   "Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality, Right on Time                                                                                                                                                                     
Images of different DPWH Projects

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

 Main

 Tarlac-Pangasinan La Union Expressway (TPLEX)

 Daang Hari–SLEX Link Road Project

 STAR Project Construction of Stage II, Phase 2 and Improvement of Stage I

 NAIA Expressway 

 Cavite–Laguna (CALA) Expressway

 Laguna Lakeshore Expressway Dike (LLED)

 Central Luzon Link Expressway (CLLEx)

 NLEX East Expressway, Ph1&2

 Operation, Maintenance, Improvement of Kennon Road and Marcos Highway

 Tagum–Davao–General Santos High Standard Highway

 Cebu–North Coastal Road

 R7 Expressway

 Manila North Expressway Project

  Metro Manila Expressway Project (C6)

 Metro Manila Skyway Stage 3 (MMSS-3)

 South Luzon Expressway Toll Road 4 (TR–4), Sto. Tomas–Lucena Project

 Improvement/Rehabilitation of the Quirino Highway Project

 Conversion of Plaridel By-Pass Road to Expressway Project

 PPP School Infrastructure Project (PSIP)

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways : 200 Km Sphere of Metro Manila
 

DPWH PPP Service Contact Information

Public Private Partnership (PPP) Center of the Philippines

  Private-Public Partnership Service


Laguna Lakeshore Expressway Dike (LLED)

As of July 25, 2014

 

Project Description :
  • The project is envisioned to provide a high standard highway cum dike that will facilitate traffic flow and mitigate flooding in the western coastal communities along Laguna Lake, from Bicutan/Taguig in Metro Manila through Calamba to Los Baños in Laguna.

  • The proposed alignment runs 500 meters away but following the shoreline of the Laguna Lake.

  • The Project has the following components:
    1. Expressway Dike, Taguig-Los Baños, 47 km, with two (2) sections as follows:
      1. Bicutan-Calamba
      2. Calamba-Los Baños
        1. 6-lane tollway with 8 interchanges and access roads
        2. Dike designed for 100-year flood, and 16 floodgates/pumping stations designed for 60-year flood.
    2. Reclamation, 700 hectares, Taguig-Muntinlupa
      1. 7 islands, about 450-500m wide and 15.6km long
      2. With horizontal development (roads, drainage, open spaces)
      3. 100-150m channel between lakeshore and reclamation

Project Objective :
  • The expressway is intended to relieve the heavily travelled Bicutan-Calamba corridor (SLEX and Manila South Road)
  • To serve as an alternate to the congested road of the National Highway from Calamba to Los Baños
  • The proposed expressway will be used to integrate a flood control system to protect the flood prone areas located along the shoreland of Laguna Lake
  • Main economic benefits include savings in vehicle operating costs, savings in passenger time, reduction in flood damages, increase in land productivity in existing communities due to flood protection, and increase in land productivity (value added) in the reclamation area.
Project Cost :
  • Expressway Dike - PhP 64.914 B
  • Reclamation - PhP 57.897 B
  • Total - PhP 122.811 B
Government Support :
Right-of-Way PhP 2.1 B
Viability Gap Fund none required
Project Status :
  • The DPWH, through its letter dated 23 June 2014, requested the Laguna Lake Development Authority (LLDA) to prepare documents necessary for the next steps that will be undertaken after NEDA’s approval of the project.

click image for a larger view



Processes/Activities Timelines
Advertisement/Invitation to Pre-qualify and Bid 03-15 August 2014
Issuance and Preparation of PQ Documents 04 Aug - 15 Oct 2014
Pre-Qualification Conference 19 September 2014
Submission of PQ Documents 16 October 2014
Evaluation of PQ Documents 17 Oct - 04 Nov 2014
Issuance of Bid Documents / Preparation of Bid Proposal 06 November 2014 - 03 July 2015
Pre-Bid Conference 08 December 2015
Submission of Bids 06 July 2015
Bid Evaluation 07 - 28 July 2015
Contract Award Approval 04 August 2015
Notice of Award 26 August 2015
Contract Approval 04 September 2015
Issuance of Notice to Proceed 07 September 2015
Concession Period 37 years
Design 8 months
Construction 6 years
Operation and Maintenance 30 years
Target Start Date September 2015
Target End of Concession September 2051