CPES
|
PCAB PROJECT
CLASSIFICATION |
REMARKS |
|
CODE |
DESCRIPTION |
CODE |
DESCRIPTION |
|
GB - 1 |
Building or
Industrial Plant |
AHD |
Project is
Ahead of Schedule |
|
GB - 2 |
Sewerage or
Sewage Treatment / Disposal System |
DEL |
Project is
Delayed of Schedule |
|
GE - 1 |
Road,
Highways, Pavement, Railways, Airport Horizontal Structure &
Bridges |
ONS |
Project is On
Schedule |
|
GE - 2 |
Irrigation and
Flood Control |
CWS |
Contract Works
Suspended |
|
GE - 3 |
Dam, Reservoir
or Tunneling |
PSC |
Project
Substantially Completed |
|
GE - 4 |
Water Supply |
TER |
Terminated |
|
GE - 5 |
Port, Harbor
of Offshore |
|
|
SP - EE |
Specially -
Electrical Work |
|
SP - WD |
Specially -
Well-Drilling Work |
|
SP |
Other
Specially Works Not Included in the Classification |
|
|
|
|
CPES RATING / QUALITATIVE
DESCRIPTION |
PCAB - ARC
CATEGORY |
|
CODE |
DESCRIPTION |
DESCRIPTION |
|
>90% |
Outstanding |
Agency
Registration Classification |
|
> 80%
But ≤ 90% |
Very
Satisfactory |
Small
"A" |
|
> 70% But ≤
80% |
Satisfactory |
Small
"B" |
|
> 60%
But ≤ 70% |
Fair |
Medium
"A" |
|
≤ 60% |
Poor |
Medium
"B" |
| |
Large
"A" |
|
Large
"B" |
|
|
|
|
CONSTRUCTOR -
RELATED PROBLEMS |
AGENCY RELATED
PROBLEMS |
|
C - W01 |
Insufficient
manpower deployed in project site |
A - V01 |
Delays in the
approval of variation orders |
|
C - E01 |
Breakdown of
equipment / equipment not operational |
A - T01 |
Delays in the
approval of contract time extension |
|
C - E02 |
Lack /
Insufficient / Inadequate equipment deployed in project site |
A - SO1 |
Delays in the
approval of suspension order |
|
C - M01 |
Lack /
Inadequate / Insufficient supply of construction Materials |
A - D01 |
Changes in
construction designs |
|
C - R01 |
Lack of
Financial resources |
A - F01 |
Delays in the
relases of funds |
|
|
A - R01 |
Right-of-Way
(ROW) acquisition problems (squatters relocation problems,
relocation of utilities, (i.e. PLDT, MERALCO post and other
similar cases) |
|
A - P01 |
Delays in
acquisition of necessary permits |
|
OTHER -
RELATED PROBLEMS |
|
O - W01 |
Unfavorable
weather condition (Occurrence of natural calamities;
occurrence of flooding / siltation on site; Unworkable
ground condition) |
|
O - P01 |
Insurgence or
peace and order problems / civil disturbances |
|
O - T01 |
Third Party
intervention |
|
* Can be a
reason for the negative slipage of constructor (please see
the CPES reports of constructor from the agency concerned). |
|
|
|
|
|
|
|