Project Description :
- Provide direct access to Food Terminal Inc. (FTI) from both Skyway and C-5
- Length 6.8 km (including ramps)
- 2 to 4 lanes
- L = 3.0 Km
|
|
Implementation Schedule :
|
Project Cost :
- PhP 5.64 Billion
- (US$125.33 Million)
- (1US$ =Php 45.00)
|
Project Status :
- Feasibility Study was completed in 2006
- Detailed Design already completed ( August, 2010)- under review by the Bureau of Design, DPWH
- Bidding/Tendering – 2012
- Detailed Design and Construction Schedule – 2013 to 2015
|
|