CONSOLIDATED CONSTRUCTORS PERFORMANCE SUMMARY REPORT

UNIFORM CODING SCHEME FOR THE CONSTRUCTORS PERFORMANCE EVALUATION SYSTEM (CPES) - INFORMATION SYSTEM

CIAP-PDCB CONSOLIDATED CONSTRUCTORS PERFORMANCE SUMMARY REPORT (ON-GOING / COMPLETED PROJECTS) 

 

 For particular information on the data of each of the CPES Rating, please contact :

Walter Ocampo

Director IV

HEAD, CPES-IU

Tel. Nos. 304-3277

MELROSE I. PAILMA

Engineer IV

CPES Program Coordinator

Tel. Nos. 304-3511 / 3508

For further information and queries, you may visit us at the Office of the Director, Bureau of Construction, Department of Public Works and Highways, Bonifacio Drive, Port Area, Manila; or e-mail us at pailma.melrose @dpwh.gov.ph
  CPES
 
PCAB PROJECT CLASSIFICATION REMARKS
CODE DESCRIPTION CODE DESCRIPTION
 GB - 1  Building or Industrial Plant  AHD  Project is Ahead of Schedule
 GB - 2  Sewerage or Sewage Treatment / Disposal System  DEL  Project is Delayed of Schedule
 GE - 1  Road, Highways, Pavement, Railways, Airport Horizontal Structure & Bridges  ONS  Project is On Schedule
 GE - 2  Irrigation and Flood Control  CWS  Contract Works Suspended
 GE - 3  Dam, Reservoir or Tunneling  PSC  Project Substantially Completed
 GE - 4  Water Supply  TER  Terminated
 GE - 5  Port, Harbor of Offshore  
 SP - EE  Specially - Electrical Work
 SP - WD  Specially - Well-Drilling Work
SP  Other Specially Works Not Included in the Classification
 
CPES RATING / QUALITATIVE DESCRIPTION PCAB - ARC CATEGORY
CODE DESCRIPTION DESCRIPTION
 >90% Outstanding Agency Registration Classification
 > 80% But  ≤ 90%  Very Satisfactory  Small "A"
> 70% But ≤ 80%  Satisfactory  Small "B"
 > 60% But ≤ 70%  Fair  Medium "A"
 ≤ 60%  Poor  Medium "B"
   Large "A"
 Large "B"
 
CONSTRUCTOR - RELATED PROBLEMS AGENCY RELATED PROBLEMS
 C - W01  Insufficient manpower deployed in project site  A - V01  Delays in the approval of variation orders
 C - E01  Breakdown of equipment / equipment not operational  A - T01  Delays in the approval of contract time extension
 C - E02  Lack / Insufficient / Inadequate equipment deployed in project site  A - SO1  Delays in the approval of suspension order
 C - M01  Lack / Inadequate / Insufficient supply of construction Materials  A - D01  Changes in construction designs
 C - R01  Lack of Financial resources  A - F01  Delays in the relases of funds
   A - R01  Right-of-Way (ROW) acquisition problems (squatters relocation problems, relocation of utilities, (i.e. PLDT, MERALCO post and other similar cases)
 A - P01  Delays in acquisition of necessary permits

OTHER - RELATED PROBLEMS 

O - W01  Unfavorable weather condition (Occurrence of natural calamities; occurrence of flooding / siltation on site; Unworkable ground condition)
O - P01  Insurgence or peace and order problems / civil disturbances
O - T01  Third Party intervention
  * Can be a reason for the negative slipage of constructor (please see the CPES reports of constructor from the agency concerned).
 
 
 