Department of Public Works and Highways
SUMMARY OF BRIDGE CONDITION  BY REGION FOR CY 2016
Table 2.1c
                         
RBIA Generated Report as of December 28, 2016            Unit of Measure: In Linear Meter (lm)
Region Good Fair Poor Bad Further Assessment Grand Total
Total % Total % Total % Total % Total % Total %
CAR 105 1.29% 135 1.65% 19 0.23% 20 0.25% 41 0.50% 320 3.92%
NCR 143 1.75% 127 1.56% 12 0.15% 5 0.06% 2 0.02% 289 3.54%
NIR 186 2.28% 148 1.81% 57 0.70% 6 0.07% 1 0.01% 398 4.88%
I 178 2.18% 253 3.10% 68 0.83% 36 0.44% 0 0.00% 535 6.56%
II 209 2.56% 189 2.32% 48 0.59% 20 0.25% 1 0.01% 467 5.72%
III 251 3.08% 385 4.72% 58 0.71% 28 0.34% 0 0.00% 722 8.85%
IV-A 279 3.42% 297 3.64% 50 0.61% 13 0.16% 3 0.04% 642 7.87%
IV-B 225 2.76% 299 3.66% 66 0.81% 8 0.10% 19 0.23% 617 7.56%
V 210 2.57% 303 3.71% 75 0.92% 59 0.72% 6 0.07% 653 8.00%
VI 175 2.14% 254 3.11% 34 0.42% 17 0.21% 5 0.06% 485 5.94%
VII 210 2.57% 153 1.87% 45 0.55% 7 0.09% 0 0.00% 415 5.09%
VIII 418 5.12% 356 4.36% 95 1.16% 4 0.05% 11 0.13% 884 10.83%
IX 109 1.34% 158 1.94% 13 0.16% 20 0.25% 0 0.00% 300 3.68%
X 198 2.43% 189 2.32% 19 0.23% 6 0.07% 0 0.00% 412 5.05%
XI 108 1.32% 154 1.89% 20 0.25% 1 0.01% 0 0.00% 283 3.47%
XII 165 2.02% 128 1.57% 17 0.21% 1 0.01% 0 0.00% 311 3.81%
XIII 155 1.90% 219 2.68% 42 0.51% 12 0.15% 0 0.00% 428 5.24%
Grand Total 3,324 40.73% 3,747 45.91% 738 9.04% 263 3.22% 89 1.09% 8,161 100.00%


Notes:
 

1.) Bridge data provided are as of  28 December 2016.

2.) "Further Assessment" refers to Bridges that are either under the circumstances of on-going construction, under major maintenance work or washed-out.

3.) National Bridges are classified into:

        Permanent Bridges - are bridges that are composed of concrete and steel.

        Temporary Bridges - are bridges consisting of timber and bailey.

For questions regarding this website contact dpwh_feedback@yahoo.com or the DPWH CFMC .

 