EMERGENCY ASSISTANCE FOR THE RECONSTRUCTION AND RECOVERY OF MARAWI (EARRM) ADB LOAN NO. 3769-PHI

 PROJECT OVERVIEW:                                                                                  

 

NAME OF PROJECT

OUTPUT 2: Reconstruction and Development Plan for a Greater Marawi – Stage 2

Value (LOAN)

 

Original (USD)

Original (PhP)

ADB

100.00 M

5,712 M

GOP

17.65 M

1,123 M

TOTAL

117.65 M

6,835 M

Loan No.

EAL-ADB Loan No. 3769-PHI

Date of NEDA Board Approval

December 13, 2018

Date of Signing

December 17, 2018

Date of Effectiveness

December 27, 2018

Loan Validity

June 30, 2024 (Original)

December 31, 2027 (Revised)

Implementation Schedule

February 2020–September 2022 (Original)

February 2020-June 2027 (Revised)

Remarks

For 57 months extension of the implementation duration and 42 months loan validity

 

 

 

 

 

 

 

 

 

 

 

 

PROJECT DESCRIPTION:

Ø    The Reconstruction and Development Plan for a Greater Marawi is a Master Development Plan geared towards inclusive economic growth for Marawi City and its peripheral areas. The plan advocates the role of infrastructure Development as a catalyst in developing new economic centers and viable living spaces.

Components of the project:    

                               ·     Transcentral Road Phase IV (16.82km)

·      Construction of Malabang Viaduct

·      Construction of four (4) Bridges

              ·      Construction of Main Drainages, Open Channels and two  (2) Connecting Bridges

·      Slope Protection Works

 

PROJECT IMPACT:

 Ø  Provide a viable solution in fully utilizing the capability of various infrastructure projects to serve as catalysts in building back a better Marawi.

 Ø  The project envisions to spark development in the peripheral areas referencing from Marawi City centered in the ideas of connectivity and community building. This shall be made evident through the improvement in the social, institutional and economic development sectors of the project areas.

 

 

 

 

Road Name

NetLength (km)

Contractor

Contract Amount

Million PHP

Implementation

 Period

Progress

CIVIL WORKS

CP1A

 Rehabilitation of Existing Trans-central Roads

5.29 km

Fiat Construction Services

177.75

Dec 10, 2021 – Dec 24, 2023

89.51%

CP1B

Rehabilitation of Existing Mindanao State University Roads

4.71 km

Kouzbary Builders

161.06

Dec 15, 2021 – Dec 30, 2023

89.40%

CP5

Slope Protection (Marawi-Bito Road) Upper and Lower Slopes; TR-28 Rehabilitation of Road along Marawi-Bito Road; and TR-29 Rehabilitation of Lasureco Road

2.51 km (roads), 1.30 km (slope protection)

 

Kouzbary Builders/MMA Achiever Construction Development Corporation (JV)

 

200.60

Aug 22, 2023 – Sept 20, 2024

13.68%

CP4A

 Construction of Rorogagus Bridge

0.51 km

-

214.96

Jan 2024 – Feb 2025

Perfection of Contract is on process/approval.

PROCUREMENT STAGE

CP4B

Construction of Cabasaran Bridge, Box Culvert (Guimba Bridge) and Kormatan Matampay Bridge

0.66 km

-

205.30

Feb 2024 – Jul 2024

For Procurement

CP1C

New Trans-central Roads and Drainage

4.31 km

-

812.57

Feb 2024 – Jul 2024

For Procurement

DED STAGE

CP2

Construction of Malabang Viaduct

2.20 km

-

2,134.84

Mar 2024 – Aug 2024

94.00% DED Completed

CP3

Construction of Main Drainage Channels

6.212 km (drainage), 0.09 km (bridge), 0.392 (roads)

-

1,153.66

Mar 2024 – Aug 2024

95.00% DED Completed