NAIA EXPRESSWAY

Project Description: 
    • The NAIA Expressway Project Phase II Project is a PPP project with a 4–lane elevated expressway starting at the end point of Phase I and ending at PAGCOR Entertainment City. It will provide access to NAIA Terminal 1, 2 and 3 as well as an interface with the Skyway and Cavitex. Aside from the Main Viaduct, there are 13 entry and exit ramps as well as 3 connecting ramps. The NAIA Expressway alignment follows the existing road along Sales Avenue, Andrews Avenue, Electrical Road, above Paranaque River and NAIA Road.
    1. Main Viaduct (four–lane elevated expressway from Sales Road to MIA Road): 4.70–km
    2. Ramps (16 entry and exit ramps including the connecting ramps to NAIA Terminals 1,2 and 3): 7.95 km
    3. At–grade (ground level) road that will provide access to and from the PAGCOR Entertainment City– 2.20 km
    • Phase II–A Macapagal Blvd. – MIA Road/NAIA Terminals 1 and 2
    • Phase II–B Domestic Road-Andrews Avenue–Sales Road including Entertainment City
    Project Objectives: 

    This project aims to:

    • provide better access to Ninoy Aquino International Airport (Terminals 1, 2 & 3) and connect to the Skyway network of NCR, in addition to providing better access to Entertainment City.
    • reduce traffic congestion of roads in the vicinity of the NAIA Terminals
    • improve international/domestic investment environment with better infrastructure.
    Project Benefits: 

    The project is expected to:

    • benefit 80,000 travellers per day and is expected to reduce travel time from Entertainment City to Terminals 1 & 2 (Phase IIA), estimated from 25 minutes to 8 minutes. With the opening of Phase IIB of the NAIAx, the travel time from SLEX to NAIA is from 1 hour to 20 minutes.
    • connect two existing expressways, the Skyway 1 and the CAVITEX Expressway.
    • The Private Concessionaire paid to government P 11 Billion as premium payment.
    Project Concessionaire: 

    Vertex Tollways Development Inc. (VTDI)

    Project Cost: 
    ActivitiesAmount (Billion)
    Civil WorksP 10.977
    Government SupportP 7.093
         Transaction Advisory ServicesP 0.014
         Right-of-Way AcquisitionP 3.977
         MeralcoP 0.200
         Independent ConsultantP 0.802
         Variation OrderP 2.100
    Total                    P 18.070                                                          
    Project Status: 
    • Under Operation and Maintenance
    • The O&M Division of PPP is conducting monthly routine inspection for the monitoring of the maintenance of the expressway structures as categorized on Section 15 of the MPSS and Section 12.4 of the Concession Agreement
    Project Alignment: 
    Project Timeline: 
    SectionsOpening Date
    Phase IIA except CAVITEX area22 September 2016
    Phase IIB except Villamor Air Base Section21 December 2016
    Cavitex Section (Ramps 11 and 12)27 December 2016
    Circulo del Mundo Bypass Road30 December 2016
    Connectivity of NAIAx 1 to NAIAx 2 (Villamor Air Base)April 2017
    Ramps going to/from Skyway (Ramps 1 and 17) 01 June 2017