   "Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality                                                                                                                                                                         

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

About PPP

 Main

 CALA Expressway - Cavite Side  

 NAIA Expressway -  Phase II  

 CLEx Phase I, Tarlac Cabanatuan

 CLEx Phase II, Cabanatuan - San Jose

 Calamba - Los Baños Expressway

 CALA Expressway - Laguna Side  

 C-5/FTI/Skyway Connector  

 C-6 Expressway - North Section

 C-6 Expressway - Remaining South Section

 C-6 Extension (Laguna de Bay Flood Control Dike Expressway)

 NLEx East/ La Mesa Parkway  

 NLEx-SLEx Link Expressway

 R-7 Expressway

 SLEx Extension (to Lucena City) 

 Daang Hari - SLEx Link 

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways : 200 Km Sphere of Metro Manila
 

PPP Contact Information

Public-Private Partnership (PPP) Center

  Private-Public Partnership Service

CALA Expressway - Cavite side section (27.5 km)

Project Objective :

To ease traffic congestion and support economic development of the Cavite-Laguna (CALA) region

Project Description :

Construction of a 27.5 km, 4-lane at grade highway from the terminus of the R-1 Expressway in Kawit, Cavite to Aguinaldo Highway at Silang, Cavite and Laguna

Project Cost

 

P 11.79 Billion

(US$ 262 Million)

(1US$ =Php 45.00)

Government Support:
  To be determined during the conduct of the study

 

 

     

 

 

click image for a larger view

 

 
Processes/Activities Timelines
JICA to submit ICC Forms and Business Case

April 2-12, 2012

Technical Feasibility

February  2012

Submission to NEDA

April 13, 2012

NEDA Board Approval

May 18, 2012

Issued Bid Documents

August 2012

Bid/Negotiate/Award

September 2012-February 2013

Final Design/ROW Acquisition

March 2013-Aug.2014

Construction/Opening

April 2014 - Nov. 2016

 
 
     
 