Davao City Bypass Construction Project

Project Description: 

The proposed Davao City Bypass Construction Project which is located within Davao City has an approximate 44.6KM length, including the tunnel section, which will start from Davao-Digos section of the Pan Philippine Highway in Toril, Davao City and will terminate intersecting the Davao-Agusan National Highway in Panabo City.

The project is divided into two phases, precisely:

PHASE I:

  • South Section (Road) and Center Section (Tunnel) — JICA PH-P261

Roads and Bridges

:  26.5 KM

Tunnel     

:  2.3 KM

Improvement of exsiting two connector (local) road

:  10.2 KM

Project Cost

:  Php 14.23 B (JICA-P9.27B; GOP-P4.96B)

Schedule

:  April 2019 – April 2022

 

  • North Section (Road) — Locally Funded

Roads and Bridges

:  15.8 KM

Project Cost

:  Php 5.577 B

Schedule

:  January 2020 – January 2022

 

PHASE II:

  • Widening of the 42.3 KM Bypass road from two-lane to four-lane road

Indicative Cost

:  Php 10 B

Schedule

:  2019 - 2025

Project Objectives: 
  • To divert the traffic to the Bypass, instead of passing through the Urban Center relieving its present chronic traffic congestion;
  • To expand urban areas towards the inland areas which will be orderly guided by a new road network which is the Bypass;
  • To strongly support economic activities, particularly for the manufactuing and agri-business industries, by providing easier transport access to seaports and airports
Project Cost: 

ESTIMATED PROJECT COST:

  • Approximately Php 29.81 Billion
Project Status: 

PHASE I – Contract Package I (10.7 km.):

·         Currently under procurement

·         Ongoing preparation of request for change in cost (additional) for submission to NEDA

 

PHASE I Contract Packages 2 and 3:

·         Detailed Engineering Design (DED) was completed.

·         DED Plans were submitted to Bureau of Design (BOD) for review and approval

·         Consultant is currently incorporating the comments and observations of BOD.

 

PHASE II :

·         DED is being finalized for submission to BOD for review and approval

Project Alignment: