Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
July 11, 2018 FY 2018 WIN8G02471 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310201100076000
Project ID: P00201260LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Primary Roads – Daang Maharlika (LZ) – K0600+ -008 – K0602+683, K0605+000 – K0605+167
Physical Target: CW1 - Road Widening/ 5.727 lane-km
CW2 - Construction of Drainage Structure along Road/ 3,873 lm.
Unit Cost: CW1 – Php 8.67 M/lane-km
CW2 – Php 12.09T/lm.
Estimated Cost: Php 100.0 M
(As Modified)
July 11, 2018 FY 2018 WIN8G02478 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310201100082000
Project ID: P00201259LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Primary Roads – Daang Maharlika (LZ) – K0530+360 – K0534+630
Physical Target: CW1 - Road Widening/ 8.91084 lane-km
Right-of-Way Acquisition (ROW)/ 22,277.10 sq.m.
Unit Cost: CW1 – Php 17.31 M/lane-km
CW2 – Php 849.68/sq.m.
Estimated Cost: Php 179.41 M
(As Modified)
July 11, 2018 FY 2018 WIN8G02473 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310201100195000
Project ID: P00201263LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Primary Roads – Rolando A Andaya Highway – K0288+513.10 – K0290+720
Physical Target: CW1 – Construction of Concrete Road/ 4.415 lane-km
CW2 - Construction of Road Slope Protection Structure/ 9,689.93sq.m.
CW3 - Construction of Drainage Structure along Road/ 2,445lm
Unit Cost: CW1 – Php 18.16M/lane-km
CW2 – Php 3,586.47/sq.m.
CW3 – Php 12,198.99/lm.
Estimated Cost: Php 150.0 M
(As Modified)
July 11, 2018 FY 2018 WIN8G02473 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310201100195000
Project ID: P00201263LZ
OO1: Ensure Safe and Reliable National Road System - Network Development Program – Road Widening – Primary Roads – Rolando A Andaya Highway – K0288+513.10 – K0290+720
Physical Target: CW1 – Construction of Concrete Road/ 4.415 lane-km
CW2 - Construction of Road Slope Protection Structure/ 9,689.93sq.m.
CW3 - Construction of Drainage Structure along Road/ 2,445lm
Unit Cost: CW1 – Php 18.16M/lane-km
CW2 – Php 3,586.47/sq.m.
CW3 – Php 12,198.99/lm.
Estimated Cost: Php 150.0 M
(As Modified)
July 11, 2018 FY 2018 WIN8G02481 FY 2018 GAA R.A. 10964 December 29, 2017 Region V Regional Office V
UACS No.: 310101100328000
Project ID: P00223278LZ
OO2: Protect Lives and Properties Against Major Floods – Flood Management Program –
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems –
Rehabilitation/Improvement of Busay Flood Control Dike, Busay, Sta. 7+267.00 - Sta. 7+462.73, Sta. 7+532 - Sta. 7+863.90, Sta. 7+991.67 - Sta. 8+321.80, Sta. 7+360 - Sta. 7+637, Daraga, Albay
Physical Target: CW1 – Construction of Dike/ 1,134.76 lm
Unit Cost: CW1 – Php 85.040 T/lm
Estimated Cost: Php 100.0 M
(As Modified)
July 10, 2018 FY - 2018 WINF05653 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
Local Program

Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0139+800 - K0142+300,
Espanola

CW1: 10.072 lane km ( Road Widening )
Allocation: 150,000,000 Php

TO:
Widening of Puerto Proncesa South Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0139+800 - K0141+891,
Espanola

CW1: 8.424 lane km ( Road Widening )
Allocation: 150,000,000 Php
July 10, 2018 FY - 2018 WIN8F05651 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
Local Program

Local Roads and Bridges - Local Roads
Construction/Repair/Rehabilitation/Improvement of
Various Infrastructure including Local Projects

FROM:
Widening of Puerto Princesa South Road
from two (2) to six (6) lanes including drainage
structures and other ancillary works,
K0105+100 - K0107+400,
Narra

CW1: 9.004 lane km ( Road Widening )
Allocation: 140,000,000 Php

TO:
Widening of Puerto Princesa South Road
from two (2) to six (6 lanes including drainage
structures and other ancillary works,
K0104+388 - K0105+742,
K0105+771 - K0106+922,
Narra

CW1: 10.064 lane km ( Road Widening )
Allocation: 140,000,000 Php
July 9, 2018 FY 2018 WIN8G02508 FY 2018 GAA January 4, 2018 Region III Nueva Ecija 1st District Engineering Office
Asset Preservation Program – Preventive Maintenance – Primary Roads – San Jose – Lupao Rd, K0160+000 – K0160+778, K0172+299.40 – K0172+565, K0172+592.20 – K0173+716.40
July 9, 2018 FY - 2018 WIN8F05649 FY - 2018 GAA DPWH Infra December 19, 2017 Region IV-B Southern Mindoro Engineering District Office
001 - Ensure Safe and Reliable National Road System

Asset Preservation -
Rehabilitation/Reconstruction/Upgrading of Damaged
Paved Roads - Secondary Roads

FROM:
Calapan South Rd
( K0169+040 - K0169+121,
K0171+000 - K0171+845,
K0172+092 - K0172+700 )

CW1: 3.068 lane km ( Reconstruction from Paved
to Concrete )
Allocation: 40,000,000 Php

TO:
Calapan South Rd
( K0169+040 - K0169+123.50,
K0177+176 - K0178+000.00,
K0178+544 - K0179+000.00 )

CW1: 2.789 lane km ( Reconstruction from Paved
to Concrete )
Allocation : 40,000,000 Php
July 9, 2018 FY - 2018 WIN8F05689 FY - 2018 GAA DPWH Infra Program December 19, 2017 Region IV-B Regional Office IV-B
001 - Ensure Safe and Reliable National Road System

Network Development - Construction of Missing Links/
New Roads

FROM:
Victoria Sablayan ( Mindoro Cross-Island Road ),
Package 2, Occidental Mindoro

CW1: 4.282 lane km ( Construction of Concrete Road )
Allocation: 150,000,000 Php

TO:
Victoria - Sablayan ( Mindoro Cross Island Road ),
Occidental Mindodo

CW1: 3.816 lane km ( Construction of Concrete Road )
Allocation : 150,000,000 Php