MT. PROVINCE

Road Name / Section ID Route Numbering Start KM End KM
Baguio-Bontoc Rd      
S00504LZ 204 K0342 + (-799) K0391 + 564
Bananao Access Rd      
S03999LZ   K0465 + (-060) K0467 + 338
Bontoc-Cadre Rd      
S03996LZ   K0392 + (-550) K0392 + 620
Dantay-Sagada Rd      
S00509LZ 206 K0385 + (-296) K0395 + 3170
EYEB-DPWH Motorpool Rd      
S00516LZ      
Govt Center-Cadre Rd      
S00510LZ      
Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd      
S00534LZ   K0377 + (-944) K0464 + 000
S00593LZ   K0463 + (-122) K0480 + 971
S00594LZ   NIA intake + (-4384) NIA intake + 000
Mt Data Access Rd      
S00505LZ      
Mt Prov-Cagayan via Tabuk-Enrile Rd      
S00514LZ 204 K0392 + (-334) K0420 + 997
Mt Prov-Ilocos Sur via Kayan Rd      
S00531LZ   K0398 + (-252) K0400 + 394
S00532LZ   K0386 + (-034) K0397 + 707
Mt Prov-Ilocos Sur via Tue Rd      
S00530LZ 205 K0387 + (-081) K0418 + 755
Mt Province-N Vizcaya Rd      
S00512LZ      
S00513LZ 109 K0363 + (-783) K0386 + 242
Mt. Province-Ifugao Rd (Kiling-Paracelis Sect)      
S00596LZ   K0456 + (-771) K0477 + 351
Mt. Province-Isabela Rd      
S00535LZ      
Otucan Diversion Rd      
S00524LZ      
PC Barracks Rd      
S00508LZ      

 

DEO / Functional Classification / Road Name / Road Number Condition Rating
Good Fair Poor Bad No Assessment Total
  Secondary Roads           9.19         54.46       68.90       14.92            2.37        149.84
1-1 Baguio-Bontoc Rd            1.11          11.87        30.67          6.18             0.33            50.15
  Concrete               -            11.87        30.67          6.18             0.30            49.02
  Asphalt            1.11               -               -               -                  -                1.11
  Gravel               -                 -               -               -               0.02              0.02
2-2 Dantay-Sagada Rd            0.50            5.06          5.18          1.85             0.97            13.56
  Concrete            0.50            5.06          5.18          1.85             0.93            13.52
  Asphalt               -                 -               -               -               0.04              0.04
3-3 Mt Prov-Cagayan via Tabuk-Enrile Rd            0.26          14.25        14.44          0.07             0.44            29.47
  Concrete            0.26          14.25        13.95          0.07             0.39            28.92
  Gravel               -                 -            0.50             -               0.05              0.55
4-4 Mt Prov-Ilocos Sur via Tue Rd            4.66          14.05          7.56          5.49             0.29            32.05
  Concrete            2.04          14.05          7.56          5.49             0.23            29.37
  Asphalt            2.62               -               -               -               0.06              2.68
5-5 Mt Province-N Vizcaya Rd            2.66            9.22        11.05          1.34             0.35            24.62
  Concrete            0.09            9.22        11.05          1.34             0.29            21.98
  Asphalt            2.57               -               -               -               0.02              2.58
  Gravel               -                 -               -               -               0.05              0.05
  Tertiary Roads         20.40         59.52       77.34       22.86            1.28        181.39
A Bananao Access Rd               -                 -            1.17          1.05             0.28              2.50
  Concrete               -                 -            1.17          1.05                -                2.22
  Gravel               -                 -               -               -               0.28              0.28
B Bontoc-Cadre Rd               -              1.16             -               -               0.01              1.17
  Concrete               -              1.16             -               -               0.01              1.17
C EYEB-DPWH Motorpool Rd               -              0.07             -               -                  -                0.07
  Concrete               -              0.07             -               -                  -                0.07
D Govt Center-Cadre Rd               -                 -            0.15             -                  -                0.15
  Concrete               -                 -            0.15             -                  -                0.15
E Jct Talubin-Barlig-Natonin-Paracelis-Calaccad Rd            9.28          43.62        50.10          8.42             0.46          111.87
  Concrete            7.44          30.38        11.03          4.86             0.42            54.12
  Gravel            1.84          13.24        39.06          3.57             0.04            57.75
F Mt Data Access Rd            0.49               -               -               -                  -                0.49
  Concrete            0.49               -               -               -                  -                0.49
G Mt Prov-Ilocos Sur via Kayan Rd            0.82            7.86          6.07          0.08             0.12            14.95
  Concrete            0.82            7.86          6.07          0.08             0.12            14.95
H Mt Province-N Vizcaya Rd               -                 -               -            0.16                -                0.16
  Concrete               -                 -               -            0.16                -                0.16
I Mt. Province-Ifugao Rd (Kiling-Paracelis Sect)            1.73            4.77        10.26          4.96             0.33            22.06
  Concrete            1.73            4.77        10.26          4.96             0.33            22.06
J Mt. Province-Isabela Rd            8.08               -            9.52          8.18             0.09            25.86
  Concrete            8.08               -            0.10          1.05                -                9.23
  Gravel               -                 -            9.42          7.13             0.09            16.63
K Otucan Diversion Rd               -              1.88          0.07             -                  -                1.95
  Concrete               -              1.88          0.07             -                  -                1.95
L PC Barracks Rd               -              0.17             -               -                  -                0.17
  Concrete               -              0.17             -               -                  -                0.17
TOTAL         29.59      113.98    146.23       37.78            3.65        331.23
 


 

Back Home Up Next

Abra / Apayao 1st / Apayao 2nd / Baguio City / Benguet 1st / Benguet 2nd / Ifugao 1st / Ifugao 2nd / Lower Kalinga / Mt. Province / Upper Kalinga

 

Notes:
 

1.) Road data provided are as of  13 December 2016.

2.) The unit of measure for Road Data is kilometers.

3.) No Assessment refers to Road Sections that are either under construction and/or segments with length below the 50-meter gauging length.

4.) National Roads are classified into:

        Primary Roads - roads that connect cities of > 100,000 population.   

        Secondary Roads - other roads which complement with the national arterial roads to provide access to main population and production centers of the country.  

        Tertiary Roads - other existing roads under DPWH which perform a local function. (In the map, these roads are represented only by letters.)

 

For questions regarding this Website contact dpwh_feedback@yahoo.com or the DPWH CFMC .

 

Last updated: 03/09/17.

Disclaimer