Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
April 19, 2017 2017 WIN7G01123 FY 2017 (R.A 10924) March 28, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Roads and Bridges - Local Roads -
Construction of Dapitan Sunrise Bypass Road, (including RROW), Dapitan City, Zamboanga del Norte,
Sta. 0+224.20 - Sta. 1+165
Allocation:
Php 50.00 Million (Total)
Php 49.00 Million (Concrete Road)
Php 1.00 Million (ROW Acquisition)
Physical Target:
1.882 lane km (Concrete Road)
18,815 sq.m. (ROW Acquisition)
Unit Cost:
Php 26,036,131.77/lane km (Concrete Road)
Php 53.15/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7C01518 FY 2017 (R.A 10924) March 28, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Network Development - Improvement/Widening of National Roads - Tertiary Roads -
Road Widening - Dipolog - Polanco - Piñan - Jct. Oroquieta Rd including RROW
K1814+680 - k1815+694.50
Allocation:
Php 43.860 Million (Total)
Php 42,982,800.00 (Road)
Php 877,200.00 (ROW Acquisition)
Physical Target:
2.029 lane km (Road)
12,174 sq.m. (ROW Acquisition)
Unit Cost:
Php 21,184,228.68/ lane km (Road)
Php 72.06/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7C01517 FY 2017 (R.A 10924) March 28, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Roads and Bridges - Local Roads -
Construction/Rehabilitation of Concrete Road, Sunset boulevard, (including RROW), Dapitan City, Zamboanga del Norte,
Sta. 0+003.05 - Sta. 1+260
Allocation:
Php 50.00 Million (Total)
Php 49.00 Million (Concrete Road)
Php 1.00 Million (ROW Acquisition)
Physical Target:
2.514 lane km (Concrete Road)
6,089.50 sq.m. (ROW Acquisition)
Unit Cost:
Php 19,490,851.23/ lane km (Concrete Road)
Php 164.22/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7G01336 FY 2017 (R.A 10924) February 10, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Road Upgrading (unpaved to paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standards (HDM-4 Project Analysis) - Tertiary Roads -
Road Upgrading Gravel to Paved - Ilaya - Isis - Polanco Rd including ROW -
K1819+218 - K1820+100
Allocation:
Php 19.075 Million (Total)
Php 18,884,250.00 (Road)
Php 190,750.00 (ROW Acquisition)
Physical Target:
1.764 lane km (Road)
10,584.00 sq.m. (ROW Acquisition)
Unit Cost:
Php 10,705,357.14/lane km (Road)
Php 18.02/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7G01339 FY 2017 (R.A 10924) February 10, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Roads and Bridges - Local Roads -
Concreting of Road including RROW, Barangay Bagong Baguio, Segio Osmeña, Zamboanga del Norte
Sta. 5+000 - Sta. 6+636
Allocation:
Php 30.00 Million (Total)
Php 29,400,000.00 (Road)
Php 600,000.00 (ROW Acquisition)
Physical Target:
3.272 lane km (Road)
6,544 sq.m. (ROW Acquisition)
Unit Cost:
Php 8,985,330.07/lane km (Road)
Php 91.69/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7E01299 GAA FY 2017 January 2, 2017 Region III Nueva Ecija 1st District Engineering Office
Roads and Bridges - Local Roads:

Rehabiliattion of Pasong-Inchik-Pura Road, Guimba-Pura, Section, Guimba, Nueva Ecija
April 19, 2017 2017 WIN7G01341 FY 2017 (R.A 10924) February 10, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Network Development - Improvement/Widening of National Roads - Other Primary Roads -
Road Widening - Dipolog - Oroquieta National Road including RROW
K1808+914 - K1809+843
Allocation:
Php 32.09 Million (Total)
Php 31,448,200.00 (Road)
Php 641,800.00 (ROW Acquisition)
Physical Target:
1.858 lane km (Road)
11,148 sq.m. (ROW Acquisition)
Unit Cost:
Php 16,925,834.23/ lane km (Road)
Php 57.57/sq.m. (ROW Acquisition)
April 19, 2017 2017 165003015100257 GAA FY 2017 January 1, 2017 Region II Isabela 4th District Engineering Office
MFO 1 : NATIONAL ROAD NETWORK SERVICES
Network Development
Improvement/Widening of National Roads
Secondary Roads
Cordon-Diffun Rd - K0317 + -105 - K0318 + 288, K0318 + 304 - K0318 + 372, K0318 + 380 - K0318 + 985, K0318 + 997 - K0318 + 1064
April 19, 2017 2017 WIN7G01337 FY 2017 (R.A 10924) February 10, 2017 Region IX Zamboanga del Norte 3rd District Engineering Office
Road Upgrading (unpaved to paved) based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road Standards (HDM-4) Project Analysis - Tertiary -
Road Upgrading Gravel to Paved including RROW Piñan - Mutia Rd -
K1833+940 - K1834+068,
K1834+320 - K1834+580,
K1838+340 - K1838+562,
K1823+115 - K1823+539
Allocation:
Php 43.403 Million (Total)
Php 42,968,970.00 (Road)
Php 434,030.00 (ROW Acquisition)
Physical Target:
2.068 lane km (Road)
13,128 sq.m. (ROW Acquisition)
Unit Cost:
Php 20,778,031.91/lane km (Road)
Php 33.06/sq.m. (ROW Acquisition)
April 19, 2017 2017 WIN7G01283 FY 2017 (R.A. 10924) April 7, 2017 Region IX Zamboanga Sibugay 2nd District Engineering Office
Buildings and Other Structures - Multipurpose/Facilities
Rehabilitation/Major Repair of Public Market Roofing at Brgy. Don Andres, Ipil, Zamboanga Sibugay
Allocation: P 2.00 Million
Physical Target: 1 no. of building
Unit Cost: P 2,000,000/no. of building