"Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality                                                                                                                                                                         

a

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

About PPP

 Main

 CALA Expressway - Cavite Side  

 NAIA Expressway -  Phase II  

 CLEx Phase I, Tarlac Cabanatuan

 CLEx Phase II, Cabanatuan - San Jose

 Calamba - Los Baños Expressway

 CALA Expressway - Laguna Side  

 C-5/FTI/Skyway Connector  

 C-6 Expressway - North Section

 C-6 Expressway - Remaining South Section

 C-6 Extension (Laguna de Bay Flood Control Dike Expressway)

 NLEx East/ La Mesa Parkway  

 NLEx-SLEx Link Expressway

 R-7 Expressway

 SLEx Extension (to Lucena City) 

 Daang Hari - SLEx Link 

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways :200 Km Sphere of Metro Manila
 

PPP Contact Information

Public-Private Partnership (PPP) Center

  Private-Public Partnership Service

NAIA Expressway (Phase II)

PROJECT OBJECTIVE

To provide improved access to Ninoy Aquino International Airport
 
To Improve traffic condition by decongesting at-grade roads;
 
Projects Description :

It is a 4-lane elevated expressway with a total length of 5.2 kms. Starting from Sales St. going to Andrews Ave, Domestic Road, MIA Rd. and ends at Roxas Blvd. It includes to construction of toll plaza and 5 on and off ramps.

Total Project Cost :

P 13.575 B

Government Support:

ROW

 P 947.76 M

IC (50%)

 P 260.71 M

Subsidy

 P 5,547.75 M

Total P 6.756 B

click image for a larger view

 

 

Project Alignment Description:

  • Traverses Pasay City and Parañaque City.

  • 5.2 kilometers NAIA Expressway Phase I to Roxas Boulevard

 
 

Typical Cross Sections: (click here to view images)

 
 
 
 
Processes/Activities Timelines

Review by JICA of the technical and financial viability

March – April 2011

Submission to NEDA

May 26, 2011

Approval of NEDA Cabinet Committee

June 17, 2011

Completion of Parcellary Survey Plan

Jun. 30, 2011

Approval of NEDA Board

January 2012

Advertisement/Publication

February 2012

Submission of Bids

July 2012

Notice of Award

August 2012

Approval of Contract

September 2012

Detailed Design and Construction (36 Months)

2012-2015

 

Project Implementation :

    Project Design & Construction

  • Govt to finance RROW acquisition
  • Private sector to finance, design,  construct operate & maintain the project

Economic Indicator:

     Economic Internal Rate of Return = 15.9 %

 
 