a

   "Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality                                                                                                                                                                         

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

About PPP

 Main

 CALA Expressway - Cavite Side  

 NAIA Expressway -  Phase II  

 CLEx Phase I, Tarlac Cabanatuan

 CLEx Phase II, Cabanatuan - San Jose

 Calamba - Los Baños Expressway

 CALA Expressway - Laguna Side  

 C-5/FTI/Skyway Connector  

 C-6 Expressway - North Section

 C-6 Expressway - Remaining South Section

 C-6 Extension (Laguna de Bay Flood Control Dike Expressway)

 NLEx East/ La Mesa Parkway  

 NLEx-SLEx Link Expressway

 R-7 Expressway

 SLEx Extension (to Lucena City) 

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways : 200 Km Sphere of Metro Manila

 

PPP Contact Information

Public-Private Partnership (PPP) Center

 

 

Project Screening and Selection of Priority Projects

 

First Screening

Particular

Weight

1. Functional Importance of a link in HSH Network and Improvement

    of Inter-modal Linkage

17%

2. Urgency based on contribution to traffic decongestion 17%
3. Project Readiness

15%

4. Contribution to National/Regional Socio-Economic Development 10%
5. Initial Investment Fund 10%
6. Environmental and Social  Impact 8%
7. Impact of a project on viability of Existing Toll Expressway 3%
8. Economic  and Financial Viability 20%

Total

100%

 

 

Second Screening

Particular

Weight

1. Necessity & Urgency of the Project

45%

2. Profitability & Fund Procurement Difficulty 30%
3. Implementability

 25%

Total

100%

 

 
 

 

 
 