Infrastructure Projects

Region I

as of August 31, 2016

 

View Project Status

Completed :: Ongoing :: Not Yet Started :: Terminated

 
 

Search for Project Name:   Submit

Download as: || CSV ||

 
 

Project ID

a) Name of Project / Location

b) Contractor

c)  Implementing Office

d) Source of Funds

 

a) Project Cost

 

(Php'000)

Implementation Schedule

a) Date Started

b) Original Completion

c) Actual Completion

Status

%

  010215H00129
a) Emergency Repair/Restoration and Removal of Slides along Tagudin-Cervantes Road, K0321+(-353) - K0380+1309, Intermittent Section OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) M.V. SABALBURO CONSTRUCTION AND SUPPLY
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  DREH
   
a)

 2,500

a)  1/7/2016
b)  3/29/2016
c)  2/29/2016

 

c)  100 %
  010315H00118
a) Manila North Road (00186LZ) near Lorma Medical Center, Carlatan, San Fernando City, La Union, within K0270+798.95 to K0270+818.95/San Fernando City,La Union 1st District Engineering Office,Region I
b) MY BUILDERS AND CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  MVUC
   
a)

 1,918

a)  12/28/2015
b)  3/4/2016
c)  3/4/2016

 

c)  100 %
  010115H00054
a) Tulnagan Br. along Manila North Rd, K0514+580 CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) R.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNNP
   
a)

 21,600

a)  12/21/2015
b)  9/27/2016
c)   

 

c)  73 %
  010315T00042
a) Local Infrastructure Program - Construction of Multi-Purpose Building (Convention Center), City of San Fernando, La Union 1st LD CONSTRUCTION/DistrictWide,La Union 1st District Engineering Office,Region I
b) MY BUILDERS AND CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  RLIP
   
a)

 40,000

a)  12/18/2015
b)  7/14/2016
c)   

 

c)  76 %
  010115F00058
a) Rehabilitation of Flood Control Projects Damaged by the recent typhoon "Ineng" Brgy. 1 & Brgy. 24 Laoag City and Carasi, Ilocos Norte REHABILITATION/Carassi,Ilocos Norte 1st District Engineering Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Ilocos Norte 1st District Engineering Office,Region I
d)  DREH
   
a)

 8,000

a)  12/11/2015
b)  2/8/2016
c)  2/8/2016

 

c)  100 %
  010415H00384
a) Repair / Rehabilitation / Improvement (Paving of Shoulders) Alaminos-Lucap Road, KO322+443 to KO326+000 CONCRETING OF SHOULDER/Alaminos City,Pangasinan 1st District Engineering Office,Region I
b) CEDAN CONSTRUCTION
c) Pangasinan 1st District Engineering Office,Region I
d)  MVUC
   
a)

 9,900

a)  12/9/2015
b)  4/5/2016
c)  4/5/2016

 

c)  100 %
  010215F00022
a) Rehabilitation/Reconstruction of Seawall along Manila North Road, K0385+650 - K0385+750, Santa, Ilocos Sur REHABILITATION/Santa,Ilocos Sur 1st District Engineering Office,Region I
b) SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  DREH
   
a)

 22,400

a)  11/27/2015
b)  6/7/2016
c)   

 

c)  97 %
  010415F00031
a) Bonuan Seawall, Dagupan City CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 50,000

a)  11/24/2015
b)  11/17/2016
c)   

 

c)  89 %
  010415F00140
a) Agno River Basin Flood Control Project - Phase II - Construction of Three (3) Boulder Spur Dikes, Brgy. Bacayao Sur, Dagupan City, Pangasinan CONSTRUCTION/Dagupan City,Pangasinan 2nd District Engineering Office,Region I
b) ZOTA TRADING & CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 3,000

a)  11/17/2015
b)  12/31/2015
c)  1/17/2016

 

c)  100 %
  010115H00066
a) Construction of Laoag City By-Pass Road including Bridge, Laoag City, Ilocos Norte 1st LD GRAVEL TO PAVED/Laoag City,Ilocos Norte 1st District Engineering Office,Region I
b) ADVANCED FOUNDATION CONSTRUCTION SYSTEMS CORP.
c) Regional Office,Region I
d)  CBPR
   
a)

 400,000

a)  11/12/2015
b)  10/7/2016
c)   

 

c)  61 %
  010415T00049
a) Local Infrastructure Program - Rehabilitation of Multi-Purpose Building, Lingayen, Pangasinan (Casa Real) CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 30,000

a)  11/9/2015
b)  7/5/2016
c)   

 

c)  97 %
  019915H00038
a) ROW - Manila North Rd - K0487 + (-418) - K0487 + 426.81, K0530+ (-579.59) - K0537+ 801 WIDENING - PAVED/DistrictWide,Regional Office,Region I
b) By Administration
c) Regional Office,Region I
d)  WANR
   
a)

 77,718

a)  10/28/2015
b)  8/22/2016
c)   

 

c)  10 %
  010415H00367
a) ROW - Pangasinan-Nueva Vizcaya Road (Villa Verde Road), Pangasinan GRAVEL TO PAVED/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) By Administration
c) Regional Office,Region I
d)  CMGN
   
a)

 4,497

a)  10/28/2015
b)  10/21/2016
c)   

 

c)  10 %
  010415F00165
a) Construction/Maintenance of Flood Mitigation Structures and Drainage System, Construction of Protection works along Agno River, Salinap Section, San Carlos City Pangasinan REHABILITATION/San Carlos City,Pangasinan 4th District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 4th District Engineering Office,Region I
d)  FMMR
   
a)

 28,000

a)  10/28/2015
b)  5/28/2016
c)  5/28/2016

 

c)  100 %
  010415F00164
a) Construction and protection works along Sinucalan River, Sta. Barbara, Pangasinan, Alibago Section REHABILITATION/Sta. Barbara,Pangasinan 4th District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 4th District Engineering Office,Region I
d)  FMMR
   
a)

 8,495

a)  10/26/2015
b)  2/18/2016
c)  3/25/2016

 

c)  100 %
  010415F00163
a) Construction and protection works along Sinucalan River, Sta. Barbara, Pangasinan, Ventinilla-Tuliao Section REHABILITATION/Sta. Barbara,Pangasinan 4th District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 4th District Engineering Office,Region I
d)  FMMR
   
a)

 20,000

a)  10/26/2015
b)  2/18/2016
c)  3/25/2016

 

c)  100 %
  010415F00121
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Supo, San Carlos City, Pangasinan CONSTRUCTION/San Carlos City,Pangasinan 4th District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 35,000

a)  10/26/2015
b)  4/20/2016
c)  4/20/2016

 

c)  100 %
  010315F00034
a) Construction/rehabilitation of flood mitigation facilities along Aringay River Basin, Brgy. San Antonio, Aringay, La Union, K0251+877 - K0252+113 REHABILITATION/Aringay,La Union 2nd District Engineering Office,Region I
b) E.E. MADAYAG CONSTRUCTION
c) La Union 2nd District Engineering Office,Region I
d)  FMMR
   
a)

 11,186

a)  10/21/2015
b)  4/9/2016
c)  4/9/2016

 

c)  100 %
  010315F00035
a) Construction/rehabilitation of flood mitigation facilities along Bauang River Basin, Brgy. Boy-utan, Bauang, La Union, K0257+978 - K0258+229.5 REHABILITATION/Bauang,La Union 2nd District Engineering Office,Region I
b) E.E. MADAYAG CONSTRUCTION
c) La Union 2nd District Engineering Office,Region I
d)  FMMR
   
a)

 11,682

a)  10/21/2015
b)  4/9/2016
c)  4/11/2016

 

c)  100 %
  010415F00130
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Poblacion Sur, Bayambang, Pangasinan CONSTRUCTION/Bayambang,Pangasinan 4th District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  10/14/2015
b)  3/1/2016
c)  3/1/2016

 

c)  100 %
  010415F00116
a) Construction of dike protection works, Ambayaoan River Control Project, Casaratan and Sobol, San Nicolas, Pangasinan CONSTRUCTION/San Nicolas,Pangasinan 3rd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 23,363

a)  10/13/2015
b)  4/4/2016
c)  3/15/2016

 

c)  100 %
  010415F00115
a) Construction/extension of dike protection works, Ambayaoan River Control Project, Calaocan and Sta. Maria West, San Nicolas, Pangasinan CONSTRUCTION/San Nicolas,Pangasinan 3rd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 17,721

a)  10/13/2015
b)  3/10/2016
c)  1/29/2016

 

c)  100 %
  010415F00113
a) Construction of dike with protection works, Agno River Control Project, Barangobong, Tayug, Pangasinan CONSTRUCTION/Tayug,Pangasinan 3rd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 27,707

a)  10/13/2015
b)  5/9/2016
c)  3/15/2016

 

c)  100 %
  010415F00112
a) Construction of bank protection works, Banila River Control Project at Pugaro-San Aurelio, Balungao, Pangasinan CONSTRUCTION/Balungao,Pangasinan 3rd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 18,926

a)  10/13/2015
b)  2/9/2016
c)  2/9/2016

 

c)  100 %
  010415F00114
a) Construction of dike with protection works, Agno River Control Project, San Patricio-Sta. Rosa, Santa Maria, Pangasinan CONSTRUCTION/Sta. Maria,Pangasinan 3rd District Engineering Office,Region I
b) ROGENOX CONSTRUCTION AND SUPPLY CORP.
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 13,920

a)  10/13/2015
b)  2/9/2016
c)  2/9/2016

 

c)  100 %
  010215H00019
a) Santiago-San Esteban Coastal Road leading to Santiago Cove, Santiago, Ilocos Sur GRAVEL TO PAVED/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) FIRST NORTHWAY DEVELOPMENT & CONSTRUCTION CORP.
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  TDTD
   
a)

 50,000

a)  10/6/2015
b)  3/16/2016
c)  8/31/2016

 

c)  100 %
  010415F00119
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Ambayat 2nd, Bayambang, Pangasinan CONSTRUCTION/Bayambang,Pangasinan 4th District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 8,000

a)  9/30/2015
b)  1/23/2016
c)  3/25/2016

 

c)  100 %
  010415F00134
a) Agno River Basin Flood Control Project - Phase I - Construction of Boulder Bank Protection - Brgy. Bantayan, Lingayen, Pangasinan CONSTRUCTION/Lingayen,Pangasinan 2nd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 10,000

a)  9/30/2015
b)  2/1/2016
c)  2/1/2016

 

c)  100 %
  010415F00120
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Ambayat 1st, Bayambang, Pangasinan CONSTRUCTION/Bayambang,Pangasinan 4th District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 15,000

a)  9/30/2015
b)  1/23/2016
c)  3/25/2016

 

c)  100 %
  010415F00118
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Managos, Bayambang, Pangasinan CONSTRUCTION/Bayambang,Pangasinan 4th District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  9/30/2015
b)  3/17/2016
c)  3/17/2016

 

c)  100 %
  010415H00356
a) Urdaneta Jct.-Dagupan Road (S00079LZ), Calasiao, Pangasinan K0206+325 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  MVUC
   
a)

 13,500

a)  9/29/2015
b)  2/25/2016
c)   

 

c)  36 %
  010415H00160
a) Stanza Br. (B02774LZ) along Lingayen-Labrador Div Rd RETROFITTING/REHABILITATION/STRENGTHENING/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  CNPB
   
a)

 7,735

a)  9/29/2015
b)  2/5/2016
c)  7/18/2016

 

c)  100 %
  010415H00146
a) Urdaneta Jct-Lingayen Rd via Zambales - K0376+800 - K0378+460 WIDENING - PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  WANR
   
a)

 25,000

a)  9/15/2015
b)  3/12/2016
c)  3/28/2016

 

c)  100 %
  010315H00005
a) Pagdalagan Br. (B02100LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,La Union 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  CNPW
   
a)

 49,500

a)  9/15/2015
b)  6/17/2016
c)   

 

c)  56 %
  010415T00065
a) Local Infrastructure Program - Completion of Multi-Purpose Building, Pozorrubio Central School, Pozorrubiio, Pangasinan 5th LD CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) FRAMECON BUILDERS
c) Pangasinan 3rd District Engineering Office,Region I
d)  RLIP
   
a)

 8,500

a)  9/14/2015
b)  3/11/2016
c)  3/11/2016

 

c)  100 %
  010415F00161
a) Improvement of Aloragat River Course, Brgy. Labayug, Calunetan and Killo, Sison, Pangasinan REHABILITATION/Sison,Pangasinan 3rd District Engineering Office,Region I
b) R.S. SEPIAN CONSTRUCTION & TRUCKING
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 14,244

a)  9/14/2015
b)  3/11/2016
c)  3/11/2016

 

c)  100 %
  010415T00070
a) Local Infrastructure Program - Completion of Multi-Purpose Building, Villanueva, Bautista, Pangasinan 5th LD CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) A.M.P. CONSTRUCTION
c) Pangasinan 3rd District Engineering Office,Region I
d)  RLIP
   
a)

 7,000

a)  9/14/2015
b)  2/10/2016
c)  2/10/2016

 

c)  100 %
  010415F00136
a) Agno River Basin Flood Control Project - Phase I - Construction of Gabion Bank Protection, Brgy. Salasa-Socony, Bugallon, Pangasinan CONSTRUCTION/Bugallon,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 10,000

a)  9/14/2015
b)  12/2/2015
c)  1/28/2016

 

c)  100 %
  010415F00162
a) Improvement of Aloragat River Course, Brgy. Villegas, Imbalbalatong, and Rosario, Pozorrubio, Pangasinan REHABILITATION/Pozorrubio,Pangasinan 3rd District Engineering Office,Region I
b) THUNDERBLAST VENTURES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 10,756

a)  9/14/2015
b)  2/10/2016
c)  2/10/2016

 

c)  100 %
  010415H00175
a) Concreting of Road from Lingayen Baywalk to Binmaley, Pangasinan GRAVEL TO PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 2nd District Engineering Office,Region I
d)  TDTD
   
a)

 50,000

a)  9/14/2015
b)  4/10/2016
c)  7/30/2016

 

c)  100 %
  010415T00010
a) Local Infrastructure Program - Construction/Rehabilitation of Multi-Purpose Building, Tayug, Pangasinan 6th LD CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) R.G.TABIN CONSTRUCTION AND SUPPLY
c) Pangasinan 3rd District Engineering Office,Region I
d)  RLIP
   
a)

 6,500

a)  9/14/2015
b)  2/10/2016
c)  2/8/2016

 

c)  100 %
  010315H00004
a) Lossoc Br. (B02647LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,La Union 2nd District Engineering Office,Region I
b) BONIMAR CONSTRUCTION ENTERPRISES
c) La Union 2nd District Engineering Office,Region I
d)  CNPW
   
a)

 36,409

a)  9/11/2015
b)  3/8/2016
c)   

 

c)  45 %
  010415H00360
a) Repair/Rehabilitation/Improvement (Additional Pavement Width) along Pangasinan-Zambales Road, S00308LZ, K0341+(-841) to K0341+(-281) with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) PANGASINAN NEW WILSON LUMBER & CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  MVUC
   
a)

 5,000

a)  9/11/2015
b)  11/9/2015
c)  5/22/2016

 

c)  100 %
  010315H00110
a) Repair/Rehabilitation/Improvement (Concreting of Existing Concrete Road) San Juan - San Gabriel Road, S05904LZ K0284+534 to K0285+360 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,La Union 1st District Engineering Office,Region I
b) H.G. LOPEZ CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  MVUC
   
a)

 11,400

a)  9/9/2015
b)  3/23/2016
c)  3/23/2016

 

c)  100 %
  010415H00372
a) Manzon Bridge (B01454LZ) along San Carlos-Calasiao Road and Approaches, San Carlos City, Pangasinan WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Regional Office,Region I
d)  CNPW
   
a)

 19,245

a)  9/5/2015
b)  2/1/2016
c)  2/15/2016

 

c)  100 %
  010415H00177
a) Tagamusing Br. (B00728LZ) along Manila North Rd WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 3rd District Engineering Office,Region I
d)  CNPW
   
a)

 48,000

a)  9/4/2015
b)  9/10/2016
c)   

 

c)  90 %
  010315T00023
a) Local Infrastructure Program - Completion of Multi-Purpose Building, Barangay Narra Oeste, San Fernando, La Union 1st LD CONSTRUCTION/DistrictWide,La Union 1st District Engineering Office,Region I
b) J.A. OLIVAR ENGINEERING DESIGN, CONSTRUCTION AND S
c) La Union 1st District Engineering Office,Region I
d)  RLIP
   
a)

 1,000

a)  8/29/2015
b)  2/22/2016
c)  1/14/2016

 

c)  100 %
  010315H00002
a) Old Poblacion Br. (B04183LZ) along Alilem-Sugpon-Sudipen Rd BRIDGE-TEMPORARY TO PERMANENT/DistrictWide,La Union 1st District Engineering Office,Region I
b) KRB CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  BTTP
   
a)

 28,750

a)  8/29/2015
b)  4/9/2016
c)   

 

c)  81 %
  010315H00044
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of RCDG Bridge and Approaches, K0284+765, along San Fernando-Bagulin Road, Brgy. Nagyubuyuhan, San Fernando City, La Union 2nd LD CONSTRUCTION/DistrictWide,La Union 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  VILP
   
a)

 20,000

a)  8/29/2015
b)  4/4/2016
c)   

 

c)  71 %
  010415F00143
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Salavante, Urbiztondo, Pangasinan CONSTRUCTION/Urbiztondo,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 14,000

a)  8/28/2015
b)  12/25/2015
c)  2/8/2016

 

c)  100 %
  010415F00139
a) Agno River Basin Flood Control Project - Phase II - Construction of Dike with Protection Works, Brgy. Sta. Cruz, San Jacinto, Pangasinan CONSTRUCTION/San Jacinto,Pangasinan 2nd District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 15,000

a)  8/28/2015
b)  11/25/2015
c)  4/8/2016

 

c)  100 %
  010415F00138
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Salavante, Mangatarem, Pangasinan CONSTRUCTION/Mangatarem,Pangasinan 2nd District Engineering Office,Region I
b) BERSONs CONSTRUCTION & TRADING
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  4/26/2016

 

c)  100 %
  010415F00137
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Caturay Sur, Mangatarem, Pangasinan CONSTRUCTION/Mangatarem,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  3/13/2016

 

c)  100 %
  010415F00135
a) Agno River Basin Flood Control Project - Phase I - Construction of Boulder Bank Protection - Brgy. Pangapisan, Lingayen, Pangasinan CONSTRUCTION/Lingayen,Pangasinan 2nd District Engineering Office,Region I
b) BERSONs CONSTRUCTION & TRADING
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 15,000

a)  8/28/2015
b)  12/30/2015
c)  1/19/2016

 

c)  100 %
  010415F00132
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Sawat, Urbiztondo, Pangasinan CONSTRUCTION/Urbiztondo,Pangasinan 2nd District Engineering Office,Region I
b) J.G. GARCIA CONSTRUCTION & SUPPLY (FOR: J.G. GARCIA CONST.)
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  5/31/2016

 

c)  100 %
  010415F00131
a) Agno River Basin Flood Control Project - Phase I - Construction of Boulder Bank Protection - Brgy. San Jose, Aguilar, Pangasinan CONSTRUCTION/Aguilar,Pangasinan 2nd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/28/2015
b)  2/8/2016
c)  1/18/2016

 

c)  100 %
  010415F00128
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Buaya, Mangatarem, Pangasinan CONSTRUCTION/Mangatarem,Pangasinan 2nd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  1/12/2016

 

c)  100 %
  010415F00126
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Malibong, Urbiztondo, Pangasinan CONSTRUCTION/Urbiztondo,Pangasinan 2nd District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  7/30/2016

 

c)  100 %
  010415F00144
a) Agno River Basin Flood Control Project - Phase I - Construction of Boulder Bank Protection - Brgy. Cabayaoasan, Bugallon, Pangasinan CONSTRUCTION/Bugallon,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/28/2015
b)  2/8/2016
c)  2/8/2016

 

c)  100 %
  010415F00124
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Caturay Norte, Mangatarem, Pangasinan CONSTRUCTION/Mangatarem,Pangasinan 2nd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  3/13/2016

 

c)  100 %
  010415F00117
a) Agno River Basin Flood Control Project - Phase I - Construction of Boulder Bank Protection - Brgy. Bocboc West, Aguilar, Pangasinan CONSTRUCTION/Aguilar,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/28/2015
b)  2/8/2016
c)  2/17/2016

 

c)  100 %
  010315H00009
a) Principe Br. (B02634LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,La Union 2nd District Engineering Office,Region I
b) ROADTECH CONSTRUCTION
c) La Union 2nd District Engineering Office,Region I
d)  CNPW
   
a)

 35,699

a)  8/28/2015
b)  2/23/2016
c)  6/1/2016

 

c)  100 %
  010415F00127
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Cabayaoasan, Mangatarem, Pangasinan CONSTRUCTION/Mangatarem,Pangasinan 2nd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  3/13/2016

 

c)  100 %
  010415H00157
a) Mangaldan-Manaoag-Binalonan Rd - K0198 + (-263) - K0200 + (-166) WIDENING - PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  WASR
   
a)

 50,000

a)  8/28/2015
b)  3/24/2016
c)  7/30/2016

 

c)  100 %
  010415H00038
a) Local Infrastructure Program - Construction of Road (Baywalk), Barangay Libsong East Lingayen to Barangay Baybay Lopez, Binmaley, Pangasinan 2nd LD GRAVEL TO PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 30,000

a)  8/28/2015
b)  2/23/2016
c)   

 

c)  92 %
  010415F00142
a) Agno River Basin Flood Control Project - Phase II - Construction of Bank Protection Works - Brgy. Galarin, Urbiztondo, Pangasinan CONSTRUCTION/Urbiztondo,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 22,000

a)  8/28/2015
b)  2/18/2016
c)  7/30/2016

 

c)  100 %
  010415H00145
a) Urdaneta Jct-Dagupan-Lingayen Rd - K0207 + (-277) - K0208 + 323 WIDENING - PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) PANGASINAN NEW WILSON LUMBER & CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  WANR
   
a)

 40,000

a)  8/28/2015
b)  2/23/2016
c)  7/30/2016

 

c)  100 %
  010215F00005
a) Construction of Riverwall/Boardwalk, Pandan, Caoayan, Ilocos Sur 1st LD CONSTRUCTION/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) MBB CONSTRUCTION
c) Ilocos Sur 1st District Engineering Office,Region I
d)  FMSD
   
a)

 46,795

a)  8/27/2015
b)  7/30/2016
c)   

 

c)  95.5 %
  010415H00174
a) Lingayen-Labrador Div Rd - K0362+-613 - K0362+498 PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION)
c) Pangasinan 2nd District Engineering Office,Region I
d)  NDOC
   
a)

 40,000

a)  8/27/2015
b)  2/22/2016
c)  3/13/2016

 

c)  100 %
  010415H00163
a) Pangasinan-Zambales Rd - K0367+820 - K0372+820 PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  NDOC
   
a)

 45,000

a)  8/27/2015
b)  2/22/2016
c)  4/13/2016

 

c)  100 %
  010415F00150
a) Agno River Basin Flood Control Project - Phase II - Construction/Extension of Boulder Bank Protection Works - Sitio Sta. Cruz, Brgy. Nacayo, Alcala, Pangasinan CONSTRUCTION/Alcala,Pangasinan 3rd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/26/2015
b)  2/21/2016
c)  2/21/2016

 

c)  100 %
  010115H00032
a) Local Infrastructure Program - Improvement of Eco Park Access Roads and Facilities, Batac, Ilocos Norte 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) CURRIMAO CONSTRUCTION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 9,900

a)  8/26/2015
b)  11/21/2015
c)  1/20/2016

 

c)  100 %
  010415F00146
a) Agno River Basin Flood Control Project - Phase II - Improvement of Anulid Poponto Floodway Low Water Channel, Brgy. Diaz-Vacante, Bautista, Pangasinan CONSTRUCTION/Bautista,Pangasinan 3rd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/26/2015
b)  1/22/2016
c)  1/22/2016

 

c)  100 %
  010415F00157
a) Agno River Basin Flood Control Project - Phase III - Raising of Grade of Dike - Brgy. Carusucan Sur, Asingan, Pangasinan CONSTRUCTION/Asingan,Pangasinan 3rd District Engineering Office,Region I
b) R.R. RICAFORT CONSTRUCTION AND SUPPLIES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMSD
   
a)

 30,000

a)  8/26/2015
b)  2/21/2016
c)  2/21/2016

 

c)  100 %
  010415H00365
a) Repair/Rehabilitation/Improvement (Construction of Lateral Drainage) Dagupan - Bonuan - San Fabian Road, S00301LZ, K0386+000 to K0387+702 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  MVUC
   
a)

 10,220

a)  8/26/2015
b)  2/21/2016
c)  2/21/2016

 

c)  100 %
  010415H00361
a) Repair/Rehabilitation/Improvement (Additional Pavement Width with Drainage Improvement) Dagupan - Bonuan - San Fabian Road, S00301LZ K0380+657 to K0382+425 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  MVUC
   
a)

 10,850

a)  8/26/2015
b)  1/22/2016
c)  7/15/2016

 

c)  100 %
  010315T00005
a) Local Infrastructure Program - Completion of Multi-Purpose Building, Barangay Bato, San Fernando, La Union 1st LD CONSTRUCTION/DistrictWide,La Union 1st District Engineering Office,Region I
b) ARM-ASIA CONSTRUCTION & ENGINEERING
c) La Union 1st District Engineering Office,Region I
d)  RLIP
   
a)

 1,000

a)  8/22/2015
b)  1/6/2016
c)  1/6/2016

 

c)  100 %
  010415H00350
a) Repair/Rehabilitation/Improvement (Drainage Improvement) Judge Jose De Venecia Sr. Ave., Calasiao, Pangasinan, S05985LZ, K0207+370 to K0207+996 with exceptions. OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/Calasiao,Pangasinan 4th District Engineering Office,Region I
b) JAM-C BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  MVUC
   
a)

 5,300

a)  8/20/2015
b)  1/16/2016
c)  2/29/2016

 

c)  100 %
  010115H00061
a) Concreting and Improvement of Laoag International Airport-Gabu-Fort Ilocandia Road, Laoag City, Ilocos Norte 1st LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Ilocos Norte 1st District Engineering Office,Region I
d)  TDAP
   
a)

 37,713

a)  8/19/2015
b)  3/27/2016
c)  3/27/2016

 

c)  100 %
  010315H00104
a) Repair/Rehabilitation/Improvement (Additional Pavement Width) Bacnotan - Luna - Balaoan Road, S00214LZ, K0303+000 to K0304+500 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/Balaoan,La Union 1st District Engineering Office,Region I
b) ROADTECH CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  MVUC
   
a)

 11,200

a)  8/19/2015
b)  1/28/2016
c)  1/24/2016

 

c)  100 %
  010315H00105
a) Repair/Rehabilitation/Improvement (Concreting of Shoulder) San Fernando Port Road S00247LZ, K0268+000 to K0269+222.90 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/San Fernando City,La Union 1st District Engineering Office,Region I
b) NORTHERN BUILDERS
c) La Union 1st District Engineering Office,Region I
d)  MVUC
   
a)

 10,000

a)  8/17/2015
b)  1/19/2016
c)  1/19/2016

 

c)  100 %
  010115H00070
a) Bongo Br. (B02411LZ) along Ilocos Norte-Abra Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) CHRISTIAN IAN CONSTRUCTION CORPORATION
c) Regional Office,Region I
d)  CNRW
   
a)

 253,000

a)  8/15/2015
b)  8/8/2016
c)   

 

c)  53 %
  010415H00183
a) Pangasinan-Nueva Vizcaya Road (Villa Verde Road), Pangasinan GRAVEL TO PAVED/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) NORTHERN BUILDERS
c) Regional Office,Region I
d)  CMGN
   
a)

 300,000

a)  8/15/2015
b)  8/8/2016
c)   

 

c)  84 %
  010415T00061
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Poblacion, Binalonan, Pangasinan 5th LD CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) R.G.TABIN CONSTRUCTION AND SUPPLY
c) Pangasinan 3rd District Engineering Office,Region I
d)  RLIP
   
a)

 7,400

a)  8/14/2015
b)  3/10/2016
c)  3/10/2016

 

c)  100 %
  010415F00147
a) Agno River Basin Flood Control Project - Phase III - Construction of Bank Protection - Brgy. San Patricio-Sta. Rosa, Sta. Maria, Pangasinan CONSTRUCTION/Sta. Maria,Pangasinan 3rd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  8/13/2015
b)  2/8/2016
c)  2/8/2016

 

c)  100 %
  010115F00048
a) Laoag River Basin Flood and Sabo Project, Marcos Flood Control along Bongo River, Brgy. Valdez Sitio Suerte, Marcos, Ilocos Norte 2nd LD CONSTRUCTION/Marcos,Ilocos Norte 2nd District Engineering Office,Region I
b) KRB CONSTRUCTION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 4,900

a)  8/12/2015
b)  12/19/2015
c)  3/1/2016

 

c)  100 %
  010115F00049
a) Laoag River Basin Flood and Sabo Project, Dike Extension along Cura River, Right Bank, Brgy. Mandaloque, Dingras, Ilocos Norte 2nd LD CONSTRUCTION/Dingras,Ilocos Norte 2nd District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 44,100

a)  8/12/2015
b)  5/2/2016
c)  8/16/2016

 

c)  100 %
  010115F00050
a) Laoag River Basin Flood and Sabo Project, Concrete Revetment along Bongo River, Brgy. Sta. Monica, Sitio 7, San Nicolas, Ilocos Norte 2nd LD CONSTRUCTION/San Nicolas,Ilocos Norte 2nd District Engineering Office,Region I
b) DJCM CONSTRUCTION CORPORATION (FORMERLY: DJCM CONSTRUCTION)
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 9,800

a)  8/12/2015
b)  12/5/2015
c)  1/22/2016

 

c)  100 %
  010115F00051
a) Laoag River Basin Flood and Sabo Project, Concrete Revetment along Bongo River, Brgy. Sta. Monica, Sitio 2, San Nicolas, Ilocos Norte 2nd LD CONSTRUCTION/San Nicolas,Ilocos Norte 2nd District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 9,800

a)  8/12/2015
b)  12/5/2015
c)  1/22/2016

 

c)  100 %
  010415H00171
a) Poblacion-San Jose-Namagbagan-Imbo-Tondol Road leading to Tondol Beach, Anda, Pangasinan GRAVEL TO PAVED/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) BERSONs CONSTRUCTION & TRADING
c) Pangasinan 1st District Engineering Office,Region I
d)  TDTD
   
a)

 50,000

a)  8/5/2015
b)  3/31/2016
c)  3/30/2016

 

c)  100 %
  010415H00161
a) Poblacion-Sabangan Road leading to Umbrella Rocks and Abagatanen White Beach, Agno, Pangasinan GRAVEL TO PAVED/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) BERSONs CONSTRUCTION & TRADING
c) Pangasinan 1st District Engineering Office,Region I
d)  TDTD
   
a)

 46,636

a)  8/3/2015
b)  3/29/2016
c)  3/29/2016

 

c)  100 %
  010215H00007
a) Bical Br. (B00589LZ) along Manila North Rd RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNPB
   
a)

 27,918

a)  8/3/2015
b)  2/20/2016
c)  8/1/2016

 

c)  100 %
  010215H00008
a) Paoa Br. along Vigan Airport Rd CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) P.T. DIAMOND MERCHANDISE AND CONSTRUCTION
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNNP
   
a)

 18,396

a)  8/3/2015
b)  2/1/2016
c)  3/31/2016

 

c)  100 %
  010115H00034
a) Caruan Br. 2 along Manila North Rd, K0511+660 CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) ZEDIK BUILDERS
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNNP
   
a)

 21,600

a)  7/31/2015
b)  8/6/2016
c)   

 

c)  94.56 %
  010115H00043
a) Baludavid Br. (B02391LZ) along Ilocos Norte-Apayao Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) BUSILAC BUILDERS INC.
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNRW
   
a)

 30,000

a)  7/31/2015
b)  8/31/2016
c)   

 

c)  72 %
  010115F00043
a) Laoag River Basin Flood Control and Sabo Project, Tonoton-Natdek Flood Control along Laoag-Sarrat-Piddig-Solsona Road, Piddig, Ilocos Norte 1st LD CONSTRUCTION/Piddig,Ilocos Norte 1st District Engineering Office,Region I
b) KATHA BUILDERS
c) Ilocos Norte 1st District Engineering Office,Region I
d)  FMSD
   
a)

 30,000

a)  7/31/2015
b)  2/15/2016
c)  2/15/2016

 

c)  100 %
  010115F00042
a) Laoag River Basin Flood Control and Sabo Project, Rehabilitation of Tonoton River Flood Control along Dingras River, Piddig, Ilocos Norte 1st LD CONSTRUCTION/Piddig,Ilocos Norte 1st District Engineering Office,Region I
b) C.T. LEONCIO CONSTRUCTION & TRADING
c) Ilocos Norte 1st District Engineering Office,Region I
d)  FMSD
   
a)

 25,000

a)  7/31/2015
b)  2/15/2016
c)  2/10/2016

 

c)  100 %
  010115F00040
a) Laoag River Basin Flood Control and Sabo Project, Construction/Extension of Revetment (Dupitac Flood Control) Piddig, Ilocos Norte 1st LD CONSTRUCTION/Piddig,Ilocos Norte 1st District Engineering Office,Region I
b) BLUE MOUNTAIN BUILDERS & GENERAL MDSE.(FOR. BLUE M
c) Ilocos Norte 1st District Engineering Office,Region I
d)  FMSD
   
a)

 10,000

a)  7/31/2015
b)  1/17/2016
c)  1/16/2016

 

c)  100 %
  010115F00039
a) Laoag River Basin Flood Control and Sabo Project, Construction/Rehabilitation of Flood Control Revetment along Bolo River, Brgy. San Isidro, Dumalneg, Ilocos Norte 1st LD CONSTRUCTION/Dumalneg,Ilocos Norte 1st District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  FMSD
   
a)

 50,000

a)  7/31/2015
b)  2/29/2016
c)  2/29/2016

 

c)  100 %
  010115H00035
a) Caruan Br. 1 along Manila North Rd, K0510+748 CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNNP
   
a)

 36,000

a)  7/31/2015
b)  8/6/2016
c)   

 

c)  95.7 %
  010115H00040
a) Caruan Br. 5 along Manila North Rd, K0513+785 CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) ZEDIK BUILDERS
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNNP
   
a)

 27,000

a)  7/31/2015
b)  8/13/2016
c)   

 

c)  94 %
  010115T00025
a) Local Infrastructure Program - Construction of Multi-Purpose Building; (Phase 7), National Highway, Batac City Ilocos Norte 2nd LD CONSTRUCTION/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 50,000

a)  7/29/2015
b)  8/9/2016
c)   

 

c)  98.2 %
  010115T00010
a) Local Infrastructure Program - Construction of Multi-Purpose Building: Phase 6, Barangay Calaguip, National Highway, Batac City, Ilocos Norte 2nd LD CONSTRUCTION/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 20,000

a)  7/29/2015
b)  11/21/2015
c)  1/18/2016

 

c)  100 %
  010115F00038
a) Laoag River Basin Flood Control and Sabo Project, Construction/Rehabilitation of Flood Control Revetment along Bolo River, Brgy. San Isidro at Sitio Kos-Kosi, Dumalneg, Ilocos Norte 1st LD CONSTRUCTION/Dumalneg,Ilocos Norte 1st District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  FMSD
   
a)

 45,000

a)  7/29/2015
b)  2/14/2016
c)  2/14/2016

 

c)  100 %
  010115H00021
a) Local Infrastructure Program - Improvement of Eco Park Access Roads and Facilities, Nueva Era, Ilocos Norte 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) GACUTAN CONSTRUCTION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 20,000

a)  7/22/2015
b)  4/18/2016
c)  5/2/2016

 

c)  100 %
  010115H00015
a) Local Infrastructure Program - Improvement of access roads and facilities of Baruyen Zigzag/Bangui Bay View Station/Sentila Hill, Bangui,. Ilocos Norte, 1st LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) ASIAN PEARL CONSTRUCTION & DEVT. CORP.
c) Ilocos Norte 1st District Engineering Office,Region I
d)  RLIP
   
a)

 20,000

a)  7/21/2015
b)  1/21/2016
c)  1/21/2016

 

c)  100 %
  010415F00036
a) Construction of River Bank Protection along Agno River, Bocboc Section, San Carlos City, Pangasinan 3rd LD CONSTRUCTION/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 50,000

a)  7/20/2015
b)  3/25/2016
c)  3/25/2016

 

c)  100 %
  010115H00031
a) Local Infrastructure Program - Construction of San Pedro Bridge with Approaches at Brgy. San Pedro, Batac City, Ilocos Norte, 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) R.U. AQUINO CONSTRUCTION AND DEVELOPMENT CORP. (FO
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 15,000

a)  7/17/2015
b)  5/5/2016
c)  8/30/2016

 

c)  100 %
  010415H00089
a) Local Infrastructure Program - Construction of Road, Baywalk, Barangay Baybay Lopez, Binmaley, Pangasinan 2nd LD GRAVEL TO PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 20,000

a)  7/14/2015
b)  12/10/2015
c)  7/30/2016

 

c)  100 %
  010415T00054
a) Local Infrastructure Program - Construction of Area Equipment Service Building (Phase II), DPWH, Pangasinan 2nd District Engineering Office CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) KENWOOD CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 9,000

a)  7/8/2015
b)  12/4/2015
c)  3/1/2016

 

c)  100 %
  010315H00106
a) Manila North Road, San Juan, La Union, S00186LZ: K0274+000 to K0280+000 with exceptions PAVED (CONCRETE) TO PAVED (CONCRETE)/San Juan,La Union 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  MVUC
   
a)

 48,330

a)  7/8/2015
b)  1/29/2016
c)  1/22/2016

 

c)  100 %
  010415H00131
a) Construction of Alaminos-Bani By-Pass Road, Pangasinan 1st LD GRAVEL TO PAVED/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) Pangasinan 1st District Engineering Office,Region I
d)  CBPR
   
a)

 50,000

a)  7/7/2015
b)  4/1/2016
c)  4/1/2016

 

c)  100 %
  010415H00133
a) Off Carriageway Improvement (Concreting of Shoulder with drainage) of Mangaldan-Manaoag-Binalonan Rd - K0210+318.4 - K0211+750 PAVED (CONCRETE) TO PAVED (CONCRETE)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  NDOC
   
a)

 30,000

a)  7/6/2015
b)  1/1/2016
c)  2/15/2016

 

c)  100 %
  010315H00008
a) Taboc Br. (B02650LZ) along Manila North Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,La Union 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  CNRW
   
a)

 30,000

a)  7/6/2015
b)  2/24/2016
c)   

 

c)  84 %
  010215T00002
a) Local Infrastructure Program - Construction of MPB, Candon Trade Center Phase II, Candon City, Ilocos Sur 2nd LD CONSTRUCTION/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) VIGAN FORTUNE CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 10,000

a)  7/1/2015
b)  2/18/2016
c)   

 

c)  60 %
  010115H00044
a) Ilocos Norte-Apayao Rd - K0537+554 - K0541+000 GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) RCD GEN. CONTRACTOR & CONSTRUCTION SUPPLY
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  CMGN
   
a)

 35,491

a)  6/26/2015
b)  3/31/2016
c)   

 

c)  91.8 %
  010115H00018
a) Local Infrastructure Program - Rehabilitation/replacement of Taytay-Pasil Bridge, Paoay, Ilocos Norte 2nd LD CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) RCD GEN. CONTRACTOR & CONSTRUCTION SUPPLY
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 7,000

a)  6/26/2015
b)  3/16/2016
c)  3/16/2016

 

c)  100 %
  010215H00117
a) ROW - Construction of Candon City By-Pass Road, Candon City, Ilocos Sur 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) By Administration
c) Regional Office,Region I
d)  CBPR
   
a)

 38,950

a)  6/25/2015
b)  4/20/2016
c)  7/25/2016

 

c)  100 %
  010115H00020
a) Local Infrastructure Program - Improvement-concreting of FMR at Brgys. Bugasi, Valdez and Sinamar, Banna, Ilocos Norte 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) ZEDIK BUILDERS
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 20,000

a)  6/18/2015
b)  3/15/2016
c)  3/15/2016

 

c)  100 %
  010115H00017
a) Local Infrastructure Program - Rehabilitation and/or replacement of Malasin Bridge, Paoay, Ilocos Norte 2nd LD CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) REMIGIO GENERAL CONSTRUCTION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 7,000

a)  6/17/2015
b)  3/7/2016
c)  3/7/2016

 

c)  100 %
  010415H00120
a) Pangasinan-La Union Inter-Provl Rd - K0385+000 - K0386+400 OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  CDNR
   
a)

 22,000

a)  6/15/2015
b)  11/13/2015
c)  4/25/2016

 

c)  100 %
  010415F00047
a) Manaoag Flood Control Projects - Construction of Boulder Bank Protection (Hand-Laid Rock Embankment & Gabion) with Spurdikes along Aloragat-Tulong River, Inamotan, Pangasinan 4th LD CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  6/9/2015
b)  10/6/2015
c)  1/19/2016

 

c)  100 %
  010415H00045
a) Local Infrastructure Program - Construction of Local Road, Lingayen to Binmaley, Pangasinan (Baywalk), Pangasinan 2nd LD GRAVEL TO PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) J.C. FERRER CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 4,000

a)  6/9/2015
b)  8/22/2015
c)  3/14/2016

 

c)  100 %
  010415H00004
a) Pangasinan-Zambales Road - K0299+000 - K0300+000, K0306+096 - K0307+197, K0308+000 - K0308+543 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) ROADTECH CONSTRUCTION
c) Pangasinan 1st District Engineering Office,Region I
d)  UPAR
   
a)

 37,843

a)  6/9/2015
b)  1/4/2016
c)  1/3/2016

 

c)  100 %
  010415F00038
a) Manaoag Flood Control Projects - Construction of Boulder Bank Protection (Hand-Laid Rock Embankment & Gabion ) with Spurdikes along Aloragat River, Bisal-Bucao and Baritao, Pangasinan 4th LD CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) BONIMAR CONSTRUCTION ENTERPRISES
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 15,000

a)  6/2/2015
b)  9/29/2015
c)  1/2/2016

 

c)  100 %
  010415H00185
a) Viray Br. (B00844LZ) along Sn Nicolas-Natividad-Sn Quintin-Umingan-Guimba Rd RETROFITTING/REHABILITATION/STRENGTHENING/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) MONOLITHIC CONSTRUCTION & CONCRETE PRODUCTS, INC.
c) Regional Office,Region I
d)  CNPB
   
a)

 60,000

a)  5/29/2015
b)  1/13/2016
c)   

 

c)  99 %
  010115H00023
a) Local Infrastructure Program - Concreting of Baresbes-San Marcelino Access Road in Sitio Sto. Domingo, San Marcelino and Baresbes, Dingras, Ilocos Norte 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 30,000

a)  5/26/2015
b)  12/6/2015
c)  1/24/2016

 

c)  100 %
  010415H00143
a) Alaminos-Bolinao Rd - K0325+000 - K0326+000, K0321+(-204) - K0323+133 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 1st District Engineering Office,Region I
d)  UPSR
   
a)

 47,110

a)  5/22/2015
b)  2/15/2016
c)  2/15/2016

 

c)  100 %
  010415H00154
a) Urdaneta Jct-Dagupan Rd - K0203+800 - K0204+700, Calasiao Section, Phase III, including ROW, Pangasinan 3rd LD WIDENING - PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  WANR
   
a)

 50,000

a)  5/20/2015
b)  12/8/2015
c)  6/25/2016

 

c)  100 %
  010415H00179
a) Bonbonan Br. (B00733LZ) along Manila North Rd WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 3rd District Engineering Office,Region I
d)  CNPW
   
a)

 16,000

a)  5/12/2015
b)  1/31/2016
c)  1/31/2016

 

c)  100 %
  010415H00003
a) Pangasinan-Zambales Rd - K0320+765 - K0321+000, K0322+810 - K0323+770, K0329+535 - K0330+000, K0330+258 - K0332+085 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Pangasinan 1st District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 1st District Engineering Office,Region I
d)  UPAR
   
a)

 49,636

a)  5/12/2015
b)  2/5/2016
c)  2/14/2016

 

c)  100 %
  010415F00039
a) Pantal Dike, Dagupan City CONSTRUCTION/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 2nd District Engineering Office,Region I
d)  FMSD
   
a)

 35,000

a)  5/12/2015
b)  3/6/2016
c)   

 

c)  73 %
  010415H00343
a) Mangaldan-Manaoag-Binalonan Road, Pangasinan, S00021LZ: C0 to C800 with exceptions; S00022LZ: K0198+460 to K0204+777 with exceptions CONSTRUCTION OF NEW BRIDGE/Districtwide-4th Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) Joint Venture - BET CONSTRUCTION & SUPPLY et. al.
c) Regional Office,Region I
d)  MVUC
   
a)

 68,788

a)  5/8/2015
b)  11/3/2015
c)   

 

c)  67 %
  010415H00168
a) Concreting/Improvement of Roads leading to Señor Divino Tesoro Shrine, Calasiao, Pangasinan GRAVEL TO PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  TDTD
   
a)

 41,755

a)  5/5/2015
b)  10/30/2015
c)  10/30/2015

 

c)  100 %
  010215H00006
a) San Juan Br. (B00590LZ) along Manila North Rd RETROFITTING/REHABILITATION/STRENGTHENING/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) SATRAP CONSTRUCTION CO., INC.
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNPB
   
a)

 18,748

a)  5/4/2015
b)  12/12/2015
c)  8/1/2016

 

c)  100 %
  019915H00020
a) Manila North Rd - K0265+-597 -K0265+-337, K0273+190 - K0276+705, K0277+000 - K0278+000, K0280+335 - K0282+000, K0282+229 - K0282+449, K0286+000 - K0286+740, K0286+754 - K0287+430, K0298+288 - K0298+928 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Regional Office,Region I
b) Joint Venture - ST. GERRARD CONSTRUCTION et. al.
c) Regional Office,Region I
d)  UPAR
   
a)

 124,739

a)  4/30/2015
b)  12/25/2015
c)  7/1/2016

 

c)  100 %
  019915H00025
a) Manila North Rd - K0265+(-658.41) - K0274+000 WIDENING - PAVED/DistrictWide,Regional Office,Region I
b) R.S. SEPIAN CONSTRUCTION & TRUCKING
c) Regional Office,Region I
d)  WANR
   
a)

 85,318

a)  4/30/2015
b)  10/26/2015
c)  4/25/2016

 

c)  100 %
  010215H00003
a) Sinabaan Br. 1 (B00764LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) P.T. DIAMOND MERCHANDISE AND CONSTRUCTION
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNPW
   
a)

 17,980

a)  4/29/2015
b)  11/6/2015
c)  7/1/2016

 

c)  100 %
  010415H00147
a) Pangasinan-Tarlac Rd - K0167 + (-880) - K0168 + 61, K0168 + 126 - K0168 + 157 WIDENING - PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Pangasinan 2nd District Engineering Office,Region I
d)  WANR
   
a)

 49,250

a)  4/28/2015
b)  11/23/2015
c)  1/6/2016

 

c)  100 %
  010415H00112
a) Local Infrastructure Program - Rehabilitation/Reconstruction of Libsong Road to Maramba Blvd., Lingayen, Pangasinan 2nd LD GRAVEL TO PAVED/Districtwide-2nd Congressional District,Pangasinan 2nd District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 9,000

a)  4/28/2015
b)  8/25/2015
c)  1/6/2016

 

c)  100 %
  010415H00115
a) Sn Carlos-Calasiao Rd - K0205 + 083 - K0207 + 083 WIDENING - PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  WASR
   
a)

 50,000

a)  4/24/2015
b)  10/11/2015
c)  12/8/2015

 

c)  100 %
  010415F00037
a) Construction of River Bank Protection along Agno River, Wawa Section, Bayambang, Pangasinan 3rd LD CONSTRUCTION/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  FMSD
   
a)

 30,000

a)  4/24/2015
b)  9/14/2015
c)  2/29/2016

 

c)  100 %
  010415H00128
a) Urdaneta Jct-Dagupan Rd - K0201+129 - K0202+300 (Tuliao Section) (B/S) OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS)/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) JASA BUILDERS
c) Pangasinan 4th District Engineering Office,Region I
d)  CDNR
   
a)

 30,000

a)  4/24/2015
b)  10/13/2015
c)  1/25/2016

 

c)  100 %
  010415H00148
a) Calasiao Old Rd - K0204 + (-30) - K0207 + 267 WIDENING - PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) BERSONs CONSTRUCTION & TRADING
c) Pangasinan 4th District Engineering Office,Region I
d)  WASR
   
a)

 40,000

a)  4/24/2015
b)  9/27/2015
c)  9/27/2015

 

c)  100 %
  010415H00180
a) Bacag Br. (B00724LZ) along Manila North Rd WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) BIG BERTHA CONSTRUCTION & DEVELOPMENT
c) Pangasinan 3rd District Engineering Office,Region I
d)  CNPW
   
a)

 28,000

a)  4/17/2015
b)  1/30/2016
c)  1/30/2016

 

c)  100 %
  010415H00181
a) Mitura Br. (B00726LZ) along Manila North Rd WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 3rd District Engineering Office,Region I
d)  CNPW
   
a)

 40,000

a)  4/17/2015
b)  1/19/2016
c)  1/19/2016

 

c)  100 %
  010115H00036
a) Binasay Br. (B02759LZ) along Laoag-Balaccad Rd WIDENING OF BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) REMIGIO GENERAL CONSTRUCTION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  CNPW
   
a)

 13,100

a)  4/16/2015
b)  12/6/2015
c)  1/5/2016

 

c)  100 %
  010215H00037
a) Construction of Candon City By-Pass Road, Candon City, Ilocos Sur 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) Joint Venture - ST. GERRARD CONSTRUCTION et. al.
c) Regional Office,Region I
d)  CBPR
   
a)

 161,050

a)  4/15/2015
b)  3/4/2016
c)  7/24/2016

 

c)  100 %
  019915H00035
a) Jct Santiago-Banayoyo-Lidlidda-Sn Emilio-Quirino - K0382+420 - K0384+1338, K0384+1475 - K0387+678 GRAVEL TO PAVED/DistrictWide,Regional Office,Region I
b) Joint Venture - MBB CONSTRUCTION et. al.
c) Regional Office,Region I
d)  RUSR
   
a)

 150,000

a)  4/15/2015
b)  10/31/2015
c)  5/31/2016

 

c)  100 %
  010215H00038
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Completion of Sugpon Bridge along Alilem-Sugpon-Sudipen Road (Phase III), Sugpon, Ilocos Sur 2nd LD CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) BMK CONSTRUCTION CORPORATION (FORMERLY B.M.K. CONSTRUCTION)
c) Regional Office,Region I
d)  VILP
   
a)

 140,000

a)  4/15/2015
b)  2/8/2016
c)   

 

c)  40 %
  010215H00018
a) Magsingal Br. (B00587LZ) along Manila North Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) P.T. DIAMOND MERCHANDISE AND CONSTRUCTION
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNRW
   
a)

 16,758

a)  4/13/2015
b)  10/21/2015
c)  2/16/2016

 

c)  100 %
  010315H00016
a) Masupi Br. along Manila North Rd CONSTRUCTION OF NEW BRIDGE/DistrictWide,La Union 1st District Engineering Office,Region I
b) KRB CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  CNNP
   
a)

 13,500

a)  4/10/2015
b)  12/1/2015
c)  2/29/2016

 

c)  100 %
  010115H00067
a) Improvement/Concreting of Jct. Ilocos Norte-Abra Road leading to Tubeg Viewdeck, Imelda Park, Hercules Mine Access to Mt. Sicapoo Camp Site, Nueva Era, Ilocos Norte GRAVEL TO PAVED/Nueva Era,Ilocos Norte 2nd District Engineering Office,Region I
b) Joint Venture - GACUTAN CONSTRUCTION et. al.
c) Regional Office,Region I
d)  TDTD
   
a)

 150,000

a)  3/31/2015
b)  12/24/2015
c)  5/31/2016

 

c)  100 %
  010315H00003
a) Bacnotan-Luna-Balaoan Rd - K0284+-781 - K0285+000, K0285+322 - K0285+992, K0304+247 - K0304+607 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,La Union 1st District Engineering Office,Region I
b) CHIARA CONSTRUCTION
c) La Union 1st District Engineering Office,Region I
d)  UPSR
   
a)

 44,564

a)  3/31/2015
b)  3/26/2016
c)  3/31/2016

 

c)  100 %
  019915H00021
a) Manila North Rd - K0487 + (-418) - K0487 + 426.81, K0530+ (-579.59) - K0537+ 801 WIDENING - PAVED/DistrictWide,Regional Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Regional Office,Region I
d)  WANR
   
a)

 123,402

a)  3/30/2015
b)  1/23/2016
c)  5/31/2016

 

c)  100 %
  010415H00189
a) Construction and Improvement of Urdaneta-Manaoag Road leading to Our Lady of Manaoag Shrine and Miraculous Virgin's Well, Manaoag, Pangasinan GRAVEL TO PAVED/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
c) Regional Office,Region I
d)  TDTD
   
a)

 142,500

a)  3/26/2015
b)  12/4/2015
c)  8/1/2016

 

c)  100 %
  010115H00060
a) Tangaoan-Pallas Road leading to Paraiso Ecotourism Project Eco and Reforestation Project, Piddig, Ilocos Norte GRAVEL TO PAVED/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) EGB CONSTRUCTION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  TDTD
   
a)

 43,706

a)  3/24/2015
b)  12/16/2015
c)  2/1/2016

 

c)  100 %
  010215H00010
a) Cabugao Br. along Manila North Rd CONSTRUCTION OF NEW BRIDGE/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNNP
   
a)

 9,890

a)  3/24/2015
b)  10/1/2015
c)  8/1/2016

 

c)  100 %
  010215H00009
a) Teppeng Br. (B00594LZ) along Manila North Rd REPLACEMENT OF DAMAGED BRIDGE/DistrictWide,Ilocos Sur 1st District Engineering Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Ilocos Sur 1st District Engineering Office,Region I
d)  CNRW
   
a)

 27,474

a)  3/16/2015
b)  10/23/2015
c)  8/1/2016

 

c)  100 %
  010215T00004
a) Local Infrastructure Program - Construction/Repair/Rehabilitation of Public Market, Suyo, Ilocos Sur 2nd LD CONSTRUCTION/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 10,000

a)  3/16/2015
b)  1/9/2016
c)  8/31/2016

 

c)  100 %
  010315H00012
a) Saytan Br. (B02627LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,La Union 2nd District Engineering Office,Region I
b) JOMARCANN GENERAL CONSTRUCTION
c) La Union 2nd District Engineering Office,Region I
d)  CNPW
   
a)

 14,452

a)  3/11/2015
b)  8/20/2015
c)  7/5/2016

 

c)  100 %
  010315H00006
a) Magsaoang Br. (B02646LZ) along Manila North Rd WIDENING OF BRIDGE/DistrictWide,La Union 2nd District Engineering Office,Region I
b) KANE CONSTRUCTION, INC.
c) La Union 2nd District Engineering Office,Region I
d)  CNPW
   
a)

 13,732

a)  3/11/2015
b)  8/20/2015
c)  2/15/2016

 

c)  100 %
  010215H00030
a) Cervantes-Quirino Rd - K0385+596 - K0386+000, K0387+317 - K0387+913 PAVED (CONCRETE) TO PAVED (CONCRETE)/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) TRIBU DESIGN & CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  UPSR
   
a)

 32,070

a)  3/11/2015
b)  3/3/2016
c)   

 

c)  98 %
  010215H00013
a) Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Completion of Del Pilar Road leading to Tirad Pass, San Emilio, Ilocos Sur 2nd LD GRAVEL TO PAVED/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) VIKING CONSTRUCTION & SUPPLY
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  VILP
   
a)

 40,000

a)  3/11/2015
b)  2/27/2016
c)  3/31/2016

 

c)  100 %
  010415H00123
a) Camiling-Wawa-Bayambang-Malasiqui-Sta Barbara - K0181 + 432.70 - K0183+ 032.70 WIDENING - PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) ORIENTAL SALES CENTER AND CONTRACTOR
c) Pangasinan 4th District Engineering Office,Region I
d)  WASR
   
a)

 40,000

a)  3/10/2015
b)  10/20/2015
c)  10/20/2015

 

c)  100 %
  010415H00152
a) Urdaneta Jct-Dagupan Rd - K0192 + 650 - K0194 + 680 WIDENING - PAVED/DistrictWide,Pangasinan 4th District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Pangasinan 4th District Engineering Office,Region I
d)  WANR
   
a)

 50,000

a)  3/9/2015
b)  8/31/2015
c)  9/21/2015

 

c)  100 %
  010415H00186
a) Bolosan Br. (B00758LZ) along Urdaneta Jct-Dagupan Rd WIDENING OF BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) AQUINO-DELA CRUZ ENGINEERING & CONSTRUCTION
c) Regional Office,Region I
d)  CNPW
   
a)

 30,855

a)  3/6/2015
b)  9/22/2015
c)  7/15/2016

 

c)  100 %
  010315H00046
a) Ribsoan Br. 2 (B00668LZ) along Bauang-Baguio Rd REPLACEMENT OF DAMAGED BRIDGE/Bauang,La Union 2nd District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Regional Office,Region I
d)  CNRW
   
a)

 65,000

a)  3/6/2015
b)  11/2/2015
c)   

 

c)  50 %
  010415H00191
a) Padilla Br. (B02144LZ) along Pangasinan-Zambales Rd RETROFITTING/REHABILITATION/STRENGTHENING/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) ST. GERRARD CONSTRUCTION
c) Regional Office,Region I
d)  CNPB
   
a)

 51,984

a)  3/6/2015
b)  9/1/2015
c)  6/2/2016

 

c)  100 %
  010415H00187
a) Construction and Improvement of San Jacinto-Manaoag Road (From Dagupan City) leading to Our Lady of Manaoag and Miraculous Virgin's Well, San Jacinto-Manaoag, Pangasinan GRAVEL TO PAVED/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Regional Office,Region I
d)  TDTD
   
a)

 92,400

a)  2/28/2015
b)  9/25/2015
c)  8/1/2016

 

c)  100 %
  010415H00184
a) Nining Br. 2 (B00840LZ) along Sn Nicolas-Natividad-Sn Quintin-Umingan-Guimba Rd REPLACEMENT OF DAMAGED BRIDGE/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
c) Regional Office,Region I
d)  CNRW
   
a)

 40,000

a)  2/25/2015
b)  8/23/2015
c)  1/15/2016

 

c)  100 %
  019915H00036
a) Manila North Rd - K0235 + 297.68 - K0236 + 127.85, K0259 + (-140.3) - K0262 + 437.37 WIDENING - PAVED/DistrictWide,Regional Office,Region I
b) Joint Venture - CHIARA CONSTRUCTION et. al.
c) Regional Office,Region I
d)  WANR
   
a)

 109,896

a)  2/20/2015
b)  9/10/2015
c)  2/11/2016

 

c)  100 %
  010315F00020
a) Construction of Flood Control Structure (Drinage Canal), Parian - Pennsylvania Ave., Parian, San Fernando City, La Union 1st LD CONSTRUCTION/DistrictWide,La Union 1st District Engineering Office,Region I
b) Joint Venture - JAJR CONSTRUCTION et. al.
c) La Union 1st District Engineering Office,Region I
d)  FMSD
   
a)

 20,000

a)  2/11/2015
b)  10/11/2015
c)  4/4/2016

 

c)  100 %
  010215T00008
a) Local Infrastructure Program - Construction of Multi-Purpose Building Candon Trade Center, Candon City, Ilocos Sur 2nd LD CONSTRUCTION/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) VIGAN FORTUNE CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 15,000

a)  2/10/2015
b)  1/18/2016
c)  5/20/2016

 

c)  100 %
  010215T00007
a) Local Infrastructure Program - Construction of Multi-Purpose Building, Sports Complex, Candon National High School, Barangay Bagani Campo, Candon City, Ilocos Sur 2nd LD CONSTRUCTION/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) MBB CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 15,000

a)  2/5/2015
b)  1/30/2016
c)  2/29/2016

 

c)  100 %
  010215T00001
a) Local Infrastructure Program - Construction of MPB, Sports Complex, (Phase II) Candon National High School, Barangay Bagani Campo, Candon City, Ilocos Sur 2nd LD CONSTRUCTION/DistrictWide,Ilocos Sur 2nd District Engineering Office,Region I
b) MBB CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 10,000

a)  2/5/2015
b)  12/10/2015
c)  3/1/2016

 

c)  100 %
  019915H00031
a) Manila North Rd - K0187 + 520 - K0189 + 280, K0189 + 919 - K0191 + 000, K0194 + 741 - K0198 + 000 WIDENING - PAVED/DistrictWide,Regional Office,Region I
b) R.A. PAHATI CONST. & SUPPLY, INC.
c) Regional Office,Region I
d)  WANR
   
a)

 142,217

a)  1/29/2015
b)  9/5/2015
c)  2/1/2016

 

c)  100 %
  010214F00023
a) Repair/Rehabilitation of Kiat Flood Control Dike, Alilem, Ilocos Sur REHABILITATION/Alilem,Ilocos Sur 2nd District Engineering Office,Region I
b) KVC CONSTRUCTION
c) Ilocos Sur 2nd District Engineering Office,Region I
d)  FMMR
   
a)

 10,000

a)  10/13/2015
b)  3/31/2016
c)  4/15/2016

 

c)  100 %
  010414F00127
a) Repair/ Rehabilitation of Bank Protection, Banila River Control Project at Brgy. Angayan Norte, Balungao, Pangasinan CONSTRUCTION/Balungao,Pangasinan 3rd District Engineering Office,Region I
b) BET CONSTRUCTION & SUPPLY
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 16,000

a)  9/14/2015
b)  3/2/2016
c)  3/2/2016

 

c)  100 %
  010414F00126
a) Repair/ Rehabilitation of Bank Protection, Banila River Control Project at Brgy Capulaan- San Aurelio, Balungao, Pangasinan CONSTRUCTION/Balungao,Pangasinan 3rd District Engineering Office,Region I
b) MKM MARKETING
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 10,000

a)  9/14/2015
b)  1/11/2016
c)  1/11/2016

 

c)  100 %
  010414F00124
a) Improvement of Aloragat River Course Brgy. Villegas, Imbalbalatong and Rosario, Pozorrubio, Pangasinan CONSTRUCTION/Pozorrubio,Pangasinan 3rd District Engineering Office,Region I
b) THUNDERBLAST VENTURES
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 5,000

a)  9/14/2015
b)  1/24/2016
c)  1/24/2016

 

c)  100 %
  010414F00130
a) Extension/Constrcution of Dike with Protection Works along Bued River Control project at Brgy.s Cauringan and Artacho, Sison, Pangasinan CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) A.C. SOLIVEN CONSTRUCTION & GENERAL MERCHANDISE
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 41,723

a)  9/8/2015
b)  3/2/2016
c)  3/2/2016

 

c)  100 %
  010414F00138
a) River Improvement using Backhoe with Clearing, Macalong River Control Project at Brgy. Mabanogbog, Nancamaliran and Bayaoas, Urdaneta City CONSTRUCTION/Districtwide-5th Congressional District,Pangasinan 3rd District Engineering Office,Region I
b) R.S. SEPIAN CONSTRUCTION & TRUCKING
c) Pangasinan 3rd District Engineering Office,Region I
d)  FMMR
   
a)

 15,000

a)  8/25/2015
b)  1/4/2016
c)  1/4/2016

 

c)  100 %
  010114T00002
a) Local Infrastructure Program - Construction of Multi-Purpose Building - Brgy. Callaguip, National Highway, Batac City CONSTRUCTION/DistrictWide,Ilocos Norte 2nd District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 2nd District Engineering Office,Region I
d)  RLIP
   
a)

 24,500

a)  7/29/2015
b)  4/1/2016
c)  3/31/2016

 

c)  100 %
  010414H00251
a) Repair/ Rehabilitation/ Improvement/ Construction of Pedestrian Overpass, Manila North Road (S00334LZ), near Lyceum University - South, Nancayan, Urdaneta, Pangasinan, K0178+100 CONSTRUCTION OF NEW BRIDGE/Urdaneta City,Pangasinan 3rd District Engineering Office,Region I
b) ALPHIN TRADING & CONSTRUCTION
c) Pangasinan 3rd District Engineering Office,Region I
d)  MVUC
   
a)

 10,000

a)  12/15/2014
b)  9/5/2016
c)   

 

c)  0.01 %
  010114H00030
a) Subec Bridge along Manila North Road WIDENING OF BRIDGE/DistrictWide,Ilocos Norte 1st District Engineering Office,Region I
b) AJ TAYLAN CONSTRUCTION CORPORATION
c) Ilocos Norte 1st District Engineering Office,Region I
d)  WPBR
   
a)

 43,200

a)  5/9/2014
b)  5/22/2015
c)  1/29/2016

 

c)  100 %
  010414H00226
a) Construction of Urdaneta City By-pass Road including RROW, Urdaneta City, Pangasinan 5th LD - Civil Works GRAVEL TO PAVED/Urdaneta City,Pangasinan 3rd District Engineering Office,Region I
b) ALCEL CONSTRUCTION
c) Regional Office,Region I
d)  CNBP
   
a)

 100,000

a)  4/1/2014
b)  10/6/2015
c)  7/31/2016

 

c)  100 %
  010411H00691
a) Construction of Carmen East-West Diversion Road, Sta. 0+730.96 - Sta. 5+793.74, Rosales, Pangasinan GRAVEL TO PAVED/Rosales,Pangasinan 3rd District Engineering Office,Region I
b) NORTHERN BUILDERS
c) Regional Office,Region I
d)  DPWH
   
a)

 244,193

a)  2/14/2015
b)  8/7/2016
c)   

 

c)  84 %

 

Back to Map

 

For more information, please contact :