TAGUM–DAVAO–GENERAL SANTOS HIGH STANDARD HIGHWAY

Widening to 4–lane divided road for Tagum–Davao Road, flyover construction within Davao City, construction of second diversion road, widening of Davao, Digos, and Gen. Santos Section and construction of Gen. Santos City Circumferential Road.

Php 2.675 B

  • Business Case Study completed. Final Report was submitted last 15 May 2013
  • Final Business Case Report concludes that although the four-lane PPP road is economically feasible based on traffic benefits, still, it is not yet financially feasible as a toll road. Even at 50%-50% Investor-GOP cost sharing and a relatively high toll rate of P6/km or P242 for the whole stretch, the toll collection cannot pay off the cost of investment, as a result of the study of United Technologies Consolidated Partnership (UTCP) Consulting Engineers.
  • It is recommended in the Final Report that the project road is suitable for an ODA funding at the time being as the study indicates very high economic indicators.