SOUTHEAST METRO MANILA EXPRESSWAY (C6) PROJECT

Project Description: 
    • The Southeast Metro Manila Expressway (C6) Project is a a toll road project with approximately 32.664 km that is intended to run from Skyway/FTI in Taguig City to Batasan Complex in Quezon City. The project is divided into six sections namely:       

SEGMENT

SECTION

LENGTH (km.)

Segment 1

Section 1: Skyway/FTI - C5/Diego Silang

        • Section 1A: Skyway to FTI
        • Section 1B: FTI to C5/Diego Silang

2.387

Section 2: C5/Diego Silang - C6/Taguig

3.202

Section 3: C6/Taguig - Ortigas Ave. Ext.

11.783

Segment 2

Section 4: Ortigas Ave. Ext. - Marcos Highway

5.337

Section 5: Marcos Highway - Tumana Bridge

6.900

Section 6: Tumana Bridge - Batasan Complex

3.055

The general features of the Project are shown below:

Project Road Type                          : Combination of elevated and At-grade

Carriageway lanes                          : 2 x 3 lanes

Design speed expressway               : 80 kph (60 kph)

Rampway design speed                   : 40 kph

Number of ramps                              : 28

Project Objectives: 

The project aims to:

  • Connect the South Luzon Expressway (SLEX) Skyway via FTI towards Batasan Complex in Quezon City
Project Benefits: 

At the end of construction, the project is expected to:

  • Provide an alternate route from Parañaque to Quezon City passing thru the developing areas of Taguig, Taytay, Antipolo and San Mateo to decongest EDSA, C5 and other major arteries of Metro Manila and Rizal.
Project Concessionaire: 
  • Citra Intercity Tollways Inc. (CITI)
Project Cost: 

• PhP 31.32 Billion (based on Basic Design)
• PhP 45.29 Billion (based on Approved FED)

Project Status: 
  • Right-of-Way Acquisition for Section 1B, ongoing.

Structures: 134 Agreement to Demolish and Remove Improvement (ADRI) documents; 121 signed by claimants and already with Advances and Reimbursement Agreement (ARA)

Lots: 77 Dead of Absolute Sales (DOAS); 41 already prepared, 18 of which have been signed by claimants and with ARA.  

  • Civil Works, ongoing

Section 1: Construction on workable areas at C5 (Piers 61 to 66),
100 % accomplishment
 
Ongoing restoration of test pits. Remaining test pitting on bored pile locations at
Pier 00 in Arca South, and Piers 71 and 72 along C5 Road Taguig, which are based
on submitted work requests, continuously took place.

Project Alignment: 
Project Timeline: 

Construction Schedule:

Section 1: 2018 - 2022