   "Daang Matuwid, Kaunlaran ang Hatid"                                                                                                                         Right Project, Right Cost, Right Quality, Right on Time                                                                                                                                                                     
Images of different DPWH Projects

::  HOME  ::  ABOUT US  ::  INFRASTRUCTURE  ::  DOING BUSINESS  ::  EMPLOYMENT  ::  DIRECTORY  ::  FEEDBACK  ::  NEWS  ::  FAQs

 Main

 Cavite-Laguna (CALA) Expressway

 NAIA Expressway 

 Central Luzon Link Expressway (CLLEX),Phase 1

 CLLEx Phase II, Cabanatuan - San Jose

 Calamba - Los Baños Expressway

 C-5/FTI/Skyway Connector

 C-6 Expressway - North Section

 C-6 Expressway and Global Link (South Section)

 C-6 Extension (Laguna de Bay Flood Control Dike Expressway)

 NLEx East Expressway

 NLEx-SLEx Link Connector

 R-7 Expressway

 SLEx Extension (to Lucena City)

 Daang Hari – SLEx Link Project

 Kennon O & M

 Dalton Pass East Alignment

 Tarlac-Pangasinan-La Union Toll Expressway (TPLEX)

 Improvement/Rehabilitation of the Quirino Highway Project

 School Buildings

 PPP Bridges in Luzon, Batch 1

 Tagum-Davao-General Santos High Standard Highway

 Cebu-North Coastal Road

 STAR Project Construction of Stage II,Phase 2 and Improvement of Stage I

 South Luzon Expressway Toll Road 4 (TR-4) Sto. Tomas-Lucena Project

 
Project Screening and Selection of Priority Projects
Recommended Types of  PPP schemes
Other  DPWH PPP Projects under Development
Water Supply and Sanitation Policy under PPP Being Developed
Master Plan for High Standard Highways/ Expressways for PPP
Expressways in Operation and Under Construction/Planning
Existing and Proposed Expressways : 200 Km Sphere of Metro Manila
 

PPP Contact Information

Public-Private Partnership (PPP) Center

  Private-Public Partnership Service

Cavite-Laguna (CALA) Expressway

Project Objective :
  • To ease traffic congestion and support economic development of the Cavite-Laguna (CALA) region
Project Description :
  • PPP Section
    • Total Length: 28.90 km (Kawit to Aguinaldo Highway at Silang
    • No. of Lanes: 4-lanes
    • Right-of-Way: 60 meters
    • Interchanges: 5 grade separated interchanges
    • Structures: 7,928 meter total length of bridges
  • ODA Section
    • Total Length: 18.10 km (Aguinaldo Hway at Silang to Mamplasan)
    • No. of Lanes: 4-lanes
    • Right-of-Way: 60 meters
    • Interchanges: 4 grade separated interchanges
    • Structures: 7,279 meter total length of bridges
Project Cost :
  • P 35.58 Billion
  • (US$ 827.44 Million)
Government Support :
GOP: P 10,118 M
IC P 72 M
Cavite ROW P 5,937 M
Laguna ROW P 4,109 M

Project Status :
Advertisement of the Project 09 April 2013
15 April 2013
22 April 2013

click image for a larger view



Processes/Activities Timelines
The project was approved by NEDA-ICC Joint TB and CC meeting 12 July 2012
NEDA Board conditional approval subject to cost reduction 29 November 2012
Project Approval 18 January 2013
Start of Bidding Process April 2013
Contract Award December 2013
Design Dec. 2013 - Dec. 2014
Construction Jan. 2015 to Dec.2017
Start of Operation January 2018
Concession Period 35 years (including construction period)