COST ESTIMATES FOR WORK ITEM OF PROJECTS
as of October 2020
Table 10
               
A. Preventive Maintenance            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
NCR CAR REGION I REGION II REGION III REGION IV-A
ASPHALT/ CONCRETE Overlay 50mm      8,172,402.92     10,288,351.55      8,995,841.64      9,589,093.50      8,131,888.29      8,015,035.50
Overlay 80mm     12,993,692.16     16,314,714.42     14,279,283.72     15,215,192.05     12,951,293.47     12,737,288.92
Overlay 100mm     15,986,734.76     20,210,009.51     17,618,095.45     18,784,040.38     15,916,258.06     15,668,637.42
               
ASPHALT Overlay 50mm with minor corrections      8,857,667.05     10,994,079.40      9,668,324.00     10,228,039.64      8,780,168.66      8,714,634.67
(Assumption : Half of the existing pavement w/ corrections) Overlay 80mm with minor corrections     13,678,956.29     17,020,442.28     14,951,766.08     15,854,138.19     13,599,573.84     13,436,888.09
Overlay 100mm with minor corrections     16,671,998.88     20,915,737.37     18,290,577.80     19,422,986.51     16,564,538.43     16,368,236.58
               
CONCRETE Reblocking with overlay 50mm     12,054,009.03     14,704,317.65     13,028,351.17     14,032,639.49     12,127,043.97     11,845,356.54
(Assumption : 30% for reblocking) Reblocking with overlay 80mm     16,875,298.27     20,730,680.53     18,311,793.26     19,658,738.04     16,946,449.15     16,567,609.96
Reblocking with overlay 100mm     19,868,340.87     24,625,975.62     21,650,604.98     23,227,586.37     19,911,413.74     19,498,958.45
               
A. Preventive Maintenance            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT/ CONCRETE Overlay 50mm     12,267,648.14     13,022,569.93     10,282,033.10     10,452,415.18     10,881,704.52     12,773,802.77
Overlay 80mm     19,514,161.58     20,720,410.37     16,305,236.30     16,625,462.27     17,286,323.94     20,322,321.19
Overlay 100mm     24,188,069.61     25,686,880.58     20,175,590.11     20,513,932.58     21,371,277.23     25,176,350.20
               
ASPHALT Overlay 50mm with minor corrections     12,967,901.69     13,695,462.99     10,930,928.30     11,117,022.65     11,536,085.29     13,486,367.73
(Assumption : Half of the existing pavement w/ corrections) Overlay 80mm with minor corrections     20,214,415.13     21,393,303.43     16,954,131.50     17,290,069.75     17,940,704.72     21,034,886.15
Overlay 100mm with minor corrections     24,888,323.17     26,359,773.64     20,824,485.30     21,178,540.06     22,025,658.01     25,888,915.16
               
CONCRETE Reblocking with overlay 50mm     17,170,125.80     17,180,335.78     14,656,744.76     15,250,564.24     15,857,856.91     17,592,745.43
(Assumption : 30% for reblocking) Reblocking with overlay 80mm     24,416,639.24     24,878,176.22     20,679,947.95     21,423,611.33     22,262,476.33     25,141,263.85
Reblocking with overlay 100mm     29,090,547.28     29,844,646.43     24,550,301.76     25,312,081.64     26,347,429.62     29,995,292.87
               
A. Preventive Maintenance            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
ASPHALT/ CONCRETE Overlay 50mm     11,617,691.74     12,166,610.15     10,964,407.83     16,927,600.51     10,909,318.58  
Overlay 80mm     18,474,472.59     19,308,512.29     17,414,020.65     27,001,232.36     17,341,476.14  
Overlay 100mm     22,866,666.12     23,954,411.92     21,532,340.68     33,496,689.96     21,446,624.04  
               
ASPHALT Overlay 50mm with minor corrections     12,330,849.83     12,819,274.19     11,665,547.32     17,621,828.60     11,588,386.38  
(Assumption : Half of the existing pavement w/ corrections) Overlay 80mm with minor corrections     19,187,630.68     19,961,176.34     18,115,160.13     27,695,460.45     18,020,543.94  
Overlay 100mm with minor corrections     23,579,824.21     24,607,075.97     22,233,480.16     34,190,918.05     22,125,691.83  
               
CONCRETE Reblocking with overlay 50mm     16,176,306.91     16,398,545.42     15,328,419.63     21,660,726.27     15,316,505.56  
(Assumption : 30% for reblocking) Reblocking with overlay 80mm     23,033,087.76     23,540,447.57     21,778,032.45     31,734,358.12     21,748,663.13  
Reblocking with overlay 100mm     27,425,281.29     28,186,347.19     25,896,352.48     38,229,815.72     25,853,811.02  
               
B. Rehabilitation/Reconstruction            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
NCR CAR REGION I REGION II REGION III REGION IV-A
ASPHALT Recon AC 50mm     13,790,419.63     16,167,209.13     13,201,321.67     14,450,701.85     13,357,942.27     12,779,196.79
(Assumption : with base failure) Recon AC 80mm     18,484,134.14     22,036,899.47     18,403,574.65     19,965,034.78     18,078,043.49     17,433,279.03
Recon AC 100mm     21,379,155.98     25,813,957.72     21,675,857.31     23,446,195.67     20,963,523.40     20,306,941.58
               
CONCRETE Reconstruction PCC 230mm     15,312,389.63     16,268,571.49     14,424,454.86     16,090,990.97     14,563,526.66     13,482,472.33
(Assumption : with base failure) Reconstruction PCC 280mm     17,427,329.66     18,616,016.77     16,528,448.59     18,481,728.64     16,600,391.26     15,493,144.72
Reconstruction PCC 300mm     18,288,589.18     19,573,562.00     17,386,166.03     19,455,151.75     17,433,237.41     16,311,784.16
               
ASPHALT Upgrade to Concrete 230mm     13,515,359.48     15,087,229.27     12,774,669.87     14,544,153.72     12,738,975.55     12,000,831.29
Upgrade to Concrete 280mm     15,908,212.13     17,782,570.30     15,059,939.45     17,182,865.31     14,994,211.30     14,167,460.08
Upgrade to Concrete 300mm     16,884,239.95     18,883,618.98     15,992,587.30     18,258,681.75     15,917,298.00     15,050,571.49
               
CONCRETE Reblocking 230mm      6,725,727.40      7,617,044.34      6,978,149.16      7,682,878.32      6,882,186.47      6,626,598.71
(Assumption : 50% reblocking) Reblocking 280mm      7,777,432.77      8,785,139.39      8,024,519.41      8,872,599.50      7,894,938.05      7,626,301.30
Reblocking 300mm      8,208,877.75      9,264,868.34      8,454,331.72      9,360,320.51      8,312,455.64      8,036,593.31
               
B. Rehabilitation/Reconstruction            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT Recon AC 50mm     17,630,947.27     18,671,489.54     15,833,692.20     15,887,306.75     16,347,251.06     18,726,399.78
(Assumption : with base failure) Recon AC 80mm     24,736,419.21     26,236,160.70     21,720,594.34     21,948,882.22     22,610,989.27     26,126,860.28
Recon AC 100mm     29,302,950.25     31,100,720.22     25,486,276.36     25,749,902.28     26,588,638.73     30,868,736.76
               
CONCRETE Reconstruction PCC 230mm     18,420,669.17     15,202,525.51     16,511,983.61     17,558,212.37     18,492,489.57     18,174,505.89
(Assumption : with base failure) Reconstruction PCC 280mm     21,078,490.15     17,382,100.08     18,779,703.50     20,130,720.84     21,202,397.08     20,773,239.73
Reconstruction PCC 300mm     22,160,755.44     18,272,238.20     19,702,939.99     21,179,533.62     22,303,108.78     21,830,586.95
               
ASPHALT Upgrade to Concrete 230mm     16,070,710.64     13,922,236.13     14,342,973.10     15,541,287.47     16,491,079.51     15,943,264.58
Upgrade to Concrete 280mm     19,027,496.18     16,398,070.97     16,902,876.84     18,354,868.59     19,504,281.96     18,857,393.25
Upgrade to Concrete 300mm     20,233,291.02     17,410,454.79     17,946,819.64     19,503,306.05     20,730,251.93     20,045,020.48
               
CONCRETE Reblocking 230mm      8,409,618.09      7,180,010.78      7,561,669.22      8,271,218.18      8,576,679.92      8,295,563.84
(Assumption : 50% reblocking) Reblocking 280mm      9,732,916.20      8,264,193.17      8,689,863.38      9,551,827.87      9,926,017.81      9,589,321.62
Reblocking 300mm     10,274,965.55      8,710,159.78      9,152,537.25     10,077,234.34     10,477,299.79     10,118,904.37
               
B. Rehabilitation/Reconstruction            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
ASPHALT Recon AC 50mm     18,069,136.74     17,217,753.21     16,417,669.01     22,974,701.93     16,345,196.18  
(Assumption : with base failure) Recon AC 80mm     24,757,916.92     24,243,186.14     22,746,001.95     32,890,578.60     22,651,159.70  
Recon AC 100mm     29,024,072.12     28,797,989.71     26,770,362.46     39,267,212.32     26,658,905.80  
               
CONCRETE Reconstruction PCC 230mm     17,484,735.41     15,208,421.10     16,163,327.36     17,816,399.55     16,323,479.72  
(Assumption : with base failure) Reconstruction PCC 280mm     19,854,745.98     17,439,981.40     18,442,024.33     20,324,307.46     18,659,673.14  
Reconstruction PCC 300mm     20,822,134.95     18,348,631.58     19,372,786.83     21,345,804.73     19,611,688.23  
               
ASPHALT Upgrade to Concrete 230mm     15,313,273.75     13,996,939.15     14,267,844.12     15,858,508.59     14,525,583.51  
Upgrade to Concrete 280mm     18,042,227.66     16,491,216.48     16,809,717.12     18,706,084.56     17,136,843.26  
Upgrade to Concrete 300mm     19,157,828.78     17,508,280.64     17,849,191.94     19,867,818.98     18,202,453.86  
               
CONCRETE Reblocking 230mm      7,857,120.18      7,312,120.53      7,557,647.36      8,140,171.51      7,604,650.25  
(Assumption : 50% reblocking) Reblocking 280mm      9,036,493.63      8,422,234.24      8,691,371.90      9,388,513.09      8,767,105.21  
Reblocking 300mm      9,521,155.49      8,877,616.70      9,157,699.82      9,900,178.42      9,244,074.92  
               
C. Road Upgrading            
               
LEVEL OF IMPROVEMENT SCOPE OF WORK UNIT COST/KM. (PESOS)
FLAT TERRAIN
NCR CAR REGION I REGION II REGION III REGION IV-A
GRAVEL TO ASPHALT AC 50mm     13,686,968.21     15,934,826.60     12,798,586.94     14,154,545.92     13,126,067.57     12,213,697.24
AC 80mm     18,567,189.90     22,025,380.60     18,127,327.14     19,834,329.35     17,997,528.89     16,976,769.35
AC 100mm     21,584,964.43     25,948,510.74     21,481,393.18     23,423,723.22     20,981,494.49     19,920,285.55
               
GRAVEL TO CONCRETE PCC 230mm     15,872,183.66     16,729,271.94     14,378,157.76     16,307,370.22     14,836,153.75     13,149,750.51
PCC 280mm     18,290,639.53     19,350,612.31     16,700,325.28     18,949,253.71     17,139,218.93     15,338,022.01
PCC 300mm     19,273,854.10     20,417,898.31     17,644,942.29     20,023,041.38     18,078,521.45     16,226,909.32
               
LEVEL OF IMPROVEMENT SCOPE OF WORK UNIT COST/KM. (PESOS)
FLAT TERRAIN
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
GRAVEL TO ASPHALT AC 50mm     17,931,327.02     18,370,045.04     15,992,447.81     15,837,425.55     16,462,501.89     19,004,406.26
AC 80mm     25,243,592.90     26,125,654.50     22,079,802.63     22,066,515.29     22,931,031.44     26,619,995.81
AC 100mm     29,946,590.25     31,115,995.04     25,977,430.46     25,977,152.52     27,043,795.25     31,504,034.54
               
GRAVEL TO CONCRETE PCC 230mm     19,624,653.88     15,480,186.94     17,491,361.95     18,141,561.26     19,419,403.65     19,368,325.88
PCC 280mm     22,677,860.03     17,910,880.15     20,123,983.39     21,023,067.82     22,481,210.05     22,358,367.77
PCC 300mm     23,919,709.97     18,901,476.82     21,194,176.69     22,195,971.17     23,723,669.74     23,573,635.37
               
LEVEL OF IMPROVEMENT SCOPE OF WORK UNIT COST/KM. (PESOS)  
FLAT TERRAIN  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
GRAVEL TO ASPHALT AC 50mm     18,417,138.57     16,764,416.76     16,366,095.11     23,161,594.21     16,263,880.67  
AC 80mm     25,346,610.05     23,959,801.54     22,873,614.88     33,303,633.17     22,754,923.59  
AC 100mm     29,772,245.48     28,625,853.22     27,015,632.39     39,829,949.86     26,884,315.66  
               
GRAVEL TO CONCRETE PCC 230mm     18,851,086.29     15,206,598.78     16,775,798.50     18,906,609.56     16,908,654.66  
PCC 280mm     21,634,667.38     17,654,521.11     19,363,585.66     21,786,519.04     19,548,920.89  
PCC 300mm     22,769,048.69     18,649,230.57     20,418,526.72     22,958,014.51     20,623,039.19  
D. Flooded Sections (Raising of Grade and Drainage)          
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
NCR CAR REGION I REGION II REGION III REGION IV-A
ASPHALT AC 50mm     42,875,356.08     42,958,508.72     36,580,790.80     39,239,775.10     40,711,856.15     38,255,671.16
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) AC 80mm     47,803,353.78     49,079,124.29     41,922,359.15     44,936,969.87     45,622,348.78     43,025,499.75
AC 100mm     50,861,369.11     53,031,088.26     45,293,755.47     48,547,049.43     48,641,872.10     45,982,398.77
               
CONCRETE PCC 230mm     45,375,844.24     43,964,010.96     38,267,942.91     41,529,222.43     42,690,644.28     39,263,391.65
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) PCC 280mm     47,891,783.53     46,654,231.05     40,630,234.42     44,219,554.15     45,079,239.46     41,481,897.00
PCC 300mm     48,915,084.26     47,750,196.25     41,592,027.08     45,313,872.88     46,053,945.07     42,384,012.50
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
ASPHALT AC 50mm     48,925,266.10     49,875,619.68     45,299,690.86     48,871,510.47     49,743,093.19     46,014,526.70
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) AC 80mm     56,289,184.91     57,674,625.95     51,433,139.82     55,153,510.08     56,255,863.64     53,667,623.47
AC 100mm     61,035,196.95     62,702,373.80     55,370,824.56     59,108,449.15     60,406,751.38     58,585,205.15
               
CONCRETE PCC 230mm     50,958,100.67     47,275,201.26     47,108,607.20     51,525,005.61     52,995,290.69     46,632,867.51
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) PCC 280mm     54,115,684.44     49,796,275.77     49,838,051.50     54,514,011.40     56,149,236.98     49,703,616.50
PCC 300mm     55,400,394.45     50,824,125.11     50,948,147.08     55,731,061.95     57,429,665.97     50,952,272.41
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
ASPHALT AC 50mm     50,396,168.45     45,442,607.01     48,969,649.31     56,818,770.81     45,686,178.79  
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) AC 80mm     57,373,805.55     52,680,938.99     55,529,950.08     67,011,529.48     52,216,239.22  
AC 100mm     61,840,403.66     57,384,958.94     59,715,895.84     73,580,238.72     56,380,489.45  
               
CONCRETE PCC 230mm     51,150,103.28     44,175,957.50     49,726,459.46     52,897,694.55     46,596,021.51  
(Assumption : raising of grade by 1.00 meter & removal/ replacement of RCPC at both sides) PCC 280mm     54,032,873.48     46,715,479.09     52,420,873.51     55,880,426.29     49,320,216.79  
PCC 300mm     55,208,062.84     47,748,002.18     53,519,588.20     57,094,159.69     50,429,038.62  
E. Drainage and Slope Protection            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/L.M. (PESOS)
NCR CAR REGION I REGION II REGION III REGION IV-A
SLOPE PROTECTION (Per Linear Meter) Grouted Riprap (H=3.00)             6,281.75             5,164.41             4,938.56             5,479.12             5,344.77             4,887.67
Stone Masonry (H=3.00)           14,391.54           12,838.63           12,184.53           13,396.44           12,710.10           11,886.54
               
DRAINAGE                        (Per Linear Meter) Grouted Line Canal (2.01x.57), v-shaped             2,256.28             2,024.78             1,864.91             2,037.85             2,056.36             1,935.37
Concrete Lined Canal (H=1.00x0.60)             7,572.74             7,333.14             6,871.34             7,466.28             7,171.94             6,961.98
RCPC (910mm. Dia.)/Manhole             9,106.52             9,005.51             8,395.21             8,714.79             8,640.27             9,851.21
             
SURFACE TYPE SCOPE OF WORK UNIT COST/L.M. (PESOS)
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
SLOPE PROTECTION (Per Linear Meter) Grouted Riprap (H=3.00)             6,081.32             5,164.85             6,104.29             6,652.77             6,137.51             6,443.07
Stone Masonry (H=3.00)           14,774.59           12,650.10           14,286.19           15,571.06           14,832.55           15,541.23
               
DRAINAGE                        (Per Linear Meter) Grouted Line Canal (2.01x.57), v-shaped             2,220.58             1,955.13             2,281.88             2,392.75             2,373.35             2,383.32
Concrete Lined Canal (H=1.00x0.60)             7,657.68             7,130.59             7,245.77             7,903.49             8,093.61             7,585.67
RCPC (910mm. Dia.)/Manhole             9,752.01           10,536.98             9,101.11           10,634.42           11,307.28             8,588.35
             
SURFACE TYPE SCOPE OF WORK UNIT COST/L.M. (PESOS)  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
SLOPE PROTECTION (Per Linear Meter) Grouted Riprap (H=3.00)             5,959.87             5,485.77             6,540.53             5,815.01             5,780.08  
Stone Masonry (H=3.00)           14,249.23           13,284.86           15,367.56           14,209.93           13,885.94  
               
DRAINAGE                        (Per Linear Meter) Grouted Line Canal (2.01x.57),v-shaped             2,328.13             2,115.21             2,345.06             2,240.54             2,175.72  
Concrete Lined Canal (H=1.00x0.60)             7,500.68             7,184.16             7,416.64             7,598.10             7,418.36  
RCPC (910mm. Dia.)/Manhole           10,380.04             9,012.92           10,482.28           11,130.61             9,664.97  
             
F. New Road Construction            
               
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
NCR CAR REGION I REGION II REGION III REGION IV-A
CONCRETE PCC 230mm     25,733,808.71     24,084,924.20     19,676,552.73     22,242,504.06     23,919,752.60     17,601,382.79
PCC 230mm, w/ slope protection     32,561,768.48     30,476,873.35     26,913,158.52     29,884,924.48     29,832,570.14     25,118,535.58
               
ASPHALT AC 50mm     26,340,207.64     25,809,873.00     20,106,758.45     22,395,766.67     24,663,334.30     18,312,708.16
AC 50mm, w/ slope protection     33,362,730.06     32,396,397.36     27,538,747.45     30,245,229.43     30,764,709.96     26,027,945.47
             
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)
REGION IV-B REGION V REGION VI REGION VII REGION VIII REGION IX
CONCRETE PCC 230mm     30,317,759.99     24,580,789.95     27,584,720.20     29,006,301.70     28,986,319.47     28,104,986.83
PCC 230mm, w/ slope protection     36,730,955.49     30,183,613.33     34,082,825.23     36,330,141.59     36,042,178.15     35,757,126.31
               
ASPHALT AC 50mm     32,226,536.85     29,797,282.00     29,415,828.12     29,543,200.45     29,243,666.00     31,297,447.63
AC 50mm, w/ slope protection     38,831,520.38     35,582,456.39     36,110,725.88     37,071,303.53     36,499,069.20     39,158,206.51
             
SURFACE TYPE SCOPE OF WORK UNIT COST/KM. (PESOS)  
REGION X REGION XI REGION XII REGION XIII AVERAGE  
CONCRETE PCC 230mm     29,064,750.98     24,478,240.00     27,480,866.27     29,294,946.36     25,759,912.93  
PCC 230mm, w/ slope protection     35,117,134.59     30,803,489.81     34,637,437.40     35,243,683.13     32,482,275.97  
               
ASPHALT AC 50mm     32,392,874.47     28,055,811.64     29,913,605.59     36,947,248.98     27,903,884.37  
AC 50mm, w/ slope protection     38,637,368.86     34,575,298.90     37,271,641.46     43,085,367.84     34,822,419.92  
             
Note :              
1. The price of construction materials are based on the regional average prices plus 15% mark-up for the hauling cost (2nd Quarter 2020 or latest CMPD value), equipment rates are based from the latest ACEL Rates (25th Edition) and labor rates are based on regional labor average (June 2020).
2. Item A to C, the Estimated Cost excludes cost for Drainage and Slope Protection Works.
3. The Estimated Cost was assumed for a flat terrain condition. A cost factor of 10% for rolling mountainous terrain condition may be applied.


Notes:
 

1.) Road data provided are as of  15 October 2020.

2.) The unit of measure for Road Data is kilometers.

3.) National Roads are classified into:

        Primary Roads - A contiguous length of significant road sections extending linearly without any breaks or forks that connect major cities (At least around 100,000 population) comprising the main trunk line or the backbone of the National Road System.   

        Secondary Roads - Directly connect cities to national primary roads (except in metropolitan areas) or those not included in the category of major cities. Likewise, said roads directly connect major ports, major ferry terminals, major airports, tourist service centers, major government infrastructure to national primary roads. They also directly connect provincial capitals within the same region.

        Tertiary Roads - Other existing roads under DPWH which perform a local function. (In the map, these roads are represented only by letters.)

4.) No Assessment refers to Road Sections that are either under construction and/or segments with length below the 50-meter gauging length.

For questions regarding this website contact feedback@dpwh.gov.ph

 

Last updated: 03/04/21.

Disclaimer