August 28, 2024 |
2024 |
320102106233000 |
GAA 2024 |
January 3, 2024 |
Region II |
Isabela 3rd District Engineering Office |
FROM:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Magat River Flood Control Project, Barangay Ambatali (Sta. 0+000 - Sta. 1+500), Ramon, Isabela
TO:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Magat River Flood Control Project, Barangay Ambatali (Sta. 0+000 - Sta. 0+520.80), Ramon, Isabela |
August 28, 2024 |
2024 |
WIN4E03606 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101373000
Project ID: P00800153MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1183 + 843 - K1183 + 881, K1185 + 053 - K1185 + 154
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 0.278 Lane Km
Allocation:
TOTAL: P 5,560,000
CW1: P 5,365,400
EAO: P 194,6000
Unit Cost:
CW1: P 19,300,000/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 655 - K1176 + 750
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 0.190 Lane Km
Allocation:
TOTAL: P 5,560,000
CW1: P 5,365,400
EAO: P 194,6000
Unit Cost:
CW1: P 28,328,947.37/Lane Km
|
August 28, 2024 |
2024 |
WIN4E03582 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
UACS No. : 320102106736000
Project ID: P00821204MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
FROM:
Construction of Gibong River Bank Protection along Barangay La Suerte, Prosperidad, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 416.724 Lineal meters
Allocation:
TOTAL: P 60,000,000
CW1: P 57,900,000
EAO: P 2,100,000
Unit Cost:
CW1: P 138,940.88/Lineal meters
TO:
Construction of Gibong River Bank Protection along Barangay La Suerte, Prosperidad, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 91.600 Lineal meters
Allocation:
TOTAL: P 60,000,000
CW1: P 57,900,000
EAO: P 2,100,000
Unit Cost:
CW1: P 632,096.07/Lineal meters
|
August 28, 2024 |
2024 |
|
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Agusan del Sur 2nd District Engineering Office |
UACS No. : 300225102255000
Project ID: P00836196MN
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Flood Mitigation Structures protecting Major/ Strategic Public Buildings/ Facilities
FROM:
Construction of Riverbank Protection of Gibong River at Brgy. Ebro, San Francisco, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 138.908 Lineal meters
Allocation:
TOTAL: P 20,000,000
CW1: P 19,800,000
EAO: P 200,000
Unit Cost:
CW1: P 142,540.39/Lineal meters
TO:
Construction of Riverbank Protection of Gibong River at Brgy. Ebro, San Francisco, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 52 Lineal meters
Allocation:
TOTAL: P 20,000,000
CW1: P 19,800,000
EAO: P 200,000
Unit Cost:
CW1: P 380,769.23/Lineal meters
|
August 28, 2024 |
2024 |
WIN4E03581 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
UACS No. : 320102107025000
Project ID: P00820426MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers
FROM:
Construction of Bank Protection along Agusan River (Poblacion-Sibagat Section) Sibagat, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 242.547 Lineal meters
Allocation:
TOTAL: P 34,922,000
CW1: P 34,223,560
EAO: P 698,440
Unit Cost:
CW1: P 141,100.735/Lineal meters
TO:
Construction of Bank Protection along Agusan River (Poblacion-Sibagat Section) Sibagat, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 87.01 Lineal meters
Allocation:
TOTAL: P 34,922,000
CW1: P 34,223,560
EAO: P 698,440
Unit Cost:
CW1: P 393,329,0426/Lineal meters
|
August 28, 2024 |
2024 |
WIN4E03587 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Dinagat Islands District Engineering Office |
UACS No. : 310102101935000
Project ID: P00801071MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Preventive Maintenance - Secondary Roads
FROM:
Dinagat-Loreto Rd - K0018 + 552 - K0019 + 000
Type of Work:
CW1: Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 0.826 Lane Km
Allocation:
TOTAL: P 13,703,000
CW1: P 13,428,940
EAO: P 274,060,000
Unit Cost:
CW1: P 16,257,796.61/Lane Km
TO:
Dinagat-Loreto Rd - K0018 + 552 - K0019 + 000
Type of Work:
CW1: Preventive Maintenance of Road: Asphalt Overlay
Physical Target:
CW1- 0.826 Lane Km
Allocation:
TOTAL: P 13,703,000
CW1: P 13,428,940
EAO: P 274,060,000
Unit Cost:
CW1: P 16,257,796.61/Lane Km
|
August 28, 2024 |
2024 |
320102106901000 |
GAA 2024 |
January 3, 2024 |
Region II |
Isabela 3rd District Engineering Office |
FROM:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Ganano River Flood Control Project, Barangay Apanay (Sta 0 + 398 - Sta 0 + 796, Alicia, Isabela
TO:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Ganano River Flood Control Project, Barangay Apanay (Sta 0 + 000 - Sta 0 + 188.30), Alicia, Isabela |
August 28, 2024 |
2024 |
320102106143000 |
GAA 2024 |
January 3, 2024 |
Region II |
Isabela 3rd District Engineering Office |
FROM:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Cagayan River Flood Control Project, Barangay Minanga Upstream, Sta.0+000 - Sta. 0+600, Naguillian, Isabela
TO:
Construction/ Rehabilitation of Flood Mitigation Facilities within Major River Basins and Principal Rivers - Construction of Cagayan River Flood Control Project, Barangay Minanga Upstream, Sta.0+000 - Sta. 0+398.30, Naguillian, Isabela |
August 28, 2024 |
2024 |
WIN4E03632 |
SR2024-01-003973 |
January 29, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Installation of Roadway Lighting Structures along Abatan - Mankayan - Cervantes Road K0334 + (-889) - K0355 + 467;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
894 Number of Units;
Allocation:
Php 125,000,000"
"To:
Installation of Roadway Lighting Structures along Abatan - Mankayan - Cervantes Road K0334 + (-889) - K0347+000;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
539 Number of Units;
Allocation:
Php 125,000,000"
|
August 28, 2024 |
2024 |
WIN4XW00132 |
SR2024-01-004588 |
January 29, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Malalao Nat'l RD (Agbannawag-Malalao-Bulo Sect) Road, K0514 + 000 -K0056 + 000, K0512 + 716 - K0513 + 000, K0516 + 415 - K0520 + 000, Tabuk City, Kalinga;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
27.214 Lane Km;
Allocation:
Php 150,000,000"
"To:
Malalao Nat'l RD (Agbannawag-Malalao-Bulo Sect) Road, K0514 + 000 -K0516 + 000, K0512 + 716 - K0513 + 000, K0516 + 415 - K0520 + 000, Tabuk City, Kalinga;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
8.03063 Lane Km;
Allocation:
Php 150,000,000"
|
August 28, 2024 |
2024 |
310205101188000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Network Development - Construction of Missing Links/ New Roads - Sampaguita-Warat-La Suerte-Catarauan-Afusing Rd Phase II |
August 28, 2024 |
2024 |
WIN4XW00131 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Bulanao-Paracelis Rd, K0508 + 645 - K0513 + 1105;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
21.768 Lane Km;
Allocation:
Php 125,000,000"
"To:
Bulanao-Paracelis Rd, K0508 + 645 - K0513 + 1105;
Type of Work:
CW1: Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
6.93154 Lane Km;
Allocation:
Php 125,000,000"
|
August 28, 2024 |
2024 |
WIN4E03643 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect), K0512+000- K0513+398, K0514+000-K0515+000, K0515+265-K0518+000, Tabuk City, Kalinga;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
15.204 Lane Km;
Allocation:
Php 150,000,000"
"To:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect), K0512+000- K0513+398, K0514+000-K0515+000, K0515+265-K0518+000, Tabuk City, Kalinga;
Type of Work:
CW1: Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
8.13557 Lane Km;
Allocation:
Php 150,000,000"
|
August 28, 2024 |
2024 |
310106101031000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 1st District Engineering Office |
FROM:
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads - Baybayog-Baggao-Dalin-Sta. Margarita Rd - K0519+330 - K0519+591, K0521+518 - K0521+803, K0522+469 - K0523+300 ,K0525+513 - K0525+720, K0533+222 - K0533+308, K0533+394 - K0533+508, K0541+123 - K0542+000, K0545+950 - K0548+000
TO:
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads - Baybayog-Baggao-Dalin-Sta. Margarita Rd - K0519+331 - K0519+600.5, K0521+381 - K0521+795, K0522+466.5 - K0523+322, K0531+375 - K0531+470, K0533+130 - K0533+290.46, K0533+376.14 - K0533+538.62, K0541+(-195.5) - K0541+1001.5, K0546+000 - K0547+1012.5 |
August 28, 2024 |
2024 |
310204102442000 |
GAA 2024 |
January 3, 2024 |
Region II |
Regional Office II |
Network Development - Construction of By-Pass and Diversion Roads - Ramon-Cordon-Diadi Bypass Road, Diadi, Nueva Vizcaya |
August 27, 2024 |
2024 |
WIN4F08105 |
SR2024-02-008173 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads – Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0702 + 483 - K0702 + 795, K0706 + 447 - K0706 + 504, K0707 + 108 - K0708 + 000, K0712 + 000 - K0712 + 050, K0718 + 637 - K0718 + 734, K0727 + (-355) - K0727 + 280, K0734 + 150 - K0734 + 558, K0734 + 595 - K0734 + 650, K0735 + 000 - K0735 + 526
Physical Target: Allocation:
CW1- Reconstruction to Concrete Pavement: P 76.578540 M
6.064 Lane Km
EAO P 2.777460 M
Total P 79.356 M
AS MODIFIED:
Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0707 + 108 - K0707 + 808, K0734 + 137 - K0734 + 539, K0777 + 389 - K0778 + 000, K0781 + 240 - K0781 + 780
Physical Target: Allocation:
CW1- Reconstruction to Concrete Pavement: P 76.578540 M
4.516 Lane Km
EAO P 2.777460 M
Total P 79.356 M
|
August 22, 2024 |
FY 2024 GAA |
WIN4XW00118 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Rehabilitation of Davao-Cotabato Rd (Jct. Digos-Cotabato Sect) - K1576 + 768 - K1578 + 158
Physical Target:
CW1: 2.800 lane km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Reconstruction to Concrete Pavement)
EAO: P 1,750,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Rehabilitation of Davao-Cotabato Rd (Jct. Digos-Cotabato Sect) - K1578 + 634 - K1578 + 929,
K1589 + 046 - K1589 + 096, K1590 + 000 - K1591 + 173, K1591 + 300 - K1591 + 522.50,
K1591 + 545 - K1591 + 600, K1591 + 654 - K1591 + 880
Physical Target:
CW1: 3.445 lane km (Reconstruction to Concrete Pavement)
CW2: 1.180 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 29,037,760.00 (Reconstruction to Concrete Pavement)
CW2: P 19,212,240.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 1,750,000.00 |
August 22, 2024 |
FY 2024 GAA |
P00835786MN |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region XI |
Davao del Norte 2nd District Engineering Office |
MODIFICATION:
FROM: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/Strategic Public Buildings/Facilities
Construction of Bank Protection Structure long Lasana River protecting Panabo City Coastal Road, Carmen
Physical Target:
CW1: 450.00 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Revetment)
EAO: P 5,250,000.00
TO: Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Flood Mitigation Structures protecting Major/Strategic Public Buildings/Facilities
Construction of Bank Protection Structure along Lasana River protecting Panabo City Coastal Road, Carmen
Physical Target:
CW1: 855.00 lineal meters (Construction of Revetment)
Allocation:
TOTAL: P 150,000,000.00
CW1: P 144,750,000.00 (Construction of Revetment)
EAO: P 5,250,000.00 |
August 21, 2024 |
FY 2024 GAA |
P00803806MN |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region XI |
Davao del Norte 2nd District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Preventive Maintenance of Road Asphalt Overlay with Road Safety Devices along Babak-Samal-Kaputian Road,
K1519 + 000 - K1522 + 000, Davao del Norte
Physical Target:
CW1: 6.558 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Preventive Maintenance - Secondary Roads
Preventive Maintenance of Road Asphalt Overlay with Road Safety Devices along Babak-Samal-Kaputian Road,
K1501 + 825 - K1504 + 140, Davao del Norte
Physical Target:
CW1: 6.852 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 100,000,000.00
CW1: P 96,500,000.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 3,500,000.00 |
August 21, 2024 |
FY 2024 GAA |
WIN4XW00120 |
FY 2024 GAA RA 11975 |
January 1, 2024 |
Region XI |
Davao del Sur District Engineering Office |
MODIFICATION:
FROM: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Rehabilitation of Davao-Cotabato Rd (Jct. Digos-Cotabato Sect) - K1572 + 000 - K1573 + 400
Physical Target:
CW1: 2.810 lane km (Reconstruction to Concrete Pavement)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 48,250,000.00 (Reconstruction to Concrete Pavement)
EAO: P 1,750,000.00
TO: OO1: Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads - Primary Roads
Rehabilitation of Davao-Cotabato Rd (Jct. Digos-Cotabato Sect) - K1578 + 339 - K1578 + 634,
K1583 + 237 - K1583 + 597, K1583 + 900 - K1584 + 058,
K1584 + 118 - K1584 + 763, K1588 + 009 - K1588 + 426
Physical Target:
CW1: 3.204 lane km (Reconstruction to Concrete Pavement)
CW2: 1.180 lane km (Preventive Maintenance of Road: Asphalt Overlay)
Allocation:
TOTAL: P 50,000,000.00
CW1: P 28,800,868.00 (Reconstruction to Concrete Pavement)
CW2: P 19,449,132.00 (Preventive Maintenance of Road: Asphalt Overlay)
EAO: P 1,750,000.00 |
August 16, 2024 |
2024 |
|
GAA FY 2024 |
January 15, 2024 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
AS PER GAA/ORIGINAL:
Basey-Marabut-Pinamitinan Rd - K0944 + 000 - K0945 + 000
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 37.730 M
Pavement: 2.002 Lane Km
EAO P .770 M
Total P 38.50 M
AS MODIFIED:
Basey-Marabut-Pinamitinan Rd - K0947 + 240 - K0947 + 835, K0948 + 240 - K0948 + 1000
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 37.730 M
Pavement: 2.71 Lane Km
EAO P .770 M
Total P 38.50 M
|
August 16, 2024 |
2024 |
|
SR2024-01-005072 |
January 30, 2024 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
AS PER GAA/ORIGINAL:
Basey-Marabut-Pinamitinan Rd - K0926 + 428 - K0927 + 700, K0928 + 524 - K0930 + 000
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 53.075 M
Pavement: 5.36 Lane Km
EAO P 1.925 M
Total P 55.00 M
AS MODIFIED:
Basey-Marabut-Pinamitinan Rd – Basey-Marabut-Pinamitinan Rd - K0915 + 958 - K0916 + 020, K0916 + 580 - K0916 + 651, K0917 + 039 - K0917 + 055, K0917 + 384 - K0917 + 412, K0917 + 503 - K0917 + 512, K0917 + 538 - K0917 + 602, K0927 + 005 - K0927 + 180, K0927 + 220 - K0927 + 260, K0927 + 374 - K0927 + 460, K0927 + 620 - K0927 + 700, K0927 + 780 - K0928 + 400, K0928 + 420 - K0928 + 500, K0929 + 020 - K0929 + 414, K0929 + 420 - K0929 + 724, K0929 + 770 - K0929 + 994
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 53.075 M
Pavement: 4.522 Lane Km
EAO P 1.925 M
Total P 55.00 M
|
August 16, 2024 |
2024 |
|
GAA FY 2024 |
January 15, 2024 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Tertiary Roads
AS PER GAA/ORIGINAL:
Sn Juanico-Basey-Sohoton Rd - K0916 + 000 - K0916 + 1009, K0914 + 000 - K0914 + 066
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 34.30 M
Pavement: 2.15 Lane Km
EAO P .700 M
Total P 35.00 M
AS MODIFIED:
Sn Juanico-Basey-Sohoton Rd - K0913 + 480 - K0913 + 540, K0913 + 623 - K0913 + 663, K0913 + 740 - K0913 + 800, K0916 +180 - K0916 + 280, K0916 +360 - K0916 + 480, K0916 + 560 - K0916 + 951, K0917 + 849 - K0917 + 970, K0918 + 080 - K0918 + 340, K0918 + 420 - K0918 + 580, K0918 + 600 - K0918 + 620, K0918 + 640 - K0918 + 680, K0918 + 820 - K0918 + 860, K0918 + 940 - K0918 + 1013
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 34.30 M
Pavement: 2.97 Lane Km
EAO P .700 M
Total P 35.00 M
|
August 16, 2024 |
2024 |
|
GAA FY 2024 |
January 15, 2024 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
AS PER GAA/ORIGINAL:
Basey-Marabut-Pinamitinan Rd - K0942 + 000 - K0943 + 000
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 39.20 M
Pavement: 2.158 Lane Km
EAO P .800 M
Total P 40.00 M
AS MODIFIED:
Basey-Marabut-Pinamitinan Rd - K0936 + 803 - K0936 + 840, K0936 + 867 - K0936 + 1266, K0942 + 000 - K0942 + 634, K0946 + 078 - K0946 + 090, K0946 + 382 - K0946 + 434, K0947 +119 - K0947 + 240
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 39.20 M
Pavement: 2.510 Lane Km
EAO P .800 M
Total P 40.00 M
|
August 16, 2024 |
2024 |
|
GAA FY 2024 |
January 15, 2024 |
Region VIII |
Samar 2nd District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation - Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved Roads - Secondary Roads
AS PER GAA/ORIGINAL:
Basey-Marabut-Pinamitinan Rd - K0943 + 000 - K0944 + 000
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 37.240 M
Pavement: 2.012 Lane Km
EAO P .760 M
Total P 38.00 M
AS MODIFIED:
Basey-Marabut-Pinamitinan Rd - K0932 + 028 - K0932 + 180, K0932 + 185 - K0932 + 286, K0932 + 317 - K0932 + 612, K0936 + 000 - K0936 + 803
Physical Target: Allocation:
CW1- Reconstruction to Concrete P 37.240 M
Pavement: 2.706 Lane Km
EAO P .760 M
Total P 38.00 M
|
August 16, 2024 |
2024 |
WIN4XY00354 |
SR2024-01-002132 |
January 24, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure along Binahaan River, Phase 2, barangay Balud to barangay Sta. Elena, Tanauan, Leyte
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 1,068.952 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
AS MODIFIED:
Construction of Flood Control Structure along Binahaan River, Phase 2, barangay Balud to barangay Sta. Elena, Tanauan, Leyte
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 637.00 Lineal Meters
EAO P 5.250 M
Total P 150.00 M
|
August 16, 2024 |
2024 |
WIN4XY00355 |
SR2024-02-008114 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program (CSSP)
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Road, Sitio Kalawit - Barangay Cadian, Oras, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Concrete P 168.875 M
Road: 3.439 Lane Km
EAO P 6.125 M
Total P 175.00 M
AS MODIFIED:
Construction of Road, Sitio Kalawit - Barangay Cadian, Oras, Eastern Samar
Physical Target: Allocation:
CW1- Construction of Concrete P 94.48471399 M
Road: 6.34 Lane Km
CW2- Construction of Road Slope Protection P 53.79930409 M
Structure: 31,891.80 Square Meters
CW3- Construction of Drainage Structure P 20.59098192 M
Along Road: 3,000 Lineal Meters
EAO P 6.125 M
Total P 175.00 M
|
August 16, 2024 |
2024 |
WIN4XY00358 |
SR2024-01-002141 |
January 27, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
OO2: Protect Lives and Properties Against Major Floods
Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
AS PER GAA/ORIGINAL:
Construction of Flood Control Structure along Calogcog River (Left Bank - Upstream), Brgy. Calogcog and Brgy. Atipolo, Tanauan, Leyte
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 1,068.952 Lineal Meters
EAO P 5.520 M
Total P 150.00 M
AS MODIFIED:
Construction of Flood Control Structure along Calogcog River (Left Bank - Upstream), Brgy. Calogcog and Brgy. Atipolo, Tanauan, Leyte
Physical Target: Allocation:
CW1- Construction of Flood Mitigation P 144.750 M
Structure: 658.00 Lineal Meters
EAO P 5.520 M
Total P 150.00 M
|
August 16, 2024 |
2024 |
WIN4F08100 |
SR2024-02-008228 |
February 1, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Construction/ Upgrading/ Rehabilitation of Drainage along National Roads – Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (LT) – K0908 + 605 – K0909 + 274
Physical Target: Allocation:
CW1- Construction of Drainage Structure P 26.502760 M
Along Road: 1,556 Lineal Meters
EAO P .961240 M
Total P 27.464 M
AS MODIFIED:
Daang Maharlika (LT) – K0908 + 605 – K0909 + 017
Physical Target: Allocation:
CW1- Construction of Drainage Structure P 26.502760 M
Along Road: 1,042 Lineal Meters
EAO P .961240 M
Total P 27.464 M
|
August 15, 2024 |
2024 |
WIN4XY00352 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Regional Office III |
Convergence and Special Support Program - Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Interjurisdictional Roads and/or Bridges (or, roads that traverse multiple LGU jurisdictions)
Construction of Dingalan-Doña Remedios Trinidad Road (Phase III), Aurora |
August 15, 2024 |
2024 |
WIN4XY00353 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0077+617 - K0078+990 |
August 15, 2024 |
2024 |
WIN4XY00356 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Rd - K0074+537 K0075+983, K0076+162 - K0076+374 |
August 15, 2024 |
2024 |
|
FY 2024 GAA |
December 20, 2023 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0069+410 - K0069+746, K0071+384 - K0071+614, K0074+351 - K0074+537, K0080+443.50 - K0080+837.60 |
August 15, 2024 |
FY 2024 |
P00820100MN |
GAA 2024 |
January 1, 2024 |
Region XII |
Cotabato 3rd District Engineering Office |
Construction of M'lang River Flood Control Project (Downstream of M'lang Bridge, Left Side), Barangay Poblacion A, M'lang, Cotabato
Amount: ₱ 132,000,000.00 |
August 15, 2024 |
2024 |
|
FY 2024 GAA |
December 20, 2023 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0078+990 - K0080+024 |
August 15, 2024 |
FY 2024 |
P00821224MN |
GAA 2024 |
January 1, 2024 |
Region XII |
Regional Office XII |
Construction of Riverbank Protection along Matampay River at Barangay Kabuntulan, Sultan Kudarat, Maguindanao del Norte
Amount: 50,000,000.00 |
August 15, 2024 |
2024 |
WIN4XY08080 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Pampanga 1st District Engineering Office |
Asset Preservation Program – Rehabilitation / Reconstruction / Upgrading of Damaged Paved Roads
Sto. Tomas - Minalin Rd (Minalin-Macabebe Section) - K0064+748 - K0065+39350, K0065+740 - K0066+037.50 |
August 15, 2024 |
FY 2024 |
P00834938MN |
GAA 2024 |
January 1, 2024 |
Region XII |
Regional Office XII |
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Buluan Bridge, Buluan, Maguindanao del Sur
Amount: ₱ 80,000,000.00
|
August 15, 2024 |
FY 2024 |
P00834939MN |
GAA 2024 |
January 1, 2024 |
Region XII |
Regional Office XII |
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
Construction of Kabulnan Bridge, Datu Hoffer Ampatuan, Maguindanao del Sur
Amount: ₱ 80,000,000.00 |
August 15, 2024 |
2024 |
WIN4XW00116 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + (-569) - K0522 + 088;
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
1.314 Lane Km;
Allocation:
Php 12,000,000"
"To:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + (-569) - K0522 + (-092.871);
Type of Work:
Preventive Maintenance of Road: Asphalt Overlay;
Physical Target:
CW1: 0.96292 Lane Km;
Allocation:
Php 12,000,000"
|
August 15, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Pantar Road, Tabuk City, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.087 Lane Km;
Allocation:
Php 5,000,000"
"To:
Construction of Pantar Road, Tabuk City, Kalinga;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 0.552 Lane Km
CW2: 365 Square meters;
Allocation:
Php 5,000,000"
|
August 15, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Cudal River Flood Control Mitigation Structure along Magabangon Bridge, Sta.0+000 -Sta.0+500 (R/S Upstream) Sta.00+000-Sta.00+500(R/S), Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
820.497 Lineal meters;
Allocation:
Php 100,000,000"
"To:
Construction of Cudal River Flood Control Mitigation Structure along Magabangon Bridge, Sta.1+865 - Sta.2+228.33 (R/S Upstream), Sta. 0+915 - Sta. 1+833.87 (R/S), Sta. 1+862-Sta. 2+259.56 (L/S), Sta. 0+915 - Sta. 1+105 (L/S), Sta. 1+075 - Sta. 1+820 (L/S), Kalinga;
Type of Work:
CW1: Construction of Flood Mitigation Structure;
Physical Target:
2518.39 Lineal meters;
Allocation:
Php 100,000,000"
|
August 14, 2024 |
2024 |
WIN4E03606 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Regional Office XIII |
UACS No. : 310201101373000
Project ID: P00800153MN
ORGANIZATIONAL OUTCOME 1 : Ensure Safe and Reliable National Road System - Network Development Program - Road Widening - Primary Roads
FROM:
Daang Maharlika (Surigao-Agusan Sect) - K1183 + 843 - K1183 + 881, K1185 + 053 - K1185 + 154
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 0.278 Lane Km
Allocation:
TOTAL: P 5,560,000
CW1: P 5,365,400
EAO: P 194,6000
Unit Cost:
CW1: P 19,300,000/Lane Km
TO:
Daang Maharlika (Surigao-Agusan Sect) - K1176 + 655 - K1176 + 750
Type of Work:
CW1: Road Widening
Physical Target:
CW1- 0.190 Lane Km
Allocation:
TOTAL: P 5,560,000
CW1: P 5,365,400
EAO: P 194,6000
Unit Cost:
CW1: P 28,328,947.37/Lane Km
|
August 14, 2024 |
2024 |
WIN4E03580 |
FY 2024 GAA, R.A 11975 |
December 25, 2023 |
Region XIII |
Agusan del Sur 1st District Engineering Office |
UACS No. : 320101112264000
Project ID: P00820210MN
ORGANIZATIONAL OUTCOME 2 : Protect Lives and Properties Against Major Floods - Flood Management Program - Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems
FROM:
Construction of Andanan RIS Flood Control Structure, Bayugan City, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 208.362 Lineal meters
Allocation:
TOTAL: P 30,000,000
CW1: P 29,400,000
EAO: P 600,000,000
Unit Cost:
CW1: P 141,100.58/Lineal meters
TO:
Construction of Andanan RIS Flood Control Structure, Bayugan City, Agusan del Sur
Type of Work:
CW1: Construction of Flood Mitigation Structure
Physical Target:
CW1- 74.80 Lineal meters
Allocation:
TOTAL: P 30,000,000
CW1: P 29,400,000
EAO: P 600,000,000
Unit Cost:
CW1: P 393,048.13/Lineal meters
|
August 12, 2024 |
2024 |
WIN4E03633 |
SR2024-01-005298 |
January 30, 2024 |
Cordillera Administrative Region |
CAR - Regional Office |
"From:
Construction of Dalimuno, Bantay Flood Control Along Chico River (Sta. 1+160 - Sta. 2+110), Bantay, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
869 Lineal meters;
Allocation:
Php 100,000,000"
"To:
Construction of Dalimuno, Bantay Flood Control along Chico River (Sta. 100+023 - Sta. 100+430) Bantay, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
449 Lineal meters;
Allocation:
Php 100,000,000"
|
August 12, 2024 |
2024 |
WIN4XY00346 |
GAA FY 2024 |
January 31, 2024 |
Region VIII |
Samar 1st District Engineering Office |
Convergence and Special Support Program
SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Road, Brgy. San Agustin-Brgy. Hinogacan Road, Gandara, Samar
Physical Target: Allocation:
CW1- Construction of Gravel Road: P 20.7475 M
1.300 Lane Km
EAO P .7525 M
Total P 21.50 M
AS MODIFIED:
Construction of Road, Brgy. San Agustin-Brgy. Hinogacan Road, Gandara, Samar
Physical Target: Allocation:
CW1- Construction of Concrete Road: P 17.28461259 M
1.258 Lane Km
CW2- Construction of Road Slope Protection: P 3.46288741 M
Structure: 1,736.00 Square Meters
EAO P .75250 M
Total P 21.50 M
|
August 10, 2024 |
2024 |
310204102804000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Network Development - Construction of By-Pass and Diversion Roads - Solana Diversion Road Phase II, Solana, Cagayan |
August 9, 2024 |
2024 |
300215104469000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Road , Brgy. Sitio San Juan, Brgy. Villa Maria- Brgy. Batu, Enrile, Cagayan |
August 9, 2024 |
2024 |
300215104478000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Sustainable Infrastructure Projects Alleviating Gaps (SIPAG) - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities - Construction of Bridge and Approaches, Brgy. Maguirig, Solana, Cagayan |
August 9, 2024 |
2024 |
310204102444000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Network Development - Construction of By-Pass and Diversion Roads - Construction of Bypass/Diversion Road, Tuguegarao North Diversion Road |
August 9, 2024 |
2024 |
310203100761000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
FROM:
Network Development - Road Widening - Tertiary Roads - Peñablanca-Callao Cave Rd - K0475 + (-582) - K0477 + 040
TO:
Network Development - Road Widening - Tertiary Roads - Peñablanca-Callao Cave Rd - K0475 + (-582) - K0476 + 220, K0476 + 220 - K0476 + 300 |
August 9, 2024 |
2024 |
310205101189000 |
GAA 2024 |
January 3, 2024 |
Region II |
Cagayan 3rd District Engineering Office |
Network Development - Construction of Missing Links/ New Roads - Sampaguita-Warat-La Suerte-Catarauan-Afusing Rd Phase III |
August 9, 2024 |
2024 |
|
GAA FY 2024 |
January 1, 2024 |
Region VIII |
Tacloban City District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Bridge – Widening of Permanent Bridges
AS PER GAA/ORIGINAL:
Apitong Br. (B00030LT) along Apitong – Paterno Rd
Physical Target: Allocation:
CW1- Widening of Bridge: P 19.6 M
24 Square Meters
EAO P .400 M
Total P 20.00 M
AS MODIFIED:
Apitong Br. (B00030LT) along Apitong – Paterno Rd
Physical Target: Allocation:
CW1- Widening of Bridge: P 19.6 M
123.84 Square Meters
EAO P .400 M
Total P 20.00 M
|
August 8, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Manuel S. Agyao Boulevard - K0496 + 501 - K0496 + 523, K0497 + 135 - K0497 + 469, K0497 + 497 - K0498 + 344, K0502 + 000 - K0503 + 104;
Type of Work:
Road Widening;
Physical Target:
4.566 Lane Km;
Allocation:
Php 74,648,000"
"To:
Manuel S. Agyao Boulevard - K0496 + 501 - K0496 + 638, K0497 + 135 - K0497 + 469, K0497 + 497 - K0498 + 344, K0502 + 000 - K0503 + 104;
Type of Work:
CW1: Road Widening
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 5.444 Lane Km
CW2: 2658 Square meters;
Allocation:
Php 74,648,000"
|
August 8, 2024 |
2024 |
WIN4E03592 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Mountain Province 1st District Engineering Office |
"From:
Construction of Multi-Purpose Building, Barangay Payeo, Sagada, Mountain Province;
Type of Work:
Construction of Multi Purpose Building;
Physical Target:
1.0 Number of Building;
Allocation:
Php 5,000,000"
"To:
Construction of Multi-Purpose Building, Barangay Payeo, Besao, Mountain Province;
Type of Work:
Construction of Multi Purpose Building;
Physical Target:
1.0 Number of Building;
Allocation:
Php 5,000,000"
|
August 8, 2024 |
2024 |
WIN4E03627 |
SR2024-01-003964 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Installation of Road Safety Devices along Gov. Bado Dangwa (Palina-Poblacion Section) K0328+(-085)-K0338+731, Bakun, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
11,442 Lineal meters;
Allocation:
Php 125,000,000"
"To:
Installation of Road Safety Devices along Gov. Bado Dangwa (Palina-Poblacion Section) K0328+(-085)-K0338+731, Bakun, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
536 Number of units;
Allocation:
Php 125,000,000"
|
August 8, 2024 |
2024 |
WIN4E03626 |
SR2024-01-003953 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Installation of Road Safety Devices along Abatan - Mankayan - Cervantes Road, K0334 + (-889) - K0353+2495 (S00387LZ);
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
22,351 Lineal meters;
Allocation:
Php 100,000,000"
"To:
Installation of Road Safety Devices along Abatan - Mankayan - Cervantes Road, K0348 + 000 - K0351+000 (S00378LZ);
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
387 Number of Units;
Allocation:
Php 100,000,000"
|
August 8, 2024 |
2024 |
WIN4E03625 |
SR2024-01-003967 |
January 29, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Installation of Road Safety Devices along Abatan - Mankayan - Cervantes Road K0334 + (-889) - K0355 + 467, Mankayan, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
22,351 Lineal meters;
Allocation:
Php 125,000,000"
"To:
Installation of Road Safety Devices along Abatan - Mankayan - Cervantes Road K0351+000 - K0353 + 2495, Mankayan, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
539 Number of units;
Allocation:
Php 125,000,000"
|
August 8, 2024 |
2024 |
WIN4E03607 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Manuel S. Agyao Boulevard - K0507 + 360 - K0507 + 737, K0510 + 015 - K0510 + 084;
Type of Work:
Road Widening;
Physical Target:
0.892 Lane Km;
Allocation:
Php 65,054,000"
"To:
Manuel S. Agyao Boulevard - K0507 + 360 - K0507 + 075;
Type of Work:
CW1: Road Widening
CW2: Construction of Drainage Structure along Road;
Physical Target:
CW1: 5.566 Lane Km
CW2: 1500 Lineal meters;
Allocation:
Php 65,054,000"
|
August 8, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Mallig River Flood Control Mitigation Structure along Cassag Bridge, Tabuk-Paracelis Mun. Baoundary (Tabuk Side), Sta.0+000 -Sta.0+930 (LS), Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
820.467 Lineal meters;
Allocation:
Php 100,000,000"
"To:
Construction of Mallig River Flood Control Mitigation Structure along Cassag Bridge, Tabuk-Paracelis Mun. Baoundary (Tabuk Side), Sta.0+000 -Sta.0+930 (LS), Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
930 Lineal meters;
Allocation:
Php 100,000,000"
|
August 8, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
3.552 Lane Km;
Allocation:
Php 80,000,000"
"To:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
CW1: Construction of Gravel Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 5.2 Lane Km
CW2: 4566 Square meters;
Allocation:
Php 80,000,000"
|
August 8, 2024 |
2024 |
P00835023MN |
GAA FY 2024 |
January 1, 2024 |
Region X |
Misamis Occidental 1st District Engineering Office |
P00835023MN
300215105056000
Convergence and Special Support System - SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/Strategic Public Buildings/ Facilities
FROM:
Construction of Barangay Libertad Road, Sapang Dalaga, Misamis Occidental
Type of Work:
CW1- Construction of Concrete Road
Physical Target:
CW1- 2.50 Lane Km
Allocation:
CW1: Php 14,435,400.00
EAO: Php 736,500.00
TO:
Construction of Barangay Libertad Road, Sapang Dalaga, Misamis Occidental
Type of Work:
CW1- Construction of Concrete Road
CW2- Construction of Road Slope Protection Structure
Physical Target:
CW1- 1.40 Lane Km
CW2- 928.30 Square Meters
Allocation:
CW1: Php 26,594,164.94
CW2: Php 9,494,335.06
EAO: Php 736,500.00 |
August 8, 2024 |
2024 |
WIN4E03536 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Mountain Province 2nd District Engineering Office |
"From:
Construction of Drainage Structure, Barangay Alunogan, Natonin, Mountain Province;
Type of Work:
Construction of Drainage Structure;
Physical Target:
482.603 Lineal meters;
Allocation:
Php 5,000,000"
"To:
Construction of Drainage Structure, Barangay Alunogan, Natonin, Mountain Province;
Type of Work:
Construction of Drainage Structure;
Physical Target:
89 Linear Meters;
Allocation:
Php 5,000,000"
|
August 8, 2024 |
2024 |
WIN4E03598 |
SR2024-03-012867 |
March 5, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Construction of Conacon - Deckan - Payeo Road, Barangay Bedbed, Mankayan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
16.938 Lane Km;
Allocation:
Php 153,000,000"
"To:
Construction of Conacon - Deckan - Payeo Road, Barangay Bedbed, Mankayan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
8.154 Lane Km;
Allocation:
Php 153,000,000"
|
August 8, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Application of Pavement Markings along Baguio-Bontoc Road - K0262 + 000- K0263 + 183, Barangay Caponga, Tublay, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
1200 Lineal meters;
Allocation:
Php 2,700,000"
"To:
Application of Pavement Markings along Baguio-Bontoc Road - K0262 + 000- K0265 + 353, Barangay Caponga, Tublay, Benguet;
Type of Work:
CW1: Road Safety: Pavement Markings
CW2: Road Safety: Guardrails;
Physical Target:
CW1: 3400 Lineal meters
CW2: 451 Lineal meters;
Allocation:
Php 2,700,000"
|
August 8, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Ifugao 1st District Engineering Office |
"From:
Construction of Flood Control Structure along Nayon River, Sta. 12+350 - Sta. 13+115 (Left Side), Nayon, Lamut, Ifugao;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
765 Lineal meters;
Allocation:
Php 50,000,000"
"To:
Construction of Flood Control Structure along Nayon River, Sta. 12+350 - Sta. 13+200, Nayon, Lamut, Ifugao;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
827 Lineal meters;
Allocation:
Php 50,000,000"
|
August 7, 2024 |
2024 |
WIN4XY00331 |
GAA 2024 |
January 19, 2024 |
Region V |
Masbate 2nd District Engineering Office |
Project ID : P00800184LZ
UACS No : 310202101697000
FROM :
OO1 - Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads - Masbate - Cataingan - Placer Rd - K0009 + 055 - K0009 + 159
Physical Target :
CW1 - Road Widening - 0.208 Lane Km
TO :
OO1 - Ensure Safe and Reliable National Road System - Network Development - Road Widening Development - Road Widening - Secondary Roads - Masbate - Cataingan - Placer Rd - K0009 + 055 - K0009 + 076
Physical Target :
CW1 - Road Widening - 0.042 Lane Km
CW2 - Construction of Drainage Structure along Road - 42 Lineal meters |
August 7, 2024 |
2024 |
WIN4XY00330 |
GAA 2024 |
January 19, 2024 |
Region V |
Masbate 2nd District Engineering Office |
Project ID : P00800186LZ
UACS No : 310202101699000
FROM :
OO1 - Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads - Masbate - Cataingan - Placer Rd - K0009 + 264 - K0009 + 367
Physical Target :
CW1 - Road Widening - 0.103 Lane Km
TO :
OO1 - Ensure Safe and Reliable National Road System - Network Development - Road Widening - Secondary Roads - Masbate - Cataingan - Placer Rd - K0009 + 091 - K0009 + 101.5
Physical Target :
CW1 - Road Widening - 0.021 Lane Km
CW2 - Construction of Drainage Structure along Road - 21 Linear meters |
August 7, 2024 |
2024 |
|
GAA 2024 |
January 19, 2024 |
Region V |
Masbate 2nd District Engineering Office |
Project ID : P00802553LZ
UACS No : 310106101181000
FROM :
OO1 - Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstructure/ Upgrading of Damaged Paved Roads - Tertiary Roads - Masbate Circumferential Rd - K0004 + 000 - K0004 + 175
Physical Target :
CW1 - Rehabilitation of Paved Road - 0.7 Lane Km
TO :
OO1 - Ensure Safe and Reliable National Road System - Asset Preservation - Rehabilitation/ Reconstructure/ Upgrading of Damaged Paved Roads - Tertiary Roads - Masbate Circumferential Rd - K0004 + 444 - K0004 + 884
Physical Target :
CW1 - Rehabilitation of Paved Road - 0.88 Lane Km
CW2 - Road Safety - Street Lighting - 32 Number of Units |
August 7, 2024 |
2024 |
WIN4XY00339 |
GAA 2024 |
January 19, 2024 |
Region V |
Catanduanes District Engineering Office |
Project ID : P00824785LZ
UACS No : 320101112028000
FROM :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage System - Construction of Flood Control Structure at Brgy. Benticayan, Baras, Catanduanes
Physical Target :
CW1 - Construction of Flood Mitigation Structure - 186 Lineal meters
TO :
ORGANIZATIONAL OUTCOME 2 - Protect Lives and Properties Against Major Floods - Construction/ Maintenance of Flood Mitigation Structures and Drainage System - Construction of Flood Control Structure at Brgy. Benticayan, Baras, Catanduanes
Physical Target :
CW1 - Construction of Flood Mitigation Structure - 149 Lineal meters
|
August 7, 2024 |
2024 |
WIN4XY00337 |
GAA 2024 |
January 19, 2024 |
Region V |
Regional Office V |
Project ID : P00839453LZ
UACS ID : 3000224100036000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Coastal Roads/ Causeway for environmental protection/ conservation - Construction of Coastal Road, Barangay Población, Rapu-Rapu, Albay
Physical Target :
CW1 - Construction of Concrete Road - 1.968 Lane Km
CW2 - Construction of Road Slope Protection - 2,601.40
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Coastal Roads/ Causeway for environmental protection/ conservation - Construction of Coastal Road, Barangay Población, Rapu-Rapu, Albay
Physical Target :
CW1 - Construction of Concrete Road - 1.38 Lane Km
CW2 - Construction of Road Slope Protection - 2,033.20 Square meters
|
August 7, 2024 |
2024 |
WIN4XY00338 |
WIN4XY00338 |
January 19, 2024 |
Region V |
Camarines Norte Sub-District Engineering Office |
Project ID : P00848239LZ
UACS No : 300226113504000
FROM :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multipurpose Buildings, Brgy. Mambungalon, Basud, Camarines Norte
Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings
TO :
CONVERGENCE AND SPECIAL SUPPORT PROGRAM - Basic Infrastructure Program (BIP) - BIP - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multipurpose Buildings, Brgy. Mambungalon, Mercedes, Camarines Norte
Physical Target :
CW1 - Construction of Multi Purpose Building - 1 Number of Buildings |
August 7, 2024 |
2024 |
|
SR2024-01-008076 |
January 31, 2024 |
Region VIII |
Regional Office VIII |
OO1: Ensure Safe and Reliable National Road System
Asset Preservation – Preventive Maintenance – Primary Roads
AS PER GAA/ORIGINAL:
Daang Maharlika (LT) – K0906 + 569 – K0906 + 915
Physical Target: Allocation:
CW1- Preventive Maintenance of Road: P 14.94206 M
Asphalt Overlay: 1.384 Lane Km
EAO P 0.54194 M
Total P 15.484 M
AS MODIFIED:
Daang Maharlika (LT) – K0906 + 520 – K0906 + 915
Physical Target: Allocation:
CW1- Preventive Maintenance of Road: P 14.94206 M
Asphalt Overlay: 1.58 Lane Km
EAO P 0.54194 M
Total P 15.484 M
|
August 7, 2024 |
2024 |
|
SR2024-04-014756 |
April 12, 2024 |
Region VIII |
Regional Office VIII |
Convergence and Special Support Program
Special Road Fund – Motor Vehicle Users Charge (MVUC) as per R.A. 11239
AS PER GAA/ORIGINAL:
Installation of Solar LED Street Lights, and Signages along Tacloban City Bypass Road Extension, Phase 1, Barangay Tigbao, Tacloban City
Physical Target: Allocation:
CW1- Road Safety: P 46.575435 M
Road Lighting: 268.00 Number of Units
CW2- Road Safety:
Guardrails: 1,760.00 Lineal Meters P 49.924565 M
EAO P 3.5 M
Total P 100.00 M
AS MODIFIED:
Installation of Solar LED Street Lights, and Signages along Tacloban City Bypass Road Extension, Phase 1, Barangay Tigbao, Tacloban City
Physical Target: Allocation:
CW1- Road Safety: P 73.16921039 M
Road Lighting: 442.00 Number of Units
CW2- Road Safety:
Guardrails: 3,100.00 Lineal Meters P 23.33078961 M
EAO P 3.5 M
Total P 100.00 M
|
August 7, 2024 |
2024 |
WIN4E03584 |
SR2024-01-003732 |
January 29, 2024 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
"From:
Installation of Road Safety Devices along Shilan-Beckel Road, K0261+(-392) - K0266+403, La Trinidad, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
5514 Lineal Meter;
Allocation:
Php 125,000,000"
"To:
Installation of Road Safety Devices along Shilan-Beckel Road, K0261+(-392) - K0266+403, La Trinidad, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
535 Number of units;
Allocation:
Php 125,000,000"
|
August 7, 2024 |
2024 |
WIN4E03507 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
CAR - Regional Office |
"From:
Construction of Bultot, Balawag Flood Control along Chico River Balawag, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
802 Lineal meters;
Allocation:
Php 100,000,000"
"To:
Construction of Bultot, Balawag Flood Control along Chico River Balawag, Tabuk City, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
386 Lineal meters;
Allocation:
Php 100,000,000"
|
August 7, 2024 |
2024 |
WIN4E03515 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
CAR - Regional Office |
"From:
Construction of Apayao-Abulog River Basin River Flood Control Structure (Bagutong Section), Apayao Sta 28 + 310 - Sta 31 + 250 (R/S);
Type of Work:
Construction of Revetment;
Physical Target:
518 Lineal meters;
Allocation:
Php 50,000,000"
"To:
Construction of Apayao-Abulog River Basin River Flood Control Structure (Bagutong Section), Apayao Sta. 29 + 760 - Sta 30 + 110 (R/S);
Type of Work:
Construction of Revetment;
Physical Target:
218 Lineal meters;
Allocation:
Php 50,000,000"
|
August 7, 2024 |
2024 |
|
GAA FY 2024 |
January 1, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
Convergence and Special Support Program
SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Road, Barangay Binolo, Tanauan Leyte
Physical Target: Allocation:
CW1- Construction of Concrete Road: P 12.250 M
0.246 Lane Km
EAO P .250 M
Total P 12.50 M
AS MODIFIED:
Construction of Road, Barangay Binolo, Tanauan Leyte
Physical Target: Allocation:
CW1- Construction of Concrete Road: P 12.250 M
1.20 Lane Km
EAO P .250 M
Total P 12.250 M
|
August 7, 2024 |
2024 |
|
GAA FY 2024 |
January 1, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
Convergence and Special Support Program
SIPAG - Access Roads and/or Bridges from the National Road/s leading to Major/ Strategic Public Buildings/ Facilities
AS PER GAA/ORIGINAL:
Construction of Road, San Antonio to Camire, Tanauan Leyte
Physical Target: Allocation:
CW1- Construction of Concrete Road: P 12.250 M
0.246 Lane Km
EAO P .250 M
Total P 12.50 M
AS MODIFIED:
Construction of Road, San Antonio to Camire, Tanauan Leyte
Physical Target: Allocation:
CW1- Construction of Concrete Road: P 12.250 M
1.50 Lane Km
EAO P .250 M
Total P 12.250 M
|
August 7, 2024 |
2024 |
WIN4XY00325 |
GAA FY 2024 |
January 1, 2024 |
Region VIII |
Leyte 1st District Engineering Office |
OO1: Ensure Safe and Reliable National Road System
Network Development – Road Widening – Tertiary Roads
AS PER GAA/ORIGINAL:
Tacloban-Baybay South Rd (Tanauan Sect) - K0921 + (-108.87) - K0921 + 356.69, K0921 + (-697) - K0921 + (-132)
Physical Target: Allocation:
CW1- Road Widening: P 23.69248 M
2.061 Lane Km
EAO P 0.48352 M
Total P 24.176 M
AS MODIFIED:
Tacloban-Baybay South Rd (Tanauan Sect) - K0921 + (-697) - K0921 + (-132)
Physical Target: Allocation:
CW1- Road Widening: P 13.20771917 M
1.130 Lane Km
CW2 – Construction of Drainage Structure: P 10.48476082 M
Along Road: 174 Lineal Meters
EAO P 0.48352 M
Total P 24.176 M
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"
"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"
"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Baguio-Bontoc Rd - K0317 + 468 - K0317 + 566;
Type of Work:
Rehabilitation /Major Repair of Road Slope Protection Structure;
Physical Target:
392.17 Square meters;
Allocation:
Php 4,310,000"
"To:
Baguio-Bontoc Rd - K0322+860 - K0323+037;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
716 Square meters;
Allocation:
Php 4,310,000"
|
August 6, 2024 |
2024 |
WIN4E03556 |
SR2024-03-012873 |
March 5, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Construction of Sagpat, Kibungan, Benguet to Santol, La Union Road (Phase II), Kibungan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
16.938 Lane Km;
Allocation:
Php 153,000,000"
"To:
Construction of Sagpat, Kibungan, Benguet to Santol, La Union Road (Phase II), Kibungan, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
6.858 Lane Km;
Allocation:
Php 153,000,000"
|
August 6, 2024 |
2024 |
WIN4E03557 |
SR2024-03-012871 |
March 5, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Construction of Poblacion Dalingoan - Sinacbat Road (Phase II), Bakun, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
16.938 Lane Km;
Allocation:
Php 153,000,000"
"To:
Construction of Poblacion Dalingoan - Sinacbat Road (Phase II), Bakun, Benguet;
Type of Work:
Construction of Gravel Road;
Physical Target:
6.30 Lane Km;
Allocation:
Php 153,000,000"
|
August 6, 2024 |
2024 |
WIN4E03559 |
SR2024-02-008368 |
February 2, 2024 |
Cordillera Administrative Region |
Benguet 2nd District Engineering Office |
"From:
Construction of Flood Mitigation Structure along Agno River, Loo Section, Sta. 0+432 - Sta. 1+836 (R.S), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
1404 Lineal meters;
Allocation:
Php 65,000,000"
"To:
Construction of Flood Mitigation Structure along Agno River, Loo Section, Sta. 0+432 - Sta. 1+043 (LS), Sta. 0+767 - Sta. 1+021 (RS), Buguias, Benguet;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
865 Lineal meters;
Allocation:
Php 65,000,000"
|
August 6, 2024 |
2024 |
|
SR2024-05-016179 |
May 20, 2024 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
"From:
Rehabilitation of Road, Bayabas Central - Calamay Road, Barangay Bayabas, Sablan, Benguet;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 0.240 Lane Km
CW2: 341.8 Square meter;
Allocation:
Php 5,000,000"
"To:
Basic Infrastructure Program (BIP) - Access Roads and/or Bridges from the National
Road/s leading to Major/ Strategic Public Buildings/ Facilities;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 0.240 Lane Km
CW2: 416.14 Square meters;
Allocation:
Php 5,000,000"
|
August 6, 2024 |
2024 |
WIN4E03541 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Mountain Province 2nd District Engineering Office |
"From:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0426 + 280 - K0426 + 580;
Type of Work:
Reconstruction to Concrete Pavement;
Physical Target:
0.6 Lane Km;
Allocation:
Php 6,008,000"
"To:
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd - K0426 + 280 - K0426 + 400;
Type of Work:
CW1: Reconstruction of Concrete Pavement
CW2: Construction of Road Slope Protection Structures;
Physical Target:
CW1: 0.240 Lane Km
CW2: 360 Square meters;
Allocation:
Php 6,008,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
3.552 Lane Km;
Allocation:
Php 80,000,000"
"To:
Tabuk-Banawe via Tanudan-Barlig Rd, Kalinga;
Type of Work:
CW1: Construction of Gravel Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 5.2 Lane Km
CW2: 4566 Square meters;
Allocation:
Php 80,000,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect) - K0505 + 722 - K0505 + 899, K0514 + 521 - K0514 + 621;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
277 Lineal meters;
Allocation:
Php 10501000"
"To:
Mt Province Bdry-Calanan-Pinukpuk-Abbut Rd (Calanan-Pinukpuk Sect) - K0505 + 722 - K0506 + 044 & K0506 + 080 - K0506 + 280, K0514 + 521 - K0514 + 621;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
652 Lineal meters;
Allocation:
Php 10,501,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + 321 - K0523 + 100;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
760 Lineal meters;
Allocation:
Php 38,257,000"
"To:
Rizal Natl Rd (Liwan West-Babalag-Macutay Sect) - K0522 + 321 - K0523 + 640, K0522 + 121 - K0523 + 220;
Type of Work:
Construction of Drainage Structure along Road;
Physical Target:
2418 Lineal Meters;
Allocation:
Php 38,257,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Flood Control Structure at Liwan East-Calaocan along Pangol Creek, Sta. 11+060-Sta. 11+160, Barangay Liwan East, Calaocan, Arsenio, Rizal, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
82.05 Lineal meter;
Allocation:
Php 10,000,000"
"To:
Construction of Flood Control Structure at Liwan East-Calaocan along Pangol Creek, Sta. 11+060-Sta. 11+320, Barangay Liwan East, Calaocan, Arsenio, Rizal, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
260 Lineal meters;
Allocation:
Php 10,000,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Rehabilitation of Flood Control Structure, Purok Riverside, Poblacion Taga, Pinukpuk, Kalinga;
Type of Work:
Construction of Flood Mitigation Structure;
Physical Target:
205.124 Lineal meters;
Allocation:
Php 25,000,000"
"To:
Rehabilitation of Flood Control Structure, Purok Riverside, Poblacion Taga, Pinukpuk, Kalinga;
Type of Work:
Rehabilitation/ Major Repair of Flood Control Structure;
Physical Target:
322 Lineal Meters;
Allocation:
Php 25,000,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Bulo-Makilo Road (Bulo Section), Barangay Bulo, Tabuk City, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.871 Lane Km;
Allocation:
Php 50,000,000"
"To:
Construction of Bulo-Makilo Road (Bulo Section), Barangay Bulo, Tabuk City, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
6.032 Lane Km;
Allocation:
Php 50,000,000"
|
August 6, 2024 |
2024 |
|
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Seet-Mabaca-Taloctoc-Mangali Road, Tanudan, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.644 Lane Km;
Allocation:
Php 37,000,000"
"To:
Construction of Seet-Mabaca-Taloctoc-Mangali Road, Tanudan, Kalinga;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: 2.124 Lane Km
CW2: 1112 Square meters;
Allocation:
Php 37,000,000"
|
August 6, 2024 |
2024 |
WIN4E03544 |
GAA 2024 |
January 1, 2024 |
Cordillera Administrative Region |
Lower Kalinga District Engineering Office |
"From:
Construction of Banagao-Mangali Road, Tanudan, Kalinga;
Type of Work:
Construction of Concrete Road;
Physical Target:
0.348 Lane Km;
Allocation:
Php 20,000,000"
"To:
Construction of Banagao-Mangali Road, Tanudan, Kalinga;
Type of Work:
CW1: Construction of Concrete Road
CW2: Construction of Road Slope Protection Structure;
Physical Target:
CW1: .2 Lane Km
CW2: 9.858 Square meters;
Allocation:
Php 20,000,000"
|
August 6, 2024 |
2024 |
WIN4E03578 |
SR2024-01-005186 |
January 30, 2024 |
Cordillera Administrative Region |
CAR - Regional Office |
"From:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0345 + 240 - K0345 + 445;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
5882.353 Square meters;
Allocation:
Php 100,000,000"
"To:
Banaue-Mayoyao-A Lista-Isabela Bdry Rd - K0345 + 240 - K0345 + 340;
Type of Work:
Construction of Road Slope Protection Structure;
Physical Target:
3850 Square meters;
Allocation:
Php 100,000,000"
|
August 6, 2024 |
2024 |
WIN4E03596 |
SR2024-01-003715 |
January 29, 2024 |
Cordillera Administrative Region |
Benguet 1st District Engineering Office |
"From:
Installation of Road Safety Devices along Pico-Lamtang Road, K0256 + 000 - K0261 + 000 - K0261 + 1965, La Trinidad, Benguet;
Type of Work:
Road Safety: Pavement Markings;
Physical Target:
6928 Lineal Meter;
Allocation:
Php 125,000,000"
"To:
Installation of Road Safety Devices along Pico-Lamtang Road, K0255+(-555) - K0261 + 000 - K0261 + 1965, La Trinidad, Benguet;
Type of Work:
Road Safety: Roadway Lighting;
Physical Target:
525 Number of units;
Allocation:
Php 125,000,000"
|
August 5, 2024 |
2024 |
WIN4XY00332 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0018+541 - K0018+1059, K0019+000 - K0019+329 |
August 5, 2024 |
2024 |
WIN4XY00336 |
FY 2024 GAA |
December 20, 2023 |
Region III |
Bulacan 2nd District Engineering Office |
Asset Preservation Program - Preventive Maintenance - Primary Roads
Manila North Road - K0021+587 - K0021+877, K0022+000- K0022+060, K0022+125 - K0022+492, K0023+801 - K0023+931 |