a

   "Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality, Right on Time                                                                                                                                                                     
Images of different DPWH Projects

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

 Main

 Tarlac-Pangasinan La Union Expressway (TPLEX)

 Daang Hari–SLEX Link Road Project

 STAR Project Construction of Stage II, Phase 2 and Improvement of Stage I

 NAIA Expressway 

 Cavite–Laguna (CALA) Expressway

 Laguna Lakeshore Expressway Dike (LLED)

 Central Luzon Link Expressway (CLLEx)

 NLEX East Expressway, Ph1&2

 Operation, Maintenance, Improvement of Kennon Road and Marcos Highway

 Tagum–Davao–General Santos High Standard Highway

 Cebu–North Coastal Road

 R7 Expressway

 Manila North Expressway Project

  Metro Manila Expressway Project (C6)

 Metro Manila Skyway Stage 3 (MMSS-3)

 South Luzon Expressway Toll Road 4 (TR–4), Sto. Tomas–Lucena Project

 Improvement/Rehabilitation of the Quirino Highway Project

 Conversion of Plaridel By-Pass Road to Expressway Project

 PPP School Infrastructure Project (PSIP)

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways : 200 Km Sphere of Metro Manila
 

DPWH PPP Service Contact Information

Public Private Partnership (PPP) Center of the Philippines

  Private-Public Partnership Service

NLEX East Expresssway, Ph1&2
As of July 25, 2014

Project Impact/Objective:
  • To spur provincial and regional economic activities and provide improved and prompt delivery of services to people in the serviced areas
  • To enhance transport network and accessibility between provinces and municipalities particularly in North Luzon Region.
  • The project’s objectives are also geared in promoting gender equality by providing equal treatment to disadvantaged women through their involvement in the project implementation activities such as promoting the employment of destitute women in highway maintenance and the establishment of women’s corners.
Project Description :

With a length of 92.1 km., the project consists of Phase I and Phase II and will form an important transport access in the eastern area of Region III. NLEX east Expressway is up to Cabanatuan City starting from the end point of La-Mesa Parkway and/or junction of C-6 in San Jose del Monte via Norzagaray, Angat, San Ildefonso, San Miguel, Gapan, and Sta. Rosa in parallel with the Pan Philippine Highway. Bridges will be required for the project to cross Angat River, Peñaranda River, and Pampanga River.

Project Cost :
  • Php 15.77 Billion
Project Status :
  • The original project duration is from February 25, 2012 to August 23, 2013
  • Pertconsult International requested for an extension of three (3) months without extra cost to the government.
  • Geotechnical Investigation Report already submitted on 30 September 2013
  • The Draft Final Report of the Business Case Study was already submitted and will be forwarded to PPP Center for comments/evaluation
  • Draft Final Report – Volume I (Revised) was submitted by Pertconsult International on 12 May 2014.
  • Based on the Draft Final Report submitted, it is recommended that the proposed NLEX East Project be implemented because of its expected robust financial performance over the project life as well as the ensuing “multiplier effects” to commerce and industry along the growth node centers of Central Luzon and the eastern corridor of the Luzon Island, Quezon, and Aurora Provinces.
Government Support :
To be determined during the conduct of the study

click image for a larger view



Processes/Activities Timelines
Procurement for the Consultancy Services of the Business Case Study March 2012
Shortlisting of Consultants July 2012
Submission of Bids July 26, 2012
Notice of Award January 16, 2013
Contract was approved February 14, 2013
Notice to Proceed was issued to Pertconsult International February 21, 2013