8.00 Lane Km
Unit Cost: ₱ 11,468,101.76/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 21,666.667 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,570,000.00
Excess: ₱ 185,185.96
Total Allocation: ₱ 102,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02238 |
310205100731000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310205100731000
Project ID: P00603740MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Missing Links/ New Roads
Sindangan - Bayog - Lakewood Road, Package 1, Zamboanga Del Norte
CW1- Construction of Concrete Road
Physical Target: 2.34 Lane Km
Unit Cost: ₱ 27,500,000.00/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 16,666.667 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,555,000.00
Excess: ₱ 1,095,000.00
Total Allocation: ₱ 73,000,000.00
|
April 29, 2022 |
FY 2022 |
WIN2E02222 |
310204101595000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310204101595000
Project ID: P00604237MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
Zamboanga City By-pass Road, (Widening of San Ramon Bridge including approaches), Zamboanga City
CW1- Widening of Bridge
Physical Target: 437.886 sq.m.
Unit Cost: ₱ 219,006.77/sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 3,333.333 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,570,000.00
Excess: ₱ 1,530,000.00
Total Allocation: ₱ 102,000,000.00
|
April 29, 2022 |
FY 2022 |
WIN2E02224 |
320101107686000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107686000
Project ID: P00620010MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Bogayo River, Kumalarang Br. 1 Section (B00549MN) (Downstream Rightside) along Pagadian City - Zamboanga City Road (S01453MN), Brgy. Bogayo, Kumalarang, Zamboanga del Sur
CW1- Construction of Flood Mitigation Structure
Physical Target: 448.00 Lineal Meters
Unit Cost: ₱ 216,294.65/Lineal Meters
EAO: ₱ 3,570,000.00
Excess: ₱ 1,530,000.00
Total Allocation: ₱ 102,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02249 |
320101107689000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107689000
Project ID: P00620013MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Rebokon River, Rebokon Bridge Section along Zamboanga del Sur Coastal National Road (S01101MN), Brgy. Rebokon, Dumalinao, Zamboanga del Sur
CW1- Construction of Flood Mitigation Structure
Physical Target: 267.50 Lineal Meters
Unit Cost: ₱ 254,828.54/Lineal Meters
EAO: ₱ 2,472,365.00
Total Allocation: ₱ 70,639,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02207 |
320101107693000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101107693000
Project ID: P00620017MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction of Flood Control Structure at Tukuran River, Militar Br. Section (B00470MN) (Upstream - Right Side), along Jct. Tukuran - Jct. Karomatan Road (S01103MN), Zamboanga del Sur
CW1- Construction of Flood Mitigation Structure
Physical Target: 610.00 Lineal Meters
Unit Cost: ₱ 163,524.59/Lineal Meters
EAO: ₱ 3,675,000.00
Excess: ₱ 1,575,000.00
Total Allocation: ₱ 105,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02225 |
320101106250000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 320101106250000
Project ID: P00620022MN
OO2: Protect Lives and Properties - Flood Management - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
Construction/Extension of Flood Control Structure along Siocon River (Upstream), Siocon, Zamboanga del Norte
CW1- Construction of Flood Mitigation Structure
Physical Target: 470.00 Lineal Meters
Unit Cost: ₱ 204,058.70/Lineal Meters
ROW- Right-Of-Way Acquisition
Physical Target: 141.368 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,535,000.00
Excess: ₱ 1,515,000.00
Total Allocation: ₱ 101,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02192 |
310108100968000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310108100968000
Project ID No.: P00601378MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Zamboanga City - Labuan - Limpapa Rd - K1973 + 218.74 - K1973 + 282.45, K1973 + 940 - K1974 + 030, K1974 + 535 - K1974 + 580.53, K1974 + 740 - K1974 + 784.13
CW1- Construction of Road Slope Protection Structure
Physical Target: 2,236.76 sq.m.
Unit Cost: ₱ 23,519.66479/Sq.m.
EAO: ₱ 2,100,000.00
Excess: ₱ 5,292,154.59
Total Allocation: ₱ 60,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02242 |
310204101786000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310204101786000
Project ID: P00604480MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Lapakan - Lamisahan - Victoria By-Pass Road Package 2, Zamboanga City
CW1- Construction of Concrete Road
Physical Target: 2 Lane km
Unit Cost: ₱ 20,895,198.33/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 5,000 sq.m.
Unit Cost: ₱ 1,440.00/sq.m.
EAO: ₱ 1,000,000.00
Excess: ₱ 9,603.36
Total Allocation: ₱ 50,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02211 |
310204101787000 |
March 23, 2022 |
Region IX |
Zamboanga City 2nd District Engineering Office |
UACS No. 310204101787000
Project ID: P00604481MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Construction of Bypass and Diversion Roads
NRJ Lapakan - Lamisahan - Victoria By-Pass Road Package 3, Zamboanga City
CW1- Construction of Concrete Road
Physical Target: 2 Lane km
Unit Cost: ₱ 20,137,042.27/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 6,055 sq.m.
Unit Cost: ₱ 1,440.00/sq.m.
EAO: ₱ 1,000,000.00
Excess: ₱ 5,915.45
Total Allocation: ₱ 50,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02195 |
310110100330000 |
March 21, 2022 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 310110100330000
Project ID: P00601320MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
Dipolog - Oroquieta National Rd - K1831 + 440 - K1831 + 967.7
CW1 - Construction of Drainage Structure along Road: 519.56 l.m.
Unit Cost: P 13,664.21/l.m.
ROW: 1,714.55 sq.m.
Unit Cost: P 1,608.95/sq.m
EAO: P 141,987.57
Allocation: P 10,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02107 |
310110100331000 |
March 21, 2022 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 310110100331000
Project ID: P00601321MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
Dipolog - Oroquieta National Rd - K1834 + 190.09 - K1834 + 807.72
CW1 - Construction of Drainage Structure along Road: 883.17 l.m.
Unit Cost: P 11,509.88/l.m.
ROW: 1,478.40 sq.m.
Unit Cost: P 1,748.00/sq.m
EAO: P 203,303.61
Allocation: P 12,953,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02051 |
310109100907000 |
March 21, 2022 |
Region IX |
Zamboanga del Norte 1st District Engineering Office |
UACS No. 310109100907000
Project ID: P00601382MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Sindangan - Bayog - Lakewood Rd (S01059MN)
Chainage 10542.2 - Chainage 10650,
Chainage 11244.8 - Chainage 11347
CW1- Construction of Slope Protection Structure
Physical Target: 11,483.13 sq.m.
Unit Cost: ₱ 5,126.22/Sq.m.
EAO: ₱ 2,135,000.00
Total Allocation: ₱ 61,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02200 |
310203100523000 |
March 30, 2022 |
Region IX |
Zamboanga del Sur 2nd District Engineering Office |
UACS No. 310203100523000
Project ID: P00602301MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Tertiary Roads
Sindangan - Bayog - Lakewood Rd - K1734 + 422 - K1735 + 000, K1735 + 362 - K1736 + 000, K1736 + 559 - K1737 + 288
CW1- Road Widening
Physical Target: 3.89 Lane Km
Unit Cost: ₱ 15,075,334.19/Lane km
EAO: ₱ 2,126,950.00
Total Allocation: ₱ 60,770,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02251 |
300217100042000 |
March 22, 2022 |
Region IX |
Zamboanga Sibugay 1st District Engineering Office |
UACS No. 300217100042000
Project ID: P00633884MN
CSSP: Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
Preventive Maintenance along Imelda-Bayog-Kumalarang-Margosatubig Rd. K1751 + (-602) - K1752 + 430.5
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 4.065 lane-km
Unit Cost : P 16,617,466.17/lane-km
EAO : P 2,450,000.00
Allocation : P 70,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02187 |
310106100824000 |
March 23, 2022 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 310106100824000
Project ID: P00601164MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
Crossing Sta. Clara - Sandayong Rd - K1796 + 050 - K1796 + 098
CW1 : Reconstruction to Concrete Pavement
Physical Target: 0.096 lane-km
Unit Cost : P 20,416,666.67/lane-km
EAO : P 40,000.00
Allocation : P 2,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02228 |
310201101020000 |
March 23, 2022 |
Region IX |
Zamboanga Sibugay 2nd District Engineering Office |
UACS No. 310201101020000
Project ID: P00602337MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Lanao-Pagadian-Zamboanga City Rd - K1791 + 864 - K1792 + 520
CW1- Road Widening
Physical Target: 1.306 Lane Km
Unit Cost: ₱ 16,406,814.70/Lane km
ROW: 3,333.33 sq.m.
Unit Cost: P 300.00/sq.m
EAO: ₱ 457,700.00
Total Allocation: ₱ 22,885,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02259 |
310101100577000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310101100577000
Project ID : P00601153MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Dipolog-Punta-Dansullan-S Osmeña-Zamboanga del Norte/Sur Bdry Rd - K1857+(-1123) - K1857+251, K1858+000 - K1858+895, K1859+000 - K1861+645
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 9.796 Lane km
Unit Cost : P 8,373,315.64/Lane km
EAO : P 2,975,000.00
Allocation : P 85,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02208 |
310104100358000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310104100358000
Project ID: P00601157MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Primary Roads
Dipolog-Oroquieta National Rd - K1818+535 - K1818+672, K1819+000 - K1819+330, K1819+345 - K1820+144, K1823+000 - K1824+000, K1826+485 - K1826+531, K1826+592 - K1826+695, K1826+1000 - K1827+064, K1828+000 - K1828+967.50
CW1 : Reconstruction to Concrete Pavement
Physical Target: 6.943 Lane km
Unit Cost : P 7,505,401.12/Lane km
EAO : P 1,890,000.00
Allocation : P 54,000,000.00
|
April 29, 2022 |
FY 2022 |
WIN2E02171 |
310105100638000 |
March 23, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310105100638000
Project ID: P00601158MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd - K1799+030 - K1799+633, K1819+766 - K1820+009, K1846+270- K1846+390, K1849+540 - K1849+601, K1859+430 - K1860+254
CW1 : Reconstruction to Concrete Pavement
Physical Target: 3.702 Lane km
Unit Cost : P 20,246,484.33/Lane km
ROW - Right-of-Way Acquisition
Physical Target: P 1,710 sq.m.
Unit Cost: P 1,500.00/sq.m.
EAO : P 2,811,515.00
Allocation : P 80,329,000.00 |
April 29, 2022 |
FY 2022 |
WIN2G02886 |
310106100822000 |
March 23, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310106100822000
Project ID: P00601159MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
Piñan-Mutia Rd - K1816+(-878.50) - K1816+(-816), K1818+000 - K1818+100, K1823+194.60 - K1823+541, (S01035MN) Chainage 0 - Chainage 548
CW1 : Reconstruction to Concrete Pavement
Physical Target: 2.1138 Lane km
Unit Cost : P 10,513,047.59/Lane km
EAO : P 453,520.00
Allocation : P 22,676,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02175 |
310108100966000 |
March 23, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310108100966000
Project ID No.: P00601388MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Jct Pulauan Port Rd - K1827+588 - K1827+782.60
CW1- Construction of Road Slope Protection Structure
Physical Target: 4,574.65 sq.m.
Unit Cost: ₱ 16,525.85/Sq.m.
ROW - Right-of-Way Acquisition
Physical Target: P 1,066.66 sq.m.
Unit Cost: P 1,500.01/sq.m.
EAO: ₱ 2,800,000.00
Total Allocation: ₱ 80,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02179 |
310108101228000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310108101228000
Project ID No.: P00601389MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd - K1828+840 - K1829+028, K1829+136 - K1829+145.40, K1836+825 - K1836+960, K1859+225 - K1859+425
CW1- Construction of Road Slope Protection Structure
Physical Target: 8,039.81 sq.m.
Unit Cost: ₱ 3,656.80/Sq.m.
EAO: ₱ 600,000.00
Total Allocation: ₱ 30,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02191 |
310101100742000 |
March 23, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310101100742000
Project ID : P00604478MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Primary Roads
Dipolog-Punta-Dansullan-S Osmeña-Zamboanga del Norte/Sur Bdry Rd - K1861+645 - K1862+631.50, K1862+810.60 - K1863+000, K1866+698 - K1867+917.80
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 4.6194 Lane km
Unit Cost : P 8,485,950.56/Lane km
EAO : P 800,000.00
Allocation : P 40,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02177 |
310102101056000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 310102101056000
Project ID : P00604479MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd - K1860+254 - K1862+427, K1868+369.80 - K1868+833
CW1 - Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 5.2724 Lane km
Unit Cost : P 7,434,944.24/Lane km
EAO : P 800,000.00
Allocation : P 40,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02174 |
300225100636000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 300225100636000
Project ID : P00631083MN
CSSP: Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Flood Mitigation Structure, Sinaad-San Francisco, Sergio Osmeña, Zamboanga del Norte
CW1 - Construction of Flood Mitigation Structure
Physical Target: 10.070 Lineal meters
Unit Cost : P 491,559.09/Lineal meters
EAO : P 50,000.00
Allocation : P 5,000,000.00 |
April 29, 2022 |
FY 2022 |
WIN2E02048 |
300225100638000 |
March 31, 2022 |
Region IX |
Zamboanga del Norte 3rd District Engineering Office |
UACS No. 300225100638000
Project ID : P00634997MN
CSSP: Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
Construction of Box Culvert Bridge, San Pedro, Dapitan City, Zamboanga Del Norte
CW1 - Construction of Flood Mitigation Structure
Physical Target: 12.10 Lineal meters
Unit Cost : P 409,090.91/Lineal meters
EAO : P 50,000.00
Allocation : P 5,000,000.00 |
April 28, 2022 |
FY 2022 GAA |
WIN2G02926 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 310108100883000
Project ID : P00611359LZ
001 : Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
FROM :
PPSR Jct - Napsan - Apurawan Road
K0038+578 - K0038+659
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,864.06 square meter
Allocation - Php 51.553 Million
TO ;
PPSr Jct - Napsan - Apurawan Road
K0038+578 - K0038+656
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,122.50 square meter
Allocation - Php 51.553 Million |
April 28, 2022 |
2022 |
WIN2E02276 |
FY 2022 GAA RA 11639 |
January 22, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310101100596000
Project ID: P00604687MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Preventive Maintenance - Primary Roads
FROM:
Butuan City-Malaybalay Rd - K1241 + 500 - K1247 + 900
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 16.371 Lane Km
Allocation:
TOTAL: P 130,000,000
CW1: P 125,450,000
EAO: P 4,550,000
Unit Cost:
CW1: P 7,662,940.566/Lane Km
TO:
Butuan City-Malaybalay Rd - K1241+500 - K1247+775
Type of Work:
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 16.887 Lane Km
Allocation:
TOTAL: P 130,000,000
CW1: P 125,450,000
EAO: P 4,550,000
Unit Cost:
CW1: P 7,428,791.378/Lane Km
|
April 28, 2022 |
2022 |
WIN2E02274 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XII |
Regional Office XII |
UACS No. : 310110100273000
Project ID: P00601369MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Asset Preservation Program - Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads
FROM:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1246 + 000 - K1247 + 219
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 1,200 Lineal meters
Allocation:
TOTAL: P 108,536,000
CW1: P 104,737,240
EAO: P 3,798,760
Unit Cost:
CW1: P 87,281.03/ Lineal meters
TO:
Butuan City-Cagayan de Oro City-Iligan City Road (Agusan-Misamis Or Rd) - K1246 + 362 - K1246 + 633
Type of Work:
CW1- Construction of Drainage Structure along Road
Physical Target:
CW1- 853 Lineal meters
Allocation:
TOTAL: P 108,536,000
CW1: P 104,737,240
EAO: P 3,798,760
Unit Cost:
CW1: P 122,786.92/ Lineal meters
|
April 28, 2022 |
2022 |
WIN2E02234 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 300214100094000
Project ID: P00633705MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239
FROM:
Preventive Maintenance along Daang Maharlika (Agusan-Davao Sect) - K1278 + 862 - K1280 + 777, K1280 + 883 - K1281 + 565, K1287 + 910 - K1288 + 964, K1290 + 846 - K1294 + 035, K1294 + 245 - K1295 + 633, K1297 + 125 - K1297 + 959, K1302 + 858 - K1303 + 600
Type of Work:
CW1- Preventive Maintenance of Road: Concrete Reblocking
Physical Target:
CW1- 6.010 Lane Km
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 17,662,229.62/ Lane Km
TO:
Preventive Maintenance along Daang Maharlika (Agusan-Davao Sect) - K1278+862.00 - K1280+777.00, K1280+883.00 - K1281+565.00, K1287+910.00 -K1288+964.00, K1290+846.00 - K1291+666.00
Type of Work:
CW1- Preventive Maintenance of Road: Concrete Reblocking
Physical Target:
CW1- 14.366 Lane Km
Allocation:
TOTAL: P 110,000,000
CW1: P 106,150,000
EAO: P 3,850,000
Unit Cost:
CW1: P 7,388,973.97/ Lane Km |
April 28, 2022 |
2022 |
WIN2E02217 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Regional Office XIII |
UACS No. : 310205100954000
Project ID: P00603827MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Construction of Missing Links/ New Roads
FROM:
East-West lateral road connecting Agusan Del Sur to Bukidnon, San Miguel Proper (Surigao del Sur) - Calaitan (Bayugan), Package 11, Surigao del Sur
Type of Work:
CW1- Construction of Gravel Road
Physical Target:
CW1- 1.218 Lane Km
Allocation:
TOTAL: P 67,000,000
CW1: P 64,655,000
EAO: P 2,345,000
Unit Cost:
CW1: P 53,082,922.82/ Lane Km
TO:
East-West lateral road connecting Agusan Del Sur to Bukidnon, San Miguel Proper (Surigao del Sur) - Calaitan (Bayugan), Package 11, Surigao del Sur
Type of Work:
CW1- Construction of Gravel Road
Physical Target:
CW1- 0.840 Lane Km
Allocation:
TOTAL: P 67,000,000
CW1: P 64,655,000
EAO: P 2,345,000
Unit Cost:
CW1: P 76,970,238.1/ Lane Km |
April 28, 2022 |
FY 2022 GAA |
WIN2G02883 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300219100141000
Project ID : P00630954LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
- Flood Mitigation Structures protecting Public
Infrastructures/Facilities
FROM :
Construction of cagancan River Control, barangay Don Pedro,
Mansalay, Oriental mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure:
1,247.95 lineal meter
Allocation - Php 150.00 Million
TO :
Construction of Cagancan River Control, barangay Don Pedro,
Mansalay, Oriental Mindoro
Physical Target - CW1 - Construction of Flood Mitigation Structure:
1,467.00 lineal meter
Allocation - Php 150.00 Million
|
April 28, 2022 |
FY 2022 GAA |
WIN2G02912 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300203101637000
Project ID : P00635432LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Construction/Improvement of Access Roads leading to
Declared Tourism Destinations
(Tourism Road Infrastructure Program - TRIP)
FROM :
San Jose - Port Barton Road leading to Various resorts in
Port Barton, San Vicente, Palawan
Physical Target - CW1 - Construction of Concrete Road :
6.662 lane km
Allocation - Php 9.930 Million
TO :
San Jose - Port Barton Road leading to various resorts in
Port Barton, San Vicente, Palawan
Physical Target - CW1 - Construction of Concrete Road ;
0.717 lane km
Allocation - Php 9.930 Million
|
April 28, 2022 |
FY 2022 GAA |
WIN2G02900 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100242000
Project ID : P00636844LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating GAPS (SIPAG)
- Access Roads and/or Bridges from the national Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and landslide along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 14+973.00 to Sta. 15+167.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,547.14 square meter
Allocation - Php 113.665 MIllion
TO :
Rehabilitation of Road with Slips, Slope Collapse, and landslide along TDC - Pagdanan Road, San Vicente, Palawan
Sta. 14+973.00 to Sta. 15+167.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 4,888.49 square meter
Allocation - Php 113.665 Million
|
April 28, 2022 |
2022 |
WIN2E02281 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Butuan City District Engineering Office |
UACS No. : 310201101058000
Project ID: P00602515MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1232 + 791 - K1232 + 851, K1240 + 305 - K1240 + 474
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 0.398 Lane Km
Allocation:
TOTAL: P 20,000,000
CW1: P 19,600,000
EAO: P 400,000
Unit Cost:
CW1: P 49,246,231.16/ Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1232 + 860 - K1233 + 128, K1240 + 694 - K1240 + 863
Type of Work:
CW1- Road Widening
Physical Target:
CW1- 1.022 Lane Km
Allocation:
TOTAL: P 20,000,000
CW1: P 19,600,000
EAO: P 400,000
Unit Cost:
CW1: P 19,178,082.19/ Lane Km |
April 28, 2022 |
FY 2022 GAA |
WIN2G02898 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100245000
Project ID : P00636847LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
- Access Roads and/or Bridges from the National Road/s leading
to Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide,
Port Barton - Kemdeng Road,
Sta. 0+052.00 - Sta. 0+300.00
San Vicente, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 3,256.118 square meter
Allocation - Php 145.303 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse and, Landslide,
Port Barton - Kemdeng Road,
Sta. 0+000.00 - Sta 0+218.00
San Vicente, Palawan
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 5,845.99 square meter
Allocation - Php 145.303 Million |
April 28, 2022 |
FY 2022 GAA |
WIN2G02927 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300215100247000
Project ID : P00636849LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG)
- Access Roads and/or Bridges from the National Road/s leading to
Major/Strategic Public Buildings/Facilities
FROM :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide,
Port Barton - Kemdeng Road,
San Vicente, Palawan
Sta. 0+767.00 - Sta. 0+887.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 1,342.13 square meter
Allocation - Php 59.892 Million
TO :
Rehabilitation of Road with Slips, Slope Collapse, and Landslide,
Port barton - kemdeng Road,
San Vicente, Palawan
Sta. 0+485.00 - Sta. 0+573.00
Physical Target - CW1 - Construction of Road Slope Protection
Structure : 2,434.80 square meter
Allocation - Php 59.892 Million
. |
April 28, 2022 |
FY 2022 GAA |
WIn2G02815 |
DPWH Infra Program FY 2022 |
December 30, 2021 |
Region IV-B |
Regional Office IV-B |
UACS No. : 300219100143000
Project ID : P00639384LZ
CONVERGENCE AND SPECIAL SUPPORT PROGRAM
Sustainable Infrastructure Program Alleviating Gaps(SIPAG)
- Flood mitigation Structures protecting Public
Infrastructure/Facilities
FFROM :
Construction of River Control Structure and Drainage System,
Cambajao River Control, Sibuyan Island, Romblon (Phase 2)
Physical Target - CW1 - Construction of Flood Mitigation Structure:
915.165 lineal meter
Allocation - Php 110.00 million
TO :
Construction of River Control Structure and Drainage System,
Cambajao River Control, Sibuyan island, Romblon (Phase 2)
Physical Target - CW1 - Construction of Flood Mitigation Structure:
560.050 lineal meter
Allocation - Php 110.00 Million |
April 28, 2022 |
2022 |
WIN2C03492 |
GAA FY 2022 |
January 1, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Tertiary Roads
AS PER GAA/ORIGINAL:
Rawis-Catubig Rd-K0798+000 - K0799+230, K0801+877 - K0802+855
Physical Target: Allocation:
CW1-Road Widening: 4.398 Lane Km P 39.20 M
EAO P 0.80 M
Total P 40.00 M
AS MODIFIED:
Rawis-Catubig Rd-K0798+020 - K0799+214.50, K0801+877 - K0802+848
Physical Target: Allocation:
CW1-Road Widening: 4.313 Lane Km P 39.20 M
EAO P 0.80 M
Total P 40.00 M |
April 28, 2022 |
2022 |
WIN2C03505 |
SR2022-03-008081 |
March 23, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Sn Policarpo-Arteche-Lapinig Rd, K0861+500 - K0861+550, K0861+800 - K0861+920
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.4928 M
Structure: 5,440 Square meters
EAO P 3.4272 M
Total P 97.92 M
AS MODIFIED:
Sn Policarpo-Arteche-Lapinig Rd, K0861+212 - K0862+060
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 94.4928 M
Structure: 6,176 Square meters
EAO P 3.4272 M
Total P 97.92 M
|
April 28, 2022 |
2022 |
WIN2C03493 |
SR2022-03-008092 |
March 23, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Sn Policarpo-Arteche-Lapinig Rd- K0862+550 - K0862+722
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.67448 M
Structure: 5,392.89 Square meters
EAO P 3.39752 M
Total P 97.072 M
AS MODIFIED:
Sn Policarpo-Arteche-Lapinig Rd-K0862+747 - K0863+085
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.67448 M
Structure: 5,967 Square meters
EAO P 3.39752 M
Total P 97.072 M
|
April 28, 2022 |
2022 |
WIN2C03515 |
SR2022-03-007863 |
March 23, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0814+661 - K0814+808
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 51.145 M
Structure: 2,944.44 Square meters
EAO P 1.855 M
Total P 53.00 M
AS MODIFIED:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0812+460 - K0812+533, K0813+320 - K0813+458, K0814+661 - K0814+808
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 51.145 M
Structure: 3,330 Square meters
EAO P 1.855 M
Total P 53.00 M
|
April 28, 2022 |
2022 |
WIN2C03483 |
SR2022-03-007872 |
March 23, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Rawis-Catubig Rd-K0805+450 - K0805+600
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.725625 M
Structure: 5,395.83 Square meters
EAO P 3.399375 M
Total P 97.125 M
AS MODIFIED:
Rawis-Catubig Rd-K0789+762.60 - K0791+000, K0793+950 - K0794+396
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 93.725625 M
Structure: 5,620.30 Square meters
EAO P 3.399375 M
Total P 97.125 M |
April 28, 2022 |
2022 |
WIN2C03490 |
SARO-BMB-A-22-0003144 |
March 21, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0820+700 - K0820+750
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 29.792 M
Structure: 1,688.89 Square meters
EAO P 0.608 M
Total P 30.40 M
AS MODIFIED:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0820+572 - K0820+756
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 29.792 M
Structure: 3,120 Square meters
EAO P 0.608 M
Total P 30.40 M
|
April 28, 2022 |
2022 |
WIN2C03491 |
SARO-BMB-A-22-0003144 |
March 21, 2022 |
Region VIII |
Northern Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
AS PER GAA/ORIGINAL:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0831+423 - K0831+640
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 44.10 M
Structure: 2,500 Square meters
EAO P 0.90 M
Total P 45.00 M
AS MODIFIED:
Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd-K0831+440 - K0831+640
Physical Target: Allocation:
CW1-Construction of Road Slope Protection P 44.10 M
Structure: 2,500 Square meters
EAO P 0.90 M
Total P 45.00 M
|
April 28, 2022 |
2022 |
WIN2E02150 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300219101256000
Project ID: P00630654MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
FROM:
Construction of River Control Structure at Daniog River, Barangay Gamuton, Lanuza, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 236.515 Lineal meters
Allocation:
TOTAL: P 30,000,000
CW1: P 29,400,000
EAO: P 600,000
Unit Cost:
CW1: P 124,305.01/Lineal meters
TO:
Construction of River Control Structure at Daniog River, Barangay Gamuton, Lanuza, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 415.600 Lineal meters
Allocation:
TOTAL: P 30,000,000
CW1: P 29,400,000
EAO: P 600,000
Unit Cost:
CW1: P 70,741.10/Lineal meters |
April 28, 2022 |
2022 |
WIN2E02164 |
FY 2022 GAA RA 11639 |
January 20, 2022 |
Region XIII |
Surigao del Sur 1st District Engineering Office |
UACS No. : 300225100707000
Project ID: P00634154MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - Flood Mitigation Structures protecting Public Infrastructures/Facilities
FROM:
Construction of Flood Control and Drainage System at Barangay Rosario, Tandag City, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 118.258 Lineal meters
Allocation:
TOTAL: P 15,000,000
CW1: P 14,850,000
EAO: P 150,000
Unit Cost:
CW1: P 125,572.90/Lineal meters
TO:
Construction of Flood Control and Drainage System at Barangay Rosario, Tandag City, Surigao del Sur
Type of Work:
CW1- Construction of Flood Mitigation Structure
Physical Target:
CW1- 931.00 Lineal meters
Allocation:
TOTAL: P 15,000,000
CW1: P 14,850,000
EAO: P 150,000
Unit Cost:
CW1: P 15,950.59/Lineal meters |
April 28, 2022 |
FY 2022 |
WIN2E02219 |
310102100846000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310102100846000
Project ID: P00601155MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Rizal-Dakak-Dapitan Coastal Loop Rd - K1805 + 000 - K1807 + 000, K1808 + 000 - K1811 + 000, K1813 + 000 - K1814 + 000.00
CW1- Preventive Maintenance of Road: Asphalt Overlay
Physical Target: 12.00 Lane Km
Unit cost: ₱ 9,515,382.50/Lane km
EAO: ₱ 4,141,410.00
Total Allocation: ₱ 118,326,000.00
|
April 28, 2022 |
FY 2022 |
WIN2E02237 |
310108100967000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310108100967000
Project ID: P00601377MN
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Zamboanga City-Labuan-Limpapa Rd - K1971 + 740.00 - K1971 + 880.00, K1971 + 960.00 - K1972 + 140.00, K1973 + 140.00 - K1973 + 200.00
CW1- Construction of Road Slope Protection Structure
Physical Target: 4,997.50 sq.m.
Unit Cost: ₱ 20,169.67/Sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 1,756.95 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,675,000.00
Total Allocation: ₱ 105,000,000.00
|
April 28, 2022 |
FY 2022 |
WIN2E02193 |
310305101539000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310305101539000
Project ID: P00602121MN
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
Sindangan Br. (B00455MN) along Dipolog-Sindangan-Liloy Rd (Phase II)
CW1- Widening of Bridge
Physical Target: 4,335.93 sq.m.
Unit Cost: ₱ 50,543.95/Sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 61,149.95 sq.m.
Unit Cost: ₱ 300.00/Sq.m.
EAO: ₱ 8,750,000.00
Excess: ₱ 3,750,000.00
Total Allocation: ₱ 250,000,000.00
|
April 28, 2022 |
FY 2022 |
WIN2E02212 |
310305101538000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310305101538000
Project ID: P00602122MN
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
Piao Br. (B00454MN) along Dipolog-Sindangan-Liloy Rd (Phase II)
CW1- Widening of Bridge
Physical Target: 2,023.434 sq.m.
Unit Cost: ₱ 27,227.31/Sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 6,357.77 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 2,100,000.00
Excess: ₱ 900,000.00
Total Allocation: ₱ 60,000,000.00
|
April 28, 2022 |
FY 2022 |
WIN2E02209 |
310305101533000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310305101533000
Project ID: P00602124MN
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
De Venta Perla Br. (B01606MN) along Dipolog-Punta-Dansullan-S Osmeña-Zamboanga del Norte/Sur Bdry Rd
CW1- Widening of Bridge
Physical Target: 1,445.31 sq.m.
Unit Cost: ₱ 72,220.66/Sq.m.
ROW- Right-Of-Way Acquisition
Physical Target: 395.838 sq.m.
Unit Cost: ₱ 300.00/sq.m
EAO: ₱ 3,850,000.00
Excess: ₱ 1,650,000.00
Total Allocation: ₱ 110,000,000.00 |
April 28, 2022 |
FY 2022 |
WIN2E02284 |
310305101536000 |
March 22, 2022 |
Region IX |
Regional Office IX |
UACS No. 310305101536000
Project ID: P00602125MN
OO1: Ensure Safe and Reliable National Road System - Bridge - Widening of Permanent Bridges
Layawan Br. (B00422MN) along Dipolog-Punta-Dansullan-S Osmeña-Zamboanga del Norte/Sur Bdry Rd
CW1- Widening of Bridge
Physical Target: 724.086 sq.m.
Unit Cost: ₱ 144,319.87/Sq.m.
EAO: ₱ 3,850,000.00
Excess: ₱ 1,650,000.00
Total Allocation: ₱ 110,000,000.00 |
April 28, 2022 |
FY 2022 |
WIN2E02190 |
310201100907000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100907000
Project ID: P00602310MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City-Zamboanga City Rd - K1858 + 978.00 - K1861 + 336.00, K1864+235.00 - K1864 + 700.00
CW1- Road Widening
Physical Target: 5.646 Lane Km
Unit Cost: ₱ 15,604,598.60/Lane km
ROW- Right-Of-Way Acquisition/
Physical Target: 44,071.45 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,675,000.00
Total Allocation: ₱ 105,000,000.00
|
April 28, 2022 |
FY 2022 |
WIN2E02189 |
310201100909000 |
March 23, 2022 |
Region IX |
Regional Office IX |
UACS No. 310201100909000
Project ID: P00602311MN
OO1: Ensure Safe and Reliable National Road System - Network Development - Road Widening - Primary Roads
Pagadian City-Zamboanga City Rd - K1883 + 794.00 - K1885 + 000.00, K1886 + 188.00 - K1887 + 148.00, K1887 + 257.00 - K1887 + 277.00, K1887 + 317.00 - K1888 + 240.00
CW1- Road Widening
Physical Target: 6.218 Lane Km
Unit Cost: ₱ 14,590,447.46/Lane km
ROW- Right-Of-Way Acquisition
Physical Target: 35,338.66 sq.m.
Unit Cost: ₱ 300.00/sq.m.
EAO: ₱ 3,675,000.00
Total Allocation: ₱ 105,000,000.00 |
April 27, 2022 |
FY 2022 |
WIN2C03523 |
UACS No. 310106100685000 |
January 24, 2022 |
National Capital Region |
Metro Manila 3rd District Engineering Office |
As per GAA/Original
UACS No. 310106100685000
Project ID.: P00603547LZ
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Gov I Santiago St. – K0015+(-197) + K0015+006, K0015+(-664) – K0015+(-197), K0015+006 – K0015+012
Physical Target: CW1- Reconstruction of Concrete Pavement = 1.312 lane km
Unit Cost = P 14,939,024/lane km
Allocation = P 19,600,000
EAO = P 400,000
Total = P 20,000,000
As Modified
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Tertiary Roads
Gov I Santiago St. – K0015+(-541) + K0015+(-238)
Physical Target: CW1- Reconstruction of Concrete Pavement = 0.606 lane km
Unit Cost = P 32,343,234/lane km
Allocation = P 19,600,000
EAO = P 400,000
Total = P 20,000,000
WIN2C03523
|
April 27, 2022 |
2022 |
320102104918000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Drainage System along Tuguegarao Diversion Road 2 K0482+471 - K0488+071, Tuguegarao City |
April 27, 2022 |
2022 |
310109100807000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Peñablanca-Callao Cave Rd - Package 1 |
April 27, 2022 |
2022 |
320102104523000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Drainage System along Caritan- Balzain Creek Sta 0+(-280) - Sta 0+(-689.20), Caritan, Tuguegarao City, Cagayan |
April 27, 2022 |
2022 |
WIN2F06031 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bataan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Secondary Roads
Gov JJ Linao Rd - K0140+047 - K0140+407 |
April 27, 2022 |
2022 |
320102104513000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Cagayan River Flood Management Projects, Anquiray (Sta 0+480 - Sta 0+780), Amulung, Cagayan (Downstream) |
April 27, 2022 |
2022 |
WIN2F06069 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bataan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Jct Layac - Balanga - Mariveles Port Rd - K0153+(-738) - K0153+(-100), K0153+265, K0153+287 - K0153+603 |
April 27, 2022 |
2022 |
300215101133000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
Convergence and Special Support Program (CSSP) - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/Facilities
Construction of Road at Barangay 4, Enrile, Cagayan |
April 27, 2022 |
2022 |
WIN2F06028 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bataan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Tertiary Roads
Visayas Ave (R01124LZ) - K0164+(-213) - K0164+520
|
April 27, 2022 |
2022 |
310107100373000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse and Landslide - Primary Roads
Kalinga-Cagayan Rd (Calanan-Enrile Section) - K0441 + 772 - K0441 + 960 |
April 27, 2022 |
2022 |
310109100808000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Peñablanca-Callao Cave Rd - Package 2 |
April 27, 2022 |
2022 |
WIN2F06027 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bataan 2nd District Engineering Office |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Secondary Roads
Jct Layac - Balanga - Mariveles Port Rd - K0158+300 - K0158+390 |
April 27, 2022 |
2022 |
320102104515000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Cagayan River Flood Management Projects, Minanga Sur (Sta. 0+000 - Sta. 0+250), Iguig, Cagayan |
April 27, 2022 |
2022 |
WIN2F06040 |
FY 2022 GAA |
December 30, 2021 |
Region III |
Bataan 2nd District Engineering Office |
Asset Preservation Program - Rehabilitation / Reconstruction of National Roads with Slips, Slope Collapse, and Landslide - Tertiary Roads
Bagac - Mariveles Rd - K0164+320 - K0165+018, K0165+030 - K0165+450 |
April 27, 2022 |
2022 |
320102104530000 |
GAA 2022 |
January 3, 2022 |
Region II |
Cagayan 3rd District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
Construction of Flood Control System along Cagayan River Basin, Brgy. Alibago, Enrile, Cagayan, Sta. 0+770-Sta. 1+170 (Downstream) |