NAIA Expressway (Phase II)
|
PROJECT OBJECTIVE |
|
To provide improved access to Ninoy Aquino International
Airport |
|
|
|
To Improve traffic condition by decongesting at-grade
roads; |
|
|
|
Projects Description : |
|
It is a 4-lane elevated expressway
with a total length of 5.2 kms. Starting from Sales
St. going to Andrews Ave, Domestic Road, MIA Rd. and
ends at Roxas Blvd. It includes to construction of
toll plaza and 5 on and off ramps. |
|
Total Project Cost : |
|
P 13.575 B |
|
Government Support: |
|
ROW |
P 947.76
M |
|
IC (50%) |
P 260.71
M |
|
Subsidy |
P
5,547.75 M |
|
Total |
P 6.756 B |
|
|

click image for a larger
view
|
|
Project Alignment Description:
|
 |
| |
 |
| |
|
Typical Cross Sections:
(click here to
view images) |
| |
| |
|
|
| |
|
Processes/Activities |
Timelines |
|
Review
by JICA of the technical and financial viability
|
March
– April 2011 |
|
Submission
to NEDA |
May 26, 2011 |
|
Approval
of NEDA Cabinet Committee |
June
17, 2011 |
|
Completion
of Parcellary Survey Plan |
Jun.
30, 2011 |
|
Approval
of NEDA
Board |
January
2012 |
|
Advertisement/Publication |
February
2012 |
|
Submission of Bids |
July
2012 |
|
Notice of Award |
August
2012 |
|
Approval
of Contract |
September
2012 |
|
Detailed
Design and Construction (36 Months) |
2012-2015 |
|
| |
|
Project Implementation :
Project Design & Construction
-
Govt to finance RROW acquisition
-
Private sector to finance, design,
construct operate & maintain the project
|
|
Economic Indicator:
Economic Internal
Rate of Return = 15.9 % |
|
|
|