Project Description: 
  • The project involves the construction of a 4 kilometer, 4–lane paved toll road that will pass through the New Bilibid Prison reservation that will connect Bacoor, Cavite to the South Luzon Expressway. 
  • Segment I – starts at junction Daang Hari – Daang Reyna, Elliptical Road or Rotunda, Km 0+000 and ends in Sta. 2 +300
  • Segment II – starts from 2+300 and ends at South Luzon Expressway near Susana Heights Interchange, Km 4+000
Project Objectives: 

The project aims to:

  • provide an alternative route to/from Metro Manila/Cavite, and improve Region IV-A’s/CALABARZON’s competitiveness as an investment destination.
  • decongest traffic in Cavite, Las Piñas, and Muntinlupa.
  • reduce travel time by an average of 45 minutes from Daang Hari to Alabang Interchange
  • provide a new access to the National Bilibid Prison (NBP) property, which is intended to be redeveloped into a mixed commercial, residential, and institutional estate.
Project Benefits: 

At the end of construction, the project is expected to:

  • benefit 25,000 travelers per day
  • reduce travel time by an average of 45 minutes from Daang Hari to Alabang Interchange
Project Concessionaire: 


Ayala Corporation (AC)


MCX Tollways, Inc.

Project Cost: 


Amount (Billion)

Private Sector

P 1.629

Government Support

P 1.025


P 0.722

New Bridge across SLEX

P 0.035

Independent Consultant

P 0.014

Advance Works Improvements

P 0.050

Variation Order

P 0.203


P 2.654

Project Status: 
  • Concession Agreement was signed on April 03, 2012
  • The project was opened to traffic on July 24, 2015
  • The O&M Division of PPP Service is conducting monthly routine inspection for the monitoring of the maintenance of the expressway structures as categorized on Section 15 of the MPSS and Section 12.4 of the Concession Agreement.
  • Certificate of Final Completion was signed by this Department on 21 December 2016 and conformed by Concessionaire on 09 February 2017
  • Completed and operational