Modification and Realignment



Date Posted GAA Year Reference No SARO Number SARO Date Region Implementing Office Description
July 2, 2018 FY 2018 WIN8G02383 FY 2018 GAA January 4, 2018 Region III Pampanga 1st District Engineering Office
Asset Preservation Program – Preventive Maintenance – Tertiary Roads – Baliwag – Candaba – Sta. Ana Rd, K0063+867 – K0064+050
July 2, 2018 FY 2018 WIN8C03274 310202100056000 June 21, 2018 Region IX Zamboanga City District Engineering Office
UACS No. 310202100056000
Project ID: P00200707MN

OO1: Ensure Safe and Reliable National Road System
Network Development - Road Widening - Primary Roads
Gov. Camins Rd incl. ROW (S01201MN), Chainage 160 -Chainage 802
Physical Target:
CW-1: Road Widening: 1.750 lane km
Unit Cost: P 18,730,086.26/lane km
Physical Target:
ROW: 39,800.00 sq.m
Unit Cost: P 1,005.47962/sq.m
EAO: P 2,640,260.00
Allocation: P 75,436,000.00
July 2, 2018 FY 2018 WIN8G02439 FY 2018 GAA January 4, 2018 Region III Pampanga 1st District Engineering Office
Asset Preservation Program – Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse and Landslide – Tertiary Roads – Candaba – San Miguel Rd, K0073+094.40 – K0073+408
July 2, 2018 FY 2018 WIN8C03276 300116201152000 June 21, 2018 Region IX Zamboanga City District Engineering Office
UACS No. 300116201152000
Project ID: P00258446MN

Local Program:

Local Roads and Bridges - Local Roads - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects
Construction of 2nd and 4th St., Aurora Village, Guiwan, Zamboanga Cirty
Physical Target:
CW-1 - Construction of Concrete Road: 1.04528 lane km
Unit Cost: P 9,375,478.341/lane km
EAO: P 200,000.00
Allocation: P 10,000,000.00
July 2, 2018 FY 2018 GAA WIN8C03313 FY 2018 GAA RA 10964 January 1, 2018 Region XI Regional Office XI
MODIFICATION:

FROM: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Malagamot Road – Jct. Mudiang Road Bypass, incl. Bridge, Davao CIty
Physical Target:
CW1: 1.442 Lane Km (Road Widening)
CW2: 421.50 Sq.m. (Replacement of Bridge)
CW3: 354.06 Sq.m. (Replacement of Bridge)
CW4: 1.442 Lane Km (Reconstruction from Paved to Concrete)
CW5: 24,712 Sq.m. (Off-Carriageway Imrpovement: Shoulder Paving/Construction)
Allocation:
TOTAL: P 297,674,000.00
CW1: P 13,915,300.00 (Road Widening)
CW2: P 38,600,000.00 (Replacement of Bridge)
CW3: P 32,424,000.00 (Replacement of Bridge)
CW4: P 35,901,860.00 (Reconstruction from Paved to Concrete)
CW5: P 166,414,590.00 (Off-Carriageway Imrpovement: Shoulder Paving/Construction)
EAO: P 10,418,590.00

TO: OO1: Ensure Safe and Reliable National Road System – Network Development Program
Construction of Bypass and Diversion Roads
Malagamot Road – Jct. Mudiang Road Bypass, incl. Bridge, Davao CIty
Physical Target:
CW1: 0.334 Lane Km (Road Widening)
CW2: 421.50 Sq.m. (Replacement of Bridge)
CW3: 354.06 Sq.m. (Replacement of Bridge)
CW4: 2.216 Lane Km (Reconstruction from Paved to Concrete)
CW5: 155.826 Sq.m. (Off-Carriageway Imrpovement: Shoulder Paving/Construction)
ROW: 1,147.83 Sq.m.
Allocation:
TOTAL: P 297,674,000.00
CW1: P 4,806,235.90 (Road Widening)
CW2: P 57,758,887.25 (Replacement of Bridge)
CW3: P 43,701,227.87 (Replacement of Bridge)
CW4: P 75,438,256.92 (Reconstruction from Paved to Concrete)
CW5: P 2,610,392.06 (Off-Carriageway Imrpovement: Shoulder Paving/Construction)
ROW: P 3,860,000.00
EAO: P 10,418,590.00
EXC: P 102,674,000.00
July 2, 2018 FY 2018 WIN8C03288 300117201961000 June 21, 2018 Region IX Zamboanga City District Engineering Office
UACS No. 300117201961000
Project ID: P00251824MN

Local Program:

Local Roads and Bridges - Local Roads - Local Infrastructure Program
Concreting of Road including drainage facilities at Carillo Drive, Tumaga, Zamboanga City
Physical Target:
CW-1 - Construction of Concrete Road: 0.12619 lane km
Unit Cost: P 31,381,250.50/lane km
EAO: P 40,000.00
Allocation: P 4,000,000.00
July 2, 2018 FY 2018 WIN8G02479 FY 2018 GAA January 4, 2018 Region III Pampanga 1st District Engineering Office
Asset Preservation Program – Rehabilitation/Reconstruction of Roads with Slips, Slope Collapse and Landslide – Tertiary Roads – Baliwag - Candaba – Sta. Ana Rd, K0066+155 – K0067+357
July 2, 2018 FY 2018 WIN8G02470 FY 2018 GAA January 4, 2018 Region III Pampanga 1st District Engineering Office
Flood Management Program – Construction / Maintenance of Flood Mitigation Structures and Drainage System – Rehabilitation / Improvement of Sapang Are Creek, Sta. 0+000 to Sta. 1+300 at Apalit, Pampanga
July 2, 2018 FY 2018 WIN8G02445 FY 2018 GAA January 4, 2018 Region III Pampanga 1st District Engineering Office
Flood Management Program – Construction / Maintenance of Flood Mitigation Structures and Drainage System – Rehabilitation / Improvement of Dawe River, Sta. 0+000 to Sta. 0+723.30 at Minalin, Pampanga
July 2, 2018 FY 2018 GAA WIN8C03312 FY 2018 GAA RA 10964 January 1, 2018 Region XI Davao Oriental 2nd District Engineering Office
MODIFICATION:

FROM: Convergence and Special Support Program
Convergence and Special Support – Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Jct. La Union – Mt. Hamiguitan Road leading to Nt. Hamiguitan, San Isidro, Davao Oriental

Physical Target:
CW1: 1.200 Lane Km (Construction of Concrete Road)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Concrete Road)
EAO: P 400,000.00

TO: Convergence and Special Support Program
Convergence and Special Support – Construction/Improvement of Access Roads leading to Declared Tourism Destinations
Jct. La Union – Mt. Hamiguitan Road leading to Nt. Hamiguitan, San Isidro, Davao Oriental

Physical Target:
CW1: 800 Sq. m. (Construction of Road Slope Protection Structure)
Allocation:
TOTAL: P 20,000,000.00
CW1: P 19,600,000.00 (Construction of Road Slope Protection Structure)
EAO: P 400,000.00