Infrastructure Projects

Region VIII

as of March 31, 2016

 

View Project Status

Completed :: Ongoing :: Not Yet Started :: Terminated

 
 

Search for Project Name:   Submit

Download as: || CSV ||

 
 

Project ID

a) Name of Project / Location

b) Contractor

c)  Implementing Office

d) Source of Funds

 

a) Project Cost

 

(Php'000)

Implementation Schedule

a) Date Started

b) Original Completion

c) Actual Completion

Status

%

  080615T00023
a) Local Infrastructure Program - Construction of MPB, Maghipid, Lope de Vega, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) By Administration
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,165

a)  12/28/2015
b)  3/25/2016
c)   

 

c)  50 %
  080615F00008
a) Local Infrastructure Program - Revetment on concrete Sheet Piles (Shore Protection), Poblacion Sur, San Isidro, N. Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) By Administration
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 3,169

a)  12/28/2015
b)  3/26/2016
c)   

 

c)  50 %
  080215F00045
a) Construction of Tabgas Flood Control along Tabgas River, Sitio Cantawagon, Tabgas Albuera Leyte CONSTRUCTION/Albuera,Leyte 4th District Engineering Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Leyte 4th District Engineering Office,Region VIII
d)  FMMR
   
a)

 13,796

a)  11/26/2015
b)  5/3/2016
c)   

 

c)  80 %
  080215H00323
a) Payment for RROW of Construction of Tacloban City By-Pass Road, (Including ROW), Sta. 3+400 - Sta. 6+400, Brgy. Caibaan, Tacloban City, Leyte RIGHT-OF-WAY/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.
c) Regional Office,Region VIII
d)  CBPR
   
a)

 13,187

a)  11/25/2015
b)  1/13/2016
c)  1/13/2016

 

c)  100 %
  080215H00305
a) Local Infrastructure Program - Construction of Road, Barangay Punong, Bato, Leyte GRAVEL TO PAVED/Bato,Leyte 5th District Engineering Office,Region VIII
b) VENUS ENGINEERING & CONSTRUCTION
c) Leyte 5th District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,882

a)  11/18/2015
b)  1/21/2016
c)  1/21/2016

 

c)  100 %
  080215H00303
a) Installation/Application/Construction of Road Safety Devices, Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara & Jaro-Dagami-Burauen-La Paz Road, K0935+(-076) to K0945+349 & K0941+(-745) to K0986+866 with exceptions ROAD SAFETY DEVICES (GUARDRAILS, PAVEMENT M/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) ROCKCON BUILDERS AND CONSTRUCTION SUPPLY
c) Leyte 2nd District Engineering Office,Region VIII
d)  MVUC
   
a)

 14,300

a)  11/13/2015
b)  3/11/2016
c)  3/11/2016

 

c)  100 %
  080215S00004
a) Local Infrastructure Program - Construction/Repair/Rehabilitation of Classrooms, San Jose High School, Tacloban City, Leyte 1st District CONSTRUCTION/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) D.L. AUREO CONSTRUCTION
c) Tacloban City District Engineering Office,Region VIII
d)  RLIP
   
a)

 4,958

a)  11/9/2015
b)  1/7/2016
c)  2/6/2016

 

c)  100 %
  080215F00044
a) Rehabilitation/Improvement of Flood Control Structure along Dungca-an, Baybay City, Leyte REHABILITATION/Baybay,Leyte 5th District Engineering Office,Region VIII
b) C N E CONSTRUCTION
c) Leyte 5th District Engineering Office,Region VIII
d)  FMMR
   
a)

 10,699

a)  11/9/2015
b)  4/6/2016
c)   

 

c)  95.5 %
  080215S00005
a) Local Infrastructure Program - Construction/Repair/Rehabilitation of Classrooms, San Jose Central Elementary School, Tacloban City, Leyte 1st District CONSTRUCTION/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) VMEJIA CONSTRUCTION AND SUPPLIES
c) Tacloban City District Engineering Office,Region VIII
d)  RLIP
   
a)

 4,900

a)  11/9/2015
b)  1/7/2016
c)  1/7/2016

 

c)  100 %
  080215H00311
a) Off-carriageway along Daang Maharlika (S00166LT), K0990+390 - K0992+390 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) FAIRCHILD BUILDERS & DEVELOPERS, INC.
c) Leyte 5th District Engineering Office,Region VIII
d)  NDOC
   
a)

 8,984

a)  11/6/2015
b)  3/5/2016
c)  3/5/2016

 

c)  100 %
  080515H00014
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Bridge located at Poblacion, Jipapad, Eastern Samar CONSTRUCTION OF NEW BRIDGE/Jipadpad,Eastern Samar District Engineering Office,Region VIII
b) A.C. RIVERO DEVELOPMENT CORPORATION
c) Regional Office,Region VIII
d)  VILP
   
a)

 72,570

a)  11/2/2015
b)  9/22/2016
c)   

 

c)  10.75 %
  080615H00023
a) Construction/Repair/Rehabilitation/Improvement of Various Infrstructure including Local Projects - Construction of New Alignment of San Antonio Circumferential Road to a higher ground elevation, Northern Samar GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  VILP
   
a)

 45,039

a)  10/30/2015
b)  6/5/2016
c)   

 

c)  45 %
  080615T00008
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Poblacion Ward I, San Antonio, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 6,300

a)  10/23/2015
b)  4/19/2016
c)   

 

c)  95 %
  080415H00089
a) Rehabilitation of Bridges along Daang Maharlika (SM), San Isidro-San Juanico Bridge, Sta.Margarita, Western Samar, Sta. Margarita Bridge (B00350SM) RETROFITTING/REHABILITATION/STRENGTHENING/Sta. Margarita,Samar 1st District Engineering Office,Region VIII
b) JUF CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 7,943

a)  10/21/2015
b)  4/8/2016
c)   

 

c)  60 %
  080215H00320
a) Off-carriageway Improvement of Roads, Daang Maharlika (LT) K0916+1011-K0919+500 WIDENING - PAVED INCLUDING DRAINAGE STRUCTURE/DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) R.T. MORABE CONSTRUCTION
c) Leyte 1st District Engineering Office,Region VIII
d)  MVUC
   
a)

 19,163

a)  10/19/2015
b)  3/7/2016
c)  1/25/2016

 

c)  100 %
  080215H00047
a) Naga-Naga Anibong Rd - K0906+(-038) - K0906+299 (S00015LT) WIDENING - PAVED/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) PACER CONSTRUCTION & DEVELOPMENT CORPORATION
c) Tacloban City District Engineering Office,Region VIII
d)  WASR
   
a)

 6,974

a)  10/15/2015
b)  2/1/2016
c)  2/1/2016

 

c)  100 %
  080215H00180
a) Local Infrastructure Program - Construction of Footbridge, Barangay Naungan, Ormoc City, Leyte 4th LD CONSTRUCTION OF NEW BRIDGE/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Leyte 4th District Engineering Office,Region VIII
d)  RLIP
   
a)

 10,961

a)  10/14/2015
b)  5/25/2016
c)   

 

c)  67 %
  080615T00011
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Office of the Vice President (OVP) - Office Senior Citizens Affairs (OSCA) (Multi-Purpose Building) Center, Gamay, Northern Samar CONSTRUCT/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) ADB DYNAMIC BUILDERS & SUPPLY
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  VILP
   
a)

 1,830

a)  10/8/2015
b)  2/22/2016
c)  1/31/2016

 

c)  100 %
  080615T00012
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Office of the Vice President (OVP) - Office Senior Citizens Affairs (OSCA) (Multi-Purpose Building) Center, San Roque, Northern Samar CONST/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) JUPA CONSTRUCTION
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  VILP
   
a)

 1,835

a)  10/8/2015
b)  2/4/2016
c)  3/31/2016

 

c)  100 %
  080415H00078
a) Repair/Rehabilitation/Improvement (Additional Pavement Width) Daang Maharlika (SM) (San Isidro - San Juanico Bridge), S00062SM, K0754+000 to K0756+000 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  MVUC
   
a)

 10,100

a)  9/29/2015
b)  1/27/2016
c)  1/27/2016

 

c)  100 %
  080415H00086
a) Rehabilitation of Bridges, Calbayog City, Western Samar, Nijaga Bridge along Calbayog Diversion Road RETROFITTING/REHABILITATION/STRENGTHENING/Sta. Margarita,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 7,176

a)  9/29/2015
b)  4/27/2016
c)   

 

c)  80 %
  080415H00085
a) Repair/Rehabilitation of Access Road leading to Calbayog Airport K0723+200-K0724+500 Calbayog City, Western Samar PAVED (CONCRETE) TO PAVED (CONCRETE)/Sta. Margarita,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  TDAP
   
a)

 35,901

a)  9/25/2015
b)  4/2/2016
c)   

 

c)  90 %
  080415H00087
a) Rehabilitation of Bridges along Daang Maharlika (SM), San Isidro-San Juanico Bridge, Sta.Margarita, Western Samar, Solsogon Bridge (B00352SM) RETROFITTING/REHABILITATION/STRENGTHENING/Sta. Margarita,Samar 1st District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 15,989

a)  9/22/2015
b)  4/20/2016
c)   

 

c)  78 %
  080415H00088
a) Rehabilitation of Bridges along Daang Maharlika (SM), San Isidro-San Juanico Bridge, Sta.Margarita, Western Samar, Arapison Bridge (B00338SM) RETROFITTING/REHABILITATION/STRENGTHENING/Sta. Margarita,Samar 1st District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 10,698

a)  9/22/2015
b)  4/8/2016
c)   

 

c)  80 %
  080315H00023
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Concreting of Hinunangan-St. Bernard Road, Southern Leyte Lone District GRAVEL TO PAVED/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) 888 ACY ENTERPRISES
c) Southern Leyte District Engineering Office,Region VIII
d)  VILP
   
a)

 47,702

a)  9/16/2015
b)  4/11/2016
c)   

 

c)  90 %
  080615H00082
a) Palapag Br. (B00552SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/Palapag,Northern Samar 2nd District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  CNWP
   
a)

 59,889

a)  9/16/2015
b)  9/5/2016
c)   

 

c)  3.5 %
  080615H00054
a) Catarman Br. (B00556SM) along Catarman-Laoang Rd WIDENING OF BRIDGE/Catarman,Northern Samar 1st District Engineering Office,Region VIII
b) J.H. PAJARA CONSTRUCTION CORPORATION
c) Regional Office,Region VIII
d)  CNPW
   
a)

 141,066

a)  9/16/2015
b)  7/11/2016
c)   

 

c)  2.15 %
  080615H00032
a) Local Infrastructure Program - Construction/Concreting of Brgy. Burabod to Brgy. Rizal Road, San Antonio, Northern Samar 1st LD GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 8,198

a)  9/15/2015
b)  2/12/2016
c)   

 

c)  91 %
  080615H00024
a) Construction/Concreting of Lagbangan Lake Circumferential Road, San Antonio, Northern Samar GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  TDTD
   
a)

 27,325

a)  9/15/2015
b)  4/5/2016
c)   

 

c)  95 %
  080615H00098
a) Repair/Rehabilitation/Improvement (Concrete Reblocking) Bugko - Nenita - Mirador - Cagpanit-an - De Maria - San Jose Road, Mondragon, Northern Samar S00014SM K0766+900 to K0769+500 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  MVUC
   
a)

 9,352

a)  9/15/2015
b)  2/12/2016
c)  2/12/2016

 

c)  100 %
  080215H00299
a) Repair/Rehabilitation/Improvement (Paving of Shoulders, Loading & Unloading Bays) Tacloban - Baybay South Road, S00177LT K0985+(-255) to K1007+783 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) JA ACHACOSO ENTERPRISES & GENERAL SERVICES
c) Leyte 5th District Engineering Office,Region VIII
d)  MVUC
   
a)

 10,368

a)  9/11/2015
b)  2/7/2016
c)  2/7/2016

 

c)  100 %
  080315H00085
a) Repair/Rehabilitation/Improvement (Construction of Road Shoulder) Lilo-An - San Ricardo Road, S00218LT K1056+(-896) to K1077+775 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) ASCENTIA CONSTRUCTION, INC.
c) Southern Leyte District Engineering Office,Region VIII
d)  MVUC
   
a)

 10,890

a)  9/2/2015
b)  4/29/2016
c)   

 

c)  45 %
  080515T00028
a) Local Infrastructure Program - Construction/Repair/Rehabilitation of Multi-Purpose Building (Evacuation Center), Guiuan, Eastern Samar Lone District CONSTRUCTION/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) TUBIGAN BUILDERS
c) Eastern Samar District Engineering Office,Region VIII
d)  RLIP
   
a)

 3,820

a)  8/28/2015
b)  5/29/2016
c)   

 

c)  13 %
  080215H00153
a) Burauen-Albuera Road (Including ROW), Sta. 0+000 - Sta. 7+650, Albuera, Leyte 4th District GRAVEL TO PAVED/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Regional Office,Region VIII
d)  CMGN
   
a)

 179,468

a)  8/25/2015
b)  9/2/2016
c)   

 

c)  54 %
  080215H00154
a) Burauen- Albuera Road (Including ROW), Sta. 7+650 - Sta. 13+350, Albuera, Leyte 4th District GRAVEL TO PAVED/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) B.M. MARKETING
c) Regional Office,Region VIII
d)  CMGN
   
a)

 186,046

a)  8/25/2015
b)  9/11/2016
c)   

 

c)  40 %
  080315H00017
a) New Road Alignment along Liloan-San Ricardo Road, Brgy. Son-Ok - Brgy. Manglit Road Section (Saddle Area), Pintuyan, Southern Leyte Lone District GRAVEL TO PAVED/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) A.C. RIVERO DEVELOPMENT CORPORATION
c) Southern Leyte District Engineering Office,Region VIII
d)  CMGN
   
a)

 46,323

a)  8/24/2015
b)  4/10/2016
c)   

 

c)  88 %
  080515T00024
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Office of the Vice President (OVP) - Office Senior Citizens Affairs (OSCA) (Multi-Purpose Building) Center, Guiuan, Eastern Samar CONSTRUCT/Guiuan,Eastern Samar District Engineering Office,Region VIII
b) ARNOLD G. COSIPAG CONSTRUCTION
c) Eastern Samar District Engineering Office,Region VIII
d)  VILP
   
a)

 1,872

a)  8/24/2015
b)  3/22/2016
c)  3/22/2016

 

c)  100 %
  080215H00129
a) Merida-Lundag-Puting Bato-Consolacion-Isabel Rd - K1112+678 - K1114+000, K1115+850 - K1118+350, K1118+550 - K1120+000 (S00162LT), Merida & Isabel, Leyte GRAVEL TO PAVED/Merida,Leyte 4th District Engineering Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Regional Office,Region VIII
d)  RUSR
   
a)

 141,705

a)  8/20/2015
b)  5/25/2016
c)   

 

c)  70.22 %
  080615T00022
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Lungib, Victoria, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) JJTP BUILDERS & SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,158

a)  8/14/2015
b)  10/12/2015
c)   

 

c)  95 %
  080615H00042
a) Local Infrastructure Program - Construction/Concreting of MPB, Calangcaan-Osmeña, Lope de Vega, Northern Samar 1st LD GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) AREX BUILDERS & CONSTRUCTION SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,817

a)  8/14/2015
b)  10/27/2015
c)   

 

c)  50 %
  080615T00018
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Henaronagan, Lope De Vega, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) AREX BUILDERS & CONSTRUCTION SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,145

a)  8/14/2015
b)  12/11/2015
c)   

 

c)  90 %
  080615T00003
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Buenasuerte, Victoria, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) JJTP BUILDERS & SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,158

a)  8/14/2015
b)  10/12/2015
c)  2/23/2016

 

c)  100 %
  080215F00002
a) Rehabilitation/Improvement of Flood Control Structures along Daguitan-Marabong River Including Dredging/Desilting (Upstream), Brgy. Caridad, Julita, Leyte CONSTRUCTION/Julita,Leyte 2nd District Engineering Office,Region VIII
b) EZJONES CONSTRUCTION INC.
c) Regional Office,Region VIII
d)  FMSD
   
a)

 112,791

a)  8/12/2015
b)  5/25/2016
c)   

 

c)  97.03 %
  080615H00012
a) Bag-ot Br. (B00311SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 13,174

a)  8/11/2015
b)  4/7/2016
c)   

 

c)  82.62 %
  080615H00072
a) Manaybanay Br. (B00309SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 16,097

a)  8/11/2015
b)  4/7/2016
c)   

 

c)  93.56 %
  080615H00073
a) Mamhot Br. (B00310SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 13,195

a)  8/11/2015
b)  4/7/2016
c)   

 

c)  92.02 %
  080315H00050
a) Sua Br. along Jct Himay-angan-Silago-Abuyog Bdry Rd CONSTRUCTION OF NEW BRIDGE/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) SQUARE CUBE CONSTRUCTION(FORMERLY SQUARE CUBE TRAD
c) Southern Leyte District Engineering Office,Region VIII
d)  CNNP
   
a)

 24,695

a)  8/10/2015
b)  3/7/2016
c)   

 

c)  91.5 %
  080615H00081
a) Naliwatan Br. (B00307SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 19,054

a)  8/3/2015
b)  4/16/2016
c)   

 

c)  86.01 %
  080615H00064
a) Moperet Br. (B00308SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 13,190

a)  8/3/2015
b)  2/28/2016
c)  2/15/2016

 

c)  100 %
  080615H00084
a) Tinampo Br. (B00551SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 22,536

a)  8/3/2015
b)  4/15/2016
c)   

 

c)  74.9 %
  080615H00080
a) Mapno Br. (B00553SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 12,457

a)  8/3/2015
b)  3/29/2016
c)   

 

c)  90.8 %
  080615H00074
a) Magtaon Br. (B00306SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 13,192

a)  8/3/2015
b)  3/29/2016
c)   

 

c)  86.55 %
  080615H00022
a) Cabatuan Br. (B00305SM) along Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd WIDENING OF BRIDGE/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  CNWP
   
a)

 32,746

a)  8/3/2015
b)  4/28/2016
c)   

 

c)  73.84 %
  080215H00295
a) Daang Maharlika, B. Palo-Carigara-Ormoc Rd, Tanauan-Dagami Rd, Mainit-San Miguel-Santol Rd, Bagahupi-Babatngon-Sta. Cruz-Barugo-Carigara Rd, Tigbao-Pulak-Sta. Fe Rd & Sta. Fe-Pastrana-Dagami Rd K0911+(-118)-K0934+358, K0916+(-809)-K0938+076, K0922+(-643) /DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) ROAD EDGE TRADING & DEVELOPMENT SERVICES
c) Leyte 1st District Engineering Office,Region VIII
d)  MVUC
   
a)

 8,364

a)  7/24/2015
b)  9/6/2015
c)  3/24/2016

 

c)  100 %
  080615T00006
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Dao, San Jose, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) CTC CONSTRUCTION & SUPPLIES
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 5,700

a)  7/23/2015
b)  11/19/2015
c)  2/12/2016

 

c)  100 %
  080615T00013
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Poblacion Sur, San Isidro, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) CHRIS AND JAMES CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 5,650

a)  7/23/2015
b)  1/18/2016
c)   

 

c)  95 %
  080615H00020
a) Eco-tourism Roads, Northern Samar, Poblacion- Rock Formation Road, Biri, Northern Samar GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) JUPA CONSTRUCTION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  TDTD
   
a)

 45,410

a)  7/23/2015
b)  2/17/2016
c)  3/8/2016

 

c)  100 %
  080215H00025
a) Cabunga-an-Tabunok-Consuegra Rd - K1022+445- K1025+000 (S00125LT), K1025+000 - K1026+5901 (S00079LT), Villaba, Leyte GRAVEL TO PAVED/DistrictWide,Leyte 3rd District Engineering Office,Region VIII
b) PREMIUM MEGASTRUCTURES INC.
c) Regional Office,Region VIII
d)  RUSR
   
a)

 191,147

a)  7/21/2015
b)  7/16/2016
c)   

 

c)  67 %
  080615H00003
a) Local Infrastructure Program - Concreting/Upgrading/National Roads, Palapag-Mapanas-Gamay-Lapinig Road, Anito-Bag-ot Section, K0810+644 - K0810+799, K0837+526 - K0837+913, K0816+797 - K0816+884, Gamay, Northern Samar 2nd LD PAVED (CONCRETE) TO PAVED (CONC/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) RHYES BUILDERS & SUPPLY
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  RLIP
   
a)

 18,330

a)  7/16/2015
b)  2/10/2016
c)  2/9/2016

 

c)  100 %
  080415F00012
a) Construction of Flood Control Structure, Brgy. Binaliw, Calbayog City, Samar 1st LD CONSTRUCTION/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) MAC BUILDERS
c) Samar 1st District Engineering Office,Region VIII
d)  FMSD
   
a)

 21,978

a)  7/14/2015
b)  1/10/2016
c)  1/10/2016

 

c)  100 %
  080415H00060
a) Construction of Brgy. Socorro-Guinsorongan-Bunu-anan-Brgy. Ibol Circumferential Road, Catbalogan City, Samar GRAVEL TO PAVED/DistrictWide,Samar 2nd District Engineering Office,Region VIII
b) RICHMARK CONSTRUCTION
c) Samar 2nd District Engineering Office,Region VIII
d)  TDTD
   
a)

 45,997

a)  7/8/2015
b)  5/30/2016
c)   

 

c)  70 %
  080415H00059
a) Concreting of Access Road from Brgy. Polangi - Brgy. Panayuran - Brgy. Literon leading to Lulugayan Falls, Calbiga River and Langun-Gobingob Caves, Calbiga, Samar GRAVEL TO PAVED/Calbiga,Samar 2nd District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  TDTD
   
a)

 90,887

a)  7/3/2015
b)  2/24/2016
c)  8/22/2016

 

c)  39.81 %
  080615T00014
a) Local Infrastructure Program - Construction of MPB, Airport Village, Catarman, Northern Samar 1st LD CONSTRUCTION/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) CANANUA CONSTRUCTION AND GENERAL SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,420

a)  7/3/2015
b)  8/31/2015
c)   

 

c)  50 %
  080415H00052
a) Tizon Br. (B00362SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) WIDENING OF BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPW
   
a)

 26,146

a)  6/30/2015
b)  4/18/2016
c)   

 

c)  78 %
  080515H00030
a) Construction of Jump-off Point to islands of Makati, San Vicente, and Makalayo, Municipality of Sulat, Eastern Samar GRAVEL TO PAVED/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Eastern Samar District Engineering Office,Region VIII
d)  TDTD
   
a)

 46,477

a)  6/30/2015
b)  4/21/2016
c)   

 

c)  87 %
  080115H00022
a) Biliran Circumferential Rd - K1103+ (-466) - K1104+180 (S00010BR) WIDENING - PAVED/DistrictWide,Biliran District Engineering Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Regional Office,Region VIII
d)  WASR
   
a)

 49,364

a)  6/26/2015
b)  3/6/2016
c)  3/4/2016

 

c)  100 %
  080415H00040
a) Minlawaan Br. (B00344SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNRW
   
a)

 28,865

a)  6/24/2015
b)  5/11/2016
c)   

 

c)  92 %
  080415H00056
a) Sapinit Br. (B00361SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) WIDENING OF BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPW
   
a)

 30,064

a)  6/24/2015
b)  4/10/2016
c)   

 

c)  80 %
  080415H00048
a) Calbayog-Catarman Rd - K0797+000 - K0802+000 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  NDOC
   
a)

 41,072

a)  6/24/2015
b)  2/19/2016
c)  2/19/2016

 

c)  100 %
  080415H00045
a) Dimakiling-JP Rizal St - CH. 112 - CH. 241.5 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  SCSR
   
a)

 21,320

a)  6/24/2015
b)  1/20/2016
c)   

 

c)  92 %
  080215H00122
a) Burauen-Albuera Road including Bridges, Leyte, Burauen Side, Leyte 2nd District GRAVEL TO PAVED/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) MWJ CONSTRUCTION
c) Leyte 2nd District Engineering Office,Region VIII
d)  CMGN
   
a)

 45,100

a)  6/15/2015
b)  2/8/2016
c)  2/8/2016

 

c)  100 %
  080515H00001
a) Pinaculan Br. (B00557SM) along Jct Taft-Oras-Sn Policarpo-Arteche Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) RNMK CONSTRUCTION AND DEVELOPMENT
c) Eastern Samar District Engineering Office,Region VIII
d)  CNRW
   
a)

 46,505

a)  6/15/2015
b)  12/26/2015
c)   

 

c)  24.45 %
  080215H00089
a) Himanglos Br. (B00487LT) along Bagahupi-Babatngon-Sta Cruz-Barugo-Carigara Rd RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) SILK AND STEEL CONSTRUCTION
c) Leyte 2nd District Engineering Office,Region VIII
d)  CNPB
   
a)

 2,852

a)  6/13/2015
b)  12/24/2015
c)  12/24/2015

 

c)  100 %
  080215H00144
a) Construction of Junction Abuyog-Silago Road-Cadac-an-Malaguicay Road Section (Malaguicay Falls) Sta.0+694 - Sta.4+500, with exceptions, Abuyog, Leyte (10.715835, 125.011826) GRAVEL TO PAVED/Abuyog,Leyte 5th District Engineering Office,Region VIII
b) LADY OF ASSUMPTION ENTERPRISES
c) Regional Office,Region VIII
d)  TDTD
   
a)

 68,925

a)  6/11/2015
b)  2/15/2016
c)  2/27/2016

 

c)  100 %
  080215H00161
a) Daang Maharlika (LT) - K0911+(-118) - K0927+000 (with exception) WIDENING - PAVED/DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) PREMIUM MEGASTRUCTURES INC.
c) Regional Office,Region VIII
d)  WANR
   
a)

 169,323

a)  6/10/2015
b)  5/14/2016
c)   

 

c)  78 %
  080215T00071
a) Local Infrastructure Program - Rehabilitation of Multi-Purpose Building, Poblacion, Tabon-Tabon, Leyte 2nd LD CONSTRUCTION/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) RAQ J BUILDERS
c) Leyte 2nd District Engineering Office,Region VIII
d)  RLIP
   
a)

 3,787

a)  6/8/2015
b)  8/6/2015
c)  8/6/2015

 

c)  100 %
  080315W00003
a) Local Infrastructure Program - Construction/Improvement of Level III Water System, Pintuyan, Southern Leyte LD CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) JQD CONSTRUCTION & GENERAL SERVICES
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 2,372

a)  6/3/2015
b)  10/30/2015
c)  1/31/2016

 

c)  100 %
  080315W00001
a) Local Infrastructure Program - Construction/Improvement of Level III Water System, San Ricardo, Southern Leyte LD CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) LJPM BUILDERS & CONSTRUCTION SUPPLY
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 2,475

a)  6/3/2015
b)  10/30/2015
c)  1/31/2016

 

c)  100 %
  080315W00002
a) Local Infrastructure Program - Construction/Improvement of Level III Water System, Liloan, Southern Leyte LD CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) JQD CONSTRUCTION & GENERAL SERVICES
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 2,450

a)  6/3/2015
b)  10/30/2015
c)  1/31/2016

 

c)  100 %
  080615H00035
a) Pob-Gengarog-Tubigdanao-Sn Lorenzo-Bonglas-Manduga - K0729+462 - K0731+348 GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) B.C. CUERPO CONSTRUCTION CORPORATION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RUSR
   
a)

 39,707

a)  5/26/2015
b)  12/11/2015
c)  2/11/2016

 

c)  100 %
  080615H00078
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Polangi-Quezon-Mabini Road, Northern Samar 1st LD GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) B.C. CUERPO CONSTRUCTION CORPORATION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  VILP
   
a)

 45,995

a)  5/15/2015
b)  1/8/2016
c)   

 

c)  92.57 %
  080415H00031
a) Naga Br. (B00349SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNRW
   
a)

 23,932

a)  5/14/2015
b)  4/30/2016
c)   

 

c)  90 %
  080415H00047
a) Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br), K0731+(-191) - 0731+196, K0731+207 - K0731+220, K0731+222 - K0731+520, K0731+522 - K0732+458, K0732+974 - K0733+129, K0733+280 - K0733+611, K0733+250 - K0736+050 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE,/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CDNR
   
a)

 37,677

a)  5/13/2015
b)  4/7/2016
c)   

 

c)  95 %
  080415H00021
a) Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0705+145 - K0705+875, K0715+000 - K0715+900 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  UPAR
   
a)

 28,865

a)  5/12/2015
b)  4/8/2016
c)   

 

c)  94 %
  080415F00001
a) Local Infrastructure Program - Drainage and Protection Works in Monbon, Sta. Margarita, Samar 1st LD CONSTRUCTION/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) R.V. CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  RLIP
   
a)

 9,647

a)  5/12/2015
b)  12/8/2015
c)   

 

c)  96 %
  080515S00001
a) Local Infrastructure Program - Construction/Repair/Rehabilitation of Classrooms, Guiuan National High School, Guiuan, Eastern Samar Lone District CONSTRUCTION/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) TUBIGAN BUILDERS
c) Eastern Samar District Engineering Office,Region VIII
d)  RLIP
   
a)

 4,693

a)  5/11/2015
b)  10/22/2015
c)  3/31/2016

 

c)  100 %
  080415H00041
a) Daang Maharlika (S00062SM) - K0697+700 - K0698+000, K0698+200 - K0698+500, K0700+300 - K0700+450, K0721+500 - K0721+800 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) HENSCHA PHILS. INC.
c) Samar 1st District Engineering Office,Region VIII
d)  SCAR
   
a)

 92,010

a)  5/11/2015
b)  1/23/2016
c)  1/23/2016

 

c)  100 %
  080215H00114
a) Construction of Tacloban City By-Pass Road, (Including ROW), Sta. 0+000 - Sta. 3+400, Brgy. Nula-Tula, Tacloban City, Leyte GRAVEL TO PAVED/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) UNITEC BUILDER, INCORPORATED
c) Regional Office,Region VIII
d)  CBPR
   
a)

 184,944

a)  5/7/2015
b)  4/30/2016
c)   

 

c)  75.2 %
  080415H00002
a) Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0772+170 - K0776+000, K0777+000 - K0778+400.4 WIDENING - PAVED/DistrictWide,Samar 2nd District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  WANR
   
a)

 117,966

a)  5/6/2015
b)  12/24/2015
c)  1/24/2016

 

c)  100 %
  080615H00011
a) Construction/Concreting of Poblacion (Ward 3) to San Antonio Circumferential Road, San Antonio, Northern Samar GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) STEVEN CONSTRUCTION & SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  TDTD
   
a)

 17,995

a)  5/1/2015
b)  10/17/2015
c)  3/1/2016

 

c)  100 %
  080215H00127
a) Burauen-Mahagnao Rd - K0985+1064 - K0986+423, K0989+120 - K0990+000, K0990+000 - K0991+893 GRAVEL TO PAVED/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  RUSR
   
a)

 102,148

a)  4/27/2015
b)  3/26/2016
c)   

 

c)  97.8 %
  080115H00033
a) Biliran Circumferential Rd - K1035+313-K1035+500, K1045+710-K1045+000, K1059+600-K1060+000, K1074+000-K1074+200, K1082+600-K1082+700 , K1106+000+K1106+200 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Biliran District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  SCSR
   
a)

 126,750

a)  4/20/2015
b)  5/30/2016
c)   

 

c)  78.95 %
  080615H00034
a) Poblacion-Barangay Trujillo Rd - K0739+740 - K0741+411, K0741+850 - K0741+1419 GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) B.C. CUERPO CONSTRUCTION CORPORATION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RUSR
   
a)

 43,687

a)  4/17/2015
b)  12/11/2015
c)  2/11/2016

 

c)  100 %
  080315T00005
a) Local Infrastructure Program - Construction of Fish Port, Barangay Casao, Bontoc, Southern Leyte Lone District CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) JQD CONSTRUCTION & GENERAL SERVICES
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 3,920

a)  4/13/2015
b)  3/7/2016
c)  3/7/2016

 

c)  100 %
  080315H00051
a) Mayuga Br. along Daang Maharlika (LT) CONSTRUCTION OF NEW BRIDGE/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) A.C. RIVERO DEVELOPMENT CORPORATION
c) Southern Leyte District Engineering Office,Region VIII
d)  CNNP
   
a)

 17,640

a)  4/13/2015
b)  12/8/2015
c)   

 

c)  95 %
  080315H00049
a) Manhilo Br. along Bdry S Leyte-Maasin-Macrohon-Sogod-Daang Maharlika CONSTRUCTION OF NEW BRIDGE/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) A.C. RIVERO DEVELOPMENT CORPORATION
c) Southern Leyte District Engineering Office,Region VIII
d)  CNNP
   
a)

 12,543

a)  4/13/2015
b)  1/7/2016
c)   

 

c)  95 %
  080615H00013
a) Arteche, Brgy. Catumsan-Jipapad-Las Navas-Catubig-Rawis Road (including Bridges and ROW), Northern Samar 2nd DEO/LD GRAVEL TO PAVED/DistrictWide,Northern Samar 2nd District Engineering Office,Region VIII
b) HENSCHA PHILS. INC.
c) Regional Office,Region VIII
d)  CMGN
   
a)

 89,382

a)  4/7/2015
b)  5/28/2016
c)   

 

c)  65.5 %
  080215H00131
a) Sn Isidro-Daja Rd - K1019+756 - K1019+980, K1019+1001 - K1020+181, K1020+275 - K1020+947, K1020+967 - K1022+020, K1026+145 - K1026+286 GRAVEL TO PAVED/San Isidro,Leyte 3rd District Engineering Office,Region VIII
b) ST. GERRARD CONSTRUCTION
c) Regional Office,Region VIII
d)  RUSR
   
a)

 52,350

a)  4/1/2015
b)  2/4/2016
c)  2/2/2016

 

c)  100 %
  080415H00051
a) Mawo Br. (B00246SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) J.H. PAJARA CONSTRUCTION CORPORATION
c) Regional Office,Region VIII
d)  CNRW
   
a)

 109,502

a)  3/31/2015
b)  3/24/2016
c)   

 

c)  78.89 %
  089915H00001
a) Jct Himay-angan-Silago-Abuyog Bdry Rd - K1121+946 - K1125+340.30, K1127+744 - K1130+896.20 (S00210LT) GRAVEL TO PAVED/DistrictWide,Regional Office,Region VIII
b) 888 ACY ENTERPRISES
c) Regional Office,Region VIII
d)  RUSR
   
a)

 79,941

a)  3/30/2015
b)  1/17/2016
c)   

 

c)  87.5 %
  080615H00077
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of San Isidro-Lope De Vega Road, Northern Samar 1st LD GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) B.C. CUERPO CONSTRUCTION CORPORATION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  VILP
   
a)

 46,257

a)  3/25/2015
b)  10/19/2015
c)  2/12/2016

 

c)  100 %
  080315T00024
a) Local Infrastructure Program - Completion of Multi-Purpose Building, Barangay Zone I, Sogod, Southern Leyte Lone District CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) JQD CONSTRUCTION & GENERAL SERVICES
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 1,792

a)  3/23/2015
b)  4/15/2016
c)   

 

c)  10 %
  080315T00014
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Barangay Zone III, Sogod, Southern Leyte Lone District CONSTRUCTION/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) JQD CONSTRUCTION & GENERAL SERVICES
c) Southern Leyte District Engineering Office,Region VIII
d)  RLIP
   
a)

 4,970

a)  3/23/2015
b)  3/14/2016
c)  3/14/2016

 

c)  100 %
  080215H00123
a) Tacloban-Baybay South Rd -K0986+050-K0986+200,K0986+580-K0986+730,K0987+000-K0987+150,K0988+000-K0988+100,K0989+000-K0989+200,K0993+700-K0993+800,K0994+700-K0994+800,K0996+400-K0996+500,K0996+800-K0997+000,K0999+000-K0999+150,K1000+000-K1000+200 OTHER IMP/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) Joint Venture - B. VICENCIO CONSTRUCTION et. al.
c) Leyte 5th District Engineering Office,Region VIII
d)  SCAR
   
a)

 31,127

a)  3/20/2015
b)  2/11/2016
c)  2/11/2016

 

c)  100 %
  080215H00116
a) Construction/Upgrading of Baybay City Diversion Road, including Bridges, Baybay City, Leyte 5th LD GRAVEL TO PAVED/Baybay,Leyte 5th District Engineering Office,Region VIII
b) ST. GERRARD CONSTRUCTION
c) Regional Office,Region VIII
d)  CBPR
   
a)

 88,840

a)  3/16/2015
b)  1/5/2016
c)  1/31/2016

 

c)  100 %
  080215F00007
a) Rehabilitation/Improvement of Dungcaan River Basin Flood Control Structure, Leyte 5th LD CONSTRUCTION/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) ST. GERRARD CONSTRUCTION
c) Regional Office,Region VIII
d)  FMSD
   
a)

 134,025

a)  3/16/2015
b)  1/25/2016
c)   

 

c)  91.6 %
  080615H00065
a) Noos Br. (B00284SM) along Allen-Catarman Rd RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) B.C. CUERPO CONSTRUCTION CORPORATION
c) Northern Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 9,134

a)  3/13/2015
b)  8/20/2015
c)  3/1/2016

 

c)  100 %
  080215F00005
a) Construction of River Control Structures along Cadac-an River, Abuyog, Leyte CONSTRUCTION/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Leyte 5th District Engineering Office,Region VIII
d)  FMSD
   
a)

 18,423

a)  3/13/2015
b)  10/13/2015
c)  2/1/2016

 

c)  100 %
  080215H00162
a) Tabing-Kawayan-Sta Rosa-Lawis-Tabango Rd - K1025+(-651) - K1025+-547.89, K1025+165 - K1031+000 (S00129LT), Tabango, Leyte GRAVEL TO PAVED/Tabango,Leyte 3rd District Engineering Office,Region VIII
b) SUPREME ABF CONST. & CONST. SUPPLY COMPANY INC.
c) Regional Office,Region VIII
d)  RUSR
   
a)

 183,178

a)  3/13/2015
b)  5/5/2016
c)   

 

c)  89.15 %
  080215H00038
a) Daang Maharlika (LT) - K0981+200 - K0982+000, K1002+830 - K1002+930 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Leyte 5th District Engineering Office,Region VIII
b) LADY OF ASSUMPTION ENTERPRISES
c) Leyte 5th District Engineering Office,Region VIII
d)  SCAR
   
a)

 35,057

a)  3/9/2015
b)  5/3/2016
c)   

 

c)  88 %
  080415H00046
a) Jasmines Br. (B00562SM) K0000+034.90 Navarro St., Calbayog City, Samar RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 16,765

a)  3/6/2015
b)  4/27/2016
c)   

 

c)  80 %
  080415H00039
a) Lambigue Br. (B00354SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 17,984

a)  3/6/2015
b)  5/16/2016
c)   

 

c)  80 %
  080415H00032
a) Binaliw Br. (B00337SM) along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) UBAS CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 5,472

a)  3/6/2015
b)  8/3/2015
c)  1/3/2016

 

c)  100 %
  080515T00035
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Barangay Sapao,Municipality of Guiuan, Eastern Samar Lone District CONSTRUCTION/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) JUCONS CONSTRUCTION &SUPPLY
c) Eastern Samar District Engineering Office,Region VIII
d)  RLIP
   
a)

 2,413

a)  3/3/2015
b)  10/13/2015
c)  1/20/2016

 

c)  100 %
  080515T00057
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Barangay Salug, Guiuan, Eastern Samar Lone District CONSTRUCTION/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) JUCONS CONSTRUCTION &SUPPLY
c) Eastern Samar District Engineering Office,Region VIII
d)  RLIP
   
a)

 2,347

a)  3/3/2015
b)  9/28/2015
c)  1/20/2016

 

c)  100 %
  080215H00115
a) Construction of Palo West By-Pass Road, including Bridge, Pawing-Campetic-Guindapunan-San Jose-Arado, Palo, Leyte GRAVEL TO PAVED/Palo,Leyte 1st District Engineering Office,Region VIII
b) HIGH-INNOVATIVE CONSTRUCTION & DEVELOPMENT PHILS.(
c) Regional Office,Region VIII
d)  CBPR
   
a)

 135,913

a)  3/2/2015
b)  7/24/2016
c)   

 

c)  63.51 %
  080215H00188
a) Palo-Carigara-Ormoc Rd - K0946+755 - K0947+000, K0959+435 - K0960+000, K0960+440 - K0961+798, K0962+000 - K0963+1000 WIDENING - PAVED/DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) PREMIUM MEGASTRUCTURES INC.
c) Regional Office,Region VIII
d)  WANR
   
a)

 93,751

a)  2/26/2015
b)  4/22/2016
c)   

 

c)  84.92 %
  080515H00025
a) Arteche, Brgy. Catumsan-Jipapad-Las Navas-Catubig-Rawis Road (including Bridges and ROW), Eastern Samar GRAVEL TO PAVED/DistrictWide,Eastern Samar District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  CMGN
   
a)

 111,677

a)  2/24/2015
b)  3/9/2016
c)   

 

c)  97 %
  080215H00169
a) Palo-Carigara-Ormoc Rd - K0945+000 - K0947+000, K0950+000 - K0951+969, K0954+320 - K0956+780 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Regional Office,Region VIII
d)  UPAR
   
a)

 103,630

a)  2/24/2015
b)  10/21/2015
c)   

 

c)  97 %
  080215H00151
a) Jaro-Dagami-Burauen-Lapaz Rd - K0969+500 - K0973+400 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) LEHCI CONSTRUCTION
c) Leyte 2nd District Engineering Office,Region VIII
d)  NDOC
   
a)

 35,819

a)  2/23/2015
b)  8/16/2015
c)   

 

c)  95 %
  080415H00036
a) Carayman Br. (B00348SM) along Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) NORSAM BUILDERS & CONSTRUCTION SUPPLY
c) Samar 1st District Engineering Office,Region VIII
d)  CNPB
   
a)

 7,377

a)  2/18/2015
b)  3/18/2016
c)  3/18/2016

 

c)  100 %
  080215H00185
a) Daang Maharlika (LT) - K0948+000 - K0949+000, K0950+000 - K0953+620 WIDENING - PAVED/DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Regional Office,Region VIII
d)  WANR
   
a)

 118,929

a)  2/13/2015
b)  2/27/2016
c)  2/20/2016

 

c)  100 %
  080315H00008
a) Panilahan Br. (B00571LT) along Ormoc-Baybay-Southern Leyte Bdry Rd RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) PREMIUM MEGASTRUCTURES INC.
c) Regional Office,Region VIII
d)  CNPB
   
a)

 53,519

a)  2/13/2015
b)  1/23/2016
c)   

 

c)  90 %
  080215H00079
a) Bernard Reed Br. (B00032LT) along Daang Maharlika (LT) WIDENING OF BRIDGE/DistrictWide,Leyte 1st District Engineering Office,Region VIII
b) LEDA CONSTRUCTION INCORPORATED
c) Leyte 1st District Engineering Office,Region VIII
d)  CNPW
   
a)

 41,060

a)  2/9/2015
b)  11/15/2015
c)   

 

c)  75 %
  080215H00145
a) Construction of Tacloban City By-Pass Road, (Including ROW), Sta. 3+400 - Sta. 6+400, Brgy. Caibaan, Tacloban City, Leyte GRAVEL TO PAVED/Tacloban City,Tacloban City District Engineering Office,Region VIII
b) EZJONES CONSTRUCTION INC.
c) Regional Office,Region VIII
d)  CBPR
   
a)

 126,052

a)  2/6/2015
b)  12/2/2015
c)   

 

c)  92 %
  080315H00015
a) Daang Maharlika (LT) - K1046+000 - K1046+720, K1046+736 - K1047+038, K1047+106 - K1048+000, K1049+000 - K1049+511, K1049+536 - K1052+129, K1052+1011 - K1054+510, K1052+129 - K1052+1011, K1054+806 - K1055+134 CONCRETE REBLOCKING RIGHT LANE/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) ASCENTIA CONSTRUCTION, INC.
c) Southern Leyte District Engineering Office,Region VIII
d)  SBAR
   
a)

 16,327

a)  2/2/2015
b)  9/28/2015
c)  3/31/2016

 

c)  100 %
  080315H00012
a) Bdry S Leyte-Maasin-Macrohon-Sogod-Daang Maharlika - K1139+400 - K1142+000 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) A.C. RIVERO DEVELOPMENT CORPORATION
c) Southern Leyte District Engineering Office,Region VIII
d)  NDOC
   
a)

 12,936

a)  2/2/2015
b)  10/9/2015
c)  1/31/2016

 

c)  100 %
  080415H00053
a) Napuro RCBC along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) CONSTRUCTION OF NEW BRIDGE/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  CNNP
   
a)

 9,004

a)  1/30/2015
b)  2/7/2016
c)  2/7/2016

 

c)  100 %
  080415H00030
a) Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) - K0705+000 - K0706+500 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  NDOC
   
a)

 13,311

a)  1/30/2015
b)  2/20/2016
c)  2/20/2016

 

c)  100 %
  080214F00091
a) Construction of River Control Structures along Cadac-an River, Abuyog, Leyte/Abuyog,Leyte 5th District Engineering Office,Region VIII
b) FAIRCHILD BUILDERS & DEVELOPERS, INC.
c) Leyte 5th District Engineering Office,Region VIII
d)  FMPR
   
a)

 7,596

a)  12/11/2015
b)  4/18/2016
c)   

 

c)  82 %
  080214F00092
a) Rehabilitation/Improvement of Flood Control Structure along Dungca-an River, Baybay City, Leye/Baybay,Leyte 5th District Engineering Office,Region VIII
b) LANOY CONSTRUCTION
c) Leyte 5th District Engineering Office,Region VIII
d)  FMPR
   
a)

 1,046

a)  12/11/2015
b)  1/19/2016
c)  1/19/2016

 

c)  100 %
  080314G00002
a) Construction of Standard Two-Storey DPWH Southern Leyte District Engineering Office, Brgy. Ibarra, Maasin City, Southern Leyte REHABILITATION/Maasin City,Southern Leyte District Engineering Office,Region VIII
b) REX E. MORALES CONSTRUCTION
c) Southern Leyte District Engineering Office,Region VIII
d)  VILP
   
a)

 24,821

a)  12/1/2015
b)  6/28/2016
c)   

 

c)  20 %
  080214F00090
a) Construction of Tabgas Flood Control along Tabgas River, Sitio Cantawagon, Tabgas Albuera Leyte CONSTRUCTION/Albuera,Leyte 4th District Engineering Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Leyte 4th District Engineering Office,Region VIII
d)  FMMR
   
a)

 9,217

a)  11/26/2015
b)  3/19/2016
c)  3/19/2016

 

c)  100 %
  080214H00399
a) Rehabilitation/Replacement of Hiagsam Bridge along Palo-Carigara-Ormoc Road K0945+284, Leyte OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
b) MWJ CONSTRUCTION
c) Leyte 2nd District Engineering Office,Region VIII
d)  RQRF
   
a)

 37,900

a)  11/16/2015
b)  7/7/2016
c)   

 

c)  41 %
  080214H00428
a) Repair/Restoration/Improvement of Road slips along Libungao-Matag-ob-Palompon Road (S00148LT), damaged by typhoon “Mario” OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Regional Office,Region VIII
d)  RQRF
   
a)

 78,748

a)  11/13/2015
b)  5/11/2016
c)   

 

c)  66.41 %
  080414H00124
a) Rehabilitation/Improvement of Roadslip along Calbayog Catarman Road (S00084SM), Calbayog City, K0795+160-K0795+218 & K0 804+000-K0804+032 RETROFITTING/REHABILITATION/STRENGTHENING/Calbayog City,Samar 1st District Engineering Office,Region VIII
b) B. VICENCIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  RQRF
   
a)

 11,485

a)  8/7/2015
b)  2/4/2016
c)  2/4/2016

 

c)  100 %
  080414H00117
a) Rehabilitation/Improvement of Slope Protection along Daang Maharlika (S00062SM) K0718+650-K0718+800, Calbayog City OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/Calbayog City,Samar 1st District Engineering Office,Region VIII
b) J. CUSTORIO CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  RQRF
   
a)

 21,612

a)  8/4/2015
b)  2/6/2016
c)  2/6/2016

 

c)  100 %
  080414H00121
a) Repair/rehabilitation of road slip along Daang Maharlika (S00062SM), K0782+900 - K0783+150, Tarangnan, Samar OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/Tarangnan,Samar 1st District Engineering Office,Region VIII
b) RNMK CONSTRUCTION AND DEVELOPMENT
c) Samar 1st District Engineering Office,Region VIII
d)  RQRF
   
a)

 17,286

a)  7/23/2015
b)  1/3/2016
c)  1/15/2016

 

c)  100 %
  080614G00003
a) Construction of Two-Storey DPWH Northern Samar 2nd District Engineering Office, Laoang, Northern Samar REHABILITATION/Laoang,Northern Samar 2nd District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Northern Samar 2nd District Engineering Office,Region VIII
d)  VILP
   
a)

 24,482

a)  7/16/2015
b)  2/10/2016
c)  3/31/2016

 

c)  100 %
  080414H00112
a) Repair/Rehabilitation of Roadslip along Calbayog Catarman Road, K0792+790.40-K0792+908, Calbayog City, Samar RETROFITTING/REHABILITATION/STRENGTHENING/Calbayog City,Samar 1st District Engineering Office,Region VIII
b) C D U CONSTRUCTION
c) Samar 1st District Engineering Office,Region VIII
d)  RQRF
   
a)

 22,558

a)  5/28/2015
b)  1/21/2016
c)  1/21/2016

 

c)  100 %
  080214H00159
a) Tigbao Br. along Daang Maharlika (LT) RETROFITTING/REHABILITATION/STRENGTHENING/CityWide,Tacloban City District Engineering Office,Region VIII
b) UNITEC BUILDER, INCORPORATED
c) Tacloban City District Engineering Office,Region VIII
d)  RHPB
   
a)

 37,915

a)  2/27/2015
b)  10/9/2015
c)   

 

c)  86 %
  080214H00353
a) Construction/upgrading of Ormoc Diversion Road including bridges & ROW, Ormoc City, Leyte 4LD - Bridges GRAVEL TO PAVED/Ormoc City,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Regional Office,Region VIII
d)  CNBP
   
a)

 212,674

a)  2/9/2015
b)  1/21/2017
c)   

 

c)  39 %
  080614H00046
a) Sn Antonio Circumferential Rd K0019+349 - K0023+805 GRAVEL TO PAVED/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) STEVEN CONSTRUCTION & SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RUSR
   
a)

 51,897

a)  1/23/2015
b)  10/19/2015
c)   

 

c)  90 %
  080614H00017
a) San Isidro Br. along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br.) RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Northern Samar 1st District Engineering Office,Region VIII
b) RHYES BUILDERS & SUPPLY
c) Northern Samar 1st District Engineering Office,Region VIII
d)  RHPB
   
a)

 12,304

a)  11/3/2014
b)  5/1/2015
c)   

 

c)  35 %
  080414H00037
a) Mawo Br. along Daang Maharlika (SM) (Sn Isidro-Sn Juanico Br) RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Samar 1st District Engineering Office,Region VIII
b) J.H. PAJARA CONSTRUCTION CORPORATION
c) Regional Office,Region VIII
d)  RHPB
   
a)

 129,520

a)  10/21/2014
b)  2/1/2016
c)   

 

c)  91.93 %
  080214F00031
a) Improvement of Drainage System along Ormoc - Baybay - So. Leyte Bdry. Road, K1025+394 - K1027+200, Albuera, Leyte CONSTRUCTION/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Leyte 4th District Engineering Office,Region VIII
d)  DPNR
   
a)

 13,947

a)  9/24/2014
b)  2/15/2016
c)  2/15/2016

 

c)  100 %
  080114H00019
a) Higatangan Circumferential Road leading to Higatangan Island, Naval, Biliran GRAVEL TO PAVED/Naval,Biliran District Engineering Office,Region VIII
b) YOYEN ENTERPRISES
c) Regional Office,Region VIII
d)  TDTD
   
a)

 92,198

a)  5/9/2014
b)  3/30/2016
c)   

 

c)  57.36 %
  080214H00115
a) Road Opening/Upgrading of Burauen-Albuera Road including Bridges, Leyte - Albuera Side, Leyte 4th District - Bridges ROAD OPENING, CONCRETE/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) PREMIUM BUILDERS CORPORATION
c) Regional Office,Region VIII
d)  CNMG
   
a)

 56,873

a)  4/18/2014
b)  5/2/2015
c)   

 

c)  89 %
  080214H00105
a) Road Opening/Upgrading of Burauen-Albuera Road including Bridges, Leyte - Albuera Side, Leyte 4th District - Roads ROAD OPENING, CONCRETE/DistrictWide,Leyte 4th District Engineering Office,Region VIII
b) PREMIUM BUILDERS CORPORATION
c) Regional Office,Region VIII
d)  CNMG
   
a)

 89,781

a)  4/18/2014
b)  2/10/2016
c)   

 

c)  88 %
  089913H00007
a) Road upgrading (gravel to paved) of Burauen-Albuera Road, Sta. 0+698.90 - Sta. 5+350.00 with exception GRAVEL TO PAVED/DistrictWide,Regional Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Regional Office,Region VIII
d)  DPWH
   
a)

 91,700

a)  3/11/2013
b)  8/20/2015
c)  1/30/2016

 

c)  100 %
  080113H00014
a) Biliran Circumferential Rd, K1008 + 000 - K1008 + 1000, K1011 + 000 - K1016 + 000, K1018 + 100 - K1019 + 600, K1019 + 750 - K1021 + 115 ASPHALT OVERLAY (50 MM THICK)/DistrictWide,Biliran District Engineering Office,Region VIII
b) YAKAL CONSTRUCTION
c) Regional Office,Region VIII
d)  PVM
   
a)

 60,122

a)  2/15/2013
b)  11/26/2013
c)   

 

c)  52.1 %
  089913H00004
a) Construction of Ormoc Diversion Road includings & Bridges & ROW, Ormoc City WIDENING - PAVED/DistrictWide,Regional Office,Region VIII
b) MAC BUILDERS
c) Regional Office,Region VIII
d)  TRAFFIC
   
a)

 128,136

a)  2/7/2013
b)  5/21/2015
c)   

 

c)  95.05 %
  080212H00519
a) Construction of Ormoc Diversion Road including bridges & ROW, Ormoc City PAVED (CONCRETE) TO PAVED (CONCRETE)/Ormoc City,Leyte 4th District Engineering Office,Region VIII
b) MAC BUILDERS
c) Regional Office,Region VIII
d)  VILP
   
a)

 112,259

a)  1/14/2014
b)  11/17/2015
c)   

 

c)  91.5 %
  080312H00061
a) Construction of Pinut-an Bridge and Approaches, Southern Leyte CONSTRUCTION OF NEW BRIDGE/DistrictWide,Southern Leyte District Engineering Office,Region VIII
b) J.D. LEGASPI CONSTRUCTION
c) Regional Office,Region VIII
d)  DPWH
   
a)

 32,524

a)  10/25/2012
b)  12/11/2015
c)   

 

c)  90 %
  089912H00010
a) Ormoc Diversion Road GRAVEL TO PAVED/DistrictWide,Regional Office,Region VIII
b) OCTAGON CONCRETE SOLUTIONS
c) Regional Office,Region VIII
d)  TRAFFIC
   
a)

 88,252

a)  2/29/2012
b)  4/20/2015
c)  1/30/2016

 

c)  100 %
  080211F00092
a) Construction of Bangon River Flood Control Revetment, Palo CONSTRUCTION/Palo,Leyte 1st District Engineering Office,Region VIII
b) YAKAL CONSTRUCTION
c) Regional Office,Region VIII
d)  VILP
   
a)

 213,683

a)  7/1/2015
b)  4/25/2016
c)   

 

c)  24.869 %

 

Back to Map

 

For more information, please contact :
Bureau of Construction

Phone: 304-3277

304-3143