Private-Public Partnership Service
School Buildings
|
Project Description :
-
A Finance-Design-Build Scheme is being studied whereby the contractor undertakes the financing, design, and construction of a package of classrooms and after completion, turns it over to DEPED which shall pay the contractor, and/or financier, its total investment plus a reasonable rate of return on an agreed schedule.
- The project is to partially construct 9,630 classrooms to fill-up the 60,000 classrooms backlog.
- Total classrooms - 9,301 classrooms
|
Project Cost :
- PhP 10.04 Billion
- (US$ 233.49 Million)
|
|
Project Status :
|
|
Government Support :
|
|
|
|
Processes/Activities
|
Timelines
|
|
Issuance of DPWH Memo Circular No. 1 S. 2012
to expedite issuance of Building Permits for
PSIP classrooms
|
March 20, 2012
|
|
Submission of Pre-qualification documents
|
April 11, 2012
|
|
Pre-bid Conference
|
May 14, 2012
|
|
Submission of Technical and Financial Proposals
|
July 2012
|
|
Signing of Contract Agreement
|
August 08, 2012
|
|
Opening of Bids
|
July 18, 2012
|
|
Issuance of Notice to Proceed
|
w/in 2 mos.after signing of CA
|
|
Construction complete deadline
|
August 14, 2013
|
NOTE:
Per DepEd and DOF as of June 05, 2012, the DBM has verbally agreed to consider limp sum appropriation in the GAAfor Y2012 or Y2013, but still 10-year repayment to the winning bidders. This is to address the concerns/issues against the 10-year MYOA.