The project is a 4-lane 45.29 km. closed-system tolled expressway connecting CAVITEX and SLEX. The project will start from the CAVITEX in Kawit, Cavite and end at the SLEX-Mamplasan Interchange in Biñan, Laguna. The project will have the following subsections:
Project Subsections | Length (km) | |
1 | Cavitex Connection to Open Canal Interchange | 8.9 |
2 | Open Canal Interchange to Governor’s Drive Interchange | 10.5 |
3 | Governor’s Drive Interchange to Silang (Aguinaldo) Interchange | 7.9 |
4 | Silang (Aguinaldo) Interchange to Silang East Interchange | 2.9 |
5 | Silang East Interchange to Sta. Rosa-Tagaytay Interchange | 5.8 |
6 | Sta. Rosa-Tagaytay Interchange to Laguna Boulevard Interchange | 1.8 |
7 | Laguna Boulevard Interchange to Laguna Technopark Interchange | 4.2 |
8 | Laguna Technopark Interchange to Mamplasan Toll Barrier | 2.9 |
PPP Scheme: Build-Transfer-Operate
-Private sector to finance, construct, operate and maintain the entire 45.292kms Cavite-Laguna Expressway (CALAx)
- Concession Period: 35 years (including 5 years design and construction)
| (Tirona Highway to the end of Greenfield Development Corporation Property near Mamplasan Exit, Laguna) |
Right of Way: | 60 meters, except for Laguna Techno Park &Laguna Boulevard 40 meters, Greenfield Development Corporation 50 meters |
Interchanges: | 8 grade separated interchanges and 1 toll barrier |
Bridges: | 12,207 meters inclusive of 4,618 meters of viaduct |
This project aims to:
- support national development policy and provide efficient transport facilities for the Eco-zones in Cavite and Laguna;
- reduce traffic congestion particularly in Governor’s Drive, Aguinaldo Highway and Sta. Rosa-Tagaytay Road which are heavily congested;
- improve competitiveness of Region IV-A/CALABARZON as an investment destination.
At the end of construction, the project is expected to:
- Reduce travel time from CAVITEX to SLEX by about 45 minutes
MPCALA Holdings Inc.
Activities | Amount (Billion) |
Civil Works | P 25.425 |
Right-of-Way | P 10.201 |
Independent Consultant (50%) | P 0.056 |
Total | P 35.682 |
Subsections 6, 7 and 8 (Sta. Rosa to Mamplasan) were partially opened to traffic on October 30, 2019.
TOP was issued last Feb 10, 2020 for Subsections 6, 7 and 8.
Contractor for Cavite Segment Subsection 1 already mobilized
Overall accomplishment for construction on Laguna segment is 100% , Sub-section 5-83.43% , Sub-section 4-11.346% and 9.908% for Cavite Segment as of January 21, 2021 based on Revised Project Schedule.
Activities | Date |
Construction Start Date | July 2017 |
Completion | July 2022 |