Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
July 6, 2017 FY 2017 WIN7E01773 UACS No. 292003020401759 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
MFO 2 – Flood Management Services – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems – Improvement of Drainage Laterals along J.B. Vargas Bridge, Brgy. Addition Hills, San Juan City [Construction of Drainage Structure along Road]
UACS No. 292003020401759
Physical Target/ Cost (‘000)
Original: 12 lm
Unit Cost (‘000): P1,666.67/lm
Allocation (‘000): P20,000.0
WIN7E01773

As Modified
MFO 2 – Flood Management Services – Construction/ Maintenance of Flood Mitigation Structures and Drainage Systems – Rehabilitationn/Improvement of Drainage System along Veloso, Diwa and Asiñas Sts., Barangay Salapan, San Juan City [Rehabilitation/Major Repair of Drainage Structure along Road]
UACS No. 292003020401759
Physical Target/ Cost (‘000)
New: 12 lm
Unit Cost (‘000): P24.272/lm
Estimated Cost (‘000): P20,000.0
WIN7E01773

July 6, 2017 2017 WIN7G01639 FY 2017 (R.A 10924) June 15, 2017 Region IX Zamboanga City District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems -
Construction/Extension of Flood Control along San Jose Gusu Creek, Baliwasan - San Jose Gusu Section (including Right of Way Acquisition), Zamboanga City
Site I
Right Side = Sta. 0+000 - Sta. 0+111
Left Side = Sta. 0+050 - Sta. 0+324
Site II
Right Side = Sta. 2+268 - Sta. 2+455.20
Allocation:
P 8.00 Million (Total)
P 7,720,000.00 (Construction of Flood Mitigation Structure)
P 280,000.00 (ROW Acquisition)
Physical Target:
572 lm. (Construction of Flood Mitigation Structure)
80 sq.m. (ROW Acquisition)
Unit Cost:
P 13,496.50/ lm (Construction of Flood Mitigation Structure)
P 3,500.00/ sq.m. (ROW Acquisition)
July 6, 2017 FY 2017 WIN7E01775 UACS No. 103004010309911 January 1, 2017 National Capital Region Metro Manila 1st District Engineering Office
As per GAA
Locally-Funded Projects – VIILP – Buildings and Other Structures – Multipurpose/Facilities – Construction of Multi-Purpose Buildings, Second District, Marikina City [Construction of Multipurpose Buildings]
UACS No. 103004010309911
Physical Target/ Cost (‘000)
Original: 1 bldg.
Unit Cost (‘000): P25,000.0/Bldg.
Allocation (‘000): P25,000.0
WIN7E01775

As Modified
Locally-Funded Projects – VIILP – Buildings and Other Structures – Multipurpose/Facilities – Construction/ Repair/Rehabilitation of Multi-Purpose Buildings including Site Developments, Second District, Marikina City [Construction of Multipurpose Buildings]
UACS No. 103004010309911
Physical Target/ Cost (‘000)
New: 6 bldg.
Unit Cost (‘000): P4,166.67/Bldg.
Estimated Cost (‘000): P25,000.0
WIN7E01775
July 6, 2017 2017 WIN7G01622 FY 2017 (R.A 10924) June 13, 2017 Region IX Zamboanga City District Engineering Office
Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 lanes -
Widening of Permanent Bridge Mialim Bridge (B00559MN) and Approaches along Pagadian City - Zamboanga City Road, Zamboanga City -
Bridge Limits: K1864+007.61 - k1864+027.25
Area = 19.64 x 9.54 = 187.3656 sq.m.
Allocation:
P 20.00 Million (Total)
P 18,400,000.00 (Bridge)
P 1,600,000.00 (ROW Acquisition)
Physical Target:
187.3656 sq.m. (Bridge)
457 sq.m. (ROW Acquisition)
Unit Cost:
P 98,203.73/ sq.m. (Bridge)
P 3,501.09/ sq.m. (ROW Acquisition)
July 6, 2017 2017 WIN7G01635 FY 2017 (R.A 10924) June 13, 2017 Region IX Zamboanga City District Engineering Office
Roads and Bridges - Local Bridges -
Construction of Permanent Bridge (Flatslab Bridge) and Approaches at Barangay Cabatangan, Zamboanga City -
Bridge Limits: Sta. 0+099.23 - Sta. 0+108.03
L = 8.80 ln.m.
Area = 8.80 x 8.92 = 78.496 sq.m.
Allocation:
P8.00 Million (Total)
p 7.20 Million (Bridge)
P 0.80 Million (ROW Acquisition)
Physical Target:
78.496 sq.m. (Bridge)
320.00 sq.m. (ROW Acquisition)
Unit Cost:
P 91,724.42/ sq.m. (Bridge)
P 2,500.00/ sq.m. (ROW Acquisition)
July 6, 2017 2017 WIN7G01625 FY 2017 (R.A 10924) June 14, 2017 Region IX Zamboanga City District Engineering Office
Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 lanes -
Widening of Permanent Bridge - Sinubong Bridge (B01163MN) along Zamboanga City - Labuan - Limpapa Road,
Bridge Limits:
Abutment A = K1963+268.33
Abutment B = K1963+299.17
L = 30.84 ln.m.
Area = 30.84 x 9.54 = 294.2136 sq.m.
Allocation:
P 30.00 Million (Total)
P 29,900,000.00 (Widening of Bridge)
P 100,000.00 (ROW Acquisition)
Physical Target:
294.2136 sq.m. (Widening of Bridge)
35 sq.m. (ROW Acquisition)
Unit Cost:
P 101,626.85/ sq.m. (Widening of Bridge)
P 2,857.14/ sq.m. (ROW Acquisition)
July 6, 2017 2017 WIN7G01620 FY 2017 (R.A 10924) June 14, 2017 Region IX Zamboanga City District Engineering Office
Construction and Maintenance of Bridges along National Roads - Replacement of Permanent Weak Bridges -
Replacement of Togtobo Bridge (PSCG) (B00560MN) along Pagadian City - Zamboanga City Road -
Bridge Limits:
Abutment A = K1864+206.25
Abutment B = K1864+244.09
Area = 37.84 x 9.54 = 360.9936 sq.m.
Allocation
P 25.00 Million (Total)
P 23.80 Million (Replacement of Bridge)
P 1.20 Million (ROW Acquisition)
Physical Target:
360.9936 sq.m. (Replacement of Bridge)
280 sq.m. (ROW Acquisition)
Unit Cost:
P 65,929.15/ sq.m. (Replacement of Bridge)
P 4,285.71/ sq.m. (ROW Acquisition)
July 6, 2017 2017 WIN7G01606 FY 2017 (R.A 10924) June 13, 2017 Region IX Zamboanga City District Engineering Office
Construction and Maintenance of Bridges along National Roads - Widening of Permanent Bridges to more than 2 lanes -
Widening of Bridge - Tarling Bridge (B01165MN) along Zamboanga City - Labuan - Limpapa Road
Bridge Limits:
Abutment A = K1964+116.08
Abutment B = K1964+136.92
Area = 20.84 x 9.54 = 198.8136 sq.m.
Allocation: P 15.00 Million
Physical Target: 198.8136 sq.m
Unit Cost: P 75,447.55/ sq.m.
July 6, 2017 2017 WIN7G01611 FY 2017 (R.A 10924) June 9, 2017 Region IX Zamboanga City District Engineering Office
Construction/Maintenance of Flood Mitigation Structures and Drainage Systems -
Construction/Extension of Flood Control at Sinunuc River, (including Right of Way Acquisition), Zamboanga City 1st District -
Sta. 0+316 - Sta. 0+416 (Left Side Downstream)
Sta. 0+000 - Sta. 0+411.41 (Right Side Upstream)
Sta. 0+040 - Sta. 0+312.47 (Left Side Upstream)
Sta. 0+336.48 - Sta. 0+411.41 (Left Side Upstream)
Allocation: P 20.00 Million
Physical Target: 858.81 lm.
Unit Cost: P 23,288.04/ lm.
July 6, 2017 2017 WIN7G01612 FY 2017 (R.A 10924) June 9, 2017 Region IX Zamboanga City District Engineering Office
Network Development - Improvement/Widening of National Roads - Secondary -
Road Widening of Gov. Camins Road including RROW (S01201MN),
Chainage 000 - Chainage 160
Allocation:
P 49.00 Million (Total)
P 11.172 Million (Road Widening)
P 37.828 Million (ROW Acquisition)
Physical Target:
0.32 lane km (Road Widening)
4,500 sq.m. (ROW Acquisition)
Unit Cost:
P 34,912,500.00/ lane km (Road Widening)
P 8,406.22/ sq.m. (ROW Acquisition)